+ All Categories
Home > Documents > lift plan 2

lift plan 2

Date post: 03-Apr-2018
Category:
Upload: mukesh-katarnavare
View: 225 times
Download: 1 times
Share this document with a friend

of 26

Transcript
  • 7/28/2019 lift plan 2

    1/26

    Safe use of cranesSite lifting plan

  • 7/28/2019 lift plan 2

    2/26

    1. Introduction

    2. Management of lifting operations

    3. Selection and duties of personnel

    4. Procedures and precautions

    5. Slinging and handling of loads

    6. Lifting equipment

    7. Risk Assessment

    8. Lifting Assessment

    9. Schedule of common lifts

    10.Record of lifting appliances and accessories

    11 C T i t t d tifi ti

    Contents

  • 7/28/2019 lift plan 2

    3/26

    In order to provide a safe system of work and to ensure compliance with

    current legislation this site lifting plan has been developed and is to be

    implemented by every member of the crane team involved with this project.

    It is vital that all lifting operations are properly planned by a competent

    person and that the plan is followed by everyone involved in the operation.

    This plan is to be read by all team members involved in lifting operations;

    this must be done prior to any lifting being carried out.

    It is essential that all team members are fully competent and certified to

    carry out their individual roles. (See section 13)

    It is essential that all team members are confident that they can fulfil their

    duties especially when works may need to be carried out at height.

    INTRODUCTION

  • 7/28/2019 lift plan 2

    4/26

    Safe system of work

    Whether the lifting operations are repetitive or if they are a one off, a safe

    system of work must be established and followed for the operation to beboth safe and successful.

    In order to provide a safe system of work the following items are to be

    included in the lift plan / Assessment:

    The selection of suitable cranes and work equipment must be carried out.

    A crane team is to be employed who are fully trained and competent and

    who have had their roles and responsibilities clearly explained to them.

    The areas for the cranes access and rigging etc must be properly planned

    and properly prepared.

    A regime of maintenance, testing and examination of equipment must be

    devised.

    Management of lifting operations

  • 7/28/2019 lift plan 2

    5/26

    When appointing a crane team it is essential that all the members of that

    team are fully aware of the role and duties and that each person has

    sufficient knowledge, training and experience to carry out their role.

    The crane team organisation chart is shown below and roles and duties are

    continued beneath.

    Appointed Person

    Crane Supervisor

    Crane Co-ordinator

    Selection and duties of personnel

  • 7/28/2019 lift plan 2

    6/26

    Appointed Person

    The appointed persons duties are to include the following;

    Being familiar with the relevant parts of the project Health and

    Safety Plan where lifting operations are to be carried out on a site .

    Assess the lifting operations to provide such planning, selection of

    cranes, lifting accessories and equipment, instruction and supervision

    as is necessary for the task to be undertaken safely. (where works areon a shared site or where logistics may be restrictive co-ordination

    with others will be required)

    Ensure that adequate inspection / examination and maintenance of

    the equipment have been carried out prior to its use.

    Establish an effective procedure for reporting defects and incidents

    and taking necessary corrective action.

    Takes responsibility for the organisation and control of the lifting

    operation.

    Ensure the crane supervisor is fully briefed in the contents of the lift

    plan / method statement etc.

    The appointed person is able to delegate his duties to another person but the

    responsibilities still remain the appointed persons.

    C S i

  • 7/28/2019 lift plan 2

    7/26

    Crane Co-ordinator

    The crane co-ordinators role is to plan and direct the sequence of

    operations of the cranes to ensure they do not collide with other cranes,

    loads and other equipment and buildings.

    This role can be carried out by a competent person with knowledge and experience in lifting operations.

    Crane Operator

    The crane operator is responsible for the correct operation of the crane inaccordance with the manufacturers instructions and within the safe system

    of work.

    The crane operator is to respond to a single slinger / signaller at any given

    time and these must be identifiable to the operator.

    Should any person near a lifting operation give the recognised stop signalthe operator must cease lifting operations immediately and confirm what

    actions are required from the slinger / signaller.

  • 7/28/2019 lift plan 2

    8/26

    Slinger / Signaller

    The slinger / signaller is responsible for the attaching and detaching of

    loads to and from the crane load lifting attachment and ensuring that the

    correct accessories are used for that operation in accordance with the

    planning of the operation.

    The slinger / signaller is responsible for the safe movement of the crane and

    clear direction must be given whether visual or hand signals.

    Where more than one slinger / signaller is required, clear instruction must

    be given when passing responsibility over to the next slinger / signaller.

    The slinger / signaller is to store lifting accessories in a suitable place when

    not being used and prior to re-using an accessory he must visually inspect itbefore use.

    The slinger / signaller must notify the appointed person of any damaged

    equipment immediately.

    Lifting Operations FlowchartLifting Operations Flowchart

  • 7/28/2019 lift plan 2

    9/26

    NON ROUTINE

    LIFT

    Need identified for liftingoperation

    Appoint a competent person to plan thelift with technical support as required

    Carry out risk

    assessment (generic)

    Lift plan (generic)

    Carry out risk assessment(new or modified)

    Lift plan

    Lift plan (new ormodified)

    Engineered lifts(project

    specific) and lift

    Technical review by

    competent person

    ROUTINE LIFT

  • 7/28/2019 lift plan 2

    10/26

    Procedures and Precautions

    Crane Operation

  • 7/28/2019 lift plan 2

    11/26

    Regular inspections of the crane are to be carried out and this must be

    recorded weekly in the site office.

    Inspection and Maintenance

    Where there is a requirement for a person to climb the mast of a crane

    whilst the crane is still operational the driver must be made aware of

    someone climbing before they commence.

    Any tools or equipment needed to be used must be secure and free from

    risk of falling and if tools are to be lifted up using the crane they must be

    done so using equipment designed for that task.

    A regime of monitoring and examination is to be established by the

    appointed person this must include a schedule of servicing for cranes and

    generators etc.

    In order to maintain production it may be necessary to carry out

    maintenance outside normal working hours.

    Other cranes / plant / buildings

    Where there are other cranes on the same site and there is a risk of

    collision, a crash radio system is to be established and be used. This will be

  • 7/28/2019 lift plan 2

    12/26

    Where available the recognised hand signals will be adopted and a copy of

    those is attached.

    The slinger / signallers are to be identifiable to the operators and this will

    be achieved by the operatives wearing orange high visibility vests.

    Slinging and handling loads

    It is essential that the weight of the load to be lifted is known to a

    reasonable accuracy and this can be determined a number of ways

    1. Check for SWL markings

    2. Phone the manufacturer

    3. Run over a weigh bridge

    4. Calculate

    If weights are to be calculated the following figures should be used;

    Material KG/M3

    Brick 2100

    Concrete 2400

  • 7/28/2019 lift plan 2

    13/26

    Once the slinger / signaler is assured of the stability of the load he will give

    direction to the crane operator to proceed with the lift.

    Where possible the direction of travel will be the shortest direction and will

    be away from where operative are working beneath. If this is not possible

    the slinger signaler is to warn operatives of loads above. On multi-crane

    sites, this is to be addressed to all site workers during their site induction.

    Loads must never be dragged as the cranes are only designed to lift in a

    vertical plane and there a possibility of damage to the crane.

    Lifting Equipment

    Only slings and other lifting accessories for which a valid report of

    thorough examination has been issued within the previous 6 months are to

    be used.

    Lifting accessories should be clearly marked with the rated capacity and

    have an identification number for record purposes.

    Lifting equipment must be visually inspected before use with any defects

    b i d i di l

  • 7/28/2019 lift plan 2

    14/26

  • 7/28/2019 lift plan 2

    15/26

  • 7/28/2019 lift plan 2

    16/26

    Risk Assessment

    Hazard Risks Control Measures

    Plant and Machinery Injury to personnel All plant and machinery

    to be inspected and

    serviced regularly .

    A maintenance andservice schedule is to be

    established and

    implemented.

    Failure of lifting

    equipment

    Damage to

    buildings/equipmentand injury/death to

    personnel

    All lifting equipment is

    to certificated andinspected regularly As

    Regulations

    A copy of certification

    is to be retained on site

    for record keeping and

    reference.

    Slinger / Signaller to

  • 7/28/2019 lift plan 2

    17/26

    and injury/death to

    personnel

    by the crane operator to

    ensure that the crane is

    safe and operable

    Heavy loads Failure of lifting

    equipment and

    machinery

    Visual assessments are

    to be made by

    competent personnel to

    ensure the correct lifting

    equipment is used for

    the lift and that thecrane is able to lift the

    weight of the load at the

    required radius

    All lifts are to be carried

    out as directed in thelifting assessments and

    schedule of common

    lifts

    High Winds Instability and loss of

    control of lifting

    operation

    Wind speeds within the

    site area are to be

    monitored and all liftingoperations are to be in

    strict conditions of the

    i d d

  • 7/28/2019 lift plan 2

    18/26

    A lifting assessment is

    to be carried out prior to

    any unique or speciallifts being carried out.

    Close proximity of

    cranes/building/public

    amenities

    Entanglement leading to

    loss of integrity of load

    A safe system of work

    is to be instigated

    ensuring the risk of

    collision is eradicated.

    This may be a crash

    radio system or a

    zoning system fitted to

    the crane.

    Sleeping or dead cranes. Collision of cranes As above

    ASSESSED BY..DATE..

  • 7/28/2019 lift plan 2

    19/26

    IDENTIFICATION AND ASSESSMENT OF LIFTING OPERATIONS

    * Change as per site requirements Issue No.:Date:

    Operation * Items to beLifted

    MaxWeight

    Crane Used Lifted From Lifted To EquipmentUsed

    Comments

    Site Set-Up offices Welfarefacilities

    2.5t Crawler Crane40 T(Hired in)

    Delivery Vehicles"On Site"

    Final positionas per sitelayout plan

    4 slings 5 T Survey required of site groundconditions prior to crane set-up.Crane Co-ordinator andSlinger/Signaller to be inattendance. Slings to be hiredwith crane.

    2t

    1.5t

    All Cranes Delivery Vehicles

    Site position Final position

    4 leg 6.7t chains

    4- Leg 6t chains

    Choke wrapped using 2 legs

    Lifting points to be clearly definedin method statement .

    RetainingWalls

    Bundles ofreinforcement

    R.M.DShutters

    Concrete by Skip

    2t

    2.5t

    3t / 6.5t

    Mobile / tower

    Mobile / Tower

    Mobile / Tower

    Delivery Vehicles

    Preparation area

    Areas between

    Areas betweenFinal position

    Wall Shutters

    2 leg 6t chains

    R.M.D liftingdevices and 2leg 6t chains

    8t Drop Chain

    Choke wrapped using 2 legs

    Approval required for R M Dsystem via Temp Work procedureC Frame.

    Ensure there are no loops or knotsin operating line. Keep tag lines asshort as practicable.

    Main FrameSteelwork

    Columns,beams, bracing

    Not yetknown

    To be advised Delivery vehicles Final position To be confirmedprior tocommencement

    All offloading to be carried outwithin site boundaries.

  • 7/28/2019 lift plan 2

    20/26

    IDENTIFICATION AND ASSESSMENT OF LIFTING OPERATIONS

    Operation * Items to beLifted

    MaxWeight

    Crane Used Lifted From Lifted To EquipmentUsed

    Comments

    Plant andmachinery

    CompressorsWeldingmachine

    3.0 t All Cranes(crawler crane)

    Site location Final position Web sling Plant and machinery to be lifted bytheir designated lifting points only.Slinger Signaller to be inattendance.

    Sheds forDA,OXYGEN

    CYLINDERSetc

    Scaffolding pipes 1t Mobile Crane /Crawler crane

    Delivery vehicle Final position Web sling Lifting points to be clearly definedin the method statement andapproved by Principal Contractor

    Formed plates 13 t Crawler crane Delivery vehicle Final position Slings 5t Slinger signaller to be inattendance.

    Saddles 9t Crawler crane Delivery vehicle Final Position Slings 5t Slinger Signaller to be inattendance

    * as itemised in works programme Issue No.:

    Date:

  • 7/28/2019 lift plan 2

    21/26

    IDENTIFICATION AND INITIAL ASSESSMENT OF LIFTING OPERATIONS

    Operation * Items to beLifted

    MaxWeight

    Crane Used Lifted From Lifted To EquipmentUsed

    Comments

    Walls Dish polar 2 t Crawler crane Delivery vehicle Final position 4 leg 6.7t chains Slinger signaller to be inattendance.

    * as itemised in works programme Issue No.:

    Date:

  • 7/28/2019 lift plan 2

    22/26

    SCHEDULE OF COMMON LIFTS

    Load Method

    Concrete or muck skip. Skip chain 8tEnsure that any rope fixed to skip is ofsingular construction and is free of allknots and loops.

    Boat Skip /Rollover skip Skip chain 8tBundles of tubes, bars or other similar materials,e.g.. scaffold tubes, bars, small diameter pipes,lengths of timber, etc. whether banded or not.

    4 leg 6.7t chains, load to be doublewrapped using 2 legs of the chains

    Reinforcement Bar Wrapped 4 leg chain slings. Ensurethat bars to be lifted are of equallength

    Flying Table Platforms Four leg chains passed through preprepared holes on top of platform andwrapped around upper platform alumsor steel supports. Use C frame wherepossible.

    Palletised materials. Crane forks with cage or net. Fork LiftTruck.

    Web Slings will be used for palletisedmaterial

    Stillages 4 leg chain slings wrapped around

  • 7/28/2019 lift plan 2

    23/26

    SCHEDULE OF COMMON LIFTS

    Load Method

    Small plant ie compressors, bowsers etc Chains to be attached to certifiedlifting eyes only 8t drop chain.

    Prefab Re Bar Cages Chains to be attached to double tiedremovable thickened re bar special

    care must be taken to ensure integrityof the load.

  • 7/28/2019 lift plan 2

    24/26

    Record of lifting appliances and accessories

    Lifting Appliances (e.g.Cranes)

    Description ID No. Supplier: Test Cert.Expiry Date:

    12 MonthlyThorough

    ExaminationExpiry Date:

    Used for lifting persons?Y/N.

    (If so, 6 MonthlyThorough Examn?)

    WeeklyInspections

    carried out by:

    Lifting Accessories (e.g. lifting gear)Description ID No. Owner S.W.L (t) Test Certificate

    Y/N6 Monthly Thorough Examination Y/N?

    Expiry Date

    Issue No.:01

    Date:

  • 7/28/2019 lift plan 2

    25/26

    Crane team appointment and certification

    Position Name Date Appointed

    Appointed Person*(Lifting Operations)

    Deputy appointedPerson

    Crane Co-ordinator

    Crane Operators*

    Signallers/Slingers*

    * Must hold appropriate CPCS CardsIssueNo.:

    01

    Date:

  • 7/28/2019 lift plan 2

    26/26


Recommended