    What is PMI? PMI is the leading global association for the

    project management profession

    Certification for Project Managers

    Experience neededExam

  • 7/31/2019 Lesson8 PMP v2

    3/35

    PMI provides certification as a ProjectManagement Professional (PMP )

    A PMP has documented sufficient projectexperience, has agreed to follow a codeof ethics, and has passed the PMP exam

    The number of people earning PMPcertification is increasing quickly

  • 7/31/2019 Lesson8 PMP v2

    4/35

    Internationally acceptedaccreditation

    Get certification 3 (5 without degree) years experience 35 hours training 4 hour, 200 questions, multiple choice

    exam

  • 7/31/2019 Lesson8 PMP v2

    5/35

    Twenty years ago, PMI volunteers sat downto distill the project management body ofknowledge. This eventually became thePMBOK Guide, now considered one of themost essential tools in the profession and isthe de facto global standard for the industry.

    More than a million copies of the PMBOK Guide-2000 Edition are in use

  • 7/31/2019 Lesson8 PMP v2

    6/35

    There are five process groups that comprisethe project management life cycle.

    There are Nine PM knowledge areasWithin these five process groups there are42 project management processesyou wont need to use all of the processeson every project.Large projects may use most of itSmall projects may not use many of it.

  • 7/31/2019 Lesson8 PMP v2

    7/35

    The five process groups are: Initiating Planning Executing Monitoring and Controlling Closing

  • 7/31/2019 Lesson8 PMP v2

    8/35

  • 7/31/2019 Lesson8 PMP v2

    9/35

    It covers nine knowledge areas are: Project Integration Management Project Scope Management

    Project Time Management Project Cost Management Project Quality Management Project Human Resource Management Project Communications Management Project Risk Management Project Procurement Management

  • 7/31/2019 Lesson8 PMP v2

    10/35

  • 7/31/2019 Lesson8 PMP v2

    11/35

    Knowledge areas describe the keycompetencies that project managers mustdevelop

    Four core knowledge areas lead to specific projectobjectives (scope, time, cost, and quality) Four facilitating knowledge areas are the means

    through which the project objectives are achieved(human resources, communication, risk, and

    procurement management One knowledge area (project integrationmanagement) affects and is affected by all of theother knowledge areas

    All knowledge areas are important

  • 7/31/2019 Lesson8 PMP v2

    12/35

  • 7/31/2019 Lesson8 PMP v2

    13/35

  • 7/31/2019 Lesson8 PMP v2

    14/35

    Ensuring that the project includes all the work required, onlythe work required.Dividing the work into major pieces, then subdividing intosmaller, more manageable pieces.Work Breakdown Structure

  • 7/31/2019 Lesson8 PMP v2

    15/35

    Process Project Group Key Deliverables

    Collect Requirements planning Requirements document

    Define Scope planning project scope statement

    Create WBS planning WBS, WBS dictionary

    Verify Scope Monitoring and Controlling Acceptance deliverables

    Control Scope Monitoring and Controlling Change Requests

  • 7/31/2019 Lesson8 PMP v2

    16/35

    Estimating TimeScheduling

    Network Critical Path MethodMilestones

  • 7/31/2019 Lesson8 PMP v2

    17/35

    Similar to Time Estimating (usually done by the sameperson/group that does the Time Estimates)

    Calculation of Cost for each WP: Example:If estimate was duration 10 daysAssign human resources 2 people

    Effort = Duration x Resources E=2x10=20pd

    e.g., Resource Cost (RC) = Effort x Rate(includes overhead)

    RC=20x$1,000=$20,000

    (Possible) Plus Fixed Cost (FC)

    e.g., FC = $5,000

    Total cost (TC) = Resource cost + Fixed Cost

    TC=20,000 + 5,000 = 25,000

  • 7/31/2019 Lesson8 PMP v2

    18/35

    ID Task Name Account Fixed Cost Total Cost36 Final Submission $0.00 $33,000.00

    37 Final Design Work C14 $5,000.00 $25,000.00

    38 Final Plan C14 $0.00 $8,000.00

    39 TB Submission $0.00 $0.00

    40 EPA $0.00 $0.00

    41 Software (Subcontract 50-B) $0.00 $133,000.00

    42 SW Design $12,000.00 $62,000.00

    43 Do Prelim SW desig n S21 $0.00 $20,000.00

    44 PDR $0.00 $0.00

    45 Do Final SW design S22 $0.00 $30,000.00

    46 CDR $0.00 $0.00

    47 SW Construction $12,000.00 $71,000.00

    48 Code CSC A S31 $0.00 $6,000.00

    49 Code CSC B S31 $0.00 $8,000.00

    50 Integrate&Tst CSCI 1 S32 $0.00 $20,000.00

  • 7/31/2019 Lesson8 PMP v2

    19/35

    $100,000.00

    $200,000.00

    $300,000.00

    $400,000.00

    Cumulativ e Cost :

    Filtered resources Total:

    CPM Total:

    Q3 Q4 Q1 Q2 Q3 Q4 Q11997 1998

    $53,920.00 $127,160.00 $274,360.00 $331,440.00 $349,920.00 $368,400.00 $376,500.00

  • 7/31/2019 Lesson8 PMP v2

    20/35

    1. Identification Anticipate the risk List the risks, event triggers, symptoms

    2. Analysis Evaluate probability, impact Qualitative vs Quantitative

    3. Risk Response Strategy Development to mitigate the risk:

    Eliminate the risk or reduce impactContingency planning

    4. Risk Control Monitor Update lists, strategies Action the contingency plan Fight the fires

  • 7/31/2019 Lesson8 PMP v2

    21/35

    Availability & Assign PeopleSkills

    More experienced peopleLess experienced people

    Similar tasks to one person to use learning curveAssign critical tasks to most reliable peopleTasks that need interaction or are similar

    Same personTwo who communicate

    Personality and team communication does matter andagain, Availability

  • 7/31/2019 Lesson8 PMP v2

    22/35

    There are several ways to define projectsuccess

    The project met scope, time, and cost goals The project satisfied the customer/sponsor The results of the project met its main

    objective

  • 7/31/2019 Lesson8 PMP v2

    23/35

  • 7/31/2019 Lesson8 PMP v2

    24/35

    Project managers need a wide variety of skills

    They should:

    Be comfortable with change

    Understand the social, political and physical

    environments of the organizations they work in andwith

    Be able to lead teams to accomplish project goals

    24

  • 7/31/2019 Lesson8 PMP v2

    25/35

    Job descriptions vary, but most includeresponsibilities like planning, scheduling,coordinating, and working with people to

    achieve project goalsRemember that 97% of successful projects wereled by experienced project managers, who can

    often help influence success factors

    25

  • 7/31/2019 Lesson8 PMP v2

    26/35

    The Project Management Body of KnowledgeApplication area knowledge, standards, andregulationsProject environment knowledgeGeneral management knowledge and skillsSoft skills or human relations skills

    26

  • 7/31/2019 Lesson8 PMP v2

    27/35

    1. People skills2. Leadership3. Listening

    4. Integrity, ethical behavior, consistent5. Strong at building trust6. Verbal communication7. Strong at building teams8. Conflict resolution, conflictmanagement9. Critical thinking, problem solving10. Understands, balances priorities

    27

  • 7/31/2019 Lesson8 PMP v2

    28/35

    Large projects: leadership, relevant priorexperience, planning, people skills, verbalcommunication, and team-building skills are mostimportant

    High uncertainty projects: risk management,expectation management, leadership, peopleskills, and planning skills are most importantVery novel projects: leadership, people skills,having vision and goals, self-confidence,expectations management, and listening skills aremost important

    28

  • 7/31/2019 Lesson8 PMP v2

    29/35

  • 7/31/2019 Lesson8 PMP v2

    30/35

    SKILL PERCENTAGE OFRESPONDENTSProject/program management 60%

    Business process management 55%Business analysis 53%Application development 52%Database management 49%Security 42%Enterprise architect 41%Strategist/internal consultant 40%

    30

    In a 2006 survey by CIO.com, IT executives ranked project/programmanagement the skills that would be the most in demand in the next

    few years

  • 7/31/2019 Lesson8 PMP v2

    31/35

    Capability Maturity Model - IntegratedCMMI is a process improvement

    approach that provides organizationswith the essential elements of effectiveprocesses that ultimately improve their performance.CMMI can be used to guide processimprovement across a project

  • 7/31/2019 Lesson8 PMP v2

    32/35

    It helps integrate: organizational functions

    set process improvement goals and priorities guidance for quality processes

  • 7/31/2019 Lesson8 PMP v2

    33/35

  • 7/31/2019 Lesson8 PMP v2

    34/35

  • 7/31/2019 Lesson8 PMP v2

    35/35

    A Guide to the Project Management Body ofKnowledge (2003). The Project Management Institute.http://www.pmi.org

    Rakos, John J. et al, A Practical Guide to ProjectManagement Documentation, Wiley, 2004

    Kerzner, Harold. Project Management: A SystemsApproach to Planning, Scheduling and Controlling. 6 th ed. John Wiley & Sons, 1998.

    Rakos, John J. Software Project Management for Smallto Medium Sized Projects. Prentice-Hall, 1990.