+ All Categories
Home > Documents > Lec2 Economic DispatchI

Lec2 Economic DispatchI

Date post: 09-Mar-2016
Category:
Upload: edward-baleke-ssekulima
View: 6 times
Download: 1 times
Share this document with a friend
Description:
Sample notes pertaining to the Economic Dispatch of thermal plants

of 32

Transcript
  • EPE507

    Power System Operation

    Dr. Amer Al-Hinai

    Economic Dispatch

  • Power System Operation 2

    The Economic Dispatch Problem

    Consider a system that consists of N thermal-generating units serving an aggregated electrical load, Pload

  • Power System Operation 3

    The Economic Dispatch Problem

    Input to each unit: cost rate of fuel consumed, Fi Output of each unit: electrical power generated, Pi

    Total cost rate, FT, is the sum of the individual unit costs

    Essential constraint: the sum of the output powers must equal the load demand

    The problem is to minimize FT

  • Power System Operation 4

    Retail Electricity Prices

    There are many fixed and variable costs

    associated with power systems, which ultimately

    contribute to determining retail electricity prices.

    The major variable operating cost is associated

    with generation, primarily due to fuel costs:

    Roughly half of retail costs.

  • Power System Operation 5

    Power System Economic Operation

    Different generation technologies vary in the:

    capital costs necessary to build the generator

    fuel costs to actually produce electric power

    For example:

    nuclear and hydro have high capital costs and low operating costs.

    Natural gas generators have low capital costs, and higher operating costs.

  • Power System Operation 6

    Power System Economic Operation

    Fuel cost to generate a MWh can vary widely

    from technology to technology.

    For some types of units, such as hydro, fuel

    costs are zero but the limit on total available

    water gives it an implicit value.

    For thermal units it is much easier to

    characterize costs.

    We will focus on minimizing the variable

    operating costs (primarily fuel costs) to meet

    demand.

  • Power System Operation 7

    Electric Fuel Prices

    Source: EIA Electric Power Annual, 2006 (October 2007)

  • Power System Operation 8

    Natural Gas Prices: 1990s to 2008

  • Power System Operation 9

    Coal Prices: 2005 to 2008

    There are four main types of coal:

    Bituminous sub-bituminous

    lignite anthracite.

    Heat values range from a low of 8Mbtu per ton to a high of 31 Mbtuper ton.

    For Illinois coal price per Mbtu is about 4/Mbtu.

  • Power System Operation 10

    Power System Economic Operation

    Power system loads are cyclical.

    Therefore the installed generation capacity is

    usually much greater than the current load.

    This means that there are typically many ways

    we could meet the current load.

    Since different states have different mixes of

    generation, we will consider how generally to

    minimize the variable operating costs given an

    arbitrary, specified portfolio of generators.

  • Power System Operation 11

    US Generation Mix (Energy)

    circa 2006-2009

    Gen Type US % Illinois % California % Texas %

    Coal 48 48 1 36

    Nuclear 19 48 15 15

    Hydro 6 0.1 22 2

    Gas 21 3 50 40

    Petroleum 1 0.1 1

    Other Renewable 3 0.4 12 (14 in 1990) 7

    Source: http://www.eia.doe.gov and Public Utility Commission of Texas

    Indiana is 94% coal, while Oregon is 71% hydro, Washington State is 76% hydro. Canada is about 60% hydro, France is also 80% nuclear, China is about 80% coal

  • Power System Operation 12

    Power System Economic Operation

    The two main types of generating units are thermal and

    hydro, with wind rapidly growing.

    For hydro the fuel (water) is free but there may be many

    constraints on operation:

    fixed amounts of water available,

    reservoir levels must be managed and coordinated,

    downstream flow rates for fish and navigation.

    Hydro optimization is typically longer term (many months

    or years).

    We will concentrate on thermal units, looking at short-

    term optimization.

  • Power System Operation 13

    Generator types

    Traditionally utilities have had three broad

    groups of generators:

    Baseload units: large coal/nuclear; almost always on

    at max.

    Midload, intermediate, or cycling units: smaller

    coal or gas that cycle on/off daily or weekly.

    Peaker units: combustion turbines used only for

    several hours.

  • Power System Operation 14

    Block Diagram of Thermal Unit

    To optimize generation costs we need to develop costrelationships between net power out and operatingcosts.

    Between 2-10% of power is used within the generatingplant; this is known as the auxiliary power.

  • Power System Operation 15

    Generator Cost Curves

    Generator costs are typically represented by one or other of the following four curves:

    input/output (I/O) curve

    fuel-cost curve

    heat-rate curve

    incremental cost curve

    For reference

    - 1 Btu (British thermal unit) = 1054 J

    - 1 MBtu = 1x106 Btu

    - 1 MBtu = 0.29 MWh

  • Power System Operation 16

    I/O Curve

    The IO curve plots fuel input (in MBtu/hr) versus net MW output.

  • Power System Operation 17

    Fuel-cost Curve

    The fuel-cost curve is the I/O curve multiplied by fuel cost.

    A typical cost for coal is $ 1.70/MBtu.

  • Power System Operation 18

    Heat-rate Curve

    Plots the average number of MBtu/hr of fuel inputneeded per MW of output.

    Heat-rate curve is the I/O curve divided by MW.

  • Power System Operation 19

    Incremental (Marginal) cost Curve

    Plots the incremental $/MWh as a function of MW.

    Found by differentiating the cost curve.

  • Power System Operation 20

    Mathematical Formulation of Costs

    Generator cost curves are usually not smooth.

    However the curves can usually be adequately

    approximated using piece-wise smooth,

    functions.

    Two approximations predominate:

    quadratic or cubic functions

    piecewise linear functions

    We'll assume a quadratic approximation:

  • Power System Operation 21

    The Economic Dispatch Problem

    H: Btu per hour heat input to the unit (Btu/h)

    F: Fuel cost times H is (/h) input to the unit for

    fuel

    The per hour operating cost rate of a unit will

    include prorated operation

    and maintenance costs.

    The labor cost for the operating crew is included

    as part of the operation

    cost.

  • Power System Operation 22

    The mathematical statement of the problem is a constrained optimization with the following functions:

    objective function:

    equality constraint:

    Note that any transmission losses are neglected and any operating limits are not explicitly stated when formulating this problem

    Problem may be solved using the Lagrange function

    The Economic Dispatch Problem

    N

    1i

    iiT PFF

    N

    1i

    iLoad 0PP

    N

    1i

    iLoad

    N

    1i

    iiT PP.PFF

  • Power System Operation 23

    The Lagrange function establishes the necessary

    conditions for finding an extreme of an objective function

    with constraints

    Taking the first derivatives of the Lagrange function with

    respect to the independent variables allows us to find the

    extreme value when the derivatives are set to zero

    There are (NF + N) derivatives, one for each independent variable

    and one for each equality constraint

    The derivatives of the Lagrange function with respect to the

    Lagrange multiplier merely gives back the constraint equation

    The NF partial derivatives result in 0

    P

    PF

    P

    L

    i

    ii

    i

    The Economic Dispatch Problem

  • Power System Operation 24

    Fuel costs

    coal: $ 3.30 / MBtu

    oil: $ 3.00 / MBtu

    The Economic Dispatch Problem

    Unit # 1: coal-fired steam unit: H1 = 510 + 7.20P1 + 0.00142P12 MBtu/h

    Unit # 2: oil-fired steam unit : H2 = 310 + 7.85P2 + 0.00194P22 MBtu/h

    Unit # 3: oil-fired steam unit : H3 = 78 + 7.97P3 + 0.00482P32 MBtu/h

    Example # 1

    Determine the economic operating point for the three generating units when delivering a total of 850 MW

    Input-output curves:

  • Power System Operation 25

    ED: Inequality Constraints In addition to the cost function and the equality constraint

    each generation unit must satisfy two inequalities

    The power output must be greater than or equal to the minimum power permitted:

    Minimum heat generation for stable fuel burning and temperature

    The power output must be less than or equal to the maximum power permitted:

    Maximum shaft torque without permanent deformation

    Maximum stator currents without overheating the conductor

    min,ii PP

    max,ii PP

  • Power System Operation 26

    Then the necessary conditions are expanded slightly

    max,ii

    i

    i

    min,ii

    i

    i

    max,iimin,ii

    i

    i

    PPdP

    dF

    PPdP

    dF

    PPP:PdP

    dF

    ED: Inequality Constraints

  • Power System Operation 27

    ED: Inequality Constraints

    Example # 2

    Reconsider the example # 1 with the following generator limits and the price of coal decreased to $2.70 / MBtu

    Generator limits:

    Unit # 1: 150 P1 600 MW

    Unit # 2: 100 P2 400 MW

    Unit # 3: 50 P3 200 MW

  • Power System Operation 28

    ED: Network Losses

    Consider a similar system, which now has a transmission network that connects the generating

    units to the load

  • Power System Operation 29

    ED: Network Losses

    The economic dispatch problem is slightly more complicated

    The constraint equation must include the network losses, Ploss

    The objective function, FT is the same as before

    The constraint equation must be expanded as:

    N

    1i

    iLoosLoad 0PPP

  • Power System Operation 30

    The same math procedure is followed to establish the necessary conditions for a minimum-cost operating solution Lagrange function and its derivatives w.r.t. the input power:

    ED: Network Losses

    N

    1i

    iLoosLoad

    N

    1i

    iiT PPP.PFF

    i

    loos

    i

    i

    i

    loos

    i

    i

    i dP

    dP

    dP

    dF0

    dP

    dP1

    dP

    dF

    dP

    d

    The transmission network loss is a function of the impedances and the currents flowing in the network

    For convenience, the currents may be considered functions of the input and load powers

    It is more difficult to solve this set of equations

  • Power System Operation 31

    step 1 pick starting values for Pi that sum to the load

    step 2 calculate Ploss/Pi and the total losses Ploss

    step 3 calculate that causes Pi to sum to Pload & Ploss

    step 4 compare Pi of step 3 to the values used in step 2; if there is significant change to any value, go back to step 2, otherwise, the procedure is done

    ED: Iterative MethodPick Pi,

    load

    N

    1i

    i PP

    Calculate

    i

    loss

    P

    P

    Calculate totallosses Ploss

    Solve for

    and Pinew

    is

    Pinew - Pi ?

    Done

    Yes

    No

    Pi = Pinew

  • Power System Operation 32

    Example # 3

    Repeat the first example, but include a

    simplified loss expression for the transmission

    network

    ED: Network Losses

    Ploss = 0.00003 P12 + 0.00009 P2

    2 + 0.00012 P32 MW


Recommended