+ All Categories
Home > Documents > LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, 2011

LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, 2011

Date post: 24-Feb-2016
Category:
Upload: jemma
View: 22 times
Download: 0 times
Share this document with a friend
Description:
Joint CERN-Pakistan Committee: 6 th meeting. LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, 2011. Status of LHC: electrical connections Description of shunt consolidation Quality Control Scenario for intervention Missing resources. 23 slides. - PowerPoint PPT Presentation
Popular Tags:
23
LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, 2011 23 slides Status of LHC: electrical connections Description of shunt consolidation Quality Control Scenario for intervention Missing resources Joint CERN-Pakistan Committee: 6 th meeting
Transcript
Page 1: LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, 2011

LHC Magnets/Splices Consolidation(20 minutes)

Francesco Bertinelli7 June, 2011

23 slides

Status of LHC: electrical connections Description of shunt consolidation Quality Control Scenario for intervention Missing resources

Joint CERN-Pakistan Committee: 6th meeting

Page 2: LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, 2011

LHC electrical interconnections

2

W bellows (see

later…)

Page 3: LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, 2011

13 kA (“main”) busbar interconnection splices

From L. Rossi, CERN Courier September 2010

3

Page 4: LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, 2011

Poor copper to copper continuity.Provided by butt soldered joints, this electrical quality depends on the:- tolerances of the mating surfaces- relative tolerances between 2 paired bus bars- cleaning of the surfaces- capacity of the soldering to fill the gap providing good contact- correct execution of the soldering.

Lack of internal contact SC cable to bus bar within the same cross-section: partial melting of the Sn-Ag in the bus bar during connection soldering, loss of solder

Need simultaneous presence of two effects:

4

Page 5: LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, 2011

2008-09: new Quench Protection nQPS S S S

S S S

EE111 EE112 EE113

EE211EE219

EE119

EE213 EE212

EE015EE014

EE013 EE012R= 100 W

EE111 EE112 EE113

EE211EE219

EE119

EE213 EE212

EE015EE014

EE013 EE012R= 100 W

DC current

MBB line

EE111 EE112 EE113

EE211EE219

EE119

EE213 EE212

EE015EE014

EE013 EE012R= 100 W

MBA line

V

5

Our new “eyes” !

Page 6: LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, 2011

LHC main IC splices today (SC)From Z.

Charifoulline

301 ± 85pΩ

Rmax = 2.7nΩRmax = 3.3nΩ

306** ± 313pΩ

(**) number of splices in the quads segments corrected, 1.3 added

Dipole Buses Quad Buses

12 23 34 45 56 67 78 81

Main Dipoles&Quads Bus, sorted by position, 2048 segmentsAll HWC pyramids and plus ~150 ramps to 3.5TeV analyzed

Top 10 Splice Resistances

2nΩ

6

Page 7: LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, 2011

Dipole magnets internal splicesFr

om R

. Prin

cipe,

A. Z

aghl

oul,

P. Fe

ssia

7

Page 8: LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, 2011

Dipole internal splices today (SC)From Z.

Charifoulline

12 23 34 45 56 67 78 81

12 23 34 45 56 67 78 81

3.1±1.2nΩ8 splices(but not all the same type)

1.4±1.3nΩ3 + 2* splices(* partially)

Main Dipoles

Main Quads

8

Page 9: LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, 2011

Cour

tesy

R. F

lora

, C.

Sche

uerle

in

(C17-A17)L2 +36μΩR16→+42μΩ(39.6μΩ, 26.6μΩ)

(C30-A30)L2 +36μΩR16→+29μΩ(41.3μΩ, 12.3μΩ)

(B29-A30)R1 +45μΩR16→+44μΩ

(22.8μΩ, 28.5μΩ, 29.9μΩ)

(B32-A33)R1 +39μΩR16→+53μΩ

(52.3μΩ, 24.9μΩ, 10.8μΩ)

(A18-B17)L2 +35μΩR16→+17μΩ

(28.0μΩ, 11.2μΩ, 13.4μΩ)

Biddle measurements: 1-2 main IC splices (NC)

9

Page 10: LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, 2011

The estimated R-8/R-16 random error is ±1 µΩ, and the systematic error is about +10 %.

R8/R16 test: main IC splices (NC)Co

urte

sy C

. Sch

euer

lein

10

Page 11: LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, 2011

Shunts on dipole interconnect

11

Page 12: LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, 2011

Chosen soldered alloy: Sn60-Pb40 for – Melting temperature (<221.15 Sn-Ag)– Wetting capability– Mechanical and electrical properties

Shunt description

Copper plate 15 mm wide, 3 mm thick.

Copper annealed at 400⁰ C for 2 hours to maximize RRR

12

Page 13: LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, 2011

Total magnet to magnet interconnects in the machine: 1 688

Total 13 kA splices: ~10 200 Number of splices to be redone: ~1 500

(15%) Number of shunts to be applied: ~27

000

Shunt work in numbers

13

Page 14: LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, 2011

Copper surface machining

14

Page 15: LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, 2011

The shunt soldering process

15

Page 16: LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, 2011

Isostatic assemblyMirror symmetry across H and V planes (assembly facilitate and cost saving)Allowed misalignment default V±5 mm, H±3 mmSecond insulation skin Pre-stress adjusted with accurate tooling (5kg)Helium ducts in order to give good cooling for the bus bars (no thermal barrier)

1) Shunt soldering in position2) Central insulation piece introduction between the bus bars3) Lateral insulation pieces introduction4) Polyimide foil wrapping around insulation pieces5) 316L collars tie clamping around

Insulation box and assembly procedure MB

16

Page 17: LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, 2011

Quality Control of main IC splices R_RT-top-side tests for the QC of individual

solder contacts. After repair the shunt contact on the wedge

of M3-QRL-connection, R_RT-top-side is reduced from 10.5 µΩ to 2.1 µΩ.

Comsol R_RT-top-side simulation for shunt with defect (courtesy S. Heck)

R_RT-top-side measurement configuration

17

Page 18: LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, 2011

Examples of damaged cables found in 2009 by the personnel performing the interconnection work

NCR 1002739: Entire cable squeezed between U-piece and wedge

NCR 990852, 2 strands cutNCR 992513: Cable overheated (>580 °C)

NCR 1002739: Entire cable was squeezed between U-piece and wedge 18

i.e. important to have experienced technicians,

specifically for the most critical activities

Page 19: LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, 2011

What activities are involved for IC work?

19

Page 20: LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, 2011

Orbital machining to cut open TIG welds

20

Page 21: LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, 2011

Duration of IC work at 50 IC/week (!!!) for critical activities, 14 weeks for 1st sector, 5 weeks later for 2nd sector, 49

weeks for 8 sectors 2 shift work (on different activities), some overlap:

• 6h–10h/break/11h-15h• 12h-16h/break/17h-21h

no learning curve, no built-in contingency, no account for holiday/closure periods

must work sequentially to adjacent sector, without access constraints (i.e. first cool-down and HWC powering)

big concern is the “other activities” to be done in parallel: more realistic is to consider an additional 2-3 months 21

Page 22: LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, 2011

Estimate of IC resources needed

22

ActivityIdentified,

trainedIdentified, but need training

Missing resources

Comment

Opening and closing W 8 20 TE-MSC-MNC, FSUs task oriented, Dubna Project Associates

Bellows inspection & protection, endoscopy beamlines 5 3 TE-VSC, Krakow Project Associates

Repair, reinstall & tack PIMs incl. 2 TE-VSC, FSUs

Orbital machining M sleeves and PIMs 3 3 5 FSUs

Busbar copper surfacing machining 7 TE-MSC-MNC

Electrical connections 8 9 3 FSUs, further CERN contribution?

QC electrical connections 4 14 TE-MSC-SCD, BE-OP

ELQA 13 10 Krakow Project Associates

Leak testing 12 7 AL 40-30 (S133 contract)

TIG welding M sleeves and PIMs 6 9 EN-MME and S142 contract

QC Welding 2 4 EN-MME, external contract, BE-OP

QC closing W 4 TE-MSC-MNC, BE-OP

Other 5 5 logistics, coordination, overall QA: further CERN contribution?

DN200 7 1 Dubna Project Associates

Special Intervention IC Team 7 4 9 TE-EPC, FSUs, further CERN contribution?

Total 70 72 57

Note: resources at peak

QPS 9 7 Krakow Project Associates

199

Pakistan Collaboration?

Page 23: LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, 2011

The current scenario

1 “train” only for standard activities A Special Intervention team to prepare non-

standard work before the arrival of the train Long Shutdown starting January (April?) 2013 [email protected] to replace F. Bertinelli

as IC&Magnet Long Shutdown Project Responsible starting 1 July, 2011

23


Recommended