+ All Categories
Home > Documents > Life Cycle Costing – Challenges and Tools SCAF February … the Challenges... · Life Cycle Costs...

Life Cycle Costing – Challenges and Tools SCAF February … the Challenges... · Life Cycle Costs...

Date post: 14-Jul-2018
Category:
Upload: lyduong
View: 215 times
Download: 0 times
Share this document with a friend
46
Life Cycle Costing – Challenges and Tools SCAF February 2012
Transcript

Life Cycle Costing – Challenges and Tools SCAF February 2012

2

AGENDA TODAY

Life Cycle Costs – Challenges & Tools Background –

What is LCC? – What you should already know Examples

Challenges Data needs Logistics factors Other challenge influences

Tools Summary

3

BACKGROUND

4

Life Cycle Cost (LCC) Definition

LCC = Acquisition Cost + Operating & Support (O&S) Cost

LCC = Development Cost + Production Cost + O&S Cost

TOC= LCC + all other Direct & Indirect Costs of Ownership (Total Ownership Costs)

5

WHAT YOU SHOULD ALREADY KNOW

Strategic Sectors where LCC are of interest Defense

Information Systems

Aeronautics

Space

These

are the types of

Products that

persist and require

consideration of

Operation &

Support costs

6

Life Cycle Costs - influence

Concept Assessment Demonstration Manufacture In-Service Disposal

PROJECT PHASE

Cum

ulat

ive

Cos

t

%

0

100

Initial Gate Main Gate

Costs fixed

Costs Incurred

Typical Cost Profiles

Typical LCC for simple one shot devices

©

Typical LCC – small aircraft

A Project Like a Trainer Aircraft e.g...... TUCANO 90 % of whole life costs can be incurred after Acquisition

EQUIPMENT PURCHASE

EQUIPMENT OPERATION & SUPPORT

OK so it’s not a Tucano picture !

10

CHALLENGES

Estimating Accuracy the Traditional View

Post costing

Contract changes Invoices

Contracts Bid data analysis

Broad order

estimates

Higher cost

Lower cost

IG MG

Concept Manufacture Assessment Demonstration Upgrades

In-Service Phase Disposal

A good estimate is good for business: The Freiman Curve

ESTIMATED COST

1

1 2x

UNDERESTIMATES LEAD TO DISASTER - insufficient resources - panicked decisions - unrealistic expectations

REALISTIC ESTIMATES MINIMIZE FINAL COST

OVERESTIMATES LEAD TO DISASTER - under-utilized resources - excess capacity - un-competitive pricing

FINAL PROJECT COST

2x

Frank Freiman, Inventor of Parametrics, 1975

12

Estimating Accuracy the amended View

Post costing Contract changes Invoices Contracts

Bid data analysis

Broad order

estimates

Higher cost

Lower cost

IG MG

Concept Manufacture Assessment Demonstration Upgrades

In-Service Phase Disposal

14

Parametrics As Basis-of-Estimate (BoE)

Today the use of parametric techniques as basis of economic analysis is widely accepted by Industry and Government organisations and growing. Some of the more common applications are: Development of independent cost estimates (ICE) (e.g., "sanity checks" on

the primary estimating methodology ), Rough Order Of Magnitude estimates (ROMs), life cycle cost estimates (LCCEs), and BoE.

Economic basis for trade studies such as Design-To-Cost (DTC), Cost as An Independent Variable (CAIV), Total Ownership Cost (TOC) and Reduced TOC (RTOC) analyses.

Parametric techniques are also used to perform cost or price analyses. In fact, the US Federal Acquisition Regulation (FAR) identifies parametrics as an acceptable price analysis technique in 15.404-1(b)(2)(iii).

Basis of Estimate for cost proposals

Decrease risks and save money on Programs

2 main roots causes of project failure Bad estimation

cost estimation should be embedded in the cost management process

Bad project control should implement EVM methods

US G.A.O. (Government Accountability Office) stated that: The ability to generate reliable cost estimates is a critical function

“Without this ability, agencies are at risk of experiencing cost overruns,

missed deadlines, and performance shortfalls”

15

ESTIMATING Boundaries ?

Life Cycle Boundaries - Define

17

• What is included? • Development? • Production? • Service Personnel?

• Service Personnel Training? • Basic training • Operator Training? • Maintainer Training?

• Maintenance Facility costs • Site Security? • Services (electricity, gas etc) • Maintenance facility upkeep?

Where is the boundary line drawn – exclusion list

Typical cost breakdown for Aircraft Life Cycle Cost

Internal resource

LSA, Training,Ground Facilities, etc

IP Spares

Support Equipment

Test Equipment

Manufacture & PI

Demonstration

Assessment

Concept

Munitions

Fuel

Ground Crew

Air Crew

Operation

Internal resource

Maintenance of Support Equip

LSA etc

Ongoing Training

Ageing Allowance

Software Maintenance

PDS

Station O/Hds

Maintenance of A/C

Support

Disposal Costs

Residual Value

Disposal

LCC

19

PBS - Equipment Hierarchy (can you expect this detail for costing 2030?)

Line Replaceable Unit (LRU)

Module

Part

System/ sub-System

Platform

20

Maintenance Levels

Equipment On-Equipment Maintenance – No Work Shop Often performed by crew

Organization (Direct Support) Performed by using organisation on its assigned equipment

Intermediate (General Support) Facility with Controlled Environment and Automated Test

Equipment Depot

Government or Contractor The challenge here is the blurring of ‘Traditional’ support

by availability or ‘power by hour’ style contracting and/ or the replacement of Service personnel by Contractor staffs delivering traditional support. See later slide

21

Maintenance On-Equipment Maintenance

Maintenance performed on the end item (i.e., air vehicle, ship, tank etc)

Possible Maintenance Actions Remove and Replace LRU Remove and Replace Module Remove and Replace Part

Note – there are two types of maintenance action Scheduled or Preventative (lifed items, engine mandatory

servicing etc) Unscheduled, this is mostly random failure driven

22

Spares – money pit Initial Spares

Initial stock required to fill maintenance pipeline or supply chain

Produced concurrent with mission equipment Quantity based on repair cycle times and failure rates

Replenishment Spares Spares needed to replenish stock of initial spares Also known as Balanced Consumed spares Total spares minus initial spares

23

OTHER CHALLENGING INFLUENCES

24

Two key Maintenance Drivers Scheduled or Preventative

For major platforms this is usually: Routine test, cleansing or POL changes 400/ 800 mandatory servicing (aero engines etc) Fatigue life replacements Fixed overhaul & upgrade cycles (ships/ submarines)

These are not dealt with in detail by commercial cost models and can be very large cost items

Unscheduled, this is dealt with and calculated in some detail by commercially available models: Driven by 3 key drivers

Maintenance Concept Mean Time Between Failures Mean Times to Repair

25

Platform Scheduled

Scheduled Maintenance Cycles Often Customer and Operational Tempo dictated Capacity and alignment of individual platform overhauls

challenging for larger fleets

Operational Non-Operational One of the Fleet

26

Life Cycle Key Input data Mean Time Between Failure

Hours assigned to MTBF can be the average time between such events as: Equipment Failures (Including Induced Failures) Overhauls (Restore To Like New) Confidence Testing (Such As Missiles and Rockets) Scheduled Replacements (Critical Items) Re-Fueling

Where does all of this data come from? Almost certainly not the Support contractor databases!

In changing contracting type environments just how relevant is this data anyway?

Staff knowledge in these areas is normally limited

27

Life Cycle Key Input data

28

Life Cycle Platform/ Equipment/ LRU Key Input data

29

Life Cycle Inputs Logistics Data

30

Life Cycle Key Input Logistics Data

31

Existing Platform/ System support

New contract types Transfer of risks from Customer to Provider AGE! (not PC but crucial)

Elements of O&S With Age Effects

It has been observed that there is an AGE effect in some elements of O&S costs, including: Scheduled Overhaul Repair Parts Other POL Centrally Provided Materials

The AGE effects in Scheduled Overhaul, Repair Parts, and Other POL were presented at SCEA in June 2003: Ship Scheduled Overhaul Costs Over Time, Summerville, Coleman, Dameron, Leach.

Since that paper was written there have been changes to the Scheduled OH, Repair Parts, and Other POL methodologies.

Another paper, presented since, at the 37th ADoDCAS, has also shown age effects in high-level O&S costs: Analysis of the Impact of OPTEMPO on Navy O&S Cost, Octeau, Hardin

33

AGE - Discovery of Overhaul Cycles

Cost vs. Avg. Age

$-

$2

$4

$6

$8

$10

$12

0.0 5.0 10.0 15.0 20.0 25.0 30.0

Avg. Age

Cost

(FY0

3$M

)CG 16CG 26CG 47DD 963DDG 51DDG 993FFG 7

The line is a 5th degree polynomial. The 2 peaks are believed to be caused by Navy policy - scheduled overhauls are set to be a given number of years apart.

1st overhaul

2nd/3rd overhaul – The steam ships may be on a different OH cycle. More data is

required to know if the steam ships have 2 or 3 overhauls in their lifetime.

34

Operating & Support Costs Over Time SCEA 2006 O&S Regression Results

01 02 03 0 3 5 0 0

6 5 0 0

9 5 0 0

1 2 5 0 0$0

$10,000

$20,000

$30,000

$40,000

$50,000

$60,000

$70,000

$80,000

$90,000

O&S

cos

t ($K

)

age weight

Total O&S vs weight & age

The coefficients were converted for raw data to produce this graph.

Note: Color bands are just visual aids to show y-axis

regions

35

Finally…… One last subject which tends to be

glossed over!

Software Support

Software Support Cost for War Fighting Systems Increases with Size Increases if it is Safety Critical Decreases with Age –

Software Support for Non-War fighting Systems

Increases with Age Increases with the presence of Software Of Unknown Pedigree

(SOUP) Decreases if it’s a Training/Testing System

My (safe) bet is that no-one is collecting suitable metrics! Note: War Fighting software is software which would critically affect the

mission (e.g. terminate it if failed).

37

TOOLS

A general guide to Method Vs Phase

38

Analogy [near neighbour]

Parametric Top down or Bottom up

[Extrapolation From]

Actuals

Engineering [Bottom - Up]

Concept and Assessment

Development and

Demonstration

Manufacture and Entry Into

Service

In-Service Operation &

Support

Cost Forecasting Cost Estimating

Pre-concept

Note – the above is a guide, no tool is exclusive in a particular phase

39

Commercially Available tools CASA EDCAS OPUS OSCAM (Air/ Land/ Sea) PRICE SEER FACET

First three bullets are not parametric models, OSCAM is a ‘systems dynamics model, PRICE & SEER are parametric models and FACET is Bayesian.

They all do a job and require significant amounts of input data with the exception of FACET

They all have gaps in coverage so one or more may be needed with assistance from bespoke Excel models to achieve a complete predictive capability

Why use Parametric methods? Model(s) is traceable and objective Once set up it is quick & easy to use For given inputs the output is repeatable May quickly be adjusted for changes to the system or sub-

system or other global parameters Important for sensitivity analysis and design trades Useful for economic analysis

Statistical results relating to the model

Includes t statistics, F statistics, R2, coefficient of variation (CV) Objective measures of validity May be used in risk analysis

41

A Complex Model – build your own?

Asks for typically 20 – 50 more pieces of information than a CER. A typical CER uses one, two, three, or perhaps four pieces of parametric information - including O&S costing can increase this data ten fold!

Algorithmically robust compared to a simple CER Generally provides more information in its output Complex models are not simplistic, rather they are sufficiently

flexible to handle the dynamics of well defined programs CERs often have much broader scope, “rules of thumb” that are

broad generalizations

42

Development of Complex Tools

Considerations: Data and cost drivers

Product operating environment Project team composition Project team environment Labour, overheads, Profit rates etc

Mathematics and logic CERs Algorithms

Outputs Phasing and spreads Inflation Cost Allocations Monte Carlo simulation Scheduling Learning Earned value management Special adjustments.

You really do not want to be trying this in

Excel – BUT YOU MAY HAVE

NO CHOICE FOR SOME COST ELEMENTS!

43

SUMMARY

LCC demands a consistent framework There is no single LCC tools that covers everything that

needs to be estimated Use a Cost framework which enables organisations to set

and manage a Base line program from the starting point to the end

LCC estimation will require collection and use of data for: Product Breakdown Structure and the Work Breakdown

Structure Platform, system, LRU – reliability data Logistics loop Resources/ Budget Operational deployment & usage Ovehaul / Fatigue Cycles Maintenance Policy

44

A Cost Frame work: The Analytic estimation application software

45

Any Questions?

Andy Nicholls Phone: +44 (0) 1256 760012 Mobile: +44 (0) 7500 866822

[email protected] [email protected]

PRICE Systems Ltd.

PRICE House, Meridian Office Park Osborn Way

Hook, Hampshire RG27 9JY

www.PRICESystems.co.uk

46


Recommended