LEVER 3rd PARTNER MEETING Presenter: Agnieszka Dadak Copengahen, 10 – 11 of April 2017
Transcript
Page 1: LEVER 3rd PARTNER MEETING FAIE - presentation of wp0… · WP 06: upstart pilot work, June – Dec 2016 • August 2016: an invitation to cooperation within the LEVER project published

LEVER

3rd PARTNER MEETING

Presenter Agnieszka Dadak

Copengahen 10 ndash 11 of April 2017

Key results and outcome of the initiation of the pilot work

including pilot courses (WP 06)

WP 06 upstart pilot work June ndash Dec 2016

bull August 2016 an invitation to cooperation within the LEVER project published (Ngopl portal ngopl newsletter FAIEs webpage amp FB mailing to local and regional institutions and organisations)

bull 5 applications received from interested organisationsinformal groups from the South of Poland

bull 2 groups one association and one informal group were invited to cooperation after preliminary dialogues via telephoneexchange of e-mails

bull 2 introductory meetings 19-09-2016 (Czernica) and 30-11-2016 (Goacutera Ropczycka) took place

WP 06 upstart pilot work June ndash Dec 2016

Our local teams

1) Stowarzyszenie Działań Lokalnych bdquoSpichlerzrdquo (Association of Local Activities bdquoSpichlerzrdquo) Czernica Śląskie voivodeship

httpwwwsdlspichlerzpl

2) Informal group from Goacutera Ropczycka Podkarpackie voivodeship

httpwwwpolskaatrakcyjnaplatrakcjapark-buczyna-w-gorze-ropczyckiejportal_attraction5Bquery5D=Muzeum+Dobranocek+ze+ZbiorC3B3w+Wojciecha+Jamy+w+Rzeszowieamppage=8

Pilot courses (WP 06) 1) Training in Czernica 19-11-2016

bdquoPlanning developing and relising projects by culture boostersrdquo

Training modules

1 Project logics (planning needs analysis goals setting activities planning budget and schedule development risks and results monitoring evaluation)

2 Business opportunities for NGOrsquos

3 Networking clustering partnerships building local strategies building

4 Team building and organizing team work

5 Conducting marketing and promotional activities by NGOrsquos

6 Grants opportunities for co-financing the projects

Pilot courses (WP 06) 2) Webinar for the team from Goacutera Ropczycka 15-12-2016

bdquoAssociation or foundationrdquo Subjects 1 The planned objectives and actions organizational forms 2 Association types of associations conditions of registration registration documents 3 Foundation the conditions of establishing registration documents 4 The legal responsibilities reporting and administrative provisions related to running an association 5 The legal responsibilities reporting and administrative provisions related to running a foundation 6 Associationrsquos bodies and their role general assembly board revision committee 7 Foundation bodies and their role founder board council 8 The advantages and disadvantages of the association 9 The advantages and disadvantages of the foundation

Plans for implementing the pilot work (WP 09)

1) bdquoSpichlerzrdquo Association

Celebrations of the 700th anniversary of the Czernica village

bull Start of planning autumn 2016

bull An idea To celebrate together inviting all interested to cooperation

bull Activities started in January until now planned by September Main events May-August 2017 (The Czernicka Museums Night the Historic Picnic and street run LARP micro-grants ndash local society ideas realisation)

httpwww7wiekow7zyczenpl

bull Main challenge To reach outside region with information amp promotion (short-term) to build widely recognisable local brand bdquoThe Zamekrdquo (long-term)

2) Goacutera Ropczycka informal group

Local summer event

bull Start of planning winter 2016

bull An asset Buczyna Park in Goacutera Ropczycka access to potential sponsors

bull Ideas for activities Light illuminations showa concerta cabareton an opera in the park thematic evenings (musical)

bull Main challenge To register a foundation and to organise 1st event (short-term) to create new sustainable workplace (long-term)

Our short-term plans

To organise a meeting of the 2 local teams

An idea for monitoring

I bdquoHISTORICAL DRAFTrdquo The place the teamhellip II AN IDEA

1 Where from ideas for activities 2 What activitiesevents are planned III MONITORING OF PREPARATIONREALISATION

3 Who takes part in preparations Who are the members of the realisation team(s) 4 At what stage are the preparations at the moment 5 Which local stakeholders support the initiative (for ex Local institutions authorities businesses important persons other organisations) What kind of support they offer 6 In what way the local society is involved in planning and preparing the activities 7 At the moment what is the main challenge What causes troublesis difficult 8 At the moment What goes better than supposed What works best 9 At the moment What kind of support would be most useful for the realisation team (materialorganisational at realisation at promotion otherhellip) 10 What is the next stage of works (next milestone) 11 How are the activities financedplanned to be financed

Dissemination activities (Jan-March 2017) - Discussing the cooperation at the meetings with The Norwegian Crafts Institute (Norsk haringndverksinstitutt) and The Norwegian Arts and Crafts Association (Norges Husflidslag) 02-04 of February 2017 during the study-visit to Norway - Presenting the project during the meeting with Senior volunteers of the bdquoSpichlerzrdquo Association in Czernica 14-03-2017 - Regular information on wwwfundacjaaieeu and FB profile httpspl-plfacebookcomFundacjaAIE

Thank you for attention

Agnieszka Dadak Foundation of Alternative Educational Initiatives

Bielsko-Biała POLAND wwwfundacjaaieeu faiefundacjaaieeu

+48 511 551 439

Page 2: LEVER 3rd PARTNER MEETING FAIE - presentation of wp0… · WP 06: upstart pilot work, June – Dec 2016 • August 2016: an invitation to cooperation within the LEVER project published

Key results and outcome of the initiation of the pilot work

including pilot courses (WP 06)

WP 06 upstart pilot work June ndash Dec 2016

bull August 2016 an invitation to cooperation within the LEVER project published (Ngopl portal ngopl newsletter FAIEs webpage amp FB mailing to local and regional institutions and organisations)

bull 5 applications received from interested organisationsinformal groups from the South of Poland

bull 2 groups one association and one informal group were invited to cooperation after preliminary dialogues via telephoneexchange of e-mails

bull 2 introductory meetings 19-09-2016 (Czernica) and 30-11-2016 (Goacutera Ropczycka) took place

WP 06 upstart pilot work June ndash Dec 2016

Our local teams

1) Stowarzyszenie Działań Lokalnych bdquoSpichlerzrdquo (Association of Local Activities bdquoSpichlerzrdquo) Czernica Śląskie voivodeship

httpwwwsdlspichlerzpl

2) Informal group from Goacutera Ropczycka Podkarpackie voivodeship

httpwwwpolskaatrakcyjnaplatrakcjapark-buczyna-w-gorze-ropczyckiejportal_attraction5Bquery5D=Muzeum+Dobranocek+ze+ZbiorC3B3w+Wojciecha+Jamy+w+Rzeszowieamppage=8

Pilot courses (WP 06) 1) Training in Czernica 19-11-2016

bdquoPlanning developing and relising projects by culture boostersrdquo

Training modules

1 Project logics (planning needs analysis goals setting activities planning budget and schedule development risks and results monitoring evaluation)

2 Business opportunities for NGOrsquos

3 Networking clustering partnerships building local strategies building

4 Team building and organizing team work

5 Conducting marketing and promotional activities by NGOrsquos

6 Grants opportunities for co-financing the projects

Pilot courses (WP 06) 2) Webinar for the team from Goacutera Ropczycka 15-12-2016

bdquoAssociation or foundationrdquo Subjects 1 The planned objectives and actions organizational forms 2 Association types of associations conditions of registration registration documents 3 Foundation the conditions of establishing registration documents 4 The legal responsibilities reporting and administrative provisions related to running an association 5 The legal responsibilities reporting and administrative provisions related to running a foundation 6 Associationrsquos bodies and their role general assembly board revision committee 7 Foundation bodies and their role founder board council 8 The advantages and disadvantages of the association 9 The advantages and disadvantages of the foundation

Plans for implementing the pilot work (WP 09)

1) bdquoSpichlerzrdquo Association

Celebrations of the 700th anniversary of the Czernica village

bull Start of planning autumn 2016

bull An idea To celebrate together inviting all interested to cooperation

bull Activities started in January until now planned by September Main events May-August 2017 (The Czernicka Museums Night the Historic Picnic and street run LARP micro-grants ndash local society ideas realisation)

httpwww7wiekow7zyczenpl

bull Main challenge To reach outside region with information amp promotion (short-term) to build widely recognisable local brand bdquoThe Zamekrdquo (long-term)

2) Goacutera Ropczycka informal group

Local summer event

bull Start of planning winter 2016

bull An asset Buczyna Park in Goacutera Ropczycka access to potential sponsors

bull Ideas for activities Light illuminations showa concerta cabareton an opera in the park thematic evenings (musical)

bull Main challenge To register a foundation and to organise 1st event (short-term) to create new sustainable workplace (long-term)

Our short-term plans

To organise a meeting of the 2 local teams

An idea for monitoring

I bdquoHISTORICAL DRAFTrdquo The place the teamhellip II AN IDEA

1 Where from ideas for activities 2 What activitiesevents are planned III MONITORING OF PREPARATIONREALISATION

3 Who takes part in preparations Who are the members of the realisation team(s) 4 At what stage are the preparations at the moment 5 Which local stakeholders support the initiative (for ex Local institutions authorities businesses important persons other organisations) What kind of support they offer 6 In what way the local society is involved in planning and preparing the activities 7 At the moment what is the main challenge What causes troublesis difficult 8 At the moment What goes better than supposed What works best 9 At the moment What kind of support would be most useful for the realisation team (materialorganisational at realisation at promotion otherhellip) 10 What is the next stage of works (next milestone) 11 How are the activities financedplanned to be financed

Dissemination activities (Jan-March 2017) - Discussing the cooperation at the meetings with The Norwegian Crafts Institute (Norsk haringndverksinstitutt) and The Norwegian Arts and Crafts Association (Norges Husflidslag) 02-04 of February 2017 during the study-visit to Norway - Presenting the project during the meeting with Senior volunteers of the bdquoSpichlerzrdquo Association in Czernica 14-03-2017 - Regular information on wwwfundacjaaieeu and FB profile httpspl-plfacebookcomFundacjaAIE

Thank you for attention

Agnieszka Dadak Foundation of Alternative Educational Initiatives

Bielsko-Biała POLAND wwwfundacjaaieeu faiefundacjaaieeu

+48 511 551 439

Page 3: LEVER 3rd PARTNER MEETING FAIE - presentation of wp0… · WP 06: upstart pilot work, June – Dec 2016 • August 2016: an invitation to cooperation within the LEVER project published

WP 06 upstart pilot work June ndash Dec 2016

bull August 2016 an invitation to cooperation within the LEVER project published (Ngopl portal ngopl newsletter FAIEs webpage amp FB mailing to local and regional institutions and organisations)

bull 5 applications received from interested organisationsinformal groups from the South of Poland

bull 2 groups one association and one informal group were invited to cooperation after preliminary dialogues via telephoneexchange of e-mails

bull 2 introductory meetings 19-09-2016 (Czernica) and 30-11-2016 (Goacutera Ropczycka) took place

WP 06 upstart pilot work June ndash Dec 2016

Our local teams

1) Stowarzyszenie Działań Lokalnych bdquoSpichlerzrdquo (Association of Local Activities bdquoSpichlerzrdquo) Czernica Śląskie voivodeship

httpwwwsdlspichlerzpl

2) Informal group from Goacutera Ropczycka Podkarpackie voivodeship

httpwwwpolskaatrakcyjnaplatrakcjapark-buczyna-w-gorze-ropczyckiejportal_attraction5Bquery5D=Muzeum+Dobranocek+ze+ZbiorC3B3w+Wojciecha+Jamy+w+Rzeszowieamppage=8

Pilot courses (WP 06) 1) Training in Czernica 19-11-2016

bdquoPlanning developing and relising projects by culture boostersrdquo

Training modules

1 Project logics (planning needs analysis goals setting activities planning budget and schedule development risks and results monitoring evaluation)

2 Business opportunities for NGOrsquos

3 Networking clustering partnerships building local strategies building

4 Team building and organizing team work

5 Conducting marketing and promotional activities by NGOrsquos

6 Grants opportunities for co-financing the projects

Pilot courses (WP 06) 2) Webinar for the team from Goacutera Ropczycka 15-12-2016

bdquoAssociation or foundationrdquo Subjects 1 The planned objectives and actions organizational forms 2 Association types of associations conditions of registration registration documents 3 Foundation the conditions of establishing registration documents 4 The legal responsibilities reporting and administrative provisions related to running an association 5 The legal responsibilities reporting and administrative provisions related to running a foundation 6 Associationrsquos bodies and their role general assembly board revision committee 7 Foundation bodies and their role founder board council 8 The advantages and disadvantages of the association 9 The advantages and disadvantages of the foundation

Plans for implementing the pilot work (WP 09)

1) bdquoSpichlerzrdquo Association

Celebrations of the 700th anniversary of the Czernica village

bull Start of planning autumn 2016

bull An idea To celebrate together inviting all interested to cooperation

bull Activities started in January until now planned by September Main events May-August 2017 (The Czernicka Museums Night the Historic Picnic and street run LARP micro-grants ndash local society ideas realisation)

httpwww7wiekow7zyczenpl

bull Main challenge To reach outside region with information amp promotion (short-term) to build widely recognisable local brand bdquoThe Zamekrdquo (long-term)

2) Goacutera Ropczycka informal group

Local summer event

bull Start of planning winter 2016

bull An asset Buczyna Park in Goacutera Ropczycka access to potential sponsors

bull Ideas for activities Light illuminations showa concerta cabareton an opera in the park thematic evenings (musical)

bull Main challenge To register a foundation and to organise 1st event (short-term) to create new sustainable workplace (long-term)

Our short-term plans

To organise a meeting of the 2 local teams

An idea for monitoring

I bdquoHISTORICAL DRAFTrdquo The place the teamhellip II AN IDEA

1 Where from ideas for activities 2 What activitiesevents are planned III MONITORING OF PREPARATIONREALISATION

3 Who takes part in preparations Who are the members of the realisation team(s) 4 At what stage are the preparations at the moment 5 Which local stakeholders support the initiative (for ex Local institutions authorities businesses important persons other organisations) What kind of support they offer 6 In what way the local society is involved in planning and preparing the activities 7 At the moment what is the main challenge What causes troublesis difficult 8 At the moment What goes better than supposed What works best 9 At the moment What kind of support would be most useful for the realisation team (materialorganisational at realisation at promotion otherhellip) 10 What is the next stage of works (next milestone) 11 How are the activities financedplanned to be financed

Dissemination activities (Jan-March 2017) - Discussing the cooperation at the meetings with The Norwegian Crafts Institute (Norsk haringndverksinstitutt) and The Norwegian Arts and Crafts Association (Norges Husflidslag) 02-04 of February 2017 during the study-visit to Norway - Presenting the project during the meeting with Senior volunteers of the bdquoSpichlerzrdquo Association in Czernica 14-03-2017 - Regular information on wwwfundacjaaieeu and FB profile httpspl-plfacebookcomFundacjaAIE

Thank you for attention

Agnieszka Dadak Foundation of Alternative Educational Initiatives

Bielsko-Biała POLAND wwwfundacjaaieeu faiefundacjaaieeu

+48 511 551 439

Page 4: LEVER 3rd PARTNER MEETING FAIE - presentation of wp0… · WP 06: upstart pilot work, June – Dec 2016 • August 2016: an invitation to cooperation within the LEVER project published

WP 06 upstart pilot work June ndash Dec 2016

Our local teams

1) Stowarzyszenie Działań Lokalnych bdquoSpichlerzrdquo (Association of Local Activities bdquoSpichlerzrdquo) Czernica Śląskie voivodeship

httpwwwsdlspichlerzpl

2) Informal group from Goacutera Ropczycka Podkarpackie voivodeship

httpwwwpolskaatrakcyjnaplatrakcjapark-buczyna-w-gorze-ropczyckiejportal_attraction5Bquery5D=Muzeum+Dobranocek+ze+ZbiorC3B3w+Wojciecha+Jamy+w+Rzeszowieamppage=8

Pilot courses (WP 06) 1) Training in Czernica 19-11-2016

bdquoPlanning developing and relising projects by culture boostersrdquo

Training modules

1 Project logics (planning needs analysis goals setting activities planning budget and schedule development risks and results monitoring evaluation)

2 Business opportunities for NGOrsquos

3 Networking clustering partnerships building local strategies building

4 Team building and organizing team work

5 Conducting marketing and promotional activities by NGOrsquos

6 Grants opportunities for co-financing the projects

Pilot courses (WP 06) 2) Webinar for the team from Goacutera Ropczycka 15-12-2016

bdquoAssociation or foundationrdquo Subjects 1 The planned objectives and actions organizational forms 2 Association types of associations conditions of registration registration documents 3 Foundation the conditions of establishing registration documents 4 The legal responsibilities reporting and administrative provisions related to running an association 5 The legal responsibilities reporting and administrative provisions related to running a foundation 6 Associationrsquos bodies and their role general assembly board revision committee 7 Foundation bodies and their role founder board council 8 The advantages and disadvantages of the association 9 The advantages and disadvantages of the foundation

Plans for implementing the pilot work (WP 09)

1) bdquoSpichlerzrdquo Association

Celebrations of the 700th anniversary of the Czernica village

bull Start of planning autumn 2016

bull An idea To celebrate together inviting all interested to cooperation

bull Activities started in January until now planned by September Main events May-August 2017 (The Czernicka Museums Night the Historic Picnic and street run LARP micro-grants ndash local society ideas realisation)

httpwww7wiekow7zyczenpl

bull Main challenge To reach outside region with information amp promotion (short-term) to build widely recognisable local brand bdquoThe Zamekrdquo (long-term)

2) Goacutera Ropczycka informal group

Local summer event

bull Start of planning winter 2016

bull An asset Buczyna Park in Goacutera Ropczycka access to potential sponsors

bull Ideas for activities Light illuminations showa concerta cabareton an opera in the park thematic evenings (musical)

bull Main challenge To register a foundation and to organise 1st event (short-term) to create new sustainable workplace (long-term)

Our short-term plans

To organise a meeting of the 2 local teams

An idea for monitoring

I bdquoHISTORICAL DRAFTrdquo The place the teamhellip II AN IDEA

1 Where from ideas for activities 2 What activitiesevents are planned III MONITORING OF PREPARATIONREALISATION

3 Who takes part in preparations Who are the members of the realisation team(s) 4 At what stage are the preparations at the moment 5 Which local stakeholders support the initiative (for ex Local institutions authorities businesses important persons other organisations) What kind of support they offer 6 In what way the local society is involved in planning and preparing the activities 7 At the moment what is the main challenge What causes troublesis difficult 8 At the moment What goes better than supposed What works best 9 At the moment What kind of support would be most useful for the realisation team (materialorganisational at realisation at promotion otherhellip) 10 What is the next stage of works (next milestone) 11 How are the activities financedplanned to be financed

Dissemination activities (Jan-March 2017) - Discussing the cooperation at the meetings with The Norwegian Crafts Institute (Norsk haringndverksinstitutt) and The Norwegian Arts and Crafts Association (Norges Husflidslag) 02-04 of February 2017 during the study-visit to Norway - Presenting the project during the meeting with Senior volunteers of the bdquoSpichlerzrdquo Association in Czernica 14-03-2017 - Regular information on wwwfundacjaaieeu and FB profile httpspl-plfacebookcomFundacjaAIE

Thank you for attention

Agnieszka Dadak Foundation of Alternative Educational Initiatives

Bielsko-Biała POLAND wwwfundacjaaieeu faiefundacjaaieeu

+48 511 551 439

Page 5: LEVER 3rd PARTNER MEETING FAIE - presentation of wp0… · WP 06: upstart pilot work, June – Dec 2016 • August 2016: an invitation to cooperation within the LEVER project published

Pilot courses (WP 06) 1) Training in Czernica 19-11-2016

bdquoPlanning developing and relising projects by culture boostersrdquo

Training modules

1 Project logics (planning needs analysis goals setting activities planning budget and schedule development risks and results monitoring evaluation)

2 Business opportunities for NGOrsquos

3 Networking clustering partnerships building local strategies building

4 Team building and organizing team work

5 Conducting marketing and promotional activities by NGOrsquos

6 Grants opportunities for co-financing the projects

Pilot courses (WP 06) 2) Webinar for the team from Goacutera Ropczycka 15-12-2016

bdquoAssociation or foundationrdquo Subjects 1 The planned objectives and actions organizational forms 2 Association types of associations conditions of registration registration documents 3 Foundation the conditions of establishing registration documents 4 The legal responsibilities reporting and administrative provisions related to running an association 5 The legal responsibilities reporting and administrative provisions related to running a foundation 6 Associationrsquos bodies and their role general assembly board revision committee 7 Foundation bodies and their role founder board council 8 The advantages and disadvantages of the association 9 The advantages and disadvantages of the foundation

Plans for implementing the pilot work (WP 09)

1) bdquoSpichlerzrdquo Association

Celebrations of the 700th anniversary of the Czernica village

bull Start of planning autumn 2016

bull An idea To celebrate together inviting all interested to cooperation

bull Activities started in January until now planned by September Main events May-August 2017 (The Czernicka Museums Night the Historic Picnic and street run LARP micro-grants ndash local society ideas realisation)

httpwww7wiekow7zyczenpl

bull Main challenge To reach outside region with information amp promotion (short-term) to build widely recognisable local brand bdquoThe Zamekrdquo (long-term)

2) Goacutera Ropczycka informal group

Local summer event

bull Start of planning winter 2016

bull An asset Buczyna Park in Goacutera Ropczycka access to potential sponsors

bull Ideas for activities Light illuminations showa concerta cabareton an opera in the park thematic evenings (musical)

bull Main challenge To register a foundation and to organise 1st event (short-term) to create new sustainable workplace (long-term)

Our short-term plans

To organise a meeting of the 2 local teams

An idea for monitoring

I bdquoHISTORICAL DRAFTrdquo The place the teamhellip II AN IDEA

1 Where from ideas for activities 2 What activitiesevents are planned III MONITORING OF PREPARATIONREALISATION

3 Who takes part in preparations Who are the members of the realisation team(s) 4 At what stage are the preparations at the moment 5 Which local stakeholders support the initiative (for ex Local institutions authorities businesses important persons other organisations) What kind of support they offer 6 In what way the local society is involved in planning and preparing the activities 7 At the moment what is the main challenge What causes troublesis difficult 8 At the moment What goes better than supposed What works best 9 At the moment What kind of support would be most useful for the realisation team (materialorganisational at realisation at promotion otherhellip) 10 What is the next stage of works (next milestone) 11 How are the activities financedplanned to be financed

Dissemination activities (Jan-March 2017) - Discussing the cooperation at the meetings with The Norwegian Crafts Institute (Norsk haringndverksinstitutt) and The Norwegian Arts and Crafts Association (Norges Husflidslag) 02-04 of February 2017 during the study-visit to Norway - Presenting the project during the meeting with Senior volunteers of the bdquoSpichlerzrdquo Association in Czernica 14-03-2017 - Regular information on wwwfundacjaaieeu and FB profile httpspl-plfacebookcomFundacjaAIE

Thank you for attention

Agnieszka Dadak Foundation of Alternative Educational Initiatives

Bielsko-Biała POLAND wwwfundacjaaieeu faiefundacjaaieeu

+48 511 551 439

Page 6: LEVER 3rd PARTNER MEETING FAIE - presentation of wp0… · WP 06: upstart pilot work, June – Dec 2016 • August 2016: an invitation to cooperation within the LEVER project published

Pilot courses (WP 06) 2) Webinar for the team from Goacutera Ropczycka 15-12-2016

bdquoAssociation or foundationrdquo Subjects 1 The planned objectives and actions organizational forms 2 Association types of associations conditions of registration registration documents 3 Foundation the conditions of establishing registration documents 4 The legal responsibilities reporting and administrative provisions related to running an association 5 The legal responsibilities reporting and administrative provisions related to running a foundation 6 Associationrsquos bodies and their role general assembly board revision committee 7 Foundation bodies and their role founder board council 8 The advantages and disadvantages of the association 9 The advantages and disadvantages of the foundation

Plans for implementing the pilot work (WP 09)

1) bdquoSpichlerzrdquo Association

Celebrations of the 700th anniversary of the Czernica village

bull Start of planning autumn 2016

bull An idea To celebrate together inviting all interested to cooperation

bull Activities started in January until now planned by September Main events May-August 2017 (The Czernicka Museums Night the Historic Picnic and street run LARP micro-grants ndash local society ideas realisation)

httpwww7wiekow7zyczenpl

bull Main challenge To reach outside region with information amp promotion (short-term) to build widely recognisable local brand bdquoThe Zamekrdquo (long-term)

2) Goacutera Ropczycka informal group

Local summer event

bull Start of planning winter 2016

bull An asset Buczyna Park in Goacutera Ropczycka access to potential sponsors

bull Ideas for activities Light illuminations showa concerta cabareton an opera in the park thematic evenings (musical)

bull Main challenge To register a foundation and to organise 1st event (short-term) to create new sustainable workplace (long-term)

Our short-term plans

To organise a meeting of the 2 local teams

An idea for monitoring

I bdquoHISTORICAL DRAFTrdquo The place the teamhellip II AN IDEA

1 Where from ideas for activities 2 What activitiesevents are planned III MONITORING OF PREPARATIONREALISATION

3 Who takes part in preparations Who are the members of the realisation team(s) 4 At what stage are the preparations at the moment 5 Which local stakeholders support the initiative (for ex Local institutions authorities businesses important persons other organisations) What kind of support they offer 6 In what way the local society is involved in planning and preparing the activities 7 At the moment what is the main challenge What causes troublesis difficult 8 At the moment What goes better than supposed What works best 9 At the moment What kind of support would be most useful for the realisation team (materialorganisational at realisation at promotion otherhellip) 10 What is the next stage of works (next milestone) 11 How are the activities financedplanned to be financed

Dissemination activities (Jan-March 2017) - Discussing the cooperation at the meetings with The Norwegian Crafts Institute (Norsk haringndverksinstitutt) and The Norwegian Arts and Crafts Association (Norges Husflidslag) 02-04 of February 2017 during the study-visit to Norway - Presenting the project during the meeting with Senior volunteers of the bdquoSpichlerzrdquo Association in Czernica 14-03-2017 - Regular information on wwwfundacjaaieeu and FB profile httpspl-plfacebookcomFundacjaAIE

Thank you for attention

Agnieszka Dadak Foundation of Alternative Educational Initiatives

Bielsko-Biała POLAND wwwfundacjaaieeu faiefundacjaaieeu

+48 511 551 439

Page 7: LEVER 3rd PARTNER MEETING FAIE - presentation of wp0… · WP 06: upstart pilot work, June – Dec 2016 • August 2016: an invitation to cooperation within the LEVER project published

Plans for implementing the pilot work (WP 09)

1) bdquoSpichlerzrdquo Association

Celebrations of the 700th anniversary of the Czernica village

bull Start of planning autumn 2016

bull An idea To celebrate together inviting all interested to cooperation

bull Activities started in January until now planned by September Main events May-August 2017 (The Czernicka Museums Night the Historic Picnic and street run LARP micro-grants ndash local society ideas realisation)

httpwww7wiekow7zyczenpl

bull Main challenge To reach outside region with information amp promotion (short-term) to build widely recognisable local brand bdquoThe Zamekrdquo (long-term)

2) Goacutera Ropczycka informal group

Local summer event

bull Start of planning winter 2016

bull An asset Buczyna Park in Goacutera Ropczycka access to potential sponsors

bull Ideas for activities Light illuminations showa concerta cabareton an opera in the park thematic evenings (musical)

bull Main challenge To register a foundation and to organise 1st event (short-term) to create new sustainable workplace (long-term)

Our short-term plans

To organise a meeting of the 2 local teams

An idea for monitoring

I bdquoHISTORICAL DRAFTrdquo The place the teamhellip II AN IDEA

1 Where from ideas for activities 2 What activitiesevents are planned III MONITORING OF PREPARATIONREALISATION

3 Who takes part in preparations Who are the members of the realisation team(s) 4 At what stage are the preparations at the moment 5 Which local stakeholders support the initiative (for ex Local institutions authorities businesses important persons other organisations) What kind of support they offer 6 In what way the local society is involved in planning and preparing the activities 7 At the moment what is the main challenge What causes troublesis difficult 8 At the moment What goes better than supposed What works best 9 At the moment What kind of support would be most useful for the realisation team (materialorganisational at realisation at promotion otherhellip) 10 What is the next stage of works (next milestone) 11 How are the activities financedplanned to be financed

Dissemination activities (Jan-March 2017) - Discussing the cooperation at the meetings with The Norwegian Crafts Institute (Norsk haringndverksinstitutt) and The Norwegian Arts and Crafts Association (Norges Husflidslag) 02-04 of February 2017 during the study-visit to Norway - Presenting the project during the meeting with Senior volunteers of the bdquoSpichlerzrdquo Association in Czernica 14-03-2017 - Regular information on wwwfundacjaaieeu and FB profile httpspl-plfacebookcomFundacjaAIE

Thank you for attention

Agnieszka Dadak Foundation of Alternative Educational Initiatives

Bielsko-Biała POLAND wwwfundacjaaieeu faiefundacjaaieeu

+48 511 551 439

Page 8: LEVER 3rd PARTNER MEETING FAIE - presentation of wp0… · WP 06: upstart pilot work, June – Dec 2016 • August 2016: an invitation to cooperation within the LEVER project published

1) bdquoSpichlerzrdquo Association

Celebrations of the 700th anniversary of the Czernica village

bull Start of planning autumn 2016

bull An idea To celebrate together inviting all interested to cooperation

bull Activities started in January until now planned by September Main events May-August 2017 (The Czernicka Museums Night the Historic Picnic and street run LARP micro-grants ndash local society ideas realisation)

httpwww7wiekow7zyczenpl

bull Main challenge To reach outside region with information amp promotion (short-term) to build widely recognisable local brand bdquoThe Zamekrdquo (long-term)

2) Goacutera Ropczycka informal group

Local summer event

bull Start of planning winter 2016

bull An asset Buczyna Park in Goacutera Ropczycka access to potential sponsors

bull Ideas for activities Light illuminations showa concerta cabareton an opera in the park thematic evenings (musical)

bull Main challenge To register a foundation and to organise 1st event (short-term) to create new sustainable workplace (long-term)

Our short-term plans

To organise a meeting of the 2 local teams

An idea for monitoring

I bdquoHISTORICAL DRAFTrdquo The place the teamhellip II AN IDEA

1 Where from ideas for activities 2 What activitiesevents are planned III MONITORING OF PREPARATIONREALISATION

3 Who takes part in preparations Who are the members of the realisation team(s) 4 At what stage are the preparations at the moment 5 Which local stakeholders support the initiative (for ex Local institutions authorities businesses important persons other organisations) What kind of support they offer 6 In what way the local society is involved in planning and preparing the activities 7 At the moment what is the main challenge What causes troublesis difficult 8 At the moment What goes better than supposed What works best 9 At the moment What kind of support would be most useful for the realisation team (materialorganisational at realisation at promotion otherhellip) 10 What is the next stage of works (next milestone) 11 How are the activities financedplanned to be financed

Dissemination activities (Jan-March 2017) - Discussing the cooperation at the meetings with The Norwegian Crafts Institute (Norsk haringndverksinstitutt) and The Norwegian Arts and Crafts Association (Norges Husflidslag) 02-04 of February 2017 during the study-visit to Norway - Presenting the project during the meeting with Senior volunteers of the bdquoSpichlerzrdquo Association in Czernica 14-03-2017 - Regular information on wwwfundacjaaieeu and FB profile httpspl-plfacebookcomFundacjaAIE

Thank you for attention

Agnieszka Dadak Foundation of Alternative Educational Initiatives

Bielsko-Biała POLAND wwwfundacjaaieeu faiefundacjaaieeu

+48 511 551 439

Page 9: LEVER 3rd PARTNER MEETING FAIE - presentation of wp0… · WP 06: upstart pilot work, June – Dec 2016 • August 2016: an invitation to cooperation within the LEVER project published

2) Goacutera Ropczycka informal group

Local summer event

bull Start of planning winter 2016

bull An asset Buczyna Park in Goacutera Ropczycka access to potential sponsors

bull Ideas for activities Light illuminations showa concerta cabareton an opera in the park thematic evenings (musical)

bull Main challenge To register a foundation and to organise 1st event (short-term) to create new sustainable workplace (long-term)

Our short-term plans

To organise a meeting of the 2 local teams

An idea for monitoring

I bdquoHISTORICAL DRAFTrdquo The place the teamhellip II AN IDEA

1 Where from ideas for activities 2 What activitiesevents are planned III MONITORING OF PREPARATIONREALISATION

3 Who takes part in preparations Who are the members of the realisation team(s) 4 At what stage are the preparations at the moment 5 Which local stakeholders support the initiative (for ex Local institutions authorities businesses important persons other organisations) What kind of support they offer 6 In what way the local society is involved in planning and preparing the activities 7 At the moment what is the main challenge What causes troublesis difficult 8 At the moment What goes better than supposed What works best 9 At the moment What kind of support would be most useful for the realisation team (materialorganisational at realisation at promotion otherhellip) 10 What is the next stage of works (next milestone) 11 How are the activities financedplanned to be financed

Dissemination activities (Jan-March 2017) - Discussing the cooperation at the meetings with The Norwegian Crafts Institute (Norsk haringndverksinstitutt) and The Norwegian Arts and Crafts Association (Norges Husflidslag) 02-04 of February 2017 during the study-visit to Norway - Presenting the project during the meeting with Senior volunteers of the bdquoSpichlerzrdquo Association in Czernica 14-03-2017 - Regular information on wwwfundacjaaieeu and FB profile httpspl-plfacebookcomFundacjaAIE

Thank you for attention

Agnieszka Dadak Foundation of Alternative Educational Initiatives

Bielsko-Biała POLAND wwwfundacjaaieeu faiefundacjaaieeu

+48 511 551 439

Page 10: LEVER 3rd PARTNER MEETING FAIE - presentation of wp0… · WP 06: upstart pilot work, June – Dec 2016 • August 2016: an invitation to cooperation within the LEVER project published

Our short-term plans

To organise a meeting of the 2 local teams

An idea for monitoring

I bdquoHISTORICAL DRAFTrdquo The place the teamhellip II AN IDEA

1 Where from ideas for activities 2 What activitiesevents are planned III MONITORING OF PREPARATIONREALISATION

3 Who takes part in preparations Who are the members of the realisation team(s) 4 At what stage are the preparations at the moment 5 Which local stakeholders support the initiative (for ex Local institutions authorities businesses important persons other organisations) What kind of support they offer 6 In what way the local society is involved in planning and preparing the activities 7 At the moment what is the main challenge What causes troublesis difficult 8 At the moment What goes better than supposed What works best 9 At the moment What kind of support would be most useful for the realisation team (materialorganisational at realisation at promotion otherhellip) 10 What is the next stage of works (next milestone) 11 How are the activities financedplanned to be financed

Dissemination activities (Jan-March 2017) - Discussing the cooperation at the meetings with The Norwegian Crafts Institute (Norsk haringndverksinstitutt) and The Norwegian Arts and Crafts Association (Norges Husflidslag) 02-04 of February 2017 during the study-visit to Norway - Presenting the project during the meeting with Senior volunteers of the bdquoSpichlerzrdquo Association in Czernica 14-03-2017 - Regular information on wwwfundacjaaieeu and FB profile httpspl-plfacebookcomFundacjaAIE

Thank you for attention

Agnieszka Dadak Foundation of Alternative Educational Initiatives

Bielsko-Biała POLAND wwwfundacjaaieeu faiefundacjaaieeu

+48 511 551 439

Page 11: LEVER 3rd PARTNER MEETING FAIE - presentation of wp0… · WP 06: upstart pilot work, June – Dec 2016 • August 2016: an invitation to cooperation within the LEVER project published

An idea for monitoring

I bdquoHISTORICAL DRAFTrdquo The place the teamhellip II AN IDEA

1 Where from ideas for activities 2 What activitiesevents are planned III MONITORING OF PREPARATIONREALISATION

3 Who takes part in preparations Who are the members of the realisation team(s) 4 At what stage are the preparations at the moment 5 Which local stakeholders support the initiative (for ex Local institutions authorities businesses important persons other organisations) What kind of support they offer 6 In what way the local society is involved in planning and preparing the activities 7 At the moment what is the main challenge What causes troublesis difficult 8 At the moment What goes better than supposed What works best 9 At the moment What kind of support would be most useful for the realisation team (materialorganisational at realisation at promotion otherhellip) 10 What is the next stage of works (next milestone) 11 How are the activities financedplanned to be financed

Dissemination activities (Jan-March 2017) - Discussing the cooperation at the meetings with The Norwegian Crafts Institute (Norsk haringndverksinstitutt) and The Norwegian Arts and Crafts Association (Norges Husflidslag) 02-04 of February 2017 during the study-visit to Norway - Presenting the project during the meeting with Senior volunteers of the bdquoSpichlerzrdquo Association in Czernica 14-03-2017 - Regular information on wwwfundacjaaieeu and FB profile httpspl-plfacebookcomFundacjaAIE

Thank you for attention

Agnieszka Dadak Foundation of Alternative Educational Initiatives

Bielsko-Biała POLAND wwwfundacjaaieeu faiefundacjaaieeu

+48 511 551 439

Page 12: LEVER 3rd PARTNER MEETING FAIE - presentation of wp0… · WP 06: upstart pilot work, June – Dec 2016 • August 2016: an invitation to cooperation within the LEVER project published

Dissemination activities (Jan-March 2017) - Discussing the cooperation at the meetings with The Norwegian Crafts Institute (Norsk haringndverksinstitutt) and The Norwegian Arts and Crafts Association (Norges Husflidslag) 02-04 of February 2017 during the study-visit to Norway - Presenting the project during the meeting with Senior volunteers of the bdquoSpichlerzrdquo Association in Czernica 14-03-2017 - Regular information on wwwfundacjaaieeu and FB profile httpspl-plfacebookcomFundacjaAIE

Thank you for attention

Agnieszka Dadak Foundation of Alternative Educational Initiatives

Bielsko-Biała POLAND wwwfundacjaaieeu faiefundacjaaieeu

+48 511 551 439

Page 13: LEVER 3rd PARTNER MEETING FAIE - presentation of wp0… · WP 06: upstart pilot work, June – Dec 2016 • August 2016: an invitation to cooperation within the LEVER project published

Thank you for attention

Agnieszka Dadak Foundation of Alternative Educational Initiatives

Bielsko-Biała POLAND wwwfundacjaaieeu faiefundacjaaieeu