Liaison Group Forum Presentation - December 2016 - Sirius ...

Date post: 26-Dec-2021
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
12
1 Agenda - Liaison Group Forum 1. Introductions 2. Declaration of interest 3. Apologies 4. Terms of reference 5. Project Update 6. Community and Stakeholder Engagement Plan 7. Future meetings 8. A.O.B
Transcript
Page 1: Liaison Group Forum Presentation - December 2016 - Sirius ...

1

Agenda - Liaison Group Forum

1. Introductions

2. Declaration of interest

3. Apologies

4. Terms of reference

5. Project Update

6. Community and Stakeholder Engagement Plan

7. Future meetings

8. A.O.B

Page 2: Liaison Group Forum Presentation - December 2016 - Sirius ...

2

Project update – DFS, contractor selection

World class partners

Shaft sinking

preferred contractor

Tunnelling preferred

contractor

US$2.9bn capital funding requirement

10Mtpa capacity, foundations for 20Mtpa

Lowest cost multi-nutrient potassium producer

High grade, long life asset of at least 50 years

Page 3: Liaison Group Forum Presentation - December 2016 - Sirius ...

3

Project update – All major approvals granted

Page 4: Liaison Group Forum Presentation - December 2016 - Sirius ...

4

Stage 1 capital

Approx. US$1.2 billion secured

Mixture of equity, convertible bonds and

strategic investment from Hancock Prospecting

Enables works to start immediately

Stage 2 capital

Exceeds requirements for 100% debt funding

Commitments expected to be in place in 2018

6 financial institutions secured to be mandated

lead arrangers

Pre-qualified with Infrastructure Projects

Authority for a HMT guarantee

Project update – Stage 1 financing secured

Equity

Firm placing, placing

and open offer

Structured capital

Convertible bond,

royalty agreement

Senior debt

Project finance bank

debt and/or corporate

bonds

Potential for IPA/ECA

support

Project

CAPEX

Stage 1 capital

Site preparation and

geotech

Production and

services shafts

MTS shafts and

mobilization

Stage 2 capital

MTS

Mine fit-out

MHF crushing and

granulation plant

US

$1

.2 b

n

Up

to

US

$2

.6 b

n

Page 5: Liaison Group Forum Presentation - December 2016 - Sirius ...

5

Headline construction schedule

Focus is on discharging planning conditions to enable construction start

Early works targeted to commence in January 2017

Site preparation in Q2 2017

2017 2018 2019 2020 2021

Shafts

main sink

Site prep

Highways

Geo-tech

Shafts

‘D’ walling

MTS

tunnelling

MHF

construction

Harbour

construction

First polyhalite

(10Mtpa 2024)

Shafts

fit out

Page 6: Liaison Group Forum Presentation - December 2016 - Sirius ...

6

Highways and geotechnical works

Geotechnical investigation Imminent highway works

Whitby

Mine

Lockwood Beck

Completed road

improvement

Road improvement

Construction traffic route

Page 7: Liaison Group Forum Presentation - December 2016 - Sirius ...

7

Site preparation

Temporary soil

store areas

Noise and

screening

bunds

Site access

Attenuation

ponds

Acoustic fence /

environmental barrier

Water injection

well platform

Shaft platform

Page 8: Liaison Group Forum Presentation - December 2016 - Sirius ...

8

Shaft sinking

Main sink Diaphragm walling up to 120 m

Page 9: Liaison Group Forum Presentation - December 2016 - Sirius ...

9

Inform community stakeholders before key construction

events

- Letters, visits, open days, media, presentations

Provide ongoing updates and establish mechanisms to

deal with queries and concerns

- Liaison groups, 24- hour helpline, public meetings, media

Deliver community benefit initiatives

- Education, apprenticeships, local employment and businesses

Community and stakeholder engagement

Page 10: Liaison Group Forum Presentation - December 2016 - Sirius ...

10

Community and stakeholder engagement

Maintaining relationships with site neighbours

Page 11: Liaison Group Forum Presentation - December 2016 - Sirius ...

11

Funding to support provision to identify and prepare

local people for employment opportunities

Education outreach

At least 50 apprentices and 15 local graduates

Training hundreds of adults people in preparation for

mining operations

Deliver quarterly employment opportunity sessions

Meet the buyer events

Partnership working with LEPs and councils

Local employment and supply chain

Providing opportunities for local people and businesses