Date post: | 31-Mar-2015 |
Category: |
Documents |
Upload: | walter-morecraft |
View: | 217 times |
Download: | 0 times |
LHCb Status Report:LHCb Status Report: B-Physics with Tracking
SAC Review MeetingApril 20, 2007Marcel Merk
for the B-physics group
Contents:• Outer Tracker • Vertex Locator• Software
2
LHCb detector
10 mrad
b
b
250 mrad
3
Silicon strip detector Reconstruct primary and
secondary vertices Tracking, use R-Phi geometry Used in L1 trigger Pile-Up Trigger in L0
The VErtex LOcator in LHCb
4
Straw tube detector Momentum determination with
TT and magnet Tracking, use XUVX geometry 3 OT stations: T1, T2, T3
The Outer Tracker in LHCb
5
The Experiment
VeloOT
6
Outer Tracker - Collaboration
J. Amoraal, R. Arink, H. Band, Th.S. Bauer, A. Berkien, L. Ceelie,
G. Fanizzi, F. Jansen, B. M’charek, A. Pellegrino, O. v. Petten,
T. du Pree, J. Rovekamp, F. Schimmel, H. Schuijlenburg,
E. Simioni, T. Sluijk, J. Spelt, H.Terrier, N. Tuning, A. Zwart
The NIKHEF OT group:
Dortmund, Heidelberg, Warsaw, Cracow, Bejing, VU, Nikhef:
NIKHEF provides OT project leader
Nikhef Activities:•Mass production: mechanics & electronics•Infrastructure: frames and support bridge•Installation & quality Assurance•Irradiation studies
7
The Outer Tracker
C-frame OT
Bridge
Table & Cable Trays
Modules
8
OT Modules and Performance
One large module: 34 x 490 cm2
4 x 64 = 256 channels
Resolution: σ 200 µm
Plateau Efficiency: ε 100%
9
Detector Installation - completed
Front-End Boxes
LV,HV, ECS/TFC..
Cooling and Gas
Detector Modules
module
Δz
[mm
]
Mechanical installation precision:
z-coordinate: deviation within 1 mm
T2-Q02-XUX-layer
10
Electronics
First C-frame equipped with FE boxes
HV board: 900 of 2000 tested and assembled Problem with alignment holes
ASDBLR amplifier board: All 4000 boards produced
OTIS TDC board: Total 2000 boards needed Bonding completed! (Major task..)
GOL AUX board: Production & Test completed
11
Quality Assurance
Tests C-frames LV, HV, Data Fibers, Gas
Tests detector modules: Gast tightness, dark currents,
signals R.A. sources
Tests Front End Amplifier threshold uniformities Time resolution
Commissioning Noise measurement Testpulse tests:
• Linearity, stability, resolution, uniformity
12
Module 61
Channel nr.
Pu
lse
he
igh
t (m
V)
Tested in the pit in the C cage
4 “dead” wires out of 6867 tested
Example QA : Straw Response to 55Fe
6 April 2006 13
Outer Tracker Irradiation Studies
Cha
nnel
Pos (cm)
Gain loss seen in production modules Damage upstream the gas flow
Damage only in low intensity region!
Electron microscope: isolating carbon layer
6 April 2006 14
Outer Tracker Irradiation Studies
Cha
nnel
Pos (cm)
Suspect out-gassing effect: Flushing of all modules started Warming of modules to force outgassing HV processing cures and part. Prevents
Gain loss seen in production modules Damage upstream the gas flow
Damage only in low intensity region!
Electron microscope: isolating carbon layer
Flushing
R
el g
ain
Flush Time (days)
2nd HV training
1st HV training
3rd HV training R
elat
ive
Gai
n
Irradiation Time (hours)
15
Velo - Collaboration
The NIKHEF Velo group:
NIKHEF provides Velo deputy projectleader
Nikhef Activities:Mechanics + RF Motion ControlVacuum control CO2 CoolingPile-Up trigger
Heidelberg, MPI, Liverpool, Glasgow, CERN, Lausanne, Syracuse, VU, Nikhef
M. Beuzekom, J. v/d Brand, M. Doets, P. de Groen, E. Jans,
L. Jansen, T. Ketel, A. Keune, M. Kraan, F. Mul, B. Munneke,
A. Papadelis, E. Roeland, F. Schimmel, A. Van Lysebetten,
B. Verlaat, T. Versloot, H. de Vries, L. Wiggers
16
VErtex LOcator
Silicon sensors
Vacuum vessel
rf-box
rectangular bellows
exit window
wake field suppressor
~1 m kaptons
The Vertex Locator
17
VELO Detector half
18
The Detector Vacuum box (“RF Box”)
Thin, leak-tight corrugated RF foil between sensors and beam
• super plastic pressing of 300 m Al foil with hot gas• welding into a vacuum tight box
30 mm
19
The Detector Vacuum box (“RF-box”)
Leak rate between beam and detector volumes determined to be : 2.4x10-5 mbar.l/s @ 1.6 mbar He Saturation NEG coating during installation Other solution considered for 2009 run
p < 5 mbar at all times!
20
Vacuum
During pumpdown and venting: p < 5 mbar between beam-vacuum and detector-vacuum
-6
-4
-2
0
2
4
6
11:16 11:31 11:45 12:00 12:14 12:28
0
200
400
600
800
1000
1200
p[mbar]
10
time
pbeam-pdet.
[mbar]
0
400
800
1200
0
4
-4
21
How the beam sees the Velo
22
Positioning the Detector in the beam: Motion Control
parking position
closed position
motion control implemented in a PLC. software and hardware limits. reproducibility < 10 m UPS system 3 d.o.f.: XR, XL and Y
Allowed regions:-5.0 < X < 29.0 mm for -1.0 < Y < 1.0 mm
-4.7 < Y < 4.7 mm for X < 5.0 mm
23
015 -1530 -30[mm]
rf-foil rf-foil
VELO open
0
.
half-open VELO tracking
LHC-beams
crossing
VELO closed
15
-15
30
-30
-45
45
[mm]
24
Cooling system and cooling plant
CO2 part ready
Next steps: Cabling, PLC control, insulation, testing
Delivery at CERN by June
Flexible in and outlet lines
Capillary and
T-Sensor channel
Cooling blocks
PT100 cables
PT100 Interface board
Vapor outlet
Liquid inlet
Cooling vacuum
feed trough
25
Pile-Up trigger
4 Upstream modules with R-sensors Uses digital readout of Beetle chips vetoes BXs with multiple PV’s
4PU-hybrids
8 opticalTx-boards
4 vertexprocessing
boards
1 outputboard
L0DU
125 Gb/s
und
er
con
stru
ctio
n
4PU-hybrids
8 opticalTx-boards
4 vertexprocessing
boards
1 outputboard
L0DU
125 Gb/s
und
er
con
stru
ctio
n
26
Software - Overview
J. Amoraal, Th. Bauer, E. Bos, H.J. Bulten, S. Cohen, L. Hooft van
Huysduyn, B. M’charek, M. Merk, J. Nardulli, A. Papadelis, G. Raven,
T. du Pree, N. Tuning, P Vankov, G. Ybeles Smit,
The NIKHEF Software group:
NIKHEF has convenorship of:
- Proper time and mixing group- Track fitting group
27
Physics Motivation
CKM Metrology:
1. Amix: Bs → Ds ms
ACP: Bs → Ds Ks
2. ACP: Bs → J/s
Rare Decays:
1. Br: B(s)→2. Afb: B0 →K* , b →s
Looking for effects of new physics in the flavour sector:
2B bs
sb
“Box”
These subjects exploit LHCb advantages over otherexperiments
Well matched to our activities:i. OT constructionii. VELO constructioniii. Track reconstruction
“Penguin”b s
1B
4 “teams”: each with 1-2 staff, 1 postdoc, 2-3 students
28
Result of track finding
Typical event display:Red = measurements (hits)
Blue = all reconstructed tracks
Efficiency vs p : Ghost rate vs pT :
Eff = 94% (p > 10 GeV)
Ghost rate = 3%(for pT > 0.5 GeV)
VELO
TT
T1 T2T3On average:
26 long tracks11 upstream tracks4 downstream tracks5 T tracks26 VELO tracks
2050 hits assigned to a long track: 98.7% correctly assigned
Ghosts:Ghosts:Negligible effect onNegligible effect onb decay reconstructionb decay reconstruction
29
Kalman Track Fit
Reconstruct tracks including multiple scattering.
Main advantage: correct covariance matrix for track parameters.
Implemented tracking in misaligned geometry.
z
Impact parameter pull distribution:
= 1.0
rec truer r
r
Momentum pull distribution:
= 1.2
rec truep p
p
30
Impact Parameter and Momentum Resolution
IP= 14 + 35 /pT
Impact parameter resolution parameter resolution
→ 1/pt (1/GeV)
1/pT spectrum B tracks
p/p = 0.35% – 0.55%
p spectrum B tracks
Momentum resolution
→ Momentum (GeV)
31
Mass and Lifetime resolution
BsDs proper time resolution
t ~ 40 fs
Example:Bs->Ds K/
Ds
Bs K
K
,K
47 m 144 m
440 m
Mass and lifetime resolutions Are typically a factor 2-3 better than ATLAS/CMS
Mass resolution: ~14 MeV Proper time resolution: ~40 fs
32
Theses b-physics
Theses on LHCb: (2001) N. Zaitsev Pile-up and Bs→J (2002) R. v.d. Eijk OT and tracking (2003) R. Hierck Tracking and Bs→DsK/ (2004) N. v. Bakel Velo and Bs mixing (2005) S. Klous Velo and Bs →J/ (2005) J. v. Tilburg Tracking and Bs→Ds K/ (2006) B. Hommels Tracking and Trigger
»
Theses on Hera-B: (2002) M. Bruinsma J/ in pA (2002) W. Hulsbergen Track reconstruction (2003) M. Mevius B cross-section (2005) H. Wahlberg B cross-section (2006) A. Sbrizzi B X-section & pentaquark
Thesis on Babar: (2006) M.Baak CKM angle gamma
33
Summary
Outer Tracker Detector installed Cabling ready Front end being tested and installed (tight schedule!) Commissioning ongoing Irradiation studies ongoing with high priority
Velo Vacuum vessel installed Vacuum control commissioned: leak detected in RF boxes Motion control commissioned Cooling infrastructure being installed in summer
Software Reconstruction framework ready Tracking algorithms being finalized Alignment algorithms being implemented Looking forward to data (hopefully already in 2007…)