+ All Categories
Home > Documents > Lecture 3 Layout Design Part1

Lecture 3 Layout Design Part1

Date post: 18-Dec-2015
Category:
Upload: salem-mohammed
View: 232 times
Download: 5 times
Share this document with a friend
Description:
good
35
1 FACULTY OF MECHANICAL ENGINEERING UNIVERSITI TEKNOLOGI MALAYSIA LAYOUT DESIGN - Part 1
Transcript
  • 1

    FACULTY OF MECHANICAL ENGINEERING

    UNIVERSITI TEKNOLOGI MALAYSIA

    LAYOUT DESIGN - Part 1

  • 2

    PRODUCT, PROCESS AND SCHEDULE

    Among the questions to be answered before facility planning can be done

    What is to be produced ?

    How are the products to be produced ?

    When are the products to be produced ?

    How much of each product will be produced ?

    For how long will the products be produced ?

    Where are the products to be produced ?

    The answers can be obtained from product design, process design, and schedule design

    Product design, process design and schedule design must be done concurrently with facilities design

  • 3

    PRODUCT DESIGN

    Product design involves the determination of which products to be produced and the detailed design of

    individual products

    DIFFERENT PRODUCT DIFFERENT FACILITY

    Basic product design data can be obtained from production drawings, prototypes of the product, etc

  • 4

    PRODUCT DESIGN assembly drawing

    Product

  • 5

    PROCESS DESIGN

    Process design decisions determine whether

    a part will be purchased or produced,

    Selection of process

    Sequence of process

    This information can be obtained from parts list, bill of materials, route sheet, assembly chart, precedence

    diagram

  • 6

    PROCESS DESIGN make or buy

    Options buy raw materials and do in house fabrication and assembly, or buy component and only do in house

    assembly

    Scope and magnitude of activities are dependent on level of vertical integration

  • 7

    PROCESS DESIGN make or buy

  • 8

    PROCESS DESIGN make or buy

    - part lists

    The input to the facilities planner is a listing of the items to be made and the items to be purchased.

    The listing often takes the form of a parts list or a bill of materials

    The parts list provides a listing of the component parts o f a product. In addition, a parts list includes at least

    the following

    Part number

    Part name

    Number of parts per product

    Drawing references

  • 9

    PROCESS DESIGN make or buy

    - parts list

    parts lists

  • 10

    PROCESS DESIGN make or buy

    - bill of materials

  • 11

    PROCESS DESIGN make or buy

    - bill of materials

  • 12

    PROCESS DESIGN selection of process

    Product identification process selection (include CAPP) Route sheet

  • 13

    PROCESS DESIGN selection of process

    route sheet

  • 14

    PROCESS DESIGN sequence of process

    Assembly chart

    Operation process chart

    Precedence diagram

  • 15

    PROCESS DESIGN sequence of process

    assembly chart

  • 16

    PROCESS DESIGN sequence of process

    operation process chart

    purchased or produced (make or buy)

  • 17

    PROCESS DESIGN sequence of process

    precedence diagram

    purchased or produced (make or buy)

  • 18

    SCHEDULE DESIGN

    Schedule design decisions provide answers to the questions

    How much to produce (volume)

    When to produce

    Associated with these decisions is the determination of the number of machines, number of shifts, number of

    employees, space requirements, storage requirements,

    material handling equipment, building size etc.

    Consequently, plant layout will be very much affected

    Information obtained from Master Production Schedule (MPS)

  • 19

    SCHEDULE DESIGN volume-variety

    Volume-variety chart (paretos law)

    Mass production area for 15% of high-volume items and a job shop arrangement for the remaining

    85% of the product mix

    Very important in determining the layout type

  • 20

    SCHEDULE DESIGN scrap estimates

    The market estimate specifies the annual volume to be produced for each product

    To produce the required amount of product, the number of units scheduled through production must

    equal the market estimate plus a scrap estimate.

    Ik = Ok

    1 Pk

    I1 = On

    (1-P1)(1-P2)(1-Pn)

  • 21

    SCHEDULE DESIGN scrap estimates

    A product has a market estimate of 97,000 components and requires three processing steps (turning, milling

    and drilling) having scrap estimates of P1 = 0.04, P2 =

    0.01 and P3 = 0.03

    Input for drilling, I3 = 97,000 = 100,000

    1 0.03

    Input for milling, I2 = 100,000 = 101,000

    1 0.01

    Input for turning, I1 = 101,000 = 105,219

    1 0.04

  • 22

    SCHEDULE DESIGN scrap estimates

    Scrap estimates

    I1 = 97,000

    (1 0.03) (1 0.01) (1 0.04)

    = 105,219

  • 23

    SCHEDULE DESIGN - Machine Assignment

    The combination of product, process and schedule design decisions influences the number of employees

    involved in producing the product

    Decisions regarding the assignment of machine to operators can affect the number of employees

    Assumptions

    Semiautomatic production equipment

    Machines are identical

    Times required to load and unload each machine are constant

    Automatic machining time is constant

    Time for operator to travel between machines is constant

  • 24

    SCHEDULE DESIGN - Machine Assignment

    Multiple activity chart shows the activities of one or more people and one or more machines

  • 25

    SCHEDULE DESIGN - Machine Assignment -

    multi activity chart

    Machine Assignment

    The

  • 26

    SCHEDULE DESIGN - Machine Assignment

    0.5 minute to travel between machines

    1.0 minute to load a machine

    1.0 minute to unload a machine

    6 minutes of automatic machine time

    0.5 minute to inspect and pack a finished part

    operator loads M-1, walks to M-2, loads M-2, walks to M-3, loads M-3, walks to M-1, unload M-1, load M-1,

    inspects and packs the part removed from M-1, travel

    to M-2 and so forth

    12 minutes to achieve a steady-state condition, thereafter a repeating cycle of 9 minutes in duration

    occurs

  • 27

    SCHEDULE DESIGN - Machine Assignment -

    assignment of three machines to one operator

    Machine Assignment

    The

  • 28

    SCHEDULE DESIGN - Machine Assignment

    Let a = concurrent activity time (eg loading / unloading )

    b = independent operator activity time (walking / inspecting )

    t = independent machine activity time (eg automatic machine time)

    n = ideal number of identical machines assigned an operator

    m = number of identical machines assigned an operator

    Tc = repeating cycle time

    Io = ideal operator time during a repeating cycle

    Im = ideal time for each machine during a repeating cycle

  • 29

    SCHEDULE DESIGN - Machine Assignment

    Excluding idle time, each machine cycle requires a + t minutes to complete a cycle. Likewise, the operator

    devotes a + b minutes to each machine during a cycle.

    Hence, an ideal assignment is

    n = (a + t) / ( a + b)

    From the example,

    n = (2 + 6) / (2 + 1) = 2.67

    Not possible to have 2.67 machines so assume 3 machines.

  • 30

    SCHEDULE DESIGN - Machine Assignment

    Consider what will happen if m machines are assigned

    The work content for the operator will be m(a + b) , while a machine cycle will be (a + t) in duration

    The repeating cycle will be the larger of the two and the difference in the two will be idle time.

    Tc = (a + t) if m n

    Im = 0 if m n

    Io = Tc m(a + b) if m n

  • 31

    SCHEDULE DESIGN - Machine Assignment

    If we wish to determine the cost per unit produced by an m machine assignment, use the following

    Co = cost per operator-hour

    Cm = cost per machine-hour v= Co/Cm TC(m) = cost per unit produced based on an

    assignment of m machines per operator

  • 32

    SCHEDULE DESIGN - Machine Assignment

    The cost per hour of a combination of m machines and an operator totals Co + mCm

    Assuming each machine produces one unit during a repeating cycle, the cost per unt produced during a

    repeating cycle can be determined as follows;

    TC(m) = (Co + mCm)(a + t)/m if m n

    to minimize TC(m) when m n,

    m should be made as small as possible.

  • 33

    SCHEDULE DESIGN - Machine Assignment

    To facilitate the determination, let

    F = TC(n) / TC(n + 1) = (Co + nCm)(a + t)

    n[ Co + (n + 1) Cm ] ( a + b)

    which reduces to F = v + n x n v + n + 1 n

  • 34

    SCHEDULE DESIGN - Machine Assignment If F < 1, then TC(n) < TC(n + 1) and n machines should

    be assigned

    If F > 1, then TC(n + 1) < TC(n) and n + 1 machines should be assigned

    If F = 1, then either n or n + 1 machines should be assigned.

  • 35

    FACULTY OF MECHANICAL ENGINEERING

    UNIVERSITI TEKNOLOGI MALAYSIA

    THE END


Recommended