Principles of correct VRV Installation
A. Refrigerant pipe work
B. Drain pipe work
C. Service space
D. Information Flow
D a i k i n E u r o p e A c a d e m y
Learning, our way
A. Refrigerant piping work
No moisture, no dirt, no leakage !
D a i k i n E u r o p e A c a d e m y
Learning, our way
1. Brazing with nitrogen replacement
D a i k i n E u r o p e A c a d e m y
Learning, our way
Correct storage of pipes
D a i k i n E u r o p e A c a d e m y
Learning, our way
Cleans the refrigerant pipes in order to prevent: – clogging of expansion valve (capillary tube)
– insufficient cooling or heating– degradation of oil– oxidation of compressor
2. Flushing
D a i k i n E u r o p e A c a d e m y
Learning, our way
Prevents Refrigerant Leakage in order to avoid:
– Gas shortage– Insufficient cooling or heating– Temperature rising of discharge gas– Frost accumulation on heat exchanger
3. Air tightening test
D a i k i n E u r o p e A c a d e m y
Learning, our way
Leak check is done with nitrogen:
10
0
20
30
40
3 min 5 min 24 hours
Step 1 Leak check after 3 min. at 10.3 Bar
Step 2 Leak check after 5 min. at 21.5 Bar
Step 3 Leak check after 24 h. at 38 Bar
3. Air tightening test
D a i k i n E u r o p e A c a d e m y
Learning, our way
3.8 Mpa during 24 hours
The test is divided in 3 parts:– 1: Vertical pipe– 2: 1+Indoor piping– 3: 2+Outdoor piping
3. Air tightening test
D a i k i n E u r o p e A c a d e m y
Learning, our way
3. Air tightening test
D a i k i n E u r o p e A c a d e m y
Learning, our way
Prevents Moisture in Refrigerant Circuit in order to avoid:
– clogging of expansion valve (capillary tube)
– insufficient cooling or heating
– degradation of oil– oxidation of
compressor
4. Vacuum drying
D a i k i n E u r o p e A c a d e m y
Learning, our way
5. Additional charge of refrigerant
Precise amount is calculated as a function of:– Length of pipe – Situation of branches
Added at the outdoor unit liquid valve– During last stage of vacuuming– At the start of the test run
Weight of additional refrigerant charge– Recorded on the outdoor unit nameplate.– Monitored with automatic system (VRV III leakage test)
D a i k i n E u r o p e A c a d e m y
Learning, our way
5. Additional charge of refrigerant
D a i k i n E u r o p e A c a d e m y
Learning, our way
B. Drain pipe work Adjust downward gradient
D a i k i n E u r o p e A c a d e m y
Learning, our way
Group Drain Piping
D a i k i n E u r o p e A c a d e m y
Learning, our way
Different orientations of outdoor units and walls Single units Installation in rows Centralised group layout
Short circuits are avoided
Maintenance is facilitated.
C. Service space
D a i k i n E u r o p e A c a d e m y
Learning, our way
Explain:
Hand over relevant printed materials.
D. Explanation to customer
1. How to use remote controller.2. How to clean air filters in indoor units.3. How to keep optimum operation.4. How to check if trouble occurs or not.5. Who to contact if an emergency occurs.
D a i k i n E u r o p e A c a d e m y
Learning, our way
Installation– By a experienced (and trained) Daikin Installer– Keywords: “Clean, Dry, Tight!”
Drainpiping– With downward slope,– Widening tubes – Space foreseen in design
Information flow to End-Customer– About skillfull installation– About system features – About preventive and corrective service.
A decent explanation on “How to use air conditioner”
brings very few service calls.