LHC machine status ~ Daily Summary ~
Daily beam commissioning meetingWeek 38 - September 18th, 2015
CERN, Geneva, CH
S. Redaelli and J. Uythovenfor the LHC commissioning teams
S. Redaelli, LHC meeting, 19-09-2015 2
Activities of the last 24h
Until 15h00 : Fill 4381, 1033b. Time in stable beams: 12h20 15h00 → 18h00 : Recovery from CRYO, the injection
- “Overcharge” caused loss of cry conditions in P4 - Recurrent problem of last 3 fills, otherwise transients mastered for the filling
18h00 → 21h00 : Injection of next physics fill, same filling scheme - Suspected problems with ADT causing emittance blowup -> dumped first fill - Still blow up (B2-V)
21h00 → now : Fill 4384, ~10h in stable beams
S. Redaelli, LHC meeting, 19-09-2015 3
Fill summary and lumi status
About 75pb-1 in the last fill
S. Redaelli, LHC meeting, 19-09-2015 4
TDI vacuum
S. Redaelli, LHC meeting, 19-09-2015 5
Emittances Fill 4384
No obvious problems with the ADT, at least in B2VQ’ controlled well to 15-17, both planes, during injection
S. Redaelli, LHC meeting, 19-09-2015 6
Heat loads in recent fills
Hannes, Kevin for ecloud team
Fill 4381
S. Redaelli, LHC meeting, 19-09-2015 7
OP scans
T. Pieloni, C. Tambasco, J . Barranco
To be discussed at the LBOC
S. Redaelli, LHC meeting, 19-09-2015 8
Chili earthquake
http://earthquaketrack.com/quakes/2015-09-17-03-55-06-utc-6-5-35
By J. Wenninger
Around 02:00 AM (local time) the operation crews noticed that the beam (at injection) was moving radially although no modulation was turned on. They suspected a malfunctioning of the real-time systems, tried some things and then it went away…
Just after 07:00 AM (local time), during the shift handover, the crews again noticed a modulation of the radial position and an oscillating lifetime. Again suspected the real-time systems. When they called me and I looked at the data, I said as a joke ‘this looks like the Costa Rica earthquake’ unaware that earthquakes had hit Chili.
S. Redaelli, LHC meeting, 19-09-2015 9
Example of effect on orbit (event 1)! LHC radial orbit change between 01:45 and 02:15 (23:45-24:15 UTC). LHC at
injection energy. Radial amplitude is large (3 times larger than Costa Rica event, 200 microns).
! Roughly 1 hour after the 8.3M quake, which roughly fits a simple estimate based on a distance of 12’000 km at a speed of 4 km/s.
Period is ~ 25 seconds.
By J. Wenninger
S. Redaelli, LHC meeting, 19-09-2015 10
Plan
Intensity ramp up:After 2 good fills with 1033b, we want to add one more train!- Will find a convenient time after the meeting to proceed
MP validation of “1200b” step ongoing to go further over WE
ParasiticEoF: TCL and Roman pot scans, RF studies - this morning, aim for a dump at ~10hRF: bunch length test for heat load