AABC Commissioning GroupAIA Provider Number: 50111116
LED Lighting: Technology Selection and System CommissioningCourse Number: CXENERGY1519
Michael Chow, P.E., CxA, LEED AP BD+C, Metro CD Engineering April 29, 2015
Credit(s) earned on completion of this course will be reported to AIA CES for AIA members. Certificates of Completion for both AIA members and non-AIA members are available upon request.
This course is registered with AIA CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner ofhandling, using, distributing, or dealing in any material or product.___________________________________________Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.
This presentation is protected by US and International Copyright laws. Reproduction, distribution, display and use of the presentation without written
permission of the speaker is prohibited.
© Metro CD Engineering, LLC 2015
Copyright Materials
This session will discuss the pros and cons of the different types of LED lighting, as well as information about commissioning different types of systems and technologies, including lighting controls.
SAMPLE SLIDE
CourseDescription
LearningObjectives
1. Learn about the various types of LED lighting technology and how to select the best product for your application.
2. Understand the unique system commissioning requirements for various types of LED lighting.
3. Learn about the necessary control systems associated with various types of LED lighting.
4. Understand the ongoing commissioning requirements for LED lighting systems over the lifetime of a building.
At the end of the this course, participants will be able to:
LED Overview
1. Efficacy (Lumens Per Watt):a. 35 LPW: 2007b. 100 LPW: 2014c. Future 100+ LPW
2. No Mercury = non-hazardous for disposal or breakage.
3. Long life. Typically 25,000 to 50,000+ hours.
4. Works well at low temperatures.a. Fluorescents do not work well at low temps.
LED Overview
5. No issues with frequently on/off cycles.a. Fluorescent lamp life will be shortened due to frequent
cycling (instant start ballasts).
6. Instant on.a. Great for replacing HID lamps.
7. Minimal UV and IR in illumination path.
8. Directional – eliminates reflectors.
9. L70 is when LED reaches 70% of its rated output.a. LEDs’ light output fades over time.
Various types of LED lighting technology
1. Screw-in LED lamps
2. Integral LED light sources
3. Retrofits
Screw-in LED Lamps
1. LED are directional; CFLs and halogen lamps are omnidirectional.a. Check light distribution.
2. Efficacy: 60-70 LPW.
Images Courtesy of DOE
Screw-in LED Lamps
3. Lower life due to driver and LEDs in relative close proximity to each other.a. Screw-in LEDs: 25,000 hours compared to 50,000+ hours for
integral LED fixtures.
4. Screw-in LEDs should not be used in totally enclosed fixtures unless rated for this application.a. Allow for heat dissipation from the heat sink.
5. Dimming: verify if compatible with dimmers.
Integral LED Light Sources
1. Longest life: 50,000+ hours.
2. Efficacy: 70 to 100+ lumens/watt.
3. Typical Dimming: 0-10 Volts.a. Verify dimmer is compatible.
Retrofit Tubular LEDs
1. Directional and not omnidirectional (fluorescent lamps are omnidirectional)
2. Life: 30,000+ hours (Source: DOE, March 2014).
3. Efficacy: 80-100+ lumens/watt (Source: DOE, March 2014).
4. Lumen output: about 2,000 lumens (T8 fluorescent lamp is about 3,000 lumens). Source: DOE, March 2014.a. Should sample tubular LED in retrofit application to
ensure light distribution is adequate (e.g., fixtures with parabolic louvers and lenses).
5. Dimming: Verify dimmer is compatible.
Retrofit LED Troffers
1. Usually where a fluorescent troffer’shousing is kept and the ballast is replaced with adriver that powers LEDs.a. Known as “LED Luminaire Conversion Retrofit Kits” by UL.
i. Required to be labeled.ii. DOE study found 50% of sampled retrofit kits would not
meet the UL Listing requirements (labeling issues, poor mounting, etc.)
2. Life: 50,000+ hours.
3. Efficacy: 85-100+ lumens/watt.
4. Dimming: Verify dimmer is compatible.
Unique System Commissioning Requirements
1. Design, Shop Drawing Reviewa. Look for IES LM-79, LM-80 and TM-21.b. Dimmer compatibility (more on this later).
2. UL Retrofit Label for retrofits (see Retrofit LED Tubes slide).
3. Functional testing a. Required by ASHRAE 90.1-2010.b. IES-DG-29, The Commissioning Process Applied to Lighting
and Control Systems
Unique System Commissioning Requirements
4. Verify distribution (Type) for exterior lighting fixtures.
Unique System Commissioning Requirements
5. In-rush Currenta. Example: dimming with 0-10 Volt DC control at 120 Volts
equates to LED and its driver to draw 0.4 Amps.i. In-rush current is 40 Amps – 100 times the normal
steady state operating current.ii. This may trip a circuit breaker depending upon the circuit
breaker type.iii. May need an in-rush current limiting device and “pairing”
of the LED/driver and the dimmer.
Unique System Commissioning Requirements
6. Harmonicsa. Dimming chops up the sine wave of current.
i. May cause excessive neutral current and may impose a fire hazard.
b. Harmonics lower the power factor (pf) of the circuiti. A pf below 95 for a building may result in a utility penalty
charge.ii. May need to add a capacitive filter in the circuit to
minimize the THD (Total Harmonic Distortion)iii. Important to match/pair LEDs, drivers and dimmers to
avoid these issues.
Control of LEDs
1. Dimminga. Re-use of incandescent dimmers: May need to meet
minimum wattage (typically 25 to 40 Watts).b. Consider min/max number of LED sources per control.c. Neutral conductor required (with 2011 NEC).d. 0-10V, DMX, DALI, Wireless.
2. Occupancy/Vacancy Sensorsa. LEDs: no ill effects from frequent cycling…use a shorter time
delay? Standard of 20 minutes was developed to help prolong fluorescent lamp life.
3. Daylight Harvesting
Understand the ongoing commissioning requirements for LED lighting systems over the lifetime of a building
1. L701. Recall that LEDs’ light output fades over time and don’t burn
out.2. Lumen maintenance is a prediction of the number of hours an LED
will operate before it fades below a useful level of intensity. L70 = 70% of initial lumen output.
2. Daylight harvestinga. Commissioning tip sheet:
http://www.ecw.org/sites/default/files/daylightcontrolstipsheet.pdf
b. Recalibration of sensors (locate so they are readily accessible)
Understand the ongoing commissioning requirements for LED lighting systems over the lifetime of a building
3. LEDs are not maintenance free
LearningObjectives
1. Learned about the various types of LED lighting technology and how to select the best product for your application.
2. Understand the unique system commissioning requirements for various types of LED lighting.
3. Learned about the necessary control systems associated with various types of LED lighting.
4. Understand the ongoing commissioning requirements for LED lighting systems over the lifetime of a building.
Recap:
This concludes The American Institute of Architects Continuing Education Systems Course
Contact Information:
Michael Chow, P.E., CxA, LEED AP BD+C
Phone: (614) 923-3930
E-mail: [email protected]