27 December 2006 LHCb Status Report (A.Vorobyov) 1
LHCb
27 December 2006 LHCb Status Report (A.Vorobyov) 2
LHCb
LHCb
27 December 2006 LHCb Status Report (A.Vorobyov) 3
MWPC production at PNPI
M3R4 M2R4 M4R4
Production plans 200 200 200
Produced by Dec.2006 200 200 200
Passed all tests at PNPI 197 200 200All classified as Class A except
3 bad M3R4 produced in the beginning of production
Delivered to CERN 197 200 130*
Production at PNPI-1 is finished. Production at PNPI-2 is finished.
*)The last transport to CERN is arriving November 28, 2006 with 70 M4R4.
27 December 2006 LHCb Status Report (A.Vorobyov) 4
MWPC preparations at CERNPreparation Phase
11 Gas leak tests
2 HV test - 1 Dark currents at HV up to 2.9 kV
3 Pad capacity tests
4 Preparations for chamber dressing
5 HV test – 2 Dark currents at HV up to 2.85 kV
6 Mounting Faraday Cages
7 Dressing with HV and LV lines
1 Installation of FE electronics
2 Pre-installation tests
- Thresh. Scan ( Noise counts, Pulse generator counts)
- HV test - 3 Dark current up to 2.85 kV
- Cosmic ray tests
Preparation Phase 2
27 December 2006 LHCb Status Report (A.Vorobyov) 5
27 December 2006 LHCb Status Report (A.Vorobyov) 6
MWPC preparations at CERN
27 December 2006 LHCb Status Report (A.Vorobyov) 7
Preparation Phase 2
Pre-installation Test Stand
5 chambers can be tested simultaneously
with the rate of5 chambers per day
27 December 2006 LHCb Status Report (A.Vorobyov) 8
27 December 2006 LHCb Status Report (A.Vorobyov) 9
Chambers M4R4 # 53, 54, 55, 56, 57 Run198 2550_0_0_0 100 sec
Cosmic Ray Counts from Internal Counters. Thresh = 15fC. GapA in 5 chambers.
27 December 2006 LHCb Status Report (A.Vorobyov) 10
27 December 2006 LHCb Status Report (A.Vorobyov) 11
Construction StatusLHCb Spectrometer
VELO
RICH1
TT
Magnet
OT
RICH2 Calo. System
Muon System
27 December 2006 LHCb Status Report (A.Vorobyov) 12
IP8 now...IP8 Now
Mu-system
PS
SPD
RICH-2
OT
27 December 2006 LHCb Status Report (A.Vorobyov) 13
27 December 2006 LHCb Status Report (A.Vorobyov) 14
27 December 2006 LHCb Status Report (A.Vorobyov) 15
Muon wall preparation
27 December 2006 LHCb Status Report (A.Vorobyov) 16
Further planning
In the optimistic planning with the pre-installation tests rate of 5 chambers per day,
all 600 chambers could be ready for installation
by the end of May,2007
However, there will be still problems with additional conditioning of the chambers ,repairs etc that may require
some additional time
HV-System for 4000 channels