+ All Categories
Home > Documents > Lecture 4. Lean Operations

Lecture 4. Lean Operations

Date post: 30-Sep-2015
Category:
Upload: samantha-siau
View: 231 times
Download: 0 times
Share this document with a friend
Popular Tags:
32
Slide 1 Lean Operations Lecture 4 Lean Operations MRP vs. JIT Professor Kihoon Kim BUSS211 OM
Transcript
  • Slide 1 Lean Operations

    Lecture 4

    Lean Operations MRP vs. JIT

    Professor Kihoon Kim

    BUSS211 OM

  • Slide 2 Lean Operations

    Outline

    Independent demand vs. dependent demand

    MRP (Push) vs. JIT (Pull)

    How MRP works?

    How JIT works?

    Lean Operations Tactics

  • Slide 3 Lean Operations

    Independent vs. Dependent Demand

    Independent Dependent

    1. End or finished items 1. Subassemblies,

    Components/Materials

    2. May be uniform demand 2. Lumpy demand

    3. Few items - carefully monitored 3. Many items less emphasis

  • Slide 4 Lean Operations

    Material Requirements Planning for Components

    EOQ analysis for Finished Goods

    1. For items with independent demand Deterministic demand Standard EOQ

    Probabilistic demand EOQ with safety stock

    2. Answers one question: How much is needed

    MRP for Components

    1. For inventory systems with dependent demand

    2. Answers two questions: How much & When

  • Slide 5 Lean Operations

    MRP vs. JIT

    MRP. (Materials Requirements Planning). MRP is the basic process of translating a production schedule for an end product (MPS or Master Production Schedule) to a set of requirements for all of the subassemblies and parts needed to make that item.

    JIT. Just-in-Time. Derived from the original Japanese Kanban system developed at Toyota. JIT seeks to deliver the right amount of product at the right time. The goal is to reduce WIP (work-in-process) inventories to an absolute minimum.

  • Slide 6 Lean Operations

    Push vs. Pull

    MRP is the classic push system. The MRP system computes production schedules for all levels based on forecasts of sales of end items. Once produced, subassemblies are pushed to next level whether needed or not.

    JIT is the classic pull system. The basic mechanism is that production at one level only happens when initiated by a request at the higher level. That is, units are pulled through the system by request.

  • Slide 7 Lean Operations

    Advantages of MRP and JIT

    Main Advantage of MRP over JIT: MRP takes forecasts for end product demand into account. In an environment in which substantial variation of sales are anticipated (and can be forecasted accurately), MRP has a substantial advantage.

    Main Advantage of JIT over MRP: JIT reduces inventories to a minimum. In addition to saving direct inventory carrying costs, there are substantial side benefits, such as improvement in quality and plant efficiency.

  • Slide 8 Lean Operations

    MRP Basics

    The MRP system starts with the MPS or Master Production

    Schedule. This is the forecast for the sales of the end item over

    the planning horizon. The data sources for determining the MPS

    include:

    Firm customer orders

    Forecasts of future demand by item

    Safety stock requirements

    Seasonal variations

    Internal orders from other parts of the organization.

  • Slide 9 Lean Operations

    The Explosion Calculus

    The explosion calculus is a set of rules for converting the master production schedule to a requirements schedule for all subassemblies, components, and raw materials necessary to produce the end item.

    Work backward from finished goods production schedule (assumed

    fixed)

    Each finished good has its Bill of Materials

    Each component has quantity multiplier & lead time

    There are two basic operations comprising the explosion calculus:

    Time phasing: Requirements for lower level items must be shifted backwards by the lead time required to produce the items

    Multiplication: A multiplicative factor must be applied when more than one subassembly is required for each higher level item.

    Given how much is ordered, determine when inputs are needed

    Determine when you would run out of the input given the fixed production

    schedule

  • Slide 10 Lean Operations

    Typical Product Structure Diagram (Bill of Materials)

  • Slide 11 Lean Operations 11

    Work downwards through the production hierarchy, starting

    with finished goods. For each item, carry out the following

    steps:

    1. Use projected requirements and scheduled receipts to

    calculate on-hand inventory (finished good):

    Developing a Materials Requirements Plan

    General On-Hand Inventory: tttt DSII 1

  • Slide 12 Lean Operations

    2. Look forward to find the first period in which on-hand

    inventory will be negative. Then work backward using the

    ordering/ production lead time to generate a planned order

    release. The order size is determined by lot sizing analysis. (In this example, lets assume that 70 has been chosen.)

    Developing a Materials Requirements Plan

  • Slide 13 Lean Operations

    3. Update on-hand inventory and continue generating planned

    order releases for this item to the end of the time horizon.

    (we assume that 90 and 30 have been chosen)

    Developing a Materials Requirements Plan

  • Slide 14 Lean Operations

    3. Update on-hand inventory and continue generating

    planned order releases for this item to the end of the time

    horizon. Then calculate projected requirements for items

    in the next level down in the production hierarchy.

    Developing a Materials Requirements Plan

  • Slide 15 Lean Operations 15

    ERP is an extension of the ideas of MRP. It aims to integrate all functions

    of the business, including planning, manufacturing, sales, and marketing.

    1960s Focus on traditional inventory control, single item

    1970s MRP emerges: translates Master Production Schedule into time-

    phased net requirements for sub-assemblies, components, and raw materials

    1980s Manufacturing Resources Planning (MRP II) emerges: extension

    of MRP to shop floor and distribution management activities

    1990s Enterprise Resource Planning (ERP) emerges: extension of MRP

    II to cover areas such as Engineering, Finance, Sales and Marketing, etc.

    Enterprise Resource Planning (ERP)

  • Slide 16 Lean Operations

    Closed-Loop Manufacturing Planning & Control System

    Capacity Requirements Planning

    Material Requirements Planning

    Master Production Scheduling

    Production Planning

    Revise No

    Realistic

    ?

    Execute Plans

    Yes

  • Slide 17 Lean Operations

    Introduction to JIT

    JIT (Just In Time) is an outgrowth of the Kanban system developed by Toyota.

    Kanban refers to the posting board where the evolution of the manufacturing process would be recorded.

    The Kanban system is a manual information system that relies on various types of cards.

    Direction of production flow

    upstream downstream

    Authorize production of next unit

  • Slide 19 Lean Operations

    River/Inventory Analogy

    Illustrating the Advantages of Just-in-Time

  • Slide 20 Lean Operations

    Scrap & Rework

    Missed Due Dates

    Too Much Space

    Late Deliveries

    Poor Quality

    Machine Downtime

    Engineering Change Orders

    Long queues

    Too much paperwork

    100% inspection

    Reducing waste: Increase Problem Visibility Analogy: Lower the Water to Expose the Rocks

    Inv

    ento

    ry

  • Slide 21 Lean Operations

    JIT purchasing system

    If we apply JIT to suppliers,

    Advantages:

    1. Inventory reduction

    2. Improved coordination

    3. Better relationships with vendors

    Disadvantages:

    1. Decreased opportunity for multiple sourcing

    2. Suppliers must react quickly

    3. Potential for congestion

    4. Suppliers must be reliable.

  • Slide 22 Supply Chain Management

    Lean Operations Tactics

  • Slide 23 Lean Operations

    Basic Tools towards Lean Operations

    In addition to Pull rather than push

    1. Batch-size reduction

    2. Mixed Level Production

    3. Quality at source

    4. Resource flexibility / Cross training

    5. Cellular layout

  • Slide 24 Lean Operations

    Lean Tool #1: cut batch sizes

    An illustrative example

    Remind that a small batch implies a small amount of inventory.

    Consider the following 4-step process:

    (Dont worry; well learn how to answer question below soon)

    What is the theoretical flow time of the process?

    What is the capacity of the process?

    What does that imply for the amount of inventory needed in the process?

    A

    1 min/job Resource 1

    B

    1 min/job Resource 2

    C

    1 min/job Resource 3

    D

    1 min/job Resource 4

  • Slide 25 Lean Operations

    Lean Tool #1: cut batch size ABCD example continued

    Batch Shop (Batchsize=4)

    A B C D

    0

    Ela

    pse

    d T

    ime

    2

    1

    4

    3

    2

    1

    4

    3

    2

    1

    4

    3

    2

    1

    4

    3

    T

    T = I = R =

    Flow Shop (Batchsize = 1)

    A B C D

    0

    Ela

    pse

    d T

    ime

    T

    1

    1

    1

    1

    T = I = R =

    2

    1

    4

    3

    2

    1

    4

    3

    2

    1

    4

    3

    2

    1

    4

    3

    2

    1

    4

    3

    2

    1

    4

    3

    2

    1

    4

    3

    2

    1

    4

    3

    2

    1

    4

    3

    2

    1

    4

    3

    2

    1

    4

    3

    2

    1

    4

    3

    2

    2

    2

    2

    3

    3

    3

    3

    4

    4

    4

    4

    1

    1

    1

    1

    2

    2

    2

    2

    3

    3

    3

    3

    4

    4

    4

    4

    1

    1

    1

    1

    2

    2

    2

    2

    3

    3

    3

    3

    4

    4

    4

    4

    1

    1

    1

    1

    2

    2

    2

    3

    3 4

    4

    4

    4

    3

    3

    2

  • Slide 26 Lean Operations

    How to run Lean Operations:

    Managing Variety

    Monthly Production Requirement:

    How should production be scheduled for the month?

    Model Sedan Station Wagon

    Quantity 10,000 10,000

  • Slide 27 Lean Operations

    Lean Tool #2: Mixed Level/Balanced Production

    Batch Production Schedule Mixed Production Schedule

    (AAAABBBB..) (ABAB...)

    Product April 1.................15...........................30 April 1....................15.......................30

    A

    B

    time

    FGI

    time

    FGI

  • Slide 28 Lean Operations

    Lean Tool #3: Quality at the Source

    Defects Found at:

    Own Station Next Station End of Line Final Inspection

    End Users Hand

    $ $ $ $ $

    Impact to the Company

    Very Minor

    Minor Delay

    Rework Resched.

    of work

    Significant Rework

    Delay in Delivery

    Additional Inspection

    Warranty costs

    Adminis tra tive costs

    Reputation Loss of

    Market Share

  • Slide 29 Lean Operations

    Lean Tool #4: Flexible Resources

    Cross training of workforce

    Use of IT in services

    Under JIT, if a problem occurs,

    the line stops; all the workers involved in the problem join the discussion to

    find out why the problem has occurred.

  • Slide 30 Lean Operations

    Lean Tool #5 to reducing waste:

    From Functional Layout to Product Cell organization

    Production Control

    Roof Cut

    Base Cut

    FA Base Assy

    Production Control

    Production Control

    Production Control

    Roof Cut

    Roof Cut

    Roof Cut

    Base Cut

    Base Cut

    Base Cut

    Base Assy

    Base Assy

    Base Assy

    FA FA FA

    Department 1

    Department 2 Department 3

    Department 5 Department 4

    Cell 1

    Production Control

    Roof Cut

    Base Cut

    FA Base Assy

    Cell 3

    Production Control

    Roof Cut

    Base Cut

    FA Base Assy

    Cell 2

    High utilization of critical resources A cell focuses on a narrow range of customer needs

  • Slide 31 Lean Operations

    Pros and Cons of Cellular Layouts

    Pros of cells:

    Synchronization of information and material flows

    Less travel distances

    more visibility within the cell

    cross-trained workforces.

    Cons of cells:

    may require additional capital

    risk of machine break-downs

    Idle time may increase for some cells

  • Slide 32 Lean Operations

    Teams in Cells and Lean Ops:

    Human Resources issues

    Advantages

    Consistent with the moral ideal of autonomy.

    Empowers the workforce through participation and autonomy in managing daily activities

    Gives unprecedented responsibility to workers:

    Immediate and impartial feedback of problems

    Investigation of process improvements

    Monitoring quality

    They also gain better understanding of the process

    Challenges:

    Team dynamics: incentives, team pressure,

    From monthly 30-day goals before to 3-minute goals now

    Does not leave much room for variability

  • Slide 33 Lean Operations

    Key Takeaways: Lean Operations

    MRP vs. JIT

    MRP is a Push system; works well even when the demand variation is high

    JIT is a Pull system; reduce inventory visibility increases, flow time

    decreases

    Lean Operations: In Search for the Holy Grail and zero Waste

    Efficient Workflow: Cellular Layout

    Level Mixed Production: Heijunka

    Reduced batch sizes

    Pull Execution: Kanbans

    Quality at source: Jidoka

    Continuous Improvement: Kaizen

    Flow Synchronization

    Low Cost

    Get ever closer to ideal


Recommended