Date post: | 03-Feb-2016 |
Category: |
Documents |
Upload: | chudhry-waqas-uddin |
View: | 221 times |
Download: | 0 times |
PROJECT MANAGEMENT
Muhammad ShakeelPMP (PMI)
MS IEM (PU) MS IT (PIMSAT)BE (Av) (NED)
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
2
WHAT IS SCOPE? A project is a sequence of -----4----, complex and ------
5---------------- having one ----3---- or purpose that must be completed by a ------1------------, wthin -----6------------- and according to ----2------------.1-specific time 2-specifications 3-goal4-unique 5-connected activities 6-budget
Project scope –The work that must be done in order to deliver a product with the specified features and functions.
Project Scope Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
Project Scope Management is primarily concerned with defining and controlling what is and is not included in the project.
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
3
VERIFY SCOPE INPUT
PROJECT MANAGEMENT PLAN REQUIREMENTS DOCUMENTATION REQUIREMENTS TRACEABILITY MATRIX VALIDATED DELIVERABLES
TOOLS AND TECHNIQUES INSPECTION (Includes activities such as measuring,
examining and verifying to determine whether work & deliverables meet requirement and product requirement criteria. Also called: review, product reviews, audits & walkthroughs)
OUTPUTS ACCEPTED DELIVERABLES
The ones that meet the acceptance criteria are formally signed off and approved.
CHANGE REQUESTS (the once not meet acceptance run through project integrated change control process)
PROJECT DOCUMENT UPDATES
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
4
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
5
CONTROL SCOPE Control Scope is the process of monitoring the status
of the project and product scope and managing changes to the scope baseline.
Controlling the project scope ensures all requested changes and recommended corrective or preventive actions are processes through the Perform Integrated Change Control process
Uncontrolled changes are often referred as Project Scope Creep.
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
6
CONTROL SCOPE INPUT
PROJECT MANAGEMENT PLAN Scope base line is compared to actual Scope management plan describes how to manage and
control scope Change management plan Configuration management plan (those items that require
formal change control) Requirement measurement plan
WORK PERFORMANCE INFORMATION Information about project process
REQUIREMENTS DOCUMENTATION REQUIEMENT TRACEABILITY MATRIX ORGANIZATIONAL PROCESS ASSETS
Existing formal & informal scope control related policies, procedures and guidelines
Reporting and monitoring methods to be used
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
7
CONTROL SCOPE TOOLS AND TECHNIQUES
VARIANCE ANALYSIS: assess the magnitude of variation from original scope baseline.
OUTPUTS WORK PERFORMANCE MEASUREMENTS (Planned vs
Original) ORGANIZATIONAL PROCESS ASSETS UPDATES
(causes of variance, corrective measures, lesson learned)
CHANGE REQUESTS to the scope baseline or other components of project management plan
PROJECT MANAGEMENT PLAN UPDATES Scope baseline cost baseline and schedule
baselines update, PROJECT DOCUMENT UPDATES
Requirements documentation Requirement traceability matrix
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
8
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
9
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
10
PROJECT TIME MANAGEMENTThird Knowledge Area of PMBOK
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
12
PROJECT TIME MANAGEMENT PROCESSESPROJECT TIME MANAGEMENT INCLUDES THE PROCESSES REQUIRED TO ACCOMPLISH TIMELY COMPLETION OF THE PROJECT.
• Define Activities• Sequence Activities• Estimated Activities Resources• Estimated Activity Durations• Develop Schedule• Control Schedule
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
13
DEFINE ACTIVITIES
• Input:– Scope baseline (Create WBS)– Enterprise Environment factors– Organizational Process Assets (Archive + Existing activity
planning related policies; lessons learnt)• Tools & Techniques:
– Decomposition (PWP to activities to produce WP Deliverables)– Rolling wave planning (Progressive Elaboration Planning)– Templates (A standard activity list from previous project)– Expert Judgment (Project Team Members & or other experts)
• Outputs:– Activity List (All scheduled activities required on the project)– Activities Attributes * next screen showing attributes– Milestone List (Significant point or event in a project)
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
14
ACTIVITY ATTRIBUTES
WBS ID Activity ID Activity Name Activity Description Predecessor Activities Successor Activities Logical Relationship Leads and Lags Resource requirements Imposed Dates, Constraints Assumptions Person responsible for work execution Geographic Area
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
15
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
16
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
17
SEQUENCE ACTIVITIES• Sequence activities is the process of identifying and
documenting relationship among project activities.• Input:
– Activity List– Activities Attributes– Milestone List (a significant point or event in the project)– Project Scope Statement– Organizational Process Assets
• Tools & Techniques:– PDM (Precedence Diagramming Method)– Dependency Determination– Schedule Network Templates– Applying Leads & Lags
• Outputs– Project Schedule Network Diagrams– Project Document Updates
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
18
SEQUENCE ACTIVITIESTOOTS & TECHNIQUES
Precedence Diagramming Method: Finish to Start (FS) Finish to finish (FF) Start to Start (SS) Start-to-finish (SF)Finish to start is the most commonly used type of
precedence relationship. The start-to-finish relationship is most rarely used but is included to complete list of the PDM relationship types
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
19
PDM EXAMPLESFS: The initiation of the successor activity depends upon the completion of the predecessor activity
“Connect Mains (Electricity)” can only start once “Install Wiring” has completed.
SF The completion of the successor activity depends upon the start of the predecessor activity
The first security guard shift (successor) cannot finish until the second security guard shift (predecessor) starts
SS:Task (B) cannot start until task (A) starts.
"Level concrete" can't begin until "Pour foundation" begins
FF:Task (B) cannot finish until task (A) finishes.
"Inspect electrical" can't finish until "Add wiring" finishes
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
20
SEQUENCE ACTIVITIESTOOTS & TECHNIQUES
• Dependency Determination– Mandatory Dependencies: Also referred as hard logic– Discretionary Dependencies: Also called as preferred logic,
preferential logic or soft logic– External Dependencies: It involves a relationship between
project activities and non-project activities. These dependencies are usually outside the project team controls.
• Applying Leads and Lags– A lead allows an acceleration of the successor activity– A lag directs a delay in the successor activities. – Example: A technical editing team can begin editing the draft
of a large document 15 days after they began writing it. SS with 15 day lag.
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
21
SEQUENCE ACTIVITIESTOOLS & TECHNIQUES
Schedule Network Templates Standardized schedule network diagram
templates can be used to expedite the preparation of network of project activities. They can include an entire project or only a portion of it. Portions of a project schedule network diagram are often referred to as a sub network or fragment network. Sub network templates are especially useful when a project includes several identical or nearly identical deliverables, such as floors on a high rise office building.
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
22
SEQUENCE ACTIVITIES
Outputs: Project Schedule Network Diagrams:
Project Schedule Network Diagrams. It can be drawn manually or through project management software. It can include full project details or have one or more summary activities.
Project Document Updates Project documents that may be updated include:
Activity list Activity attributes
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
23
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
24
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
25
NOTATIONS FOR PDM Activity on Node
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
26
NOTATIONS FOR PDM Activity on Node
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
27
NOTATIONS FOR PDM Activity on Arrow
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
28
Activity on ArrowNOTATIONS FOR PDM
Earliest Start
Activity Duration
Activity Number/ description Earliest Finish
Latest Start Latest Finish
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
29
ASSIGNMENT # 2 DRAW A NETWORK DIAGRAMActivity Precedence
DurationA - 3B A 15C - 5D C 20E A 5F A 1G F 25H G 10I H,K 3J B 5K J 10L B 1M L 10N E,D 10O M,I,N 10
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
30
ESTIMATE ACTIVITY RESOURCES6.3
Estimate activity Resources is the process of estimating the type and the quantities of material, people, equipment or supplies required to perform each activity. The estimate activity resource process is closely coordinated with the estimate cost process.
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
31
ESTIMATE ACTIVITY RESOURCES• Inputs:
– Activity List– Activity Attributes– Resource Calendar specify when and how long identified project resources
(people, equipment & Material) will be available during the project.– Enterprise environmental factors (Resource availability & Skills)– Organizational Process Assets (Policies & Procedures for staffing, supplies
and equipment plus previous experience on similar projects)• Tools & Techniques
– Expert Judgment– Alternative Analysis (Make or buy, Machinery & Tools)– Published estimating data (production rates & unit costs of resources)– Bottom-up estimating (when activity cannot be estimated with confidence)– Project Management Software (Plan, organize, manage resource pools and
develop resource estimates.• Outputs
– Activity resource requirements– Resource breakdown structure– Project document updates (activity List, Activity attributes & Resource
calendar)
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
32
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
33
ESTIMATE ACTIVITY DURATION6.4
• Estimate activity duration is the process of approximating the number of work periods needed to complete individual activities with estimated resources.
• Input:– Activity List– Activity Attributes– Activity Resource Requirement (6.3.3.1)– Resource Calendars (6.3.1.3)– Project Scope Statement (5.2.3.1)– Enterprise environmental factors (Databases and Ref. data, Productivity
metrics & published commercial information– Organizational Process Assets -Historical, Project Calendar, Scheduling
methodology, Lessons Learnt
• Tools & Techniques– Expert Judgment– Analogous estimating (Duration, budget, size, weight & Complexity from a
previous project)– Parametric estimating (square footage – cost budget & duration)– Three-point estimates (PERT) Most likely, Optimistic, Pessimistic– Reserve analysis (Cater for schedule uncertainty)
• Outputs– Activity duration estimates (@ weeks +- 2 days etc)– Project document updates (activity attributes, assumptions made in
developing the activity duration)
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
34
ACTIVITY DURATION ESTIMATES
Activity duration estimates are quantitative assessments of the likely number of work periods that will be required to complete a schedule activity. Activity duration estimates include some indication of the range of possible results. For example:
•2 weeks ±2 days to indicate that the schedule activity will take at least eight days and no more than twelve (assuming a five-day workweek).
•15 percent probability of exceeding three weeks to indicate a high probability—85 percent—that the schedule activity will take three weeks or less.
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
35
ANALOGOUS ESTIMATING
It uses parameters such as duration, budget, size, weight and complexity from a previous and similar project as the basis for estimating the same parameters or measures of a future project.
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
36
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
37
DEVELOP SCHEDULE 6.5• Develop Schedule is the process of analyzing activity sequence, duration,
resource requirements and constraints to create project schedules• Input
– Activity List (6.1.3.1)– Activity Attributes (6.1.3.2)– Project Schedule Network Diagrams (6.2.3.1)– Activity Resource Requirements (6.3.3.1)– Resource Calendars (6.3.1.3)– Activity duration estimates (6.4.3.1)– Project Scope Statement (5.2.3.1)– Enterprise environment factors– Organizational process assets
• Tools & Techniques– Schedule network analysis– Critical path method– Critical chain method– Resource Leveling– What-if scenario analysis– Applying leads and lags– Schedule compression– Scheduling tool
• Output– Project Schedules (milestone chart, bar charts, project schedule network diagrams)– Schedule baseline Component of project management plan with baseline start &
finish dates.– Schedule Data (resource requirement by time period in resource histogram best &
worst case– Project document updates (Activity resource requirements, activity attributes,
calendar, risk register)
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
38
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
39
SCHEDULE COMPRESSION
Crashing. Schedule compression technique in which cost and schedule tradeoffs are analyzed to determine how to obtain the greatest amount of compression for the least incremental cost. Crashing does not always produce a viable alternative and can result in increased cost.
Fast tracking. A schedule compression technique in which phases or activities that normally would be done in sequence are performed in parallel. An example would be to construct the foundation for a building before all the architectural drawings are complete. Fast tracking can result in rework and increased risk. This approach can require work to be performed without completed detailed information, such as engineering drawings. It results in trading cost for time, and increases the risk of achieving the shortened project schedule.
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
40
CRASHING PROJECTS Causes:
Initial schedule may be too optimistic Market needs change and the project is in
demand earlier than anticipated The project has considerably slipped
behind the schedule The contractual situation provides more
incentives to avoid schedule slippage
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
41
CALCULATING THE COST OF CRASHING
slope= crash cost – normal cost normal time – crash timeActivity Duratio
nCost C.
Duration
C. Cost
A 5 1000 3 1500
B 7 700 6 1000
C 3 2500 2 4000
D 5 1500 5 1500
E 9 3750 6 9000
F 4 1600 3 2500
G 6 2400 4 3000
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
42
CRITICAL PATH & CRITICAL CHAIN Critical Path: calculates the theoretical
early start and finish dates for all activities, irrespective of resource any resource limitations by performing forward and backward pass analysis through the schedule network.
Critical chain: is a schedule network analysis technique that modifies the project schedule to account for limited resources. The resource constraint critical path is known as critical chain.
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
43
CONTROL SCHEDULE6.6• It is the process of monitoring the status of the
project progress and manage changes to the schedule baseline.
• It is concerned with– Determine the current status of the project schedule– Influencing the factors that create schedule changes– Determining that the project schedule has changed– Managing the actual changes as they occur
• Input:– Project management Plan (4.2.3.1)– Project Schedule – Work Performance Information– Organizational Process Assets
• Existing formal and informal schedule control related policies, procedures & Guidelines
• Schedule control tools• Reporting and monitoring methods to be used
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
44
CONTROL SCHEDULE6.6 Tools & Techniques:
Performance review Measures, compares, and analyzes schedule
performance such as actual start and finish dates, percent complete and remaining duration of work in progress.
Also reviews if corrective action is required Variance Analysis:
Schedule performance measurements are used to assess the magnitude of variation to the original schedule baseline.
Project Management Software It provides the ability to track planned dates versus
actual dates and to forecast the effects of changes to the project schedule.
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
45
CONTROL SCHEDULE6.6
Resource Leveling To optimize the distribution of work among resources
Resource Smoothing. A technique that adjusts the activities of a schedule model
such that the requirements for resources on the project do not exceed certain predefined resource limits.
In resource smoothing, as opposed to resource leveling, the project’s critical path is not changed and the completion date may not be delayed
In other words, activities may only be delayed within their free and total float.
Thus resource smoothing may not be able to optimize all resources.
Schedule Compression (6.5.2.7)
Scheduling Tool Data is updated and compiled into the schedule to reflect
actual progress of the project and remaining work to be completed.
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
46
CONTROL SCHEDULE
• Outputs– Work performance measurements– Organizational Process Assets Updates– Change Request– Project management plan updates
• Schedule Baseline• Schedule management plan• Cost baseline
– Project Document Updates• Schedule data• Project Schedule
Saturday, April 22, 2023Project Management By:- Muhammad Shakeel
47