© 2013 Larsen & Toubro Limited : All rights reserved
Life Cycle
Assessment of
Process Gas
Boiler System
Larsen & Toubro
8th November, 2013
© 2013 Larsen & Toubro Limited : All rights reserved
Larsen & Toubro
Larsen & Toubro is a USD 14 Billion technology, engineering,
construction, manufacturing and financial services conglomerate with
global operations
© 2013 Larsen & Toubro Limited : All rights reserved 3
Powai Campus – Founded in 1958
Plate Cutting
Heavy Engineering - Powai
Machining
Welding Fabrication
© 2013 Larsen & Toubro Limited : All rights reserved 4
Plant Profile – Heavy Engineering
Design & Engineering
• System design, thermal / mechanical design, material and welding engineering
Technology Centre
•Process design, radar and transmitters, ship stabilizer, launcher designs and analysis
Manufacturing
•Heavy fabrication and machining test, site service
•200 mm thickness acetylene and plasma cutting
•1000 ton hydraulic press
•25000 ton rolling machine (hot & cold bending)
Welding
• SAW, TIG, MIG, SMAW, ESSC, FCAW processes, automatic and robotic welding
Machining
•CNC Horizontal and Vertical Boring, Turning, Drilling, Deep Hole Drilling
Fabrication
•Max Equipment Size: Weight – 400 Ton, Length - 47m, Diameter – 6m
•Destructive & Non Destructive Testing
Commissioning & Site Support
© 2013 Larsen & Toubro Limited : All rights reserved
L&T – Product Responsibility
© 2013 Larsen & Toubro Limited : All rights reserved
Background of LCA Study
Sr.
No. Parameters
Weightages
(Points)
1 Energy Efficiency 150
2 Water Conservation 100
3 Renewable Energy 100
4 GHG Emission Reduction 100
5 Material Conservation, Recycling & Recyclables 100
6 Waste Management 100
7 Green Supply Chain 100
8 Product Stewardship 75
9 Life Cycle Assessment 75
10 Others (Ventilation, Site Selection & Innovation) 100
“To promote and champion conservation of natural resources in Indian industry without compromising on high and accelerated growth"
© 2013 Larsen & Toubro Limited : All rights reserved
Objective of LCA Study
• The main objective of the study is to evaluate the
“cradle-to-gate lifecycle” i.e. from raw material
acquisition, material production, transport,
assembly and fabrication data for Process Gas
Boiler system in order to calculate life cycle
inventories (“Life Cycle Inventory” or ”LCI”).
• To fulfil the requirements of GreenCo Rating
system
© 2013 Larsen & Toubro Limited : All rights reserved
Life Cycle Assessment – L&T
“Compilation and evaluation of the inputs, outputs and the
potential environmental impacts of a product system
throughout its life cycle” – ISO 14040/44
Target
• To conduct the LCA of process gas boiler assembly (1 No. – 36 TPH
capacity).
• This product has been chosen as the Company has developed an expertise in
the manufacturing of the same over several years and it represents a
significant portion (> 25 %) of the Company’s order book (Powai – West) for
FY 2012-13.
• The Company expects to receive similar orders in future.
© 2013 Larsen & Toubro Limited : All rights reserved
LCA study framework
Scope • To evaluate various
environmental impacts of all activities associated with fabrication of a process gas boiler assembly
System Boundary • The LCA of the process
gas boiler assembly covers the cradle to gate approach, consisting of raw materials transport, manufacturing, assembling, energy and auxiliary materials consumption till dispatch
Functional Unit • One Process Gas -
Waste Heat Recovery Boiler assembly having three subassemblies as steam drum, rise and down comer pipe and process gas boiler and capacity of 36TPH of steam generation.
© 2013 Larsen & Toubro Limited : All rights reserved
LCA study - Flow chart
Goal and Scope
Definition
Data Collection and Data Quality Check
LCA System Modelling
(using GaBi Software)
LCI and LCIA calculations
and comparison if
any
Final Report
• Standards followed - ISO 14040/44 • Software used for modeling - GaBi 6 developed by PE International AG.
© 2013 Larsen & Toubro Limited : All rights reserved
Natural
Resources
Air
Emissions
Water
Effluents
Solid
Waste
Life Cycle stages
Raw material acquisition
Material
processing
Production
Use and
maintenance
End-of-life
Cradle to gate boundary
© 2013 Larsen & Toubro Limited : All rights reserved
System Boundaries
• The Life Cycle Analysis of one process gas boiler covers the cradle to
gate approach, consisting of raw materials transport, manufacturing,
fabrication, assembly, energy and auxiliary material consumption.
Life Cycle
stages
Life Cycle
sub-stages Definitions
Materials &
energy
production
Primary raw materials Raw material receipt
Sub components
Formation
Energy, fuel and raw materials used in the process of
formation of the primary sub components production
Upstream
Transport
Transport of the raw materials for primary production of the
assembly
Assembly Diesel, electricity and lubricating oil consumption during in-
house assembly of the boiler production and testing
In-house
locomotive In-house transport of various materials
© 2013 Larsen & Toubro Limited : All rights reserved
Process Gas boiler breakup
Process gas boiler assembly
Riser & Down comer piping
Steam Drum General Assembly
© 2013 Larsen & Toubro Limited : All rights reserved
1
3
4
LH-RH Dishend fabrication
2
7
9
8
10
5
6
Process Gas Boiler System
Shell fabrication
Tube sheet fabrication
Nozzle fabrication
External fabrication
Internal fabrication
Post Weld Heat Treatment
Hydro testing
Refractory
Dispatch
© 2013 Larsen & Toubro Limited : All rights reserved
Data was collected from various functions on bill of materials, fuel, energy,
transportation which further were imported to the GaBi software for analysis.
Consolidated primary data for various machining and fabrication processes
are considered wherever part specific data was not available
The environmental profiles of various materials used in the fabrication of boiler
are sourced from GaBi 6 Professional 2012 databases wherein close
substitutes for materials are considered wherever the dataset was not available
Upstream transportation data has been considered in the assessment.
Data Collection & Assumptions
© 2013 Larsen & Toubro Limited : All rights reserved
LCA – Environmental Impact
S.N Parameters
Process gas
Boiler
Assembly
(1)
Riser &
Down
comer
piping
(2)
Steam Drum
General
Assembly
(3)
Waste-Heat Recovery
Boiler Assembly
(1+2+3)
1 Acidification Potential (AP)
[kgSO2- Equiv.] 447.93 386.37 316.5 1,150.77
2 Global Warming Potential (GWP100 years) [kgCO2-
Equiv.] 1,02,115.36 74,507.01 91,644.3 2,68,266.64
3
Ozone Layer Depletion
Potential (ODP, steady state)
[kg R11-Equiv.]
0.00 0.00 0.00 0.00
4
Photochemical. Ozone
Creation Potential (POCP)
[kg Ethene-Equiv.]
38.53 28.57 38.15 105.26
5 Primary energy demand from
ren. and non-ren. Resources
(net cal. value) [MJ]
14,50,834.09 11,19,062.71 12,37,340.16 38,07,236.97
6 Total freshwater consumption
(including rainwater) [cu.m] 54,093.7 20,238.1 38,931.2 1,13,263.0
© 2013 Larsen & Toubro Limited : All rights reserved
Observations
34%
33%
33%
Primary energy demand (38,07,236 MJ)
Process gasBoiler Assembly
Riser & Downcomer piping
Steam DrumGeneralAssembly
35%
30%
35%
Global Warming Potential (2,68,266 kg CO2-Equiv.)
Process gasBoiler Assembly
Riser & Downcomer piping
Steam DrumGeneralAssembly
© 2013 Larsen & Toubro Limited : All rights reserved
Observations
48%
18%
35%
Total freshwater consumption (1,13,263 cu.m)
Process gasBoilerAssemblyRiser &Down comerpipingSteam DrumGeneralAssembly
76%
4%
19%
0.00 0.5 0%
Material consumption (1,03,956 kg)
Carbon Steel
High DenseAlumina
Low Alloy steel
Stainless Steel
High tensilebolting
© 2013 Larsen & Toubro Limited : All rights reserved
Observations
37%
35%
27%
Acidification Potential (AP) assembly wise %[kg SO2-Equiv.]
1150 Kg
Process gasBoiler Assembly
Riser & Downcomer piping
Steam DrumGeneralAssembly
34%
29%
37%
Photochem. Ozone Creation Potential break-up % by
assembilies (POCP) [kg Ethene-Equiv.] 105 Kg
Process gas BoilerAssembly
Riser & Downcomer piping
Steam DrumGeneral Assembly
© 2013 Larsen & Toubro Limited : All rights reserved
L&T- LCA study results
S.No Parameters
Activities
outside L&T
campus
Activities
inside L&T
campus
Total
1 Acidification Potential (AP)
[kgSO2- Equiv.] 936.47
(81.38%)
214.3 (18.62%)
1,150.77
2 Global Warming Potential (GWP100 years) [kgCO2-Equiv.]
1,42,518.01 (53.13%)
1,25,748.63 (46.87%)
2,68,266.64
3 Ozone Layer Depletion Potential
(ODP, steady state) [kg R11-Equiv.] 0.00 0.00 0.00
4 Photochemical. Ozone Creation
Potential (POCP) [kg Ethene-Equiv.] 80.31
(76.30%)
24.95 (23.70%)
105.26
5 Primary energy demand from ren.
and non-ren. Resources (net cal.
value) [MJ]
20,47,260.62 (53.78%)
17,59,976.35 (46.22%)
38,07,236.97
6 Total freshwater consumption
(including rainwater) [cu.m] 1,13,171.29
(99.92%)
91.71 (0.08%)
1,13,263.0
© 2013 Larsen & Toubro Limited : All rights reserved
Recommendations
1. Reduce material consumption by 5%.
2. Material substitution with less resource intensive materials
3. Material substitution with locally sourced materials
4. Increase renewable energy component
5. Reduce absolute energy consumption by 5%
6. Decrease in natural gas consumption by 5%
© 2013 Larsen & Toubro Limited : All rights reserved
S.No. Parameters If Weight of material is
reduced by 5%
1 Reduction Global Warming Potential (GWP100
years) [kgCO2-Equiv.]
12,199 (4.55%)
2
Reduction in Primary energy demand from ren. and
non-ren. resources(net cal. value) [MJ]
1,69,658 (4.46%)
3 Reduction Total freshwater consumption(in-clouding
rainwater) [cu.m.]
5,663 (4.99%)
Reduction in weight of material & Environmental Impact
If weight of material is reduced by 5%, the key environmental parameters like
GWP, Primary energy demand & total fresh water consumption for the
process gas boiler system reduces as mentioned in below table:
© 2013 Larsen & Toubro Limited : All rights reserved
Replacement of Steel by:
• Advanced high strength plates
• Light weight plates
• Sourcing IS grade materials
Scrap:
Substitution with scrap metal in similar line downstream / upstream
Material substitution
© 2013 Larsen & Toubro Limited : All rights reserved
• Consider the public private partnership with locally present steel companies like
Steel Authority of India Ltd. (Bhilai), Essar Steel for developing high strength & light
weight plates.
• Sourcing from L&T Forge shop, Hazira.
Local sourcing of materials
© 2013 Larsen & Toubro Limited : All rights reserved
At present, the Powai West campus is sourcing approx. 75% of
total energy demand from renewable sources. Further, if the
percentage of renewable energy over the entire lifecycle is
increased to 90%, the reduction in environmental impacts is
mentioned in table :
Increase in renewable energy sources
S.No. Parameters 90% Renewable
Energy
1 Reduction in Global Warming Potential (GWP100 years) [kgCO2-
Equiv.]
16,025 (5.97%)
2 Reduction in Primary energy demand from ren. and non-ren.
resources(net cal. value) [MJ]
1,60,297 (4.21%)
3 Reduction in Total freshwater consumption(in-clouding rainwater)
[cu.m.]
68,913 (60.8%)
© 2013 Larsen & Toubro Limited : All rights reserved
S.No. Parameters
If absolute energy
consumption is
reduced by 5%
1 Reduction in Global Warming Potential (GWP100
years) [kgCO2-Equiv.]
1,201 (0.44%)
2 Reduction in Primary energy demand from ren. and
non-ren. resources(net cal. value) [MJ]
12,016 (0.33%)
3 Reduction in Total freshwater consumption(in-clouding
rainwater) [cu.m.]
5,165 (4.56%)
Reducing absolute energy consumption by 5%
If absolute energy consumption is reduced by 5% the key environmental
parameters like GWP, Primary energy demand & total fresh water
consumption in process gas boiler system reduces as mentioned in below
table:
© 2013 Larsen & Toubro Limited : All rights reserved
S.No. Parameters
If Natural Gas
consumption is
reduced by 5%
1 Reduction in Global Warming Potential (GWP100
years) [kgCO2-Equiv.]
3,741.5 (1.39%)
2 Reduction in Primary energy demand from ren. and
non-ren. resources(net cal. value) [MJ]
63,796 (1.67%)
3 Reduction in Total freshwater consumption(in-clouding
rainwater) [cu.m.]
1.5 (~0.01%)
Reducing Natural Gas consumption by 5%
If Natural Gas (NG) consumption is reduced by 5% the key environmental
parameters like GWP, Primary energy demand & total fresh water
consumption reduces by as mentioned in below table:
© 2013 Larsen & Toubro Limited : All rights reserved
Reduction in
parameters
If energy
consumption
reduces by 5%
If Natural Gas
consumption
reduced by 5%
Sourcing of Wind
power
(90 %)
If weight of
material is
reduced by 5%
External L&T
In-house External
L&T
In-house External
L&T
In-house Cradle to Gate
Acidification
Potential (AP) [kg
SO2- Equiv.]
0.81 0.19 8.1 1.9 6.48 1.52 58 (5.04%)
Global Warming
Potential (GWP
100 years) [tons
CO2-Equiv.]
638.09 562.91 1,987.59 1,753.91 8,509.27 7,510.92 12199 (4.55%)
Primary energy
demand (net cal.
value) [MJ]
6,462.20 5,553.8 34,309.49 29,486.51 86,207.73 74,089.27 169658 (4.46%)
Total freshwater
consumption
[cu.m]
5,160.87 4.13 1,479.04 1.18 68,857.86 55.13 5663.2 (5.0%)
Recommendations
© 2013 Larsen & Toubro Limited : All rights reserved
Benefits of LCA Study
• Demonstrates the ecological performance of the product
• Supports the decision-making during product development
• Helps the Company to revisit and improve its own benchmark
• Provides a business connect
© 2013 Larsen & Toubro Limited : All rights reserved
Way forward
Environmental Product Declaration / Eco-labeling
Development of LCA framework
LCA of more products
Gate to grave (end-of-life)
© 2013 Larsen & Toubro Limited : All rights reserved
Thank You