+ All Categories
Home > Documents > LHC Performance Workshop – Chamonix, 24–28 January, 2011 Session 2 –Shutdown 2012

LHC Performance Workshop – Chamonix, 24–28 January, 2011 Session 2 –Shutdown 2012

Date post: 22-Feb-2016
Category:
Upload: iain
View: 25 times
Download: 0 times
Share this document with a friend
Description:
LHC Performance Workshop – Chamonix, 24–28 January, 2011 Session 2 –Shutdown 2012 Work Organisation for Splice Consolidation Francesco Bertinelli – TE/MSC 24 January, 2011 (15 minutes + 10 minutes discussion). Are there other systematic splice / circuit defects? - PowerPoint PPT Presentation
Popular Tags:
21
LHC Performance Workshop – Chamonix, 24–28 January, 2011 Session 2 –Shutdown 2012 Work Organisation for Splice Consolidation Francesco Bertinelli – TE/MSC 24 January, 2011 (15 minutes + 10 minutes discussion) 17 slide s Are there other systematic splice / circuit defects? Magnets / interconnects work organisation for shutdown Do we have the necessary resources? How long will the shutdown take? Cost?
Transcript
Page 1: LHC Performance Workshop – Chamonix, 24–28 January, 2011 Session 2 –Shutdown 2012

LHC Performance Workshop – Chamonix, 24–28 January, 2011Session 2 –Shutdown 2012

Work Organisation for Splice Consolidation

Francesco Bertinelli – TE/MSC24 January, 2011 (15 minutes + 10 minutes discussion)

17 slides

Are there other systematic splice / circuit defects? Magnets / interconnects work organisation for shutdown Do we have the necessary resources? How long will the shutdown take? Cost?

Page 2: LHC Performance Workshop – Chamonix, 24–28 January, 2011 Session 2 –Shutdown 2012

24 January, 2011 Splice Consolidation 2

LHC Splices Task Force Membership: F. Bertinelli, N. Catalan Lasheras, P. Fessia, C. Garion, S.

Mathot, A. Perin, C. Scheuerlein, S. Sgobba, H. Ten Kate, J.-P. Tock, A. Verweij, G. Willering

35 meetings, documented in www.cern.ch/LHCsplices work priorities:

• Design of 13 kA main interconnection splice consolidation (see P. Fessia)

• 6 kA praying hands splices• Overall risk assessment of splices

“1st” Splice Review (J. Strait / Fermilab, D. Bresson / Alstom, G. Ganetis / BNL, T. Ogitsu / KEK, F. Savary / ITER, P. Vedrine / Saclay), 18-22 October 2010

• 2nd Review (was) planned for September 2011 (Production Readiness)

Work organised within Group structure (TE-MSC and TE-MPE): to be followed up …

End of Task Force? June 2011 2

Page 3: LHC Performance Workshop – Chamonix, 24–28 January, 2011 Session 2 –Shutdown 2012

24 January, 2011 Splice Consolidation 3

6 kA praying hands splices Detailed electrical schematics done (types and number of splices) Mapping measurements of splice resistances at cold in the tunnel

(during Technical Stops, ongoing) average splice resistance 1.14 nΩ, no outliers

Review and collection of existing documentation Fatigue testing at cold in Block4

• 3 samples in series• 12 000 cycles to 9 kA, then 12 000 cycles to 6 kA without belt• microscopic examination of solder no deterioration of splice resistance (1.9 – 2.9 nΩ)

Planned upgrade of 6 kA QPS (will allow monitoring of segments) Plan for partial inspections during long shutdown keep present design

“issue has been laid to rest” (Splice Review)

3

Page 4: LHC Performance Workshop – Chamonix, 24–28 January, 2011 Session 2 –Shutdown 2012

24 January, 2011 Splice Consolidation 4

Min. / Max. splice resistance for each measurement

0.00

2.00

4.00

6.00

8.00

10.00

12.00

14.00

DFLC

S.7L

1.1

DFLC

S.7L

1.4

DFLC

S.7L

1.7

DFLC

S.7L

1.10

DFLC

S.7L

2.1

DFLC

S.7L

2.4

DFLC

S.7L

2.7

DFLC

S.7L

2.10

DFLC

S.7R

2.1

DFLC

S.7R

2.4

DFLC

S.7R

2.7

DFLC

S.7R

2.10

DFLC

S.7L

4.1

DFLC

S.7L

4.4

DFLC

S.7L

4.7

DFLC

S.7L

4.10

DFLC

S.7R

4.1

DFLC

S.7R

4.4

DFLC

S.7R

4.7

DFLC

S.7R

4.10

DFLC

S.7L

5.1

DFLC

S.7L

5.4

DFLC

S.7L

5.7

DFLC

S.7L

5.10

DF

LCS.

7R5.

1 DF

LCS.

7R5.

4DF

LCS.

7R5.

7 DF

LCS.

7R5.

10DF

LCS.

7L8.

1 DF

LCS.

7L8.

4DF

LCS.

7L8.

7 DF

LCS.

7L8.

10

DFLC

S.7R

8.1

DFLC

S.7R

8.4

DFLC

S.7R

8.7

DFLC

S.7R

8.10

Current lead name

Slop

e er

ror [

nW]

Maximuns

Minimums

L2Q10 -> Q7

R2Q10 -> Q7

L4Q10 -> Q7

R4Q10 -> Q7

L8Q10 -> Q7

R8Q10 -> Q7

L5Q10 -> Q7

R5Q10 -> Q7

L1Q10 -> Q7

4

Page 5: LHC Performance Workshop – Chamonix, 24–28 January, 2011 Session 2 –Shutdown 2012

24 January, 2011 Splice Consolidation 5

Sextupole spool circuit assessment (H. ten Kate) Octupole spool circuit assessment (D. Tommasini)

identified issues and started actions, ongoing but needing resources:• Prepare detailed electrical schematics (N. Catalan Lasheras,

…)• Model electrical circuits (A. Verweij, E. Ravaioli …)• Simulate hot spot temperatures after quenches (A. Verweij, A.

Perin)• Re-evaluate peak voltage levels at operation (N. Catalan

Lasheras)• …

MB circuit inventory of singularities (R. Principe) assessment is useful, needs integrated approach. H. ten Kate given

mandate (Sept. 2010) to guide and co-ordinate pool of “magnet experts” for the overall risk assessment: recommend practical actions, finish by May-June 2011.

no obvious showstoppers, but cannot exclude necessary actions once the risk assessment is completed (e.g. spiders?)

Overall risk assessment of splices

5

Page 6: LHC Performance Workshop – Chamonix, 24–28 January, 2011 Session 2 –Shutdown 2012

24 January, 2011 Splice Consolidation 6

Overall risk assessment of splices

6

Page 7: LHC Performance Workshop – Chamonix, 24–28 January, 2011 Session 2 –Shutdown 2012

24 January, 2011 Splice Consolidation 7

IC “train” - splice consolidation activities

e.g. activity “open & close W bellows”

For ~ 70-80 IC / week, requires 20 mechanics organised as 7-8 teams working in parallel

Cost ~2 500 kCHF

Cour

tesy

T. R

enag

lia

7

Page 8: LHC Performance Workshop – Chamonix, 24–28 January, 2011 Session 2 –Shutdown 2012

24 January, 2011 Splice Consolidation 8

Schedule for splice consolidation “train”

8

Page 9: LHC Performance Workshop – Chamonix, 24–28 January, 2011 Session 2 –Shutdown 2012

24 January, 2011 Splice Consolidation 9

Schedule for IC “train” work At 50 IC / week for critical activities“IC train work” 12 months, defined as “from first W open to last

W closed” Assuming:

• Work sequentially through adjacent sectors, starting at Point 4, clockwise

• No contingency included (learning, holidays …)• No RP limitations, no access limitations (cryogenics, testing,

…), no coactivity limitations (transport …)• 2 shifts (6h to 15h and 12h to 21h), Monday to Friday, 40 h /

week (FSU contracts)• Special Intervention Team (SIT) will intervene before the

“train” arrives to re-connect• To be integrated within overall shutdown planning

9

Page 10: LHC Performance Workshop – Chamonix, 24–28 January, 2011 Session 2 –Shutdown 2012

24 January, 2011 Splice Consolidation 10

Other activities before and after “train”

Beam OFF • Dedicated electrical testing at cold (see M. Pojer, N. Catalan

Lasheras)• Survey <100K• Start warm-up• Vacuum characterisation, leak testing and localisation (see P.

Cruikshank)• RP checks• RF ball test for PIMs• Disconnect BLM, survey wires, QPS wiring open first W

Close last W• RF ball test for PIMs• Reconnect BLM, survey wires, QPS wiring• Start cool-down• Electrical testing• Survey measure and smoothing <100K (~4 weeks per sector)• HWC Beam ON

Cour

tesy

D.

Miss

iaen

10

Page 11: LHC Performance Workshop – Chamonix, 24–28 January, 2011 Session 2 –Shutdown 2012

24 January, 2011 Splice Consolidation 11

Needed resources for IC/magnet workActivity Identified,

trained

Identified, but need training

Missing resources Comment

Opening and closing W 8 20 TE-MSC-MNC, FSUs task oriented, Dubna Project Associates

Bellows inspection & protection, endoscopy beamlines5 3 TE-VSC, Krakow Project Associates

Repair, reinstall & tack PIMs incl. 2 TE-VSC, FSUs

Orbital machining M sleeves and PIMs 3 3 5 FSUs

Busbar copper surfacing machining 7 TE-MSC-MNC

Electrical connections 8 9 3 FSUs, further CERN contribution?

QC electrical connections 4 13 TE-MSC-SCD, BE-OP

ELQA 13 10 Krakow Project Associates

TIG welding M sleeves and PIMs 6 9 EN-MME and S146 contract

QC Welding 2 4 EN-MME, external contract, BE-OP

QC closing W 4 TE-MSC-MNC, BE-OP

Other 5 5 logistics, coordination, overall QA: further CERN contribution?

DN200 7 1 Dubna Project Associates

Special Intervention IC Team 7 4 9 TE-EPC, FSUs, further CERN contribution?

Total 58 64 57179

11

Page 12: LHC Performance Workshop – Chamonix, 24–28 January, 2011 Session 2 –Shutdown 2012

24 January, 2011 Splice Consolidation 12

Needed resources for IC/magnet work

12

Page 13: LHC Performance Workshop – Chamonix, 24–28 January, 2011 Session 2 –Shutdown 2012

24 January, 2011 Splice Consolidation 13

Available resources Current estimate for IC/magnet work (IC train, SIT, DN200):

~200 persons needed (was ~130 in Chamonix 2010 !) ~1/3 are identified (but not all at CERN) and experienced: core team

from TE (including FSUs!), EN-MME, Krakow, Dubna After several discussion in 2010, identified ~1/3 as special

contributions:• TE-MSC-MNC (if injectors stopped and no issues with maintenance)• BE-OP (if injectors stopped),• TE-EPC• Krakow

Still missing ~1/3, mainly mechanics: ongoing discussions with PH-DT, BE-RF, but unrealistic to expect further Project Associates (Dubna, Protvino)

The balance 50-50 (experienced to new) for critical activities is already lost, resulting in increase in quality and follow-up risk

Possibilities:• Accept to increase duration of shutdown by 2-4 months• Recruit 5-10 additional FSUs in the next months, train and

integrate them to ongoing work (collimators, welding, busbars, …)13

Page 14: LHC Performance Workshop – Chamonix, 24–28 January, 2011 Session 2 –Shutdown 2012

24 January, 2011 Splice Consolidation 14

Available resourcesIC work resources: identified, trained

0

2

4

6

8

10

12

14

EN

-MM

E

TE-

MPE

TE

-MS

C-C

I

TE-

MSC

-LM

Fst

aff

TE-

MS

C-L

MF

FSU

TE

-MSC

-ML

TE-M

SC

-MN

C

TE-M

SC

-SC

D

TE-

VS

C

Kra

kow

Pro

j.A

ss.

Dub

na P

roj.

Ass

.

Num

ber o

ff

IC work resources: identified, need training

0

2

4

6

8

10

12

14

16

BE

-OP

TE-E

PC

TE-M

SC

-CI

TE-M

SC

-LM

F

TE-M

SC

-MN

C

TE-M

SC

-SC

D

TE-M

SC

-TF

TE-M

SC

-ML

Kra

kow

Pro

j.A

ss.

Dub

na P

roj.

Ass

.

Num

ber

off

Thanks for support!

Detailed work to identify names

14

Page 15: LHC Performance Workshop – Chamonix, 24–28 January, 2011 Session 2 –Shutdown 2012

24 January, 2011 Splice Consolidation 15

IC/magnet work organisation

Requires discussion, key roles still to be filled 15

IC Train work IC/magnets QA

P. Fessia to be defined

technical responsibility electrical QC: C. Scheuerleincomponents & tooling welding QC: to be defined

Open&close W vacuum QC: C. GarionCoordination EN-MME welding open & close W QC: to be defined

organise work with EDMS-Supportto be defined

Special Intervention Team ELQAweekly work planning

link to shutdown Coordination J.-P. Tock / N. Bourcey N. Catalan Lasheraslink to other intervenants

DN200 Team Vacuum

to be defined P. Cruikshank

Page 16: LHC Performance Workshop – Chamonix, 24–28 January, 2011 Session 2 –Shutdown 2012

24 January, 2011 Splice Consolidation 16

Cost estimates (kCHF)Chamonix 2010 Chamonix

2011Comments

Splice consolidation (99117)

2 000 (development

2010 and 2011)14 445

17 500 Copper surfacing, larger teams,save on QC (BE-OP)

ELQA 4 800 2 850 1 shift onlyVacuum 1 755 2 600 PIMs and QCCRG 400 400

Special Team - 2 600Total 23 400 26 000

16

Page 17: LHC Performance Workshop – Chamonix, 24–28 January, 2011 Session 2 –Shutdown 2012

24 January, 2011 Splice Consolidation 17

Conclusions i/ii Are there other systematic splice / circuit defects?

• we should know by June 2011 with the end of the Task Force risk assessment: currently no major showstoppers

Magnets / interconnects work organisation for shutdown• IC train, Special Intervention Team, DN200 Team• Some key roles still to be covered (QA, coordination)

Do we have the necessary resources?• No, Still missing 1/3, mainly mechanics• Efforts to identify additional resources has been done,

unrealistic to expect further contribution as Project Associates

17

Page 18: LHC Performance Workshop – Chamonix, 24–28 January, 2011 Session 2 –Shutdown 2012

24 January, 2011 Splice Consolidation 18

Conclusions ii/ii• Injectors stop would free valuable resources:

conditions and priorities to be clarified• Recruit 5-10 FSUs now and start integration and

trainingHow long will the shutdown take?

• defined as “IC train work” could be 12 months, but more realistic to consider 2-4 months extra

Cost?• splice consolidation “IC train”: 23 MCHF• Special Intervention Team: 3 MCHF

18

Page 19: LHC Performance Workshop – Chamonix, 24–28 January, 2011 Session 2 –Shutdown 2012

24 January, 2011 Splice Consolidation 19

Thanks for your attention

Acknowledgement: work, discussions, experience of Interconnections Teams, LHC Splices Task Force and many others

19

Page 20: LHC Performance Workshop – Chamonix, 24–28 January, 2011 Session 2 –Shutdown 2012

24 January, 2011 Splice Consolidation 2020

Supporting slides

Page 21: LHC Performance Workshop – Chamonix, 24–28 January, 2011 Session 2 –Shutdown 2012

24 January, 2011 Splice Consolidation 2121


Recommended