+ All Categories
Home > Documents > Lessons from the Pathfinder: KAT-7 to meerKATto SKA · PDF fileFibre Junction box Digitiser...

Lessons from the Pathfinder: KAT-7 to meerKATto SKA · PDF fileFibre Junction box Digitiser...

Date post: 20-Mar-2018
Category:
Upload: lythien
View: 212 times
Download: 0 times
Share this document with a friend
26
Lessons from the Pathfinder: KAT-7 to meerKAT to SKA T. L. Venkatasubramani T. L. Venkatasubramani Sub-System Manager – RFE (KAT-7) Sub-System Manager – STaN (meerKAT) Bruce Wallace SKA-SA Site Bid Manager SKA-South Africa SKA STaN CoDR, Jodrell Bank, 28-30 June 2011 STan CoDR Draft A
Transcript

Lessons from the Pathfinder: KAT-7 to meerKAT to SKA

T. L. VenkatasubramaniT. L. VenkatasubramaniSub-System Manager – RFE (KAT-7)

Sub-System Manager – STaN (meerKAT)

Bruce Wallace SKA-SA Site Bid Manager

SKA-South Africa

SKA STaN CoDR, Jodrell Bank, 28-30 June 2011STan CoDR Draft A

•Quite a lot has been learnt while building kat-7•These are currently being applied to meerKAT•The experience gained is of direct relevance to SKA

The approach in the presentation is to

Approach

The approach in the presentation is to give an overview without going into the full depth of a topic right now and to provide additional details on specific issues of interest during the discussions.

STan CoDR Draft A

•RF Broadband (1.2 to 1.95 GHz) analog optical fibre link over 5 km with required stability, repeatability, gain flatness, Signal-to-Noise and Head room for kat-7

Success of the effort can be judged by the fact that the overall system is in critical study on a 24x7 basis by the Commissioning and Operations Team for the past one year. There has been

STaN in SKA-SA

and Operations Team for the past one year. There has been negligible issues with the STaN after the initial hiccups were resolved by late 2010.

•40 GB digital link OVER ABOUT 11 km for meerKAT.•Long haul Data links over hundreds of kms for supporting KAT-7 and meerKAT requirements

STan CoDR Draft A

The SKA-SA Efforts for STaN has highly benefited by involving Industry

The key players are:

1. FOXCOMM, Israel (R&D on Standard Analog OTx-ORx Units

Industry Partners

1. FOXCOMM, Israel (R&D on Standard Analog OTx-ORx Units for Radio Astronomy needs and Supply)

2. CBi, South Africa (R&D on OF Cables, Supply)3. SIA, South Africa (Commissioning, Installation)4. Aurecon, South africa (Reticulation)5. NSN , Germany (OTx-ORx, Digital)

Note that the E-O and O -E segments of the receptor were treated as a part of the KAT-7 STaN

STan CoDR Draft A

The Karoo Site

STan CoDR Draft A

•RF Broadband (1.2 to 1.95 GHz) analog optical fibre link over 5 km with required stability, repeatability, gain flatness, Signal-to-Noise and Head room for kat-7

Success of the effort can be judged by the fact that the overall system is in critical study on a 24x7 basis by the Commissioning and Operations Team for the past one year. There has been

STaN in SKA-SA

and Operations Team for the past one year. There has been negligible issues with the STaN after the initial hiccups were resolved by late 2010.

•40 GBe digital link OVER ABOUT 11 km for meerKAT.•Long haul Data links over hundreds of kms for supporting KAT-7 and meerKAT requirements

STan CoDR Draft A

KAT-7 PathFinderA Bird’s Eye View

The Antenna Services Container (ASC), the

Node Point where fibre cables from seven

antennas meet and continue as a single

cableCabinet at Antenna pedestal

STan CoDR Draft A

KAT-7 PathFinder

The Computing

Container (CC)

Where the fibres

From all KAT-7

The Reticulation Design

From all KAT-7

antennas terminate

And RF signals are

down-converted

For the Digital

Back-end

STan CoDR Draft A

•40 mm sub-ducts installed in 110 mm sleeves

•Conventional cable and blown fibre considered -conventional cable implemented due to ~50% cost

• 48 fibre Single Mode cable installed from ASC to CC for a distance of 5 kms without any joints.

•Man holes at a spacing of 500m was constructed to help in

Salient Features

•Man holes at a spacing of 500m was constructed to help in pulling the cable

•Length from ASC to antenna pedestal is around 200m. Composite cable with 12 Core MM and 12 SM fibres intalled.

• SM currently in operation for analog RF transmission and MM, for CAM purposes

•E2000 connectors selected as a standard

•All fibre buried at 1 m below surface to minimise temperature effects

STan CoDR Draft A

•Incoming quality inspection EXTREMELY IMPORTANT

•The initial behaviour of non-repeatable performance was traced to the non-concentricity in the pigtails and patch cords supplied, thanks to the investigation helped by the advanced facilities available at CBi

Lessons Learnt

helped by the advanced facilities available at CBi

•The whole batch was changed after one year of supply

•This was possible because acceptance procedures involving measurements with OTDR, Optical Loss and RF loss techniques were laid in the tender

LESSON: Include incoming inspection and verification of components in the planning stage!!

STan CoDR Draft A

DELINK the antenna pedestal availability and Buried Optical Fibreinstallation, test and release targetsFor meerKAT , the process is getting

Lessons Learnt

For meerKAT , the process is getting defined to ensure the above

LESSON: Eliminate linking two jobs with different time lines

STan CoDR Draft A

Be allergic to dust…. A Fibreoscopetells all!The process of “cleaning” an optical fibre connector sometimes only

Lessons Learnt

fibre connector sometimes only moves the dust around without ACTUALLY removing itLESSON: Do not be satisfied by just Doing… See and confirm.

STan CoDR Draft A

Avoid junction points with over-the -ground facilities like ASC if possible. •Note ASC was an ESSENTIAL NEED for the Fringe Finder phase of KAT -7 project. All the mid -coupler junctions at ASC have

Lessons Learnt

All the mid -coupler junctions at ASC have now been spliced.LESSON: If there is no need to do any checking at intermediate junction point/s it is better to splice, protect and BURY the joint – Concept to be followed for meerKAT

STan CoDR Draft A

The meerKAT STaN

CC

C

L-band Receiver

Fibre Junction box

DigitiserNoise

switching

UHF-band Receiver

CAM unit

CAM ethernet

Noise

switching

X-band Receiver

CAM unit

CAM ethernet

Noise

switching

Receiver2 fibre cable

Receiver1 fibre cable

Receiver

CAM

Rece

iver

CA

M

3

3

Digitiser fibre

cable

17

Feed Indexer

Vacuum

pump

CKey:Connector

interface

Fibre optic

cable

Conductive

CAM cables

CA

M e

thern

et

CA

M e

th

CAM

ethernet

The meerKAT StaN will

Have 18 fibres from each

Antenna focus to pedestal 2 cores - reference clock

2 cores - 1PPS

2x4 = 8 cores for digitised Data

6 spare to make 18 fibres

There will be 6 fibred used

at pedestal,

CC

Pedestal

L band Receiver

CAM fibre cable to focus

Receptor fibre cable

Receiver3 fibre cableCAM unit

CAM ethernet

Noise

switching

Receiver CAM

Data, clock,

PPS & CAM

fibres

Receptor CAM2

Data (8)

Clock(2)

1PPS(2)

14 (+10 spares = 24)

8

20

3

ACU RFI shielded box

Sw

itch

Position

controller

8

2

Receiver &

digitiser CAMPatch

Panel

17

14

1210

GM

compressor

TrenchesTo mini-subs

(circuit breaker monitoring)

C

Mini-sub

monitoring

eth

ernet

C

2

C

Yoke/Outside Pedestal

at pedestal, 2 for CAM and 4 spare

THUS A 24 SM FIBRE

NETWORK FOR EACH OF

THE 64 ANTENNAS TO A

COMMON LOCATION 12

KMS AWAY IS REQUIRED.

This is considered as a Low

Risk Option and actual

Usage can change as the

receiver design evolves

STan CoDR Draft A

The meerKAT STaN

The solution for a

24-core flexible

Optical cable

Which could be

Strung from

Pedestal to focus

Through azimuth

And elevationAnd elevation

Loops has been

Successfully solved.

The Alpha version

Of the cable is

Undergoing field

Evauation in a few

of the KAT-7

Antennas

STan CoDR Draft A

The meerKAT STaN

A Christmas Tree

Structure has been

designed with sub-sub-

nodes, sub-nodes and

nodes through

which buried cables

originating from

each of the 64 antennaeach of the 64 antenna

pedestals congregate

into 4 nodes

with out any splicing.

The buried cable

continues from the 4

nodes to Karoo

Array Processor Building

(KPAB) to complete the

transport scheme

STan CoDR Draft A

The meerKAT KPAB

The design of the signal

Path ADC and following

digital Circuitry at

focus , pedestal (if

needed) and KPAB has

Been assigned to DBE

Sub-system ManagerSub-system Manager

Discussions with NSN is

In progress to evaluate

The suitability of their

Products for the

meerKAT signal chain

STan CoDR Draft A

1. A new 33 kV Powerline has been constructed from Carnarvon to the SKA Core site encompassing a MASS (Metal-Armoured Self Supporting) fibre optic cable implemented as the earth-wire.

2. SKA SA has established the SKA SA POP Station in Carnarvon.

The Long-Haul

POP Station in Carnarvon.

3. SANReN has implemented a 10 Gbit/s fibre “metro ring” from the SKA POP site in Carnarvon, connecting the Losberg Core Site and the Klerefontein Support Base. This will provide full flexibility between these three sites. The sites terminate in Cisco switches with DWDM functionality.

Carnarvon POP Site

STan CoDR Draft A

4. A contract has been placed by SANReN (South African National Research Network) on SA national operators Neotel / Broadband Infraco for the initial 10 Gbit/s connectivity from Cape Town to Carnarvon. The full fibre optic connectivity will be in place by end June 2011.

5. SANReN placed a contract on the SA national operator Telkom for a temporary capacity of 10 Mbit/s from Carnarvon to the SKA Cape Town Project Office to facilitate KAT-7 antenna commissioning

The Long-Haul

Town Project Office to facilitate KAT-7 antenna commissioning activities. This fibre link will be upgraded in future to provide a redundant fibre optic link. The link from Losberg to Cape Town office was commissioned in November 2010 enabling KAT-7 remote operations.

6. The SKA Cape Town Project Office will be connected into the new SANReN fibre optic DWDM Cape Town “metro ring” mid 2011. This will provide full DWDM fibre connectivity via the Infraco L/D network from SKA Core Site to Cape Town.

STan CoDR Draft A

The Long-Haul

STan CoDR Draft A

The Long-Haul

STan CoDR Draft A

1. The current fibre network provides the foundation for the future SKA transport network from the Core Site to Cape Town or Mtunzini for connectivity to the undersea cable systems.

2. Broadband Infraco will install an additional170 kms of fibre optic cable to provide a fully redundant DWDM fibre network from the MeerKAT Site to Cape Town (as per previous diagram). An additional fibre cable will be incorporated into the power supply system required for the SKA Core site.

The Long-Haul

required for the SKA Core site.

3. The initial Telkom SA link will be retained to provide an additional level of redundancy via a totally independent operator network

4. The fibre network will interface to the WACS (West African Cable System) submarine cable from Cape Town to Europe / United Kingdom with a capacity of 5.12 Tbit/s. 10/100 Gbit/s reserved for MeerKAT/SKA respectively. Redundancy to this system to Europe will be provided by East Coast cable systems such as SEACOM / EASY / SAFE cable systems.

STan CoDR Draft A

The Long-Haul

The African Under-sea

Cable System

STan CoDR Draft A

The three antenna cores and the antenna network spirals out to 180 kmswill be implemented as a private network. The fibre optic cable network will be installed in the most cost effective network for both electrical and data transport networks. Nokia Siemens Networks (NSN) are assisting with the development of equipment to meet the asymmetrical nature of the network but with fully management capability across all DWDM wavelengths.

The remote sites will be overlaid on the networks of three of the SA fibre

The Long-Haul

The remote sites will be overlaid on the networks of three of the SA fibre optic network operators. Discussions are in hand to develop the following options:

Access to dark fibre / utilise existing repeater infrastructure

Access to managed bandwidths

Access to servitudes / provision own electronics

The same process will be applied to the African Partner countries. A comprehensive report has been received from a UK-based consultancy to confirm the availability of fibre networks and/or managed bandwidth.

STan CoDR Draft A

De-link the implementation and commissioning frominfrastructure development, where possible, to avoiddelays and extended fibre commissioning times.

Always be prepared for bad products – ImplementIncoming Inspection and Verification process for allcomponents

Implement a large number of spare fibres, especially in

In summary……

Implement a large number of spare fibres, especially inbackhaul routes - the requirement grows!

Consider dust in arid conditions, especially duringconstruction periods (which normally align with fibrecommissioning periods). Implementation of gravelsurfaces was a great improvement.

Challenge: follow-up on all network builds and detail as-built records. Be ahead of the game to maintain in-houseconfidence in the record system!

STan CoDR Draft A

And….

Thanx for the patient listening!

Any questions?

STan CoDR Draft A


Recommended