Date post: | 22-Nov-2015 |
Category: |
Documents |
Upload: | amirriyyah |
View: | 63 times |
Download: | 1 times |
[Suit No. 22-119-2011]
1
MALAYSIA 1
IN THE HIGH COURT OF SABAH AND SARAWAK 2
AT KUCHING 3
SUIT NO. KCH-22-119-2011 4
BETWEEN 5
6
GOLDEN ANTS DYNASTY SDN BHD PLAINTIFF 7
(Company No. 740215-T) 8
No. 205, 1st Floor 9
Green Ville Park Shophouse 10
Jalan Batu Kitang 11
93250 Kuching 12 13
AND 14
15
NAIM CENDERA SDN BHD DEFENDANT 16
(Company No. 261213-T) 17
9th Floor, Wisma Naim 18
2 Jalan Rock 19
93200 Kuching Sarawak 20
GROUNDS OF DECISION 21
1. In this action the Plaintiff claims against the Defendant for the 22
following: 23
a. The sum of RM959,282.28 being the additional cost 24
incurred by the Plaintiff for the additional work; 25
b. Alternatively, the sum of RM959,282.28 for additional 26
work carried out on a quantum meruit basis. 27
c. Further and/or alternatively, damages for breach of 28
contract to be assessed by the Honourable Court; 29
[Suit No. 22-119-2011]
2
d. Interest on all sums payable under prayers (a), (b) and (c) 1
hereof at 8% per annum from the date of practical 2
completion of the works, namely 29th May 2008, till the 3
date of final payment; 4
e. Such further and other relief as the Honourable Court may 5
deem just; and 6
f. Costs. 7
The Plaintiffs Case 8
2. By a Letter of Award dated 16th November, 2007 ["LOA"] 9
issued by Naim Cendera Holding Bhd, the Plaintiff was 10
appointed as the contractor for the Defendant to carry out site 11
clearance and earthworks for the proposed affordable housing 12
development project on Lot 4710, Block 14, Salak Land 13
District, Kuching, Sarawak [Package A] ["the Work"] for the 14
sum of RM3,383,580.00 ["the Contract Sum"]. 15
3. Naim Cendera Holding Bhd. is the Holding company which 16
had appointed its subsidiary/associate company, the Defendant, 17
to enter into the contract with the Plaintiff, which the Plaintiff 18
agreed. 19
4. Due to the urgency of the Work, the Defendant gave the 20
Plaintiff only one day to prepare and submit their quotation for 21
the Work. Neither the Plaintiff nor the Defendant had carried 22
out actual survey work on the site. The Plaintiff relied on the 23
topographical survey of the site, which the Defendant supplied 24
to them, to prepare the quotation. 25
[Suit No. 22-119-2011]
3
5. During the price negotiation stage of the tender, the Plaintiff 1
requested for 35% - 40% settlement and compaction of the 2
earth fill, as the site was situated on a swampy land. The 3
Defendant, relying on the settlement data of 8% - 9% of the 4
adjoining Package C of the project, allowed the Plaintiff only 5
15% settlement and compaction. The Plaintiff finally accepted 6
15% settlement and compaction on the clear understanding that 7
they would be paid by the Defendant for any additional volume 8
of earth in excess of 380,000 cubic meters. 9
6. Due to the urgency of the Work, the Defendant handed the site 10
over to the Plaintiff and requested the Plaintiff to commence 11
the execution of the Work immediately and the Plaintiff 12
immediately commenced execution of the Work on 26th 13
October 2007, even before the issuance of the LOA. In the 14
LOA issued on 16th November 2007, it stated the official site 15
handing over was 26th November 2007. 16
7. In the course of execution of the Work, the Plaintiff discovered 17
that the volume of earth required for the earthfill work 18
exceeded the agreed volume of 380,000 cubic meter under the 19
Contract and additional work had to be carried out to transport 20
the excess volume of earth ["additional work"]. The Plaintiff 21
informed the Defendants then Project Manager, Encik Abdul 22
Razak Ahmad Marzuki, on several occasions that the Plaintiff 23
would be applying for variation of the additional work. The 24
Project Manager instructed the Plaintiff to continue with the 25
earthfill work and informed the Plaintiff that their application 26
for variation works would be considered upon practical 27
completion of Work. 28
[Suit No. 22-119-2011]
4
8. The Work was duly completed on 28th May, 2008 and handed 1
over to the Defendant on 29th May, 2008. The Defects 2
Liability period of the Work ended on 29th November, 2008. 3
9. On 29th May, 2008 and 26th November, 2008, the Plaintiff 4
submitted to the Defendant their claim for variation on the 5
additional work. There was no decision by the Defendant 6
although several meetings were held between the Plaintiff and 7
the Defendant. 8
10. On 31st October, 2009, the Defendant informed the Plaintiff 9
that their application for additional Work has not been 10
approved by the Defendants management. 11
11. The Plaintiff claimed by way of alternative, that the additional 12
work was carried out with the full knowledge of the Defendant 13
and was duly accepted by the Defendant without any protest or 14
reservation whatsoever. As a result the Plaintiff claimed the 15
sum of RM959,282.28 being the reasonable remuneration for 16
the additional work carried out on a quantum meruit basis. 17
12. Hence, the claim by the Plaintiff. 18
The Defendants Defence 19
13. The Defendant denied there was urgency of Work and 20
additional work. 21
14. The Defendant averred that under the Preliminary and 22
Generally attached to the Plaintiffs letter dated 23rd October 23
2007 that the contract is based on a fixed price lump sum 24
tender. 25
[Suit No. 22-119-2011]
5
15. It is provided under the Special Instruction to the Tenderer 1
dated 24th October 2007 that the Plaintiff is to take note that all 2
levels as shown on the drawings are for information only and 3
shall not be taken to represent the true ground levels of the site. 4
It is the responsibility of the Plaintiff to ascertain the existing 5
ground levels at their own expenses for the purpose of 6
computing their earthworks quantity and no claim shall be 7
entertained if the actual ground levels are higher or lower than 8
the levels indicated on the drawings. 9
16. It is agreed between the Plaintiff and the Defendant that 10
immediately after taking possession of the site and before 11
commencing any work, the Plaintiff shall check the actual 12
levels and dimension against those shown on the drawing and 13
immediately inform the Engineer in the event of any alleged 14
discrepancy. If no communication has reached the Engineer, 15
the Contractor shall be held to accept all levels and dimension 16
and no claim for extra payment in this connection will be 17
entertained. 18
17. It is understood between the Plaintiff and the Defendant that 19
the Plaintiff is only entitled to claim for the sum contracted and 20
shall not be entitled to any further sum for any additional work. 21
The Defendant, its agent and/or employee and/or representative 22
never led the Plaintiff into believing that the Plaintiff will be 23
paid for any additional work done. 24
Bundles of Documents 25
18. At the trial, the following Bundle of Documents have been 26
filed by the Parties: 27
[Suit No. 22-119-2011]
6
a. Bundle of Agreed Documents marked exhibit BAD 1
[agreed only as to authenticity only]; 2
b. Disputed Bundle of Documents marked as DBD; 3
c. Plaintiffs Supplementary Bundle of Documents Volume 1 4
to 5 marked as PSBOD Vol. 1 to Vol. 5. 5
d. Statement of Agreed Fact marked as SAF. 6
Agreed Facts 7
19. Below are the agreed facts as per the Statement of Agreed Fact 8
marked SAF: 9
STATEMENT OF AGREED FACTS 10
THE CONTRACT 11
1. Under and by virtue of award NCSB/SPNB/GADSB/2007-12
0863 dated 16th November, 2007 (for brevity, the LOA), 13
the Plaintiff was the contractor of the Defendant in respect of 14
the execution and completion of the proposed site clearance 15
and earthworks for the proposed affordable housing 16
development on Lot 4710, Block 14, Salak Land District, 17
Kuching, Sarawak (Package A) (for brevity, the Contract 18
Sum). 19
2. The LOA was issued by Naim Cendera Holdings Bhd., who 20
appointed its subsidiary or associate company, the Defendant, 21
to enter into the contract with the Plaintiff, which the 22
Plaintiff agreed. 23
3. Paragraph 2 of the LOA provides that the mode of payment 24
(of the Contract Sum) shall be RM3,146,729.40 in cash 25
through monthly progress payment and the balance of 26
RM236,850.60 to be set off against your (the Plaintiffs) 27
purchase of properties undertaken by Desa Ilmu Sdn. Bhd. at 28
Kota Samarahan. 29
[Suit No. 22-119-2011]
7
4. Paragraph 3 of the LOA provides as follows:- 1
You will be required to execute in due course a Formal 2
Contract Agreement. However, until the Formal Contract 3
Agreement is executed, your quotation together with this 4
Letter of Acceptance and the following letter and discussion 5
shall constitute a binding contract between Golden Ants 6
Dynasty Sdn. Bhd. and Naim Cendera Sdn. Bhd. The 7
contract number for this Contract is NC/SPNB/ST/C05/2007. 8
(a) Your quotation ref. no. QUO/NAIM/1007-01 dated 23rd 9
October, 2007. 10
(b) Your scope of works shall consist of extracting of earth 11
filling material at Naim Ready Mix Sdn. Bhd. borrow 12
pit and to transport imported earth filling including 13
filling up to the required level and well compacted all 14
to specification. 15
(c) You are to carry out the works all in accordance to 16
drawings and specification (attached). 17
(d) To maintain the finished proposed platform level as 18
stated above for an additional three (3) months after 19
completion of works with Licensed Surveyors 20
endorsement. 21
5. Paragraph 8 of the LOA provides as follows:- 22
8. The time for completion of the project shall be 2 23
Months after the date of official commencement date 24
which shall be on 26th November, 2007 and shall be 25
completed on 25th January, 2008. Failure to complete 26
the whole works by or before the Date for Completion 27
or within any extended time fixed under Clause 23.0 or 28
sub-clause 32.1(iii), we reserve the right to impose 29
Liquidated and Ascertained Damages (LAD) at the rate 30
of 0.0262% of the Contract Sum or Malaysian Ringgit: 31
[Suit No. 22-119-2011]
8
Eight Hundred Eight Six and Cents Fifty Only 1
(RM886.50) per calendar day. 2
6. No formal Contract Agreement had been executed between 3
the parties. 4
EXECUTION OF THE WORKS 5
7. On 26th October, 2007, the Defendant handed over the site to 6
the Plaintiff and the Plaintiff immediately commenced the 7
execution of the Works, before the issuance of the LOA on 8
16th November, 2007, and the official commencement date of 9
26th November, 2007, stated in the LOA. 10
8. The Plaintiff duly completed the Works in accordance with 11
the terms of the Contract on 29th May, 2008, as certified in 12
the Defendants Certificate of Practical Completion dated 13
28th July, 2008. 14
9. The Plaintiff duly handed over the completed Works to the 15
Defendant immediately after 29th May, 2008, and the 16
Defendant accepted the handover subject to the Plaintiff 17
making good minor defects to the Works. 18
10. The Defects Liability Period of the Works ended on 28th 19
November, 2008, as certified in the Defendants Certificate of 20
Making Good Defects dated 13th February, 2009. 21
EXTENSION OF TIME 22
11. On 7th January, 2008, the Plaintiff, vide their letter 23
REQ/NAIM/0108-01 of idem date, applied to the Defendant 24
for extension of time (for brevity, EOT) of two months to 25
complete the Works on the ground of inclement weather. 26
12. On 1st February, 2008, the Defendant, vide their letter 27
NCSB/SPNB/GADSB/2008-1108 of idem date, granted the 28
Plaintiff EOT of two months till 25th March, 2008, to 29
complete the Works. 30
[Suit No. 22-119-2011]
9
13. The Plaintiff subsequently encountered further delay of 63 1
days to complete the Works owing to inclement weather and 2
other circumstances beyond their control. The Defendant 3
proceeded to impose on the Plaintiff liquidated and 4
ascertained damages (for brevity, LAD) at the rate of 5
RM886.50 per day for 63 days amounting to the sum of 6
RM55,849.50. 7
14. On 15th April, 2009, the Plaintiff, vide their letter, 8
REQ/NAIM/WLAD/0409-01 of idem date, applied to the 9
Defendant for waiver of the LAD of RM55,849.50. 10
15. On 31st October, 2009, the Defendant, vide their letter 11
NCSB/SPNB/GoldenAnts-ST/2009-2430 of idem date, 12
approved the waiver of the LAD of RM55,849.50. 13
16. On 14th November, 2009, the Defendant issued Payment 14
Certificate No. 10 (Final LAD Waiver) certifying the refund 15
of the amount of RM55,849.50 representing the waiver of the 16
LAD. 17
ADDITIONAL WORKS 18
17. The contract sum for the Works agreed between the parties 19
was the sum of RM3,383,580.00, comprising the following 20
items as shown in the Summary of Tender. 21
Item Description Unit Qty Rate Amount
(RM)
1. Preliminary & Generally LS 522,280.00
2. Site clearance Acre 25 1,000.00 25,000.00
3.
(a)
(b)
Earthworks
Transport only imported
earth filling
Earth bund
M3
LS
380,000
6.97
2,650,000.00
135,000.00
4. Spot turfing LS 13,500.00
5. Earth drain LS 24,300.00
6. Temporary access road
and culvert
LS 11,300.00
22
[Suit No. 22-119-2011]
10
1
7. Permanent settlement
reference station
LS 1,000.00
8. Rod settlement gauge LS 1,200.00
Total 3,383,580.00
2
18. On 25th April, 2008, there was a meeting between the parties 3
in respect of the additional works. 4
19. On 29th May, 2008, the Plaintiff, vide their letter 5
GAD/TO/NC/0504-2008 of idem date, submitted to the 6
Defendant their claim on the additional work in the sum of 7
RM963,411.19, which comprised the cost of transport from 8
Naim Ready Mix Sdn. Bhd. to the site of an additional volume 9
of 137,630.17m of earthfilling material at RM7.00 per m. 10
20. Immediately upon receipt of the Plaintiffs letter, a meeting 11
took place between the parties on the additional works. 12
21. On 15th April, 2009, the Plaintiff, vide their letter 13
GAD/TD/NC/0401/2009 of idem date, re-submitted to the 14
Defendant the relevant documents on the additional works. 15
22. On 31st October, 2009, the Defendant vide their letter 16
NCSB/SPNB/GoldenAnts-ST/2009-2429 of idem date, 17
informed the Plaintiff that the application for extra 18
volume . . . has not been approved by our management. 19
PAYMENT CERTIFICATES 20
23. The Defendant had issued the following interim and final 21
payment certificates on the Works, namely:- 22
(1) Payment Certificate No. 1 (Advance Payment) dated 4th 23
December, 2007; 24
(2) Payment Certificate No. 2 dated 7th January, 2008; 25
(3) Payment Certificate No. 3 dated 31st January, 2008; 26
(4) Payment Certificate No. 4 dated 23rd February, 2008; 27
[Suit No. 22-119-2011]
11
(5) Payment Certificate No. 5 dated 27th March, 2008; 1
(6) Payment Certificate No. 6 dated 29th April, 2008; 2
(7) Payment Certificate No. 7 dated 15th July, 2008; 3
(8) Payment Certificate No. 8 (Penultimate) dated 26th 4
September, 2008; 5
(9) Payment Certificate No. 9 (Final) dated 23rd February, 6
2009; and 7
(10) Payment Certificate No. 10 (Final LAD Waiver) dated 8
14th November, 2009. 9
Issues To Be Tried 10
20. The parties have not agreed on the issues to be tried, Gleaning 11
from the pleadings, I am of the opinion that the main issue to 12
be tried is as follows: 13
Whether the Plaintiff is entitled to claim RM959,282.28 being 14
the alleged costs for the additional work, i.e. the additional 15
work done to transport the volume of earth in excess of 16
380,000 cubic metres? 17
21. In order to answer the main issue, it is necessary first to 18
consider the following subsidiary issues, namely: 19
(a) Whether it was the Plaintiffs responsibility to ascertain 20
the existing ground levels in order to fill the site to the 21
required level? 22
(b) Whether the Plaintiff has been dispensed from 23
ascertaining the existing ground level due to the urgency 24
of the Work? 25
[Suit No. 22-119-2011]
12
(c) Whether there was a promise by the Defendants 1
representative to the Plaintiff that the Defendant would 2
pay the Plaintiff for the additional work 3
Subsidiary Issue (a) 4
22. It is opportune at this juncture to look at the following terms 5
and conditions in the contract documents: 6
(i) Under Item (d) of the Scope of Work provided by the 7
Preliminary and Generally [page 150 Exhibit BAD], the 8
Work involved Earthworks including compaction to the 9
level as shown in the drawings and as directed by the 10
Engineer, including forming earth bunds, all as indicated 11
in the drawings. 12
(ii) Item A of the Preliminary and Generally [page 11 13
Exhibit BAD] states: 14
VISIT TO SITE 15
The Contractor shall visit the site of the Works and shall be 16
independent inquiry and observation ascertain the 17
following in connection with the works:- 18
a. The nature, character and extent of the works 19
b. Local conditions 20
c g .. 21
h. The character of the soil or strata and the nature of 22
subsoil upon which the works are to be executed. 23
Tenderers are to be bore trial holes at their own 24
expense if they deem it necessary. 25
i. . 26
[Suit No. 22-119-2011]
13
No claims made on the ground of failure to visit the site 1
and/or of want of any of the aforesaid matters or other like 2
information which might financially affect the Contract, 3
will be considered. 4
(iii) Item C of Preliminary and Generally [page 12 Exhibit 5
BAD] states: 6
"SITE INSPECTION 7
Immediately after taking possession of the site and before 8
commencing any work, the Contractor shall check actual 9
levels and dimension against those shown on the 10
drawings and immediately inform the Engineer in the 11
event of any alleged discrepancy. If no communications 12
has reached the Engineer, the Contractor shall be held to 13
accept all levels and dimensions and no claims for extra 14
payments in this connection will be entertained. 15
23. Paragraph 1 of the Special Instruction to Tenderer (page 3 16
Exhibit BAD] states: 17
"Existing ground levels 18
Tenderer are to take note that all levels as shown on the 19
drawings are for information only and shall not be taken to 20
represent the true ground levels of the site. It is the 21
responsibility of the tenderer to ascertain the existing 22
ground levels. 23
24. In the light of the foregoing provisions in the Contract 24
documents, it is vividly clear that it is the Plaintiffs 25
responsibility to ascertain the ground level in order to 26
determine the quantity of earth needed to fill the site to the 27
required level. 28
[Suit No. 22-119-2011]
14
Subsidiary Issue (b) 1
25. It is undisputed fact that the Plaintiff did not carry out any 2
topographical survey. 3
26. Counsel for the Defendant submitted that no evidence was ever 4
adduced by the Plaintiff that at the material time when they 5
tendered for the work, they tendered it unwillingly or were 6
forced to take over the project. There was also no allegation 7
that the signature of the Plaintiff on the Special Instruction to 8
Tender [pages 3 - 4 Exhibit BAD], Form of Tender [pages 5-6 9
Exhibit BAD], Summary of Tender [page 7 Exhibit BAD] and 10
Preliminary and Generally [pages 8 - 42 Exhibit BAD] by fraud 11
or misrepresentation. The Plaintiff having signed the above 12
documents voluntarily have given their assent to the whole 13
contract. It was submitted that under the contract, it was the 14
duty of the Plaintiff to carry out independent inquiry to 15
ascertain the level of the ground for the purpose of computing 16
the earthwork quantity, any loss or damage suffered by the 17
plaintiff due to their failure to ascertain the ground level cannot 18
be claimed against the Defendant. 19
27. Counsel for the Defendant submitted that even PW3, the 20
licensed land surveyor, testified that it is not recommendable 21
for a contractor to tender for a contract without carrying out a 22
topographical survey of the ground condition and the level of 23
the ground. It was submitted that the Plaintiff had only 24
themselves to blame for failing to ascertain the actual ground 25
level and that the Defendant cannot be penalised for the 26
Plaintiffs own failure. 27
[Suit No. 22-119-2011]
15
28. Counsel for the Defendant submitted that the evidence showed 1
that the Plaintiff was given possession of the site after they 2
tendered for the Work i.e. on 26th November 2007, which was 3
one month before the actual official site handing over. The size 4
of the project site is 25 acres and, according to PW3, it would 5
take one month to conduct the survey of the 25 acres of land. 6
The Plaintiff, therefore, had ample opportunity to carry out the 7
survey work but they have failed to do so. Thus, the Plaintiffs 8
contention that they were not given ample time to carry out site 9
survey to determine the ground level ought to be disregarded. 10
29. PW1 explained that no topographical survey was carried out 11
prior to the tender because this is not the usual contract due to 12
the urgent nature of the contract. PW1 said that on 19th October 13
2007, Datuk Hasmi from the Defendant Company invited him 14
to tender for the contract because his previous contractor could 15
not complete the Work and they needed a contractor to do the 16
Work urgently. On 22nd October 2007 he collected the tender 17
form and met Gordon Kab on 23rd October 2007 to discuss 18
about the contract (more will be said of what were discussed 19
between PW1 and Gordon Kab later). On 24th October, 2007 20
the Plaintiff submitted its tender [pages 1 - 42 Exhibit BAD]. 21
The Defendant accepted the Plaintiffs tender vide their letter 22
dated 25th October, 2007 [page 43 Exhibit BAD], which states, 23
amongst others, You are required to mobilize your 24
machineries to the project site and to proceed with the works 25
immediately. 26
30. PW1 said that the Plaintiff on 26th October 2007 mobilized 27
their machineries to the project and proceeded with the Work 28
[Suit No. 22-119-2011]
16
immediately as instructed in the Defendants letter dated 25th 1
October 2007. In other words, the Plaintiff took possession of 2
the site and commenced work even before the Letter of Award 3
(which was only issued on 16th November 2007) was issued to 4
him and well before the official commencement of work 5
(which was on 26th November 2007). Based on the Letter of 6
Award, the time for completion of the Project shall be two 7
months after the official commencement date i.e. 26th 8
November 2007 until 25th January 2008. PW1 said that the 9
Defendant had waived the requirement of site inspection by 10
virtue of the Defendants letter dated 25th October 2007 [page 11
43 Exhibit BAD]. 12
31. DW1, the project manager of the Work, testified that the 13
Plaintiff was supposed to check the ground level of the site 14
immediately after taking possession of the site, before 15
commencement of any work and should have immediately 16
informed the Engineer in the event of any alleged discrepancy 17
on the level and dimension given. DW1 disagreed when it was 18
put to him that the Defendant had waived the requirement for 19
site inspection by virtue of the letter dated 25th October 2007. 20
[page 43 Exhibit BAD]. 21
32. However, in cross-examination, DW1 had testified: 22
Q215 PUT: The Plaintiff was unable to do the site survey 23
because the Defendant instructed the Plaintiff to 24
mobilize your machineries to the site and to proceed 25
with the works immediately as per the letter dated 26
25.10.2007 at page 43 of BAD. 27
A: Yes, thats correct. 28
[Suit No. 22-119-2011]
17
. 1
Q226 PUT: By instructing the Plaintiff to mobilize its 2
machinery onto the project site and to proceed with 3
works immediately, the Plaintiff was not given any 4
opportunity to survey the site at all. 5
A: I do not agree. 6
Q227 PUT: Upon immediate mobilization of machinery 7
and immediate commencement of works on the 8
Defendants instruction, the Plaintiff was unable to 9
ascertain the original ground level at the site. 10
A Yes, I agree. 11
Q228 Now refer to page 3 of Exhibit BAD. Here, the special 12
instructions to tendered stipulated 7 months from site 13
possession as the time for completion of Package A, 14
didnt it? 15
A Yes, thats correct. 16
Q229 Now refer to paragraph 8 at page 49 of BAD. 17
Although 7 months for completion of works for 18
Package A was stipulated in the special instruction to 19
tenderers, the Plaintiff was only given 2 months from 20
site possession to complete the works werent they? 21
A Yes, I agree. 22
Q230 The reduction in time to complete the work from 7 23
months to 2 months shows the urgency of the works, 24
correct? 25
A Yes, that is correct. 26
Q231 PUT: The works were needed to be completed 27
urgently as stated by Datuk Hasmi Hasnan in his 28
memo at page 119 of BAD as well. 29
A Yes, thats correct. 30
[Suit No. 22-119-2011]
18
Q233 PUT: The 2 months given to the Plaintiff to complete 1
the proje4ct, which is less than 1/3 of the stipulated 2
time frame of 7 months shows that the works were 3
needed to completed urgently. 4
A Yes, that is correct. 5
33. In my opinion, the Plaintiff has amply shown that the Project 6
was of urgent nature given that the former incompetent 7
contractor had already wasted four out of seven months of the 8
contract period. This is vividly evident in the note written by 9
Datuk Hasmi to Gordon Kab on 19th October, 2007 [page 119 10
Exhibit BAD], that reads, Interview and get this contractor to 11
do part of with/without Naim Realty mix .... give more to 12
whoever faster. Urgent, Get them to bid for future earth 13
work. 14
34. The urgency of the Work is further evident from the fact that 15
upon accepting the Plaintiffs tender, the Defendant in their 16
letter dated 25th October, 2007 [page 43 Exhibit BAD], states, 17
amongst others, You are required to mobilize your 18
machineries to the project site and to proceed with the works 19
immediately. In response to that request, it is undisputed fact 20
that the Plaintiff promptly moved his machinery onto the site 21
and started work the very next day i.e. 26th October 2007 22
without surveying the actual ground level of the site. DW1 23
agreed that once machinery had been moved onto the site and 24
work commenced, it would not be possible to survey the 25
original ground condition. 26
35. I do not agree with the Defendants contention that the 27
Defendant allowed the Plaintiff to take possession of the site a 28
[Suit No. 22-119-2011]
19
month before the official commencement of the Work so that 1
the Plaintiff could carry out the survey of the ground level. My 2
reason for saying so is that survey of ground level would be 3
conducted by surveyor and does not require utilising the 4
machinery of the Plaintiff. In my view, in asking the Plaintiff 5
to mobilize the machinery to the site and start work 6
immediately, the Defendant has obliquely waived the need to 7
survey the ground level of the site. 8
36. In my opinion, due to the urgency of the Work (that had been 9
already been delayed for about four months out of seven 10
months) and pursuant to the request of the Defendant per the 11
letter dated 25th October 2007 [page 43 Exhibit BAD] in which 12
the Defendant requested the Plaintiff to mobilize the machinery 13
to start work immediately, the Plaintiff was literally left with 14
no opportunity to carry out site survey. The Defendant had not 15
given the Plaintiff an opportunity/time to carry out the site 16
survey and had waived the necessity to do so. As such, it does 17
not lie in the mouth of the Defendant to say that the Plaintiff 18
have only themselves to blame for not carrying out the site 19
survey. 20
Subsidiary Issue (c) 21
Whether 380,000 cubic meter of earth was the estimated or 22
maximum volume of earth 23
37. It is an agreed fact that the agreed contract sum of 24
RM3,383,580 comprised of RM2,650,000.00 for Transport 25
only Imported Earth Filling at the quantity of 380,000 cubic 26
meter at RM6.97 per cubic meter. 27
[Suit No. 22-119-2011]
20
38. It is the Plaintiffs contention that 380,000 cubic meters based 1
on 15% compaction is the maximum volume of earth quoted by 2
the Plaintiff and the Defendant had assured the Plaintiff of 3
payment for any additional volume of earth in excess of 4
380,000 cubic meter. 5
39. The Defendant, on the other hand, contended that 380,000 6
cubic meter is the estimate volume of earth quoted by the 7
Plaintiff to earthfill the site to the required level. 8
40. On 23rd October, 2007 the Plaintiff submitted their contract 9
price based on the settlement and compaction of approximately 10
35% to 40% as the site was situated in swampy area. However, 11
during the price negotiation between the Plaintiff and one 12
Gordon Kab and one Abdul Razak Ahmad Marzuki for the 13
Defendant, they relied on the settlement data of 8% - 9% of the 14
adjourning "Package C" of the project and allowed the Plaintiff 15
only 15% settlement and compaction. They assured the 16
Plaintiff that the Defendant would pay for any additional costs 17
in transporting any additional volume of earth. PW1 said that it 18
was with this assurance and understanding that the Plaintiff 19
then agreed to amend their tender price and submitted their 20
amended tender on 24th October, 2007. PW1 stressed that the 21
Plaintiff finally accepted 15% settlement and compaction on 22
the clear understanding that the Defendant would pay the 23
Plaintiff for any additional volume of earth in excess of 24
380,000 cubic meters. 25
41. On 24rd October, 2007 the Plaintiff submitted its amended 26
tender for the Work at the price of RM3,383,580.00, of which 27
[Suit No. 22-119-2011]
21
Transport only imported earth filling including filling to 1
required level in approved layers well compacted as directed. 2
The quotation was accepted by the Defendant as evidenced by 3
the LOA dated 25th October, 2007 [page 43 Exhibit BAD]. See, 4
Q & A 110 p. 45 notes of proceedings. 5
42. The letter at page 43 Exhibit BAD stated, amongst others: 6
Please be informed that your appointment as our 7
earthwork contractor shall be subject to the terms and 8
conditions of the scope of works and agreed Contract Sum 9
of which will be discussed and confirmed upon at a later 10
date by both parties. 11
43. It should be noted also that in the FORM OF TENDER [page 5 12
Exhibit BAD], it states, Unless and until a formal Agreement 13
is prepared and executed this tender, together with your written 14
acceptance thereof, shall constitute a binding Contract between 15
us. 16
44. It is an agreed fact that no formal agreement was drawn up 17
between the parties. 18
45. Counsel for the Defendant submitted that as no formal 19
agreement had been signed, the Plaintiffs quotation, List of 20
Preliminary and Generally and Appendix shall constitute a 21
binding Contract between the Plaintiff and the Defendant. 22
46. Counsel for the Defendant contended that at page 150 of 23
Exhibit BAD, under Item D Type of Contract, the Contract is 24
based on a fixed price lump sum tender. 25
[Suit No. 22-119-2011]
22
47. Counsel for the Defendant contended that there was never any 1
additional work carried out by the Plaintiff for the following 2
reasons: 3
a. It is the Plaintiffs responsibility under the agreement to 4
complete the project including filling up the site to the 5
required level for a fixed price of RM3,383,580.00; 6
b. Under the Scope of Work provided by the Preliminary and 7
Generally [page 150 Exhibit BAD], it stated: 8
"SCOPE OF WORK 9
The Contract comprises generally the supply of all 10
labours, materials, tools, equipments and 11
everything else necessary for the construction and 12
completion of the works in which comprise briefly 13
the following:- 14
(a) to (c).. 15
(d) Earthworks including compaction to the level as 16
shown in the drawings and as directed by the 17
Engineer, including forming earth bund, all as 18
indicated in the drawings. 19
(e) to (h). 20
c. Under the Method Statement [page 53 Exhibit BAD] 21
prepared by the Plaintiff, it is stated under paragraph 1: 22
"The earthwork shall include the excavation of 23
earth from borrow pit situated at Pasir Pandak 24
from the earth licensee (Naim Ready Mix Sdn. Bhd.), 25
transportation by 10 wheeler dump truck to the 26
earthfilling site and levelling work to the required 27
level (as per the drawing) which is up to the 28
maximum of 3.45 meter above sea level in the 29
frontage of the site and 3.3 meter above sea level 30
[Suit No. 22-119-2011]
23
towards the ending of the site. The estimated 1
volume of earth to be earthfilled is about 370,000 2
meter cubic based on the settlement of 15 percent. 3
48. Counsel for the Defendant submitted that it is the responsibility 4
of the Plaintiff to earthfill the site to the required level as per 5
the drawing. Hence, when the Defendant asked the Plaintiff to 6
earthfill the site to the required level as per the drawing, the 7
work so required was within the scope of work under the 8
agreement. It does not vary from the scope of work. Counsel 9
for the Defendant submitted that there is no additional work 10
carried out by the Plaintiff and any claim by the Plaintiff for the 11
so-called additional work must be disallowed. 12
49. In support of the contention that no claim be allowed for work 13
done within the scope of work under the contract, reliance was 14
placed on Teknik Segala Sdn. Bhd. v Salcon Engineering Bhd 15
[2012] 9 MLJ 543 where Justice Zaleha Yusof J held: 16
"Further, as submitted by the learned counsel for the 17
Defendant, and upon scrutinising the evidence of PW1, I 18
totally agree with the Learned counsel, that those work 19
shown in the so called variation orders fall within the work 20
scope of the Plaintiff under the contract. 21
50. It should be noted that Justice Zaleha Yusof went on to say: 22
Since the contract was a lump sum contract the plaintiff 23
must prove that there was an agreement between the 24
parties for variations and additional works in order for it 25
to recover further payments. There was no agreement 26
between the parties for any variation (see para 37). 27
[Suit No. 22-119-2011]
24
51. As submitted by Counsel for the Plaintiff, it should be noted 1
that under the heading FORM OF CONTRACT in the 2
Preliminary and Generally on page 154 Exhibit BAD, Item A 3
Conditions of Contract provides: 4
The Article of agreement and Schedule Conditions of 5
Contract into which the Contractor will be required to 6
enter in connection with this project shall be those 7
contained in the AGREEMENT AND SCHEDULE OF 8
CONDITIONS OF BUILDING CONTRACT PRIVATE 9
EDITION (WITHOUT QUANTITIES) (as issued under the 10
sanction of Pertubuhan Akitek Malaysia Edition 1998 11
(Revised October 1998)). 12
52. Item B of the Schedule of Conditions of Contract states: 13
"The Contractor is referred to the full text of the under 14
mentioned clauses of the Conditions of Contract to which 15
the following are short references and against which the 16
contractor is to provide any sum he considers necessary in 17
complying with the terms of these clauses. 18
Clause No.; 19
53. The Pertubuhan Akitek Malaysia Edition 1998 (Without 20
Quantities) Standard form (Annexure A) of the Plaintiffs 21
Submission shows additional payment for variation work is 22
permissible in Article 2, which states: 23
The Employer will pay the Contractor the sum of . 24
(RM) ..) (hereinafter referred as the Contract Sum) 25
or such other sum as shall become payable hereunder at 26
the times and in the manner specified in the Conditions. 27
54. Clause 11.0 of Conditions of Building Contract provides, inter 28
alia, as follows:- 29
[Suit No. 22-119-2011]
25
11.1 The term "Variation" as used in these Conditions means: 1
11.1 (i) alteration or modification of the design, quality or 2
quantity of the Works as shown in the Contract 3
Drawings and described by or referred to in the 4
Specification. 5
11.1 (ii) the addition, omission or substitution of any work. 6
11.1 (iii) the alteration of the kind or standard of any 7
materials or goods to be used in the Works. 8
(emphasis provided) 9 10 11.2 The Architect may issue instructions requiring a Variation 11
and he may sanction in writing any Variation made by 12
the Contractor otherwise than pursuant to an instruction 13
of the Architect. No Variation required by the Architect or 14
subsequently sanctioned by him shall vitiate this Contract. 15
(emphasis provided) 16
. . . 17
11.5 . . . 18
11.5 (v) Effect shall be given to the measurement and 19
evaluation of all Variations in Interim 20
Certificates and by adjustment of the Contract 21
Sum. 22
(emphasis provided) 23
55. In Chow Kok Fongs Law and Practice of Construction 24
Contracts, 4th Edition, Volume 1, on page 124, it was written in 25
respect of Contract Models and Standard Forms: 26
2.41 The "contract sum" is based on the work delivered in 27
accordance with the stipulations of the project brief or 28
client's requirements. In most situations, it will operate as 29
a fixed price or "lump sum" contract. The contractor is 30
only entitled to claim for additional payments where it is 31
demonstrated that the works, as defined in the project 32
brief or client's requirements, have been varied or where 33
there has been a breach of obligations by the owner and, 34
[Suit No. 22-119-2011]
26
as a result of which, the contractor had to incur additional 1
expense. 2
(emphasis provided) 3
56. In the light of the foregoing, it can thus be seen that the 4
contract sum in a lump sum agreement, like any contract, can 5
still be adjusted on the ground of any additional works 6
executed by the Plaintiff under the provisions of Clause 11.0 of 7
Conditions of Building Contract. 8
57. The Court is mindful that it was provided under the 9
Preliminary and Generally that no claim whatsoever shall be 10
allowed for any variation in the costs of wages, materials, 11
construction plant, fuel, duty, taxes, temporary works or 12
transport or anything else whatsoever which may occur during 13
the period of this contract. Suffice it to say that the Plaintiffs 14
claim has nothing to do with fluctuation in the prices of labour 15
and materials in the course of the Work. Hence, it is of no 16
relevance to the Plaintiffs claim. 17
58. It is significant to note that in the LOA, it informed the Plaintiff 18
of the acceptance of the Plaintiffs quotation for the sum of 19
RM3,383,580.00 subject to terms and conditions as stipulated 20
herein and in the tender documents". It further stated: 21
"You will be required to execute in due course of Formal 22
Contract Agreement. However, until the Formal Contract 23
Agreement is executed, your quotation together with this 24
Letter of Appointment and the following letters and 25
discussion shall constitute a binding Contract between 26
Golden Ants Dynasty Sdn. Bhd. and Naim Cendera Sdn. 27
Bhd. [underline added] 28
[Suit No. 22-119-2011]
27
59. It would appear that the agreement between the parties is both 1
written and oral. This is consistent with the Plaintiffs assertion 2
that due to the urgency of the Work, they were not given time 3
to carry out the survey to determine the volume of earth 4
required. However, the Defendants representatives in allowing 5
the Plaintiff to quote only 15% compaction had assured the 6
Plaintiff in the meeting that the Defendant would pay for 7
transporting the additional volume of earth if the volume of 8
earth exceeded the quoted sum. It was on this understanding 9
that the Plaintiff had agreed to carry out the Work without 10
conducting a proper site survey. 11
60. Counsel for the Plaintiff submitted and, I concur - that 12
defence of lump sum contract pleaded in paragraphs 3, 13, 13
14(b), 17 and 22 of the statement of defence is an afterthought. 14
I say so because from the time the Plaintiff wrote the letter 15
dated 25th April, 2008 [page 8 Exhibit BAD] informing the 16
Defendant of their intended claim for transporting the 17
additional volume of earth until the filing of the defence on 7th 18
February 2012, a period spanning over approximately three 19
years and nine months, the Defendant never once gave their 20
reasons for rejecting the Plaintiffs claim for the additional 21
costs. The defence was raised for the first time in the statement 22
of defence. 23
61. The Court is also of the view that if it is a lump sum agreement 24
whereby the Plaintiff was contractually bound to fill the site to 25
the required level for the quoted price regardless of volume of 26
earth that would be required, then it would not be necessary to 27
make any estimate of volume of earth required to achieve the 28
[Suit No. 22-119-2011]
28
earth filling. The fact that the Plaintiff had to put in the quantity 1
of the volume of earth at 380,000 cubic meters is consistent 2
with the testimony of PW1 and PW2 that during the price 3
negotiation, Gordon Kab and Abdul Razak Ahmad Marzuki 4
only allowed him to put in 15% compacting and filling. 5
62. It should be further noted that in the Bill No. 1 Preliminary 6
and Generally in respect of Payment Certificates No. 2 7
(Advance Payment) [page 227 Exhibit BAD], it states under 8
Item B: 9
ITEM DESCRIPTION UNIT QTY
B Earth works as
specified to the required
area and platform level
including forming earth
bund, all as indicated on
the drawings
M3 380,000
10
63. The description shown in Bill No. 1 Preliminary and 11
Generally in respect of Payment Certificate No. 2 (Advance 12
Payment) above [page 227 Exhibit BAD] also appear in the 13
following bills: 14
a. Bill No. 1 Preliminary and Generally in respect of 15
Payment Certificate No. 3 [page 235 Exhibit BAD] under 16
the cover of letter dated 13th December 2007 [page 229 17
Exhibit BAD]; 18
b. Bill No. 1 Preliminary and Generally in respect of 19
Payment Certificate No. 4 [page 243 Exhibit BAD] under 20
the cover of letter dated 11th January 2007 [page 237 21
Exhibit BAD]; 22
[Suit No. 22-119-2011]
29
c. Bill No. 1 Preliminary and Generally in respect of 1
Payment Certificate No. 5 [page 257 Exhibit BAD] sent 2
under cover of letter dated 11th February 2007 [page 250 3
Exhibit BAD]; 4
d. Bill No., 1 Preliminary and Generally in respect of 5
Payment Certificate No. 6 [page 263 Exhibit BAD]; 6
e. Bill No. 1 Preliminary and Generally in respect of 7
Payment Certificate No. 7 [page 275 Exhibit BAD] under 8
cover of letter dated 11th April 2008 [page 267 Exhibit 9
BAD]; 10
f. Bill No. 1 Preliminary and Generally in respect of 11
Payment Certificate No. 8 [page 283 Exhibit BAD] under 12
cover of letter dated 29th May 2008 [page 276 Exhibit 13
BAD]. 14
64. It should be noted that in all the above bills for the Payment 15
Certificates, the Plaintiff stated the quantity of the earth and the 16
Defendant paid the Plaintiff without raising any question about 17
the insertion of the quantity of earth to be transported to the 18
project site. This, in my view, is consistent with PW1s 19
evidence regarding the amended tender that they subsequently 20
tendered after discussion with Gordon Kab. In other words, 21
380,000 cubic meters is not an estimated volume of earth but 22
the maximum volume of earth quoted by the Plaintiff upon the 23
promise by Gordon Kab and Abdul Razak Ahmad Marzuki that 24
the Defendant would pay the Plaintiff for the additional work in 25
respect of any volume of earth in excess of 380,000 cu meters. 26
[Suit No. 22-119-2011]
30
65. For all the reasons above, my answer to Issue No. 1 is in the 1
affirmative. 2
Unsigned Memorandum [Exhibits 1 - 4 DBD] 3
66. PW1 testified that when there was no reply was forthcoming 4
from the Defendant regarding his claim for transporting the 5
additional volume of earth, on 26th November, 2008, he 6
approached one Datuk Hasmi bin Hasnan to assist. Datuk 7
Hasmi referred it to one Vincent Kueh to solve the problem. 8
On 27th November 2008, the Plaintiff submitted the letter at 9
page 101 BAD to Vincent Kueh who then called for a meeting 10
on 4th December 2008 after which Vincent Kueh asked the 11
Project Manager, Sivakumar (DW1) to make proposal for 12
payment to the top management as discussed in the meeting. 13
67. According to PW1, few days later one Nazri bin Madom, 14
Quantity Surveyor from Naim Cendera Sdn. Bhd., called the 15
Plaintiff to collect the draft memorandum [Exhibits 1 - 4 DBD] 16
and to confirm the contents before submission to the top 17
management. The Plaintiff brought back the unsigned 18
memorandum and confirmed its contents. PW 1 explained that 19
Exhibits 1 - 4 DBD was unsigned because they only wanted the 20
Plaintiff to confirm the contents before Nazri bin Madom 21
submitted it to the top management. PW1 did not know why 22
the Defendant did not give the Plaintiff the signed original 23
memorandum. PW1 believed the signed copy of the Exhibits 1 24
- 4 DBD would be in the possession of the Defendant. 25
68. It is to be recalled that the admissibility of the memorandum to 26
propose settlement was objected to by the Defendant on the 27
[Suit No. 22-119-2011]
31
ground that PW1 was not the maker. Counsel for the Plaintiff 1
informed the court that the Plaintiff had, on 8th June 2012, filed 2
and served notice to produce, under section 66 of the Evidence 3
Act 1950, on the ground that it was a document prepared by the 4
Defendant and at all material times in possession of the 5
Defendant to which the Plaintiff has no access. For the 6
Defendant, it was contended that Nazri bin Madom referred to 7
by PW1 must come to give evidence. 8
69. The Court allowed the admission of the unsigned memorandum 9
on the ground that upon receipt of the section 66 notice, the 10
Defendant did not produce the document for inspection. There 11
is nothing to show or suggest that the Defendant had informed 12
the Plaintiff that they are not in possession of the said 13
memorandum. Absence of such response gives rise to 14
irresistible inference that the Defendant must have the 15
memorandum in their possession. 16
70. In his witness statement, it should be noted that DW1 made no 17
allusion to the unsigned memorandum [Exhibits 1 - 4 DBD] 18
alleged to be written by him. When it was shown to him in the 19
cross-examination, to the question which was put to him that 20
Exhibits 1 - 4 DBD reflected his recommendation to the 21
management pertaining to the Plaintiffs claim for the 22
additional earthwork, DW1 replied, I disagreed because I did 23
not sign it. In further re-examination, DW1 explained that he 24
did not sign because he did not prepare it. This testimony of 25
DW1 was not challenged in further cross-examination of DW1. 26
[Suit No. 22-119-2011]
32
71. In my opinion it is safe to rely on the unsigned memorandum 1
[Exhibits 1 - 4 DBD] for the following reasons. It should noted 2
that the Plaintiffs letter dated 26th November 2008 addressed 3
to the Defendant for the attention of Datuk Hasmi Bin Hasnan 4
[page 101 BAD] bore two receipts of acknowledgement, one of 5
which was by Vincent on 27th November 2008. This is 6
consistent with PW1s testimony that after the letter dated 26th 7
November 2008, he called Datuk Hasmi to explain the problem. 8
As Datuk Hasmi did not have any clue of the matter, he then 9
asked Mr Vincent Kueh to help solve the problem. On 27th 10
November 2008, PW1 brought the said letter to see Vincent 11
Kueh and the letter was acknowledged by his staff on the same 12
day. [Q & A 4 page 5 NOP]. 13
72. I, therefore, believe and accept PW1s evidence that there was 14
a discussion with Mr Vincent Kueh on 4th December 2008. As 15
a result of that meeting Mr Vincent Kueh asked DW1 to 16
prepare a memorandum proposing payment to the Plaintiff as 17
discussed in the meeting. In the premise, it is my finding of 18
fact that in all probability DW1 had prepared the draft 19
memorandum for the management. It is significant to note that 20
the memorandum made two recommendations, namely, (1) 21
payment of RM953,218.39 being the additional earth 22
transported by the Plaintiff; and (2) waiver of LAD amounting 23
RM55,849.00. It is undisputed fact that the second proposal 24
was adopted by the management whereas the first proposal was 25
rejected vide the Defendants letter dated 30th October 2009. 26
73. The Plaintiff had tried to rely on the grounds of 27
recommendation written in the unsigned memorandum as 28
[Suit No. 22-119-2011]
33
admission of the Plaintiffs claim. Counsel for the Plaintiff 1
submitted that DW1 as Project Manager of the Package A 2
project had full and complete knowledge of what was going on 3
at the site. Further, DW1 was at the material time in the 4
employment of the Defendant and his admission in the 5
unsigned memorandum could be imputed to the Defendant and 6
such admission is deemed to be that of the Defendant. 7
74. It is pertinent, however, to take note that in the cross-8
examination of DW1, DW1 agreed to the Plaintiffs counsels 9
question that he only took over from Abdul Razak Ahmad 10
Marzuki in respect of the Project in this case around April 2008; 11
that his knowledge of all the events that occurred during the 12
tender negotiation stage and initial stage of the works are from 13
the documents that he had read and from what was told to him 14
by other people; and he had no personal knowledge of the 15
tender negotiation and initial period of work for the Project. 16
75. A comparison of the unsigned memorandum and the Plaintiffs 17
letter dated 26th November 2008 [Exhibit 101 BAD] shows that 18
ground (a), (b) and (c) of the recommendation also appeared in 19
Exhibit 101 BAD i.e. (a) no actual survey works was carried 20
out on site as the contractor was only given one day to prepare 21
the quotation; (b) the Plaintiff had to rely on the topographical 22
survey supplied to them; and (c) the Defendant only allowed 23
15% for the settlement and compaction during the price 24
negotiation based on the available information obtained from 25
the Package C settlement data. 26
[Suit No. 22-119-2011]
34
76. It would appear to me that the grounds (a), (b) and (c) is not 1
based on DW1s personal knowledge but on what other people 2
told to him and based on what he has read. As such, I do not 3
agree with Plaintiff that they amounted to admission of facts. In 4
my view, Exhibits 1 - 4 DBD is a mere recommendation based 5
on what the Plaintiff had told DW1 in their letter dated 26th 6
November 2008 [page 101 BAD]. They do not prove the fact as 7
alleged by the Plaintiff. 8
Calling of Mr Gordon Kab and Mr Abdul Razak Ahmad 9
Marzuki 10
77. Counsel for the Defendant submitted that the burden is upon 11
the Plaintiff to call Gordon Kab to testify on their behalf that 12
the Defendant agreed to pay the Plaintiff for the alleged 13
additional work to transport the additional volume of earth, 14
citing Juahir Sadilon v Perbadanan Kemajuan Ekonomi Negeri 15
Johor [1996] 4 MLJ 1. 16
78. In Juahir Bin Sadikon, the Court of Appeal held: 17
The allegation of the oral representation has been 18
pleaded by the appellant at para 8 of his statement of 19
claim, and denied by the respondent at para 5(a) of its 20
amended statement of defence. 21
He who alleges must prove such allegation and the onus is 22
on the appellant to do so. See s 103 of the Evidence Act, 23
1950. Thus, it is incumbent upon the appellant to produce 24
Tan Sri Basir as his witness to prove the allegation. The 25
fact that the appellant was unable to secure the attendance 26
of Tan Sri Basir as a witness does not shift the burden to 27
the respondent to produce the witness and testify as to 28
what he had uttered as firstly the respondent never raised 29
[Suit No. 22-119-2011]
35
such an allegation and secondly has denied even making 1
one. 2
79. Counsel for the Defendant contended that in Genisys Integrated 3
Engineers Pte Ltd v UEM Genisys Sdn. Bhd. & Ors [2008] 6 4
MLJ 237 (CA), the Court of Appeal referred to an Indian case 5
of Krishna Kamini v Nilmadhab (1923) AIR Cal 63 where 6
Buckland J said: 7
"So far the learned subordinate judge relies upon the fact 8
that Arjun is not in the defendants service, that is no 9
excuse at all. The only evidence as to the omission is that 10
enquiries were made at the Bombay office. If a party 11
wishes not have a presumption raised against him by the 12
fact that an important witness has not been called, he 13
should exhaust to the utmost of his power every means to 14
bring that witness before the court. 15
The Court further added: 16
An example of satisfactory explanation is where evidence 17
is led to show that a potential witness is absconding or has 18
left the country and could not be traced despite all 19
reasonable attempts. 20
80. Counsel for the Defendant submitted that the Plaintiff had led 21
no evidence to show that Gordon Kab had either absconded or 22
left the country and could not be traced despite all reasonable 23
attempts. It was submitted that it is for the Court to draw 24
adverse inference under section 114(g) Evidence Act and to 25
make presumption that Gordon Kabs evidence, if produced, 26
would be unfavourable to the Plaintiff. 27
[Suit No. 22-119-2011]
36
81. Counsel for the Plaintiff contended that the Plaintiff does not 1
have the burden to call Gordan Kab and Abdul Razak Ahmad 2
Marzuki as these two persons were in the employment of the 3
Defendant at the material time. It was contended that the 4
Defendant should have called them and in failing to do so, the 5
Court ought to draw adverse inference under section 114(g) 6
Evidence Act against the Defendant. 7
82. In my view, pursuant to section 101 of the Evidence Act, the 8
Plaintiff who wants the Court to believe that Gordon Kab and 9
Abdul Razak Ahmad Marzuki in allowing the Plaintiff only 10
15% of compaction and settlement had assured the Plaintiff 11
that they would be paid for any extra volume of earth in excess 12
of the 380,000 cubic meters, bears the burden to call these two 13
persons. 14
83. In Johara Bi Binte Abdul Kadir Marican v Lawrence Lam 15
Kwok Fou & Anor [1981] 1 MLJ 139, Chang Min Tat FJ states: 16
. that until and unless the plaintiff had discharged the 17
onus on her to prove her case on a balance of probabilities the 18
burden did not shift to the defendant and no matter if the 19
defendant's case was completely unbelievable, the claim 20
against him must in this circumstance be dismissed. 21
84. In Juahir Sadilon v Perbadanan Kemajuan Ekonomi Negeri 22
Johor, supra, Mokhtar Sidin JCA opines as follows: 23
The other issue before us, was there such an offer. It is 24
clear that it was the plaintiff who asserts that Tan Sri 25
Dato' Haji Bashir who made the offer, the onus is on the 26
plaintiff to satisfy the Court that such an offer was ever 27
[Suit No. 22-119-2011]
37
made. This is clearly provided for by ss. 101 and 103 of 1
the Evidence Act 1950. The sections read as follows: 2
101. Burden of Proof 3
(1) whoever desires any Court to give judgment as 4
to any legal right or liability, dependant on the 5
existence of facts which he asserts, must prove 6
that these facts exist; 7
(2) when a person is bound to prove the existence 8
of any fact, it is said that the burden of proof 9
lies on that person. 10
103. Burden of Proof as to Particular fact 11
The burden of proof as to any particular fact lies 12
on that person who wishes the Court to believe in 13
its existence unless it is provided by any law that 14
the proof of that fact shall lie on any particular 15
person. 16
It is clear from the above provisions on whom the onus lies. 17
In the present case it is the plaintiff who had asserted that 18
there exists a particular fact viz. that there was an offer to 19
sell the said land at the price between RM7,000 to 20
RM8,000. The onus is on the plaintiff to satisfy the Court 21
there was such an offer. 22
85. It is clear from the authorities above that the burden of proof in 23
civil cases shifts depending on whether the party that bears the 24
burden has discharged the burden of proof. In the present case, 25
I have earlier given my reasons that I am satisfied that the 26
Plaintiff has proven on the balance of probability that there was 27
price negotiation with Gordon Kab and Abdul Razak Ahmad 28
Marzuki in which they only allowed the Plaintiff to quote 15% 29
settlement and compaction with the assurance that the 30
[Suit No. 22-119-2011]
38
Defendant would pay the Plaintiff for any additional costs to 1
transport earth in excess of 380,000 cubic meters. In the 2
circumstance, the burden of proof has shifted to the Defendant 3
to call Gordon Kab and Abdul Razak Ahmad Marzuki to rebut 4
the Plaintiffs assertion, which they have failed to do. 5
Accordingly, I draw the adverse inference under section 114(g) 6
Evidence Act against the Defendant. 7
Whether there is Additional Work 8
86. PW1 told the court that sometime in March, 2008, the Plaintiff 9
discovered that the total volume of earth for the Work would 10
exceed the agreed volume of 380,000 cubic meters. He then 11
informed the project manager Abdul Razak Ahmad Marzuki in 12
a meeting on 29th March, 2008, that the Plaintiff intended to 13
claim for the additional work. 14
87. On 25th April, 2008, there was a meeting with the new project 15
manager, DW1, and he briefed DW1 on the Plaintiffs intended 16
claim for the additional volume of earth for the Work. DW1 17
instructed the Plaintiff to carry on with the Work and he 18
assured PW1 that, after practical completion of the Work, the 19
Defendant would consider favourably the Plaintiffs intended 20
claim. 21
88. In my view, PW1s evidence of having informed the Defendant 22
through their project manager, Abdul Razak Ahmad Marzuki 23
and DW1, that the volume of earth for the Work had exceeded 24
the agreed volume and that the Plaintiff intended to claim for 25
the additional work in transporting the additional volume of 26
[Suit No. 22-119-2011]
39
earth is credible. My belief is based on the Plaintiffs letter to 1
the Defendant for the attention of DW1, which mentioned: 2
"As discussed in our last meeting on 25th April 2008, we 3
would like to bring to your attention that we have 4
exceeded our initial quotation price for the above project 5
as the work carried out has exceeded the volume of 6
380,000 meter cubic of earth. . 7
89. PW1 told the court that the actual total volume of earth 8
transported by the Plaintiff to the project site was 517,630.17 9
cubic meters. 10
90. PW2 (Lu Din Kiong, Managing Director of Plaintiff Company) 11
told the court that the additional earth transported by the 12
Defendant was 137,630.17 cubic meters, which is the 13
difference between the 517,630.17 cubic meters total volume of 14
earth filled by the Plaintiff and 380,000 cubic meters volume of 15
earth agreed to be filled at the project site. 16
91. PW2 said that the Plaintiff and the Defendant used lorry token 17
ticket system as a record to calculate the actual delivery of 18
earth to the site. A lorry token ticket was issued for every trip 19
made by the lorry carrying the earth. The token ticket was 20
given to five parties, i.e. 21
a. Lorry driver; 22
b. Bulldozer driver; 23
c. Excavator driver; 24
d. The earth supplier, Naim Ready Mix Sdn. Bhd. (the 25
Defendants associate company); and 26
[Suit No. 22-119-2011]
40
e. The Plaintiff. 1
92. PW2 said that at the end of each day, the Plaintiff provided all 2
the lorry token tickets issued for the day to the Defendant for 3
verification, which the Defendant did by putting an initial on 4
the reverse page of the token ticket and photocopied every lorry 5
token ticket for its retention. 6
93. According to PW2, the purpose of the lorry token ticket is to 7
quantify the actual volume of earth transported to the site. 8
These tickets are controlled documents and serially numbered. 9
Based on these tickets, the Plaintiff worked out the volume of 10
earth transported to the site each month. The volume of earth 11
carried by each lorry per day is calculated based on its number 12
of daily trips multiplied by the volume dimension of the lorry 13
bucket. 14
94. PW2 said that the Plaintiff had been using the lorry token ticket 15
system as part of its internal operating procedure for control 16
and tracking of actual earthworks done at all its project sites 17
since 2006. The Defendant had never commented that there 18
were deficiencies in the Plaintiffs lorry token ticket system. 19
95. The original lorry token ticket are found at pages 25 - 430 of 20
the Plaintiffs Supplementary Bundle of Documents Volume 1, 21
at pages 431 719 of the Plaintiffs Supplementary Bundle of 22
Document Volume 2, at pages 720 - 1121 of the Plaintiffs 23
Supplementary Bundle of Document Volume 3 and at pages 24
1122 1673 of the Plaintiffs Supplementary Bundle of 25
Document Volume 4. The Summary of total lorry trips and 26
[Suit No. 22-119-2011]
41
volume by month is found at page 1 of the Plaintiffs 1
Supplementary Bundle of Document. 2
96. Counsel for the Defendant submitted that although there was a 3
column provided in these lorry token ticket to fill in the actual 4
volume of earth loaded on to each lorry, it was nevertheless not 5
completed by the Plaintiff. It was submitted that the Plaintiff 6
never explained why the column provided for was never 7
completed with the actual volume of earth transported by each 8
of the lorry. The logical explanation for such omission, 9
contended counsel for the Defendant, would be that the volume 10
of earth was never a concern of both the Plaintiff and the 11
Defendant as it was the Plaintiffs obligation to earthfill the site 12
to the required level regardless of the volume of earth 13
transported. 14
97. Counsel for the Defendant further submitted that PW3 (Land 15
Surveyor) stated that the only way for a surveyor to calculate 16
the total volume of earth filled on the site is by looking at the 17
original ground survey and as build survey. The Plaintiff has 18
not adduced any evidence that they have submitted the original 19
ground survey. Without the original ground survey and the "as 20
build survey, even PW3 could not calculate the actual volume 21
of earth transported to the project site. 22
98. This contention of the counsel for the Defendant is not correct. 23
I say so because PW2 had explained in his examination in chief 24
as well as in cross examination that the column for volume of 25
earth was not filled in because each lorry has its measurement 26
dimension in cubic meters and from the lorry plate number, the 27
[Suit No. 22-119-2011]
42
volume of earth it carried can be calculated/ascertained because 1
its bucket does not change. 2
99. Although it was put to PW2 during cross-examination that the 3
Defendant never agreed to the use of the lorry token ticket 4
system to calculate the volume of earth transported by the 5
Plaintiff to the site, the Defendant, however, did not call any 6
witness to rebut PW2s testimony. 7
100. In the premise, based on the unchallenged evidence of PW2, 8
the Plaintiff has proved that the Plaintiff had transported the 9
total volume of 517,630 cubic meters of earth to the site. Thus 10
the additional volume of earth the Plaintiff had transported to 11
the project site was 137,630.17 cubic meters [517,630.17 - 12
380,000], the total cost of which, at the agreed rate of RM6.97 13
per cubic meter, is RM959,282.28. 14
Failure to inform the project engineer of the alleged 15
discrepancies of the actual ground levels and dimension 16
against those shown on the drawings 17
101. Counsel for the Defendant contended that in the event the 18
Court finds that the Plaintiff did incur expenses to carry out 19
additional work to transport the additional volume of earth, the 20
Defendant is not liable to pay the Plaintiff for such expenses on 21
the ground that the Plaintiff has failed to comply with the 22
following provisions in the Preliminary and Generally. 23
102. Item C of the Preliminary and Generally on page 12 Exhibit 24
BAD states: 25
26
[Suit No. 22-119-2011]
43
"SITE INSPECTION 1
Immediately after taking possession of the site and before 2
commencing any work, the Contractor shall check actual 3
levels and dimensions against those shown on the 4
drawings and immediately inform the Engineer in the 5
event of any alleged discrepancy. If no communications 6
has reached the Engineer, the Contractor shall be held to 7
accept all levels and dimensions and no claims for extra 8
payments in this connection will be entertained. 9
103. Item B on page 10 of Exhibit BAD, paragraphs 2 thereof states: 10
DEFINITIONS OF TERMS 11
Engineer shall mean Jurutera CSD Sdn. Bhd. 12
104. Item A on page 29 Exhibit BAD states: 13
AUTHORISATION OF VARIATIONS AND EXTRAS 14
No variations and extras shall be valid unless authorised 15
in writing by the Engineer. It is the responsibility of the 16
Contractor to inform the Engineer in writing of any 17
variations and extras not authorised in writing. 18
105. Counsel for the Defendant submitted that the provisions of the 19
terms referred to above vividly showed that it is the 20
responsibility of the Plaintiff to ascertain the ground levels and 21
dimension and to inform the Engineer if there is variance from 22
the drawing provided. If there is no communication by the 23
Plaintiff to the Engineer, then the Plaintiff shall be held to 24
accept all levels and dimension as shown on the drawing and 25
will not be entitled to any extra claim. 26
106. Counsel for the Defendant submitted that PW1 had admitted in 27
re-examination that the Plaintiff did not communicate with the 28
[Suit No. 22-119-2011]
44
Engineer because they were assured by Gordon Kab and Abdul 1
Razak Ahmad Marzuki that the Defendant would pay the 2
Plaintiff for the costs in transporting the additional volume of 3
earth. PW1 also admitted in cross-examination that Gordon 4
Kab and Abdul Razak Ahmad Marzuki is not the Engineer 5
provided under the Agreement. It was submitted that the 6
Plaintiff has not adduced any evidence to show that the alleged 7
additional work to transport the extra volume of earth was 8
authorised by the Engineer. By reason of the Plaintiffs failure 9
to comply with the provision of the Agreement by informing 10
the Engineer of the alleged variance in the ground level and 11
dimension, the Plaintiff is not entitled to claim for the 12
additional costs for the additional work in transporting the 13
alleged additional volume of earth. 14
107. To support the argument, counsel for the Defendant relied on ss 15
53 and 55 of the Contracts Act 1950. S 53 of the Contracts Act 16
states: 17
53. Order of performance of reciprocal promises 18
Where the order in which reciprocal promises are to be 19
performed is expressly fixed by the contract, they shall be 20
performed in that order; and, where the order is not 21
expressly fixed by the contract, they shall be performed in 22
that order which the nature of the transaction requires. 23
ILLUSTRATIONS 24
(a) 25
A and B contract that A shall build a house for B at a 26
fixed price. A's promise to build the house must be 27
performed before B's promise to pay for it. 28
[Suit No. 22-119-2011]
45
(b) 1
A and B contract that A shall make over his stock-in-2
trade to B at a fixed price, and B promises to give 3
security for the payment of the money. A's promise need 4
not be performed until the security is given, for the 5
nature of the transaction requires that A should have 6
security before he delivers up his stock. 7
Section 55 of the Contracts Act states: 8
55. Effect of default as to that promise which should be first 9
performed, in contract consisting of reciprocal promises 10
When a contract consists of reciprocal promises, such that 11
one of them cannot be performed, or that its performance 12
cannot be claimed till the other has been performed, and 13
the promisor of the promise last mentioned fails to perform 14
it, the promisor cannot claim the performance of the 15
reciprocal promise, and must make compensation to the 16
other party to the contract for any loss which the other 17
party may sustain by the non-performance of the contract. 18
ILLUSTRATIONS 19
(a) 20
A hires B's ship to take in and convey, from Kelang to 21
Singapore, a cargo to be provided by A, B receiving a 22
certain freight for its conveyance. A does not provide 23
any cargo for the ship. A cannot claim the performance 24
of B's promise, and must make compensation to B for 25
the loss which B sustains by the non-performance of the 26
contract. 27
(b) 28
A contracts with B to execute certain builders' work for 29
a fixed price, B supplying the scaffolding and timber 30
[Suit No. 22-119-2011]
46
necessary for the work. B refuses to furnish any 1
scaffolding or timber, and the work cannot be executed. 2
A need not execute the work, and B is bound to make 3
compensation to A for any loss caused to him by the 4
non-performance of the contract. 5
(c) 6
A contracts with B to deliver to him, at a specified 7
price, certain merchandise on board a ship which 8
cannot arrive for a month, and B engages to pay for the 9
merchandise within a week from the date of the 10
contract. B does not pay within the week. A's promise to 11
deliver need not be performed, and B must make 12
compensation. 13
(d) 14
A promises B to sell him one hundred bales of 15
merchandise, to be delivered next day, and B promises 16
A to pay for them within a month. A does not deliver 17
according to his promise. B's promise to pay need not 18
be performed, and A must make compensation. 19
108. Further reliance was also placed on Mars Equity Sdn. Bhd. v 20
Tis "Ata"ashar Sdn. Bhd. [2006] 4 MLJ 320, where Gopal Sri 21
Ram JCA [as he then as] held: 22
Now, the order of performance of obligations in a 23
contract is governed by s 53 of the Contracts Act 1950 24
which provides: 25
53. Where the order in which reciprocal promises 26
are to be performed is expressly fixed by the 27
contract, they shall be performed in that order; and, 28
where the order is not expressly fixed by the 29
contract, they shall be performed in that order 30
which the nature of the transaction requires. 31
[Suit No. 22-119-2011]
47
The section is ipsissima verba s 52 of the Indian Contract 1
Act 1872. In the leading textbook on the subject, viz, 2
Singhal & Subrahmanyan's Indian Contract Act (4th Ed) p 3
984, the commentary to s 52 reads: 4
Standing alone, however, the mere order of 5
performances in time is not always decisive of the 6
case. The promise to render the earlier performance 7
is not conditional on tender of an agreed equivalent 8
by the other party; but may be conditional on other 9
factors even though it is not expressly so provided. 10
For example, the promisor's duty to render the 11
earlier performance is constructively conditional on 12
the absence of a material increase in his risk of not 13
getting the agreed exchange. He is privileged to 14
withhold his performance, if the other party 15
repudiates in advance, or if, for any reason, he 16
becomes prospectively unable to render the agreed 17
exchange, whether because of objective 18
impossibility, or of insolvency, or other personal 19
inability. So, if a seller promises to ship goods on a 20
certain day, in return for the buyer's promise to pay 21
for them after delivery, the seller's duty to ship is 22
constructively conditional on the buyer's 23
prospective ability to pay. If the seller can show that 24
the buyer will not in fact be able to pay, he is 25
privileged not to ship; this is true, in spite of the fact 26
that shipment is to be first in time. 27
28
It follows that the respondent was clearly in breach 29
of its primary obligation to transfer the land to the 30
appellant. Therefore, it was not in a position to call 31
for the performance of the appellant's obligation 32
under the timber agreement to apply for the licence. 33
[Suit No. 22-119-2011]
48
The present case, in my judgment, falls plumb 1
within s 55 of the Contracts Act 1950. That section 2
says: 3
When a contract consists of reciprocal 4
promises, such that one of them cannot be 5
performed, or that its performance cannot 6
be claimed till the other has been performed, 7
and the promisor of the promise last 8
mentioned fails to perform it, the promisor 9
cannot claim the performance of the 10
reciprocal promise, and must make 11
compensation to the other party to the 12
contract for any loss which the other party 13
may sustain by the non performance of the 14
contract. 15
Section 55 is, of course of general application when 16
it speaks of the promisor having to pay 17
compensation to the promisee. But, whether 18
compensation is sufficient in a given case depends 19
on the subject matter of the contract. 20
109. Counsel for the Plaintiff contended that no evidence had been 21
led to show that the Engineer played any role on the site during 22
the execution of the Work by the Plaintiff. On the contrary, the 23
testimony of DW1 amply showed that it was DW1, and not the 24
Engineer, who told the Plaintiff that the Defendant would pay 25
the Plaintiffs claim for additional volume of earth upon proof 26
that they had done the additional work. (Q & A 243 and 254 if 27
the notes of proceedings). 28
110. Counsel for the Plaintiff submitted that the Defendant had by 29
their conduct allowed the role of the Engineer to be usurped by 30
[Suit No. 22-119-2011]
49
their own Project Manager. Under the circumstance, the 1
Defendant cannot expect the Plaintiff, at the same time, to seek 2
the instruction of the Engineer on the additional volume of 3
earth. 4
111. I have no reason to disagree with counsel for the Plaintiff. 5
112. It should also be recalled that earlier on I have made a finding 6
of fact that during price negotiation the Plaintiff was asked to 7
quote only 15% of compaction and settlement i.e. with the 8
promise of being paid for any volume of earth in excess of 9
380,000 cubic meter; and that the Defendant through the 10
Letters of Appointment dated 25th October 2007 [page 43 11
Exhibit BAD] directed the Plaintiff to mobilize the machinery 12
to the site and to proceed with the work immediately had 13
effectively not given the Plaintiff a chance to check the actual 14
ground level through survey. In the circumstances, it does not 15
lie in the mouth of the Defendant to say that the Plaintiff had 16
failed to comply with the terms of the agreement. 17
113. In Chow Kok Fongs Law and Practice of Construction 18
Contract, 4th Edition, Volume 1, p. 285, the learned author 19
observes: 20
Recovery Without Written Orders 21
Implied Promised to Pay 22
5.29 In certain circumstances, the courts may be prepared to 23
impute an implied promise on the part of the employer to 24
pay for work which has not been ordered in accordance 25
with the formalities stipulated in the contract conditions. 26
A situation which warrants such an imputation is where 27
the employer has done some act suggesting that he is 28
waiving the condition precedent, and which has the 29
[Suit No. 22-119-2011]
50
effect of leading the contractor reasonably to believe 1
that the strict legal rights will not be insisted on. In 2
Molloy v Liebe (1910), the employer ordered the 3
contractor to execute a certain item of work. The 4
contractor argued that this was extra work. The employer 5
maintained that the work was not an extra and insisted 6
that the contractor carry out the work. The matter was 7
referred to arbitration. In an award which was 8
subsequently upheld in court, the arbitrator ruled that that 9
work was indeed, as the contractor claimed, extra works 10
and that the employer had, by his insistence that the work 11
should be done, impliedly promised the contractor that the 12
work would be paid for. It was considered immaterial, in 13
the circumstances, that the subject work was not ordered 14
in writing in accordance with the procedures stipulated 15
under the terms of the contract. 16
(emphasis provided) 17
114. I also agree with the Plaintiff that this head of defence is an 18
afterthought. As rightly submitted by counsel for the Plaintiff, 19
for the period of some three years since the Plaintiff made their 20
claim for the additional work, the Defendant had never 21
informed the Plaintiff that they were not entitled to claim for 22
the additional work until the defence was filed. 23
CONCLUSION 24
115. For all the reasons aforesaid, I am satisfied that the Plaintiff, on 25
the balance of probability, has proven their claim. As such I 26
allow the claim as prayed for with costs of RM50,000.00. 27
Interest at 8% per annum from 29th May 2008 to 1st October 28
2012, thereafter at 5% per annum until full settlement. 29
[Suit No. 22-119-2011]
51
Alternative Claim: 1
116. In the light of my above decision it is not necessary to consider 2
the alternative claim. 3
4
5
(DATUK YEW JEN KIE) 6
Judge 7
8
Date of Grounds of Decision: 10.3.2014 9
10
Date of Delivery of Judgment: 21.1.2014 11
12
Date of Hearing: 4.3.2013 13
6.3.2013 14
18.4.2013 15
22 24.7.2013 16 17
For Plaintiff: Mr. Satinder Singh 18
Messrs Sandhu & Co. Advocates 19
Kuching 20
21
For Defendant: Mr. Bong Siak Peng 22
Messrs Bong Siak Peng Advocates 23
Kuching 24
25
26
27
28
29
30
31
32
Notice: This copy of the Court's Reasons for Judgment is subject to editorial 33 revision. 34