+ All Categories
Home > Documents > LER 95-014-00:on 951209,reactor tripped following ...

LER 95-014-00:on 951209,reactor tripped following ...

Date post: 17-Nov-2021
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
20
~ CATEGORY 3y REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS) ACCESSION NBR:9601160443 DOC.DATE: 96/01/09 NOTARIZED: NO DOCKET FACIL:STN-50-528 Palo Verde Nuclear Station, Unit 1, Arizona Publi 05000528 AUTH. NAME AUTHOR AFFILIATION GRABO,B.A. Arizona Public Service Co. (formerly Arizona Nuclear Power LEVINE,J.M. Arizona Public Service Co. (formerly Arizona Nuclear Power RECIE . NAME RECIPIENT AFFILIATION SUBJECT: LER 95-014-00:on 951209,reactor tripped'ollowing degradation of main FW flow. Caused by malfunction of FWCS power supply,NNN-Dll,transfer switch.NNN-D11 aligned to "Normal" power supply.W/960109 ltr. DISTRIBUTION CODE: ZE227 COPIES RECEIVED:LTR ) ENCI L SIZE: TITLE: 50.73/50.9 Licensee Event Report (LER), Incident Rpt,. etc. NOTES:STANDARDIZED PLANT 05000528 G RECIPIENT ID CODE/NAME PD4-2 PD INTERNAL: ACRS AEOD/SPD/RRAB NRR/DE/ECGB NRR/DE/EMEB NRR/DRCH/HICB NRR/DRCH/HQMB NRR/DSSA/SPLB RES/DSIR/EIB EXTERNAL: L ST LOBBY WARD 'OAC MURPHY,G.A NRC PDR COPIES LTTR ENCL 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1' 1 1 1' 1 1 1 1 RECIPIENT ID CODE/NAME HOLIANP B 'PD/2RABE E CE NRR/DE/EELB NRR/DRCH/HHFB NRR/DRCH/HOLB NRR/DRPM/PECB NRR/DSSA/SRXB RGN4 FILE 01 LITCO BRYCE,J H NOAC POOREPW. NUDOCS FULL TXT COPIES LTTR ENCL 1 1 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 2 2 1 1 1 1 D N NOTE TO ALL "RIDS" RECIPIENTS: PLEASE HELP US TO REDUCE WASTEI CONTACT THE DOCUMENT CONTROL DESK, ROOM OWFN 5D-5(EXT. 415-2083) TO ELIMINATE YOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED! FULL TEXT CONVERSZON REQUIRED TOTAL NUMBER OF COPIES REQUIRED: LTTR 26 ENCL 26
Transcript
Page 1: LER 95-014-00:on 951209,reactor tripped following ...

~ CATEGORY 3yREGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)

ACCESSION NBR:9601160443 DOC.DATE: 96/01/09 NOTARIZED: NO DOCKETFACIL:STN-50-528 Palo Verde Nuclear Station, Unit 1, Arizona Publi 05000528

AUTH.NAME AUTHOR AFFILIATIONGRABO,B.A. Arizona Public Service Co. (formerly Arizona Nuclear PowerLEVINE,J.M. Arizona Public Service Co. (formerly Arizona Nuclear Power

RECIE . NAME RECIPIENT AFFILIATION

SUBJECT: LER 95-014-00:on 951209,reactor tripped'ollowingdegradation of main FW flow.Caused by malfunction of FWCS

power supply,NNN-Dll,transfer switch.NNN-D11 aligned to"Normal" power supply.W/960109 ltr.

DISTRIBUTION CODE: ZE227 COPIES RECEIVED:LTR ) ENCI L SIZE:TITLE: 50.73/50.9 Licensee Event Report (LER), Incident Rpt,. etc.

NOTES:STANDARDIZED PLANT 05000528 G

RECIPIENTID CODE/NAME

PD4-2 PD

INTERNAL: ACRSAEOD/SPD/RRABNRR/DE/ECGBNRR/DE/EMEBNRR/DRCH/HICBNRR/DRCH/HQMBNRR/DSSA/SPLBRES/DSIR/EIB

EXTERNAL: L ST LOBBY WARD'OACMURPHY,G.A

NRC PDR

COPIESLTTR ENCL

1 1

1 11 11 11 11 11 11'

1 1

1'

1 11 1

RECIPIENTID CODE/NAME

HOLIANP B

'PD/2RABEE CE

NRR/DE/EELBNRR/DRCH/HHFBNRR/DRCH/HOLBNRR/DRPM/PECBNRR/DSSA/SRXBRGN4 FILE 01

LITCO BRYCE,J HNOAC POOREPW.NUDOCS FULL TXT

COPIESLTTR ENCL

1 1

2 21 11 11 11 11 11 11 1

2 21 11 1

D

N

NOTE TO ALL "RIDS" RECIPIENTS:PLEASE HELP US TO REDUCE WASTEI CONTACT THE DOCUMENT CONTROL DESK,

ROOM OWFN 5D-5(EXT. 415-2083) TO ELIMINATE YOUR NAME FROM

DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED!

FULL TEXT CONVERSZON REQUIREDTOTAL NUMBER OF COPIES REQUIRED: LTTR 26 ENCL 26

Page 2: LER 95-014-00:on 951209,reactor tripped following ...
Page 3: LER 95-014-00:on 951209,reactor tripped following ...

JAMES M. LEVINEVICE PRESIDENT

NUCLEAR PRODUCTION

Arizona Public Service Company'PALO VERDE NUCLEAR GENERATING STATION

P.O, BOX 52034 ~ PHOENIX. ARIZONA85072-2034

192-00956-JIL/IL/BAG/BEJanuary 9, 1996

U. S. Nuclear Regulatory CommissionATTN: Document Control DeskMail Station P1-37Washington, DC 20555-0001

Dear Sirs:

Subject: Palo Verde Nuclear Generating Station (PVNGS)Unit 1

Docket No. STN 50-528 (License No. NPFP1)Licensee Event Report 95-014-00

Attached please find Licensee Event Report (LER) 95-014-00 prepared andsubmitted pursuant to 10CFR50.73. This LER reports a December 9, 1995, reactortrip on low water level in Steam Generator Number 2. and the automatic actuation ofan Engineered Safety Feature, Emergency Diesel Generator (EDG) Train A in Unit 1

and EDG Train B in Unit 2. In.accordance with 10CFR50.73(d), a copy of this LERis being forwarded to the Regional Administrator, NRC Region IV.

Ifyou have any questions, please contact Burton A. Grabo, Section Leader, NuclearRegulatory Affairs, at (602) 393-6492.

Sincerely,

/ . (Ii.f

JML/BAG/BE/pv

Attachment

(all with attachment)

III60'L160443 'II60 109PDR ADOCK 05000528S PDR

gbPy1 ~

cc: L. J. CallanK. E. PerkinsK. E. JohnstonINPO Records Center

Page 4: LER 95-014-00:on 951209,reactor tripped following ...
Page 5: LER 95-014-00:on 951209,reactor tripped following ...

LICENSEE EVENT REPORT (LER)

ACIUlYNAME(1)

Palo Verde Unit 1

DOCKET NUMBER (2) PAGE (3)

0 5 0 0 0 5 2 8 1DF 0 7

TLE (4)

Reactor Trip Following,the Degradation of Main Feedwater FlowEVENT DA16 5

MONTH DAY YEAR YEARLER NUMBER 6

SEQUENTIALNUMBER

REPORT DATE 7DAY YEAR, REVISION MONTH

'„'rv) NUMBER

OTHER FACIUTIES INVOLVED 6FACIUTYNAMES

Palo Verde Unit 2

NUMBERS

0 5 0 0 0 5 2 9

1 2 0 9 9 5 9 5 0 1 4 0 0 0 1 0 9 9 6 teal/A 0 5, 0 0 0OPERATING

MODE (9)

POWER

LEVEL(fo) 4 0

HIS REPORT S SUBMITTEDP URSUANT TO

20.402(b)

20.45(a)(1)(i)

20.45(a)(1)(ij

20.405(aXIXeq

20.45(aXIXN)

20.405(aX1)(v)

20.405(c)

50.36(c)(1)

50.36(cX2)

50.73(aX2)gi

5IL73(aX2X9)

50.73(a)(2XE)

50 73(aX2Xrv)

50.73(aX2Xv)

50.73(aX2Xvi)

50.73(a)(2Xv~aA)

50.73(aX2Xve~8)

50.73(aX2Xx)

THE REQUIREMENTs oF 10 cFR 5: (check one or more of the IINown9) (11)

73.71(b)

73.71(c)

OTHER (Specify MAbetletf

below arvf MTexL NRC Form

LICENSEE CONTACT FOR THIS LER (12)

E

Burton A. Grabo, Section Leader, Nuclear Regulatory Affairs

ELEPHONE NUMBER

EA CODE

6 0 2 3 9 3 - 6 4 9 2COMPLETE ONE LINE FOR EACH COMPONENT FAILUREDESCRIBED IN THIS REPOR T (13)

CAUSE SYSTEM

B E E

COMPONENT

ASU

MANUFACTURER

G 0 8 0

REPORTABLETO NPRDS

Yes

CAUSE''J~

„';;1;:I ',

';," <~.fft .jP:>A,'-.',

SYSTEM COMPONENT MANUFACTURER

REPORTABLETO NPRDS

SUPPLEMENTAL REPORT EXPECTED (I4)

X NOYES (Ifyea. oomplete EXPECTED SUBMISSION DATE)

~ear O»

EXPECTED

SUBMISSION

DATE (15)

MONTH DAY YEAR

On December 9, 1995, at approximately 0320 MST, Palo Verde Unit 1 was in Mode 1(POWER OPERATZON), operating at approximately 40 percent power when a nativedesert animal (Ringtail Cat) caused a momentary phase to ground path on startuptransformer NAN-X03 (non-class 1E) causing the Transformer Differential relayto trigger from a phase imbalance. This resulted in deenergization ofnon-class 13.8 kV buses NAN-S05, NAN-S03, and class 1E 4.16 kV bus PBA-S03 inUnit 1. Also, NAN-X03 has a second set of windings supplying Unit ;- when thetransformer was isolated from the fault, this resulted in deenergizingnon-class 13.8 kV buses NAN-S06 and NAN-S04, and class 1E 4.16 kV bus PBB-S04in Unit 2. The loss of power to the class 1E 4.16 kV buses resulted in a validESFAS signal starting the EDGs. The loss of PBA-S03, in Unit 1, also resultedin the loss of non-class 1E instrument power to the feedwater and steam bypasscontrol systems (FWCS and SBCS).

At approximately 0322 MST, a reactor trip occurred in Unit 1 when SteamGenerator Number 2 (SG-2) water level reached the Reactor Protection System(RPS) trip setpoint for low SG water level following the degradation of mainfeedwater (FW) flow.

The root cause for the Unit 1 reactor trip was determined to be a malfunctionof the FWCS'ower supply, NNN-D11, transfer switch. An evaluation of theadequacy of NNN-D11 to support the FWCS and SBCS during power losses isongoing. Any corrective actions identified will be tracked under the APSCommitment Action Tracking System.

Previous similar events were reported pursuant to 10 CFR 50.73 in LERs529/95-005, 528/95-008, 530/94-007, 530/94-005, 530/93-001 and 529/92-001.

Page 6: LER 95-014-00:on 951209,reactor tripped following ...

Cl II

Page 7: LER 95-014-00:on 951209,reactor tripped following ...

LICENSEE EVENT REPORT (LER) TEXT CONTINUATION

ACIUTYNAME

Palo Verde Unit 1

DOCKET NUMBERYEAR

LER NUMBERSEQUENTIAL

NUMBEREVISIO

. NUMBER

PAGE

1. REPORTING REQUIREMENT:

0 5 0 0 0 5 2 8 9 5 0 1 4 0 0 020f 0 7

This LER 528/95-014 is being written to report an event that resulted inan automatic actuation of an Engineered Safety Feature (ESF) including theReactor Protection System (RPS) as specified in 10 CFR 50.73(a)(2)(iv).

Specifically, on December 9, 1995, at approximately 0320 MST, Palo VerdeUnit 1 was in Mode 1 (POWER OPERATION), operating at approximately 40

percent power when a native desert animal (Ringtail Cat) caused a

momentary phase to ground path on start-up transformer NAN-X03 (non-class1E) causing the Transformer Differential relay to trigger from a phaseimbalance, and deenergizing non-Class 13.8 kV buses (EA) NAN-S05, NAN-S03,

and class 1E (EB) 4.16 kV bus PBA-S03 in Unit 1. Additionally, non-class13.8 kV buses NAN-S06 and NAN-S04 and class 1E 4.16 kV bus PBB-S04 inUnit 2 (which are also feed from startup transformer NAN-X03) weredeenergized. The loss of power to the class 1E 4.16 kV buses resulted ina valid ESFAS (JE) signal starting the Unit 1 Train A Emergency DieselGenerator (1EDG-A)(EK) and the Unit 2 EDG-B (2EDG-B). No further impactswere noted in Unit 2.

When Unit 1 PBA-S03 deenergized, the control power (NNN-Dll) to theFeedwater Control System (FWCS)(JB) and Steam Bypass Control System(SBCS)(JI) was lost when the automatic bus transfer (ABT) switch did nottransfer to its "Normal" (non-class) power supply (NAN-S01).Subsequently, Main Feedwater Pump A (MFP-A)(SG) went to minimum speed,causing water levels in both steam generators (SG)(AB) to decrease. Steam

Generator Number 2 (SG-2) water level reached the Reactor ProtectionSystem (RPS)(JC) trip setpoint resulting in a reactor trip at 0322 MST.

Required plant equipment and safety systems responded to the event asdesigned. No other safety actuations occurred and none were required.The plant was stabilized in Mode 3 (HOT STANDBY) at approximately 0348 'MST

on December 9, 1995.

2. EVENT DESCRIPTION:

On December 9, 1995, at approximately 0320 MST, Unit 1 was in Mode 1

(POWER OPERATION) at approximately 40 percent power. Condenser hotwell(SG) leak detection activities were in progress in condenser shell C when

a momentary phase to ground occurred on the Z winding of NAN-X03, phase C,

causing relay 386-T1,, Transfer Differential, to trigger from a phaseimbalance which deenergized the non-Class 1E 13.8 kV buses NAN-SOS,

Page 8: LER 95-014-00:on 951209,reactor tripped following ...

il

Page 9: LER 95-014-00:on 951209,reactor tripped following ...

'LICENSEE EVENT REPORT (LER) TEXT CONTINUATION

ACILAYNAME

Palo Verde Unit 1

DOCKETNUMBER LER NUMBERSEQUENTIAl

NUMBEREVISIO

NUMBER

PAGE

0 5 0 0 0 5 2 8 9 5 0 1 4 0 .0 0 3 of 0 7

NAN-S03, and the Class 1E, 4.16 kV bus (PBA-S03)in Unit 1. Also, non-class13.8 kV buses NAN-S06, NAN-S04, and class 1E 4.16 kV bus PBB-S04 in Unit 2

were deenergized.

The loss of power to the class 1E 4.16 kV buses resulted in a valid ESFAS

signal starting EDG-A in Unit 1 and EDG-B in Unit 2. There were no otheractions required in Unit 2, and the remainder of the event description isfor Unit 1 only.

When PBA-S03 ("Emergency" power supply) was deenergized, the ABT forNNN-Dll responded to the undervoltage condition and attempted to transferto the "Normal" power source (NHM13). (Note: NNN-Dll was lined up to the"Emergency" power supply per Operations'rocedures as the preferred powersource.)

The ABT switch is a break-before-make switch which causes output voltageto drop for approximately 0.5 seconds on a transfer. During the event,the ABT switch attempted to transfer to the "Normal" power source;however, the Normal" breaker did not close, leaving both supply breakersopen at the same time. This resulted in the deenergization of bus NNN-Dllfor approximately ninety seconds.

The deenergization of bus NNN-D11 resulted in a loss of power to the FWCS.

With the loss of power to the FWCS and its components, the economizervalves failed "as is," MFP-A went to the governor minimum speed, and .themaster controllers reverted to manual with no output. Non-safety relatedcontrol room indications of valve positions, flows, and SG levels werelost. Annunciation of the loss of FWCS power was received. All of theabove is expected on a loss of power to the FWCS. (Note: MFP-B was notin service at the time because the plant was at 40,percent power and asecond MFP is not required at this power level.)

At approximately 0322 MST on December 9, 1995, the Unit 1 reactor (AC)

tripped when SG-2 water level reached the RPS trip setpoint for low SG

water level following the degradation of main FW flow.

With the loss of power, the SBCS went to Emergency Off, all SBCVs failedclosed as designed, and annunciation of loss of SBCS, rack power wasreceived. Without any automatic functions, reactor coolant system (RCS)

temperature and SG pressure were controlled by a main steam safety valve(MSSV) (SB, RV) and atmospheric dump valves, (ADVs) (SB) until the SBCS was

Page 10: LER 95-014-00:on 951209,reactor tripped following ...

II V'C

Page 11: LER 95-014-00:on 951209,reactor tripped following ...

LICENSEE EVENT REPORT (LER) TEXT CONTINUATION

ACiLITYNAME

Palo Verde Unit 1

OOCKETNUMBERYEAR -:-i

LER NUMBERSEQUENTNL

NUMBERSIO

NUMBER

PAGE

0 5 0 0 0 5 2 8 S 5 0 1 4 0 0 0 4 0 7

available for use. Required plant equipment and safety systems respondedto the event as designed. No other safety system actuations occurred andnone were required.

The Shift Supervisor diagnosed the event as an uncomplicated reactor trip.At approximately 0348 MST on December 9, 1995, the plant was stabilized inMode 3 (HOT STANDBY).

3. ASSESSMENT OF THE SAFETY CONSEQUENCES AND IMPLICATION OF THIS EVENT:

This Unit 1 reactor trip can be classified as a Loss of Feedwater which isa moderate frequency event. Equipment and systems assumed in SafetyAnalysis were functional, and plant response was normal for the situationthat occurred. Scenarios defined in Updated Final Safety Analysis Report(UFSAR) Chapter 15 and design assumptions of the reactor protection systemare bounding for this event. Scenarios defined in UFSAR Chapter 6,concerning Loss of Coolant Accidents (LOCA), were not challenged duringthis transient.

The reactor coolant system (RCS)(AB) pressure peak was below 2275 poundsper square inch absolute (psia) during this event. The peak pressurecriteria of 110 percent of design (2750 psia) was not challenged duringthis RCS pressure transient. The steam generator peak pressure was

approximately 1246 psia. A main steam safety valve operated as designedto maintain SG pressure until the ADVs were used to maintain SG pressure.The ADVs were used until the SBCS became available to maintain SG

pressure.

The transient did not cause any violation of the Specified Acceptable FuelDesign Limits (SAFDLs). This event did not result in any challenges tothe fission product barriers or result in any releases of radioactivematerials. Therefore, there were no adverse safety consequences orimplications as a result of this event. This event did not adverselyaffect the safe operation of the plant or the health and safety of thepublic.

Page 12: LER 95-014-00:on 951209,reactor tripped following ...
Page 13: LER 95-014-00:on 951209,reactor tripped following ...

LICENSEE EVENT REPORT (LER) TEXT CONTINUATION

ACIUlYNAME

Palo Verde Unit 1

DOCKETNUMBER LER NUMBERSEOUENTIAL EVISIO

NUMBER . NUMBER

PAGE

4. CAUSE OF THE EVENT:

0 5 0 0 0 5 2 6 gl5 0 1 4 - 0 0 0 5 of 0 7

An incident investigation for the Unit 1 reactor trip is being performedin accordance-,with the APS Corrective Action Program. The cause for theUnit 1 reactor trip was that the transfer switch malfunctioned by nottransferring to its "Normal" power source (SALP Cause Code B: Design).APS'esign does not provide immediate uninterrupted transfer of power forthe FWCS upon loss of power. The current plant configuration is inaccordance with design; however, the 500 milliseconds that it takes totransfer power is not adequate to ensure that the FWCS control power isnot interrupted.

No unusual characteristics of the work location (e.g., noise, heat, orpoor lighting) directly contributed to this event. There were noprocedural errors which contributed to this event.

Zf the incident investigation results differ from this determination or ifinformation is developed which would affect the readers understanding orperception of this event, a supplement to this report will .be submitted'.

5. STRUCTURES, SYSTEMS, OR COMPONENTS INFORMATZONI

On December 9, 1995, while Unit 1 Control Room personnel were changing thebreaker configuration of NNN-Dll to .the "Normal" power source, the"Normal" breaker would not close. Upon investigation, ElectricalMaintenance personnel (utility, nonlicensed) determined that NNN-Dll wouldnot transfer from "Emergency" to "Normal" and that it had not transferredduring the reactor trip.

NNN-Dll's transfer switch is manufactured by General Electric and themodel number is CR160TC. The switch's operating voltage is 120 VAC andhas a current rating of 400 amps.

6. CORRECTIVE ACTIONS TO PREVENT RECURRENCE:

The incident investigation of the event has not been completed to date.Any corrective actions identified will be tracked under the APS CommitmentAction Tracking System.

On December 9, 1995, Electrical Maintenance performed an as-found visualinspection of the breakers and ABT for NNN-Dll; no obvious problems were

Page 14: LER 95-014-00:on 951209,reactor tripped following ...

0

Page 15: LER 95-014-00:on 951209,reactor tripped following ...

LICENSEE EVENT REPORT (LER) TEXT CONTINUATION

ACILllYNAME DOCKET NUMBER LER NUMBER PAGE

Palo Verde Unit 1

YEAR ";:.'„: SEQUENTIAL SIONUMBER NUMBER

0 5 0 0 0 5 2 8 9 5 0 1 4 - 0 0 06of 0 7

noted. Upon testing, NNN-Dll would not automatically transfer to the"Normal" from the "Emergency" power supply but would consistentlyautomatically transfer from the "Normal" to the "Emergency" power supply.

On December 10, 1995, the operating mechanism was removed from NNN-Dll andwas tested in a spare breaker assembly. The alignment was satisfactory,and the operating mechanism would operate in both manual positions. The

operating mechanism was being reinstalled in NNN-Dll when it was

identified that the support bracket on the left side of the "Normal"source breaker had a gap of approximately one-eighth .of an inch. All ofthe other support brackets were flush against their respective breakers.Visual inspection revealed that a micarta clipboard was. used as a, shim.The shim was removed, and the operating mechanism was reinstalled on thebreaker assembly with satisfactory alignment. However, when tested, theoperating mechanism would not close in the "Normal" position withoutmanual assistance.

Review of the work history for NNN-Dll did not reveal the time period, thatthe shim was installed. Electrical Maintenance personnel involved introubleshooting NNN-Dll during the refueling outage (1RS) did not noticethat a shim was installed nor did they install a shim.

On December 10, 1995, Plant Management decided to leave the work orderopen and to replace the supply breakers during the next refueling outage.This decision .was reviewed and concurred by the Plant Review Board. Thisdecision was based. on the following two facts:

1. If power is lost while in the "Normal" position, the fast bus transfercan swap power to the motor control center that feeds NNN-Dll fasterthan the ABT could transfer if on the "Emergency" source. (Refer toSection 8, Additional 1nformation)

2. If the fast bus transfer failed and total power was lost to the"Normal" power supply, the unit would trip anyway because of the lossof power to two reactor coolant pumps.

On December 9, 1995, a night order was issued to all three units detailingthe power configuration for NNN-Dll and NNN-D12 in Unit 1 and a briefhistory and explanation for the change.

Page 16: LER 95-014-00:on 951209,reactor tripped following ...

II

Page 17: LER 95-014-00:on 951209,reactor tripped following ...

LICENSEE EVENT REPORT (LER) TEXT CONTINUATION

AGILITYNAME DOCKETNUMBER LER NUMBER PAGE

Palo Verde Unit 1

YEAR i,; SEOUENTIAL 'IONUMBER NUMBER

0'5 0 0 0 5 2 8 9 5 0 1 4 - 0 0 0 70f0 7EXT By December 21, 1995, Unit 1 Operation procedures were revised to reflect

the Plant Management decision to align NNN-Dll to the "Normal" powersupply. This decision was reviewed and concurred by the Plant ReviewBoard. LER 529/95-005 identified a Unit 2 reactor trip,due to low levelin SG-2. The cause of the trip was that the FWCS did not considermomentary power interruptions. The evaluations of this event to improvethe FWCS have not been completed to date. The corrective. actions takenfor LER 529/95-005 would not have prevented this event because the ABT didnot automatically transfer.

If the evaluation results differ from this determination or if informationis developed which would affect the readers understanding or perception ofthis event, a supplement to this report will be submitted.

7. PREVIOUS SIMILAR EVENTS:

Reactor trips attributed to a Feedwater Control System (FWCS) malfunctionhave been previously reported in LERs 528/95-008, 530/94-007, 530/94-005,530/93-001 and 529/92-001. The corrective actions taken in these previousevents would not hav= prevented this event from occurring.

8. ADDITIONAL INFORMATION:

Figure 1.0 provides a simplified electrical drawing of the non-Class 1E AC

distribution system for Unit 1. The three startup transformers (NAN-X01,NAN-X02, and NAN-X03) connect to the switchyard through two 525 kVswitchyard breakers each and feed six 13.8 kV intermediate buses (NAN-S05

and NAN-S06). These buses are arranged in three pairs, each feeding onlyone unit.

Each startup transformer is capable of supplying 100 percent of thestartup or normally operating loads of one unit simultaneously with theESF loads associated with two load groups of another unit. The non-Class1E AC:buses normally are supplied through the startup transformers. Inthe event of failure of the unit auxiliary transformer, turbine trip, orreactor trip, an automatic fast transfer of the 13.8 kV buses to thestartup transformers is initiated to provide power to the auxiliary loads.During power operation, the unit auxiliary transformers (MAN-X02) supplytwo 13.8 kV buses (NAN-X01 and NAN-X02) which provide the'majority of thepower to the non-Class 1E loads.

Page 18: LER 95-014-00:on 951209,reactor tripped following ...

Il 0 r

Page 19: LER 95-014-00:on 951209,reactor tripped following ...

Simplifie Electrical Braving, Unit 1, Igure 1.0

WESTW1NG

STARTUPAE-NAN-X03

3TARTUPAE-NAN-X01

GRID

NORM. ALIE-NANZ05 ) NC NO )

) NC 3'8KV

)NC

2ENANS06

YARDBRK

@QUAN XFMR525-22.8KVIE-~-X01

GENERATOR Unit Aux~ 24- 13.8KVIE-MAN-X02

Fast Bus Transfer ) NCIE-NAN-S03 2 IE-NAN-SOI

) NC NO )"""".

13.8 - 4.160KVESF XFMRIE-NBN-X03

P

13800-480V

IE-NGN-L25)NC

1E-NHN-M13

)NC

416OV Ne1E-NNN-V11

IE-PBA-S03

) NO

480:120V120 VAC, Non-Class 1E

1E-NNN-DIINormal

4160-480V

> NC:IE PGA.~L3-I

0NC: IE-PHA-M31

)NC

EhIERG. DG A

lE-NN

4803 l20VV13'mergencyAUTO

XFRSWITCH

Nore: Dl l & DI2 are

Normally kft on

Emer8ency source.

FWCS/SBCS

Page 20: LER 95-014-00:on 951209,reactor tripped following ...

il 41J


Recommended