+ All Categories

LHCb

Date post: 15-Jan-2016
Category:
Upload: conan
View: 40 times
Download: 0 times
Share this document with a friend
Description:
LHCb. LHCb. LHCb. MWPC production at PNPI. Production at PNPI-1 is finished. Production at PNPI-2 is finished. *)The last transport to CERN is arriving November 28, 2006 with 70 M4R4. MWPC preparations at CERN. Preparation Phase 1. Preparation Phase 2. MWPC preparations at CERN. - PowerPoint PPT Presentation
Popular Tags:
16
27 December 2006 LHCb Status Report (A.Vorobyo v) 1 LHCb
Transcript
Page 1: LHCb

27 December 2006 LHCb Status Report (A.Vorobyov) 1

LHCb

Page 2: LHCb

27 December 2006 LHCb Status Report (A.Vorobyov) 2

LHCb

LHCb

Page 3: LHCb

27 December 2006 LHCb Status Report (A.Vorobyov) 3

MWPC production at PNPI

M3R4 M2R4 M4R4

Production plans 200 200 200

Produced by Dec.2006 200 200 200  

Passed all tests at PNPI 197 200 200All classified as Class A except

3 bad M3R4 produced in the beginning of production

Delivered to CERN 197 200 130*

Production at PNPI-1 is finished. Production at PNPI-2 is finished.

*)The last transport to CERN is arriving November 28, 2006 with 70 M4R4.

Page 4: LHCb

27 December 2006 LHCb Status Report (A.Vorobyov) 4

MWPC preparations at CERNPreparation Phase

11 Gas leak tests

2 HV test - 1 Dark currents at HV up to 2.9 kV

3 Pad capacity tests

4 Preparations for chamber dressing

5 HV test – 2 Dark currents at HV up to 2.85 kV

6 Mounting Faraday Cages

7 Dressing with HV and LV lines

1 Installation of FE electronics

2 Pre-installation tests

- Thresh. Scan ( Noise counts, Pulse generator counts)

- HV test - 3 Dark current up to 2.85 kV

- Cosmic ray tests

Preparation Phase 2

Page 5: LHCb

27 December 2006 LHCb Status Report (A.Vorobyov) 5

Page 6: LHCb

27 December 2006 LHCb Status Report (A.Vorobyov) 6

MWPC preparations at CERN

Page 7: LHCb

27 December 2006 LHCb Status Report (A.Vorobyov) 7

Preparation Phase 2

Pre-installation Test Stand

5 chambers can be tested simultaneously

with the rate of5 chambers per day

Page 8: LHCb

27 December 2006 LHCb Status Report (A.Vorobyov) 8

Page 9: LHCb

27 December 2006 LHCb Status Report (A.Vorobyov) 9

Chambers M4R4 # 53, 54, 55, 56, 57 Run198 2550_0_0_0 100 sec

Cosmic Ray Counts from Internal Counters. Thresh = 15fC. GapA in 5 chambers.

Page 10: LHCb

27 December 2006 LHCb Status Report (A.Vorobyov) 10

Page 11: LHCb

27 December 2006 LHCb Status Report (A.Vorobyov) 11

Construction StatusLHCb Spectrometer

VELO

RICH1

TT

Magnet

OT

RICH2 Calo. System

Muon System

Page 12: LHCb

27 December 2006 LHCb Status Report (A.Vorobyov) 12

IP8 now...IP8 Now

Mu-system

PS

SPD

RICH-2

OT

Page 13: LHCb

27 December 2006 LHCb Status Report (A.Vorobyov) 13

Page 14: LHCb

27 December 2006 LHCb Status Report (A.Vorobyov) 14

Page 15: LHCb

27 December 2006 LHCb Status Report (A.Vorobyov) 15

Muon wall preparation

Page 16: LHCb

27 December 2006 LHCb Status Report (A.Vorobyov) 16

Further planning

In the optimistic planning with the pre-installation tests rate of 5 chambers per day,

all 600 chambers could be ready for installation

by the end of May,2007

However, there will be still problems with additional conditioning of the chambers ,repairs etc that may require

some additional time

HV-System for 4000 channels


Recommended