Date post: | 03-Apr-2018 |
Category: |
Documents |
Upload: | mukesh-katarnavare |
View: | 225 times |
Download: | 1 times |
of 26
7/28/2019 lift plan 2
1/26
Safe use of cranesSite lifting plan
7/28/2019 lift plan 2
2/26
1. Introduction
2. Management of lifting operations
3. Selection and duties of personnel
4. Procedures and precautions
5. Slinging and handling of loads
6. Lifting equipment
7. Risk Assessment
8. Lifting Assessment
9. Schedule of common lifts
10.Record of lifting appliances and accessories
11 C T i t t d tifi ti
Contents
7/28/2019 lift plan 2
3/26
In order to provide a safe system of work and to ensure compliance with
current legislation this site lifting plan has been developed and is to be
implemented by every member of the crane team involved with this project.
It is vital that all lifting operations are properly planned by a competent
person and that the plan is followed by everyone involved in the operation.
This plan is to be read by all team members involved in lifting operations;
this must be done prior to any lifting being carried out.
It is essential that all team members are fully competent and certified to
carry out their individual roles. (See section 13)
It is essential that all team members are confident that they can fulfil their
duties especially when works may need to be carried out at height.
INTRODUCTION
7/28/2019 lift plan 2
4/26
Safe system of work
Whether the lifting operations are repetitive or if they are a one off, a safe
system of work must be established and followed for the operation to beboth safe and successful.
In order to provide a safe system of work the following items are to be
included in the lift plan / Assessment:
The selection of suitable cranes and work equipment must be carried out.
A crane team is to be employed who are fully trained and competent and
who have had their roles and responsibilities clearly explained to them.
The areas for the cranes access and rigging etc must be properly planned
and properly prepared.
A regime of maintenance, testing and examination of equipment must be
devised.
Management of lifting operations
7/28/2019 lift plan 2
5/26
When appointing a crane team it is essential that all the members of that
team are fully aware of the role and duties and that each person has
sufficient knowledge, training and experience to carry out their role.
The crane team organisation chart is shown below and roles and duties are
continued beneath.
Appointed Person
Crane Supervisor
Crane Co-ordinator
Selection and duties of personnel
7/28/2019 lift plan 2
6/26
Appointed Person
The appointed persons duties are to include the following;
Being familiar with the relevant parts of the project Health and
Safety Plan where lifting operations are to be carried out on a site .
Assess the lifting operations to provide such planning, selection of
cranes, lifting accessories and equipment, instruction and supervision
as is necessary for the task to be undertaken safely. (where works areon a shared site or where logistics may be restrictive co-ordination
with others will be required)
Ensure that adequate inspection / examination and maintenance of
the equipment have been carried out prior to its use.
Establish an effective procedure for reporting defects and incidents
and taking necessary corrective action.
Takes responsibility for the organisation and control of the lifting
operation.
Ensure the crane supervisor is fully briefed in the contents of the lift
plan / method statement etc.
The appointed person is able to delegate his duties to another person but the
responsibilities still remain the appointed persons.
C S i
7/28/2019 lift plan 2
7/26
Crane Co-ordinator
The crane co-ordinators role is to plan and direct the sequence of
operations of the cranes to ensure they do not collide with other cranes,
loads and other equipment and buildings.
This role can be carried out by a competent person with knowledge and experience in lifting operations.
Crane Operator
The crane operator is responsible for the correct operation of the crane inaccordance with the manufacturers instructions and within the safe system
of work.
The crane operator is to respond to a single slinger / signaller at any given
time and these must be identifiable to the operator.
Should any person near a lifting operation give the recognised stop signalthe operator must cease lifting operations immediately and confirm what
actions are required from the slinger / signaller.
7/28/2019 lift plan 2
8/26
Slinger / Signaller
The slinger / signaller is responsible for the attaching and detaching of
loads to and from the crane load lifting attachment and ensuring that the
correct accessories are used for that operation in accordance with the
planning of the operation.
The slinger / signaller is responsible for the safe movement of the crane and
clear direction must be given whether visual or hand signals.
Where more than one slinger / signaller is required, clear instruction must
be given when passing responsibility over to the next slinger / signaller.
The slinger / signaller is to store lifting accessories in a suitable place when
not being used and prior to re-using an accessory he must visually inspect itbefore use.
The slinger / signaller must notify the appointed person of any damaged
equipment immediately.
Lifting Operations FlowchartLifting Operations Flowchart
7/28/2019 lift plan 2
9/26
NON ROUTINE
LIFT
Need identified for liftingoperation
Appoint a competent person to plan thelift with technical support as required
Carry out risk
assessment (generic)
Lift plan (generic)
Carry out risk assessment(new or modified)
Lift plan
Lift plan (new ormodified)
Engineered lifts(project
specific) and lift
Technical review by
competent person
ROUTINE LIFT
7/28/2019 lift plan 2
10/26
Procedures and Precautions
Crane Operation
7/28/2019 lift plan 2
11/26
Regular inspections of the crane are to be carried out and this must be
recorded weekly in the site office.
Inspection and Maintenance
Where there is a requirement for a person to climb the mast of a crane
whilst the crane is still operational the driver must be made aware of
someone climbing before they commence.
Any tools or equipment needed to be used must be secure and free from
risk of falling and if tools are to be lifted up using the crane they must be
done so using equipment designed for that task.
A regime of monitoring and examination is to be established by the
appointed person this must include a schedule of servicing for cranes and
generators etc.
In order to maintain production it may be necessary to carry out
maintenance outside normal working hours.
Other cranes / plant / buildings
Where there are other cranes on the same site and there is a risk of
collision, a crash radio system is to be established and be used. This will be
7/28/2019 lift plan 2
12/26
Where available the recognised hand signals will be adopted and a copy of
those is attached.
The slinger / signallers are to be identifiable to the operators and this will
be achieved by the operatives wearing orange high visibility vests.
Slinging and handling loads
It is essential that the weight of the load to be lifted is known to a
reasonable accuracy and this can be determined a number of ways
1. Check for SWL markings
2. Phone the manufacturer
3. Run over a weigh bridge
4. Calculate
If weights are to be calculated the following figures should be used;
Material KG/M3
Brick 2100
Concrete 2400
7/28/2019 lift plan 2
13/26
Once the slinger / signaler is assured of the stability of the load he will give
direction to the crane operator to proceed with the lift.
Where possible the direction of travel will be the shortest direction and will
be away from where operative are working beneath. If this is not possible
the slinger signaler is to warn operatives of loads above. On multi-crane
sites, this is to be addressed to all site workers during their site induction.
Loads must never be dragged as the cranes are only designed to lift in a
vertical plane and there a possibility of damage to the crane.
Lifting Equipment
Only slings and other lifting accessories for which a valid report of
thorough examination has been issued within the previous 6 months are to
be used.
Lifting accessories should be clearly marked with the rated capacity and
have an identification number for record purposes.
Lifting equipment must be visually inspected before use with any defects
b i d i di l
7/28/2019 lift plan 2
14/26
7/28/2019 lift plan 2
15/26
7/28/2019 lift plan 2
16/26
Risk Assessment
Hazard Risks Control Measures
Plant and Machinery Injury to personnel All plant and machinery
to be inspected and
serviced regularly .
A maintenance andservice schedule is to be
established and
implemented.
Failure of lifting
equipment
Damage to
buildings/equipmentand injury/death to
personnel
All lifting equipment is
to certificated andinspected regularly As
Regulations
A copy of certification
is to be retained on site
for record keeping and
reference.
Slinger / Signaller to
7/28/2019 lift plan 2
17/26
and injury/death to
personnel
by the crane operator to
ensure that the crane is
safe and operable
Heavy loads Failure of lifting
equipment and
machinery
Visual assessments are
to be made by
competent personnel to
ensure the correct lifting
equipment is used for
the lift and that thecrane is able to lift the
weight of the load at the
required radius
All lifts are to be carried
out as directed in thelifting assessments and
schedule of common
lifts
High Winds Instability and loss of
control of lifting
operation
Wind speeds within the
site area are to be
monitored and all liftingoperations are to be in
strict conditions of the
i d d
7/28/2019 lift plan 2
18/26
A lifting assessment is
to be carried out prior to
any unique or speciallifts being carried out.
Close proximity of
cranes/building/public
amenities
Entanglement leading to
loss of integrity of load
A safe system of work
is to be instigated
ensuring the risk of
collision is eradicated.
This may be a crash
radio system or a
zoning system fitted to
the crane.
Sleeping or dead cranes. Collision of cranes As above
ASSESSED BY..DATE..
7/28/2019 lift plan 2
19/26
IDENTIFICATION AND ASSESSMENT OF LIFTING OPERATIONS
* Change as per site requirements Issue No.:Date:
Operation * Items to beLifted
MaxWeight
Crane Used Lifted From Lifted To EquipmentUsed
Comments
Site Set-Up offices Welfarefacilities
2.5t Crawler Crane40 T(Hired in)
Delivery Vehicles"On Site"
Final positionas per sitelayout plan
4 slings 5 T Survey required of site groundconditions prior to crane set-up.Crane Co-ordinator andSlinger/Signaller to be inattendance. Slings to be hiredwith crane.
2t
1.5t
All Cranes Delivery Vehicles
Site position Final position
4 leg 6.7t chains
4- Leg 6t chains
Choke wrapped using 2 legs
Lifting points to be clearly definedin method statement .
RetainingWalls
Bundles ofreinforcement
R.M.DShutters
Concrete by Skip
2t
2.5t
3t / 6.5t
Mobile / tower
Mobile / Tower
Mobile / Tower
Delivery Vehicles
Preparation area
Areas between
Areas betweenFinal position
Wall Shutters
2 leg 6t chains
R.M.D liftingdevices and 2leg 6t chains
8t Drop Chain
Choke wrapped using 2 legs
Approval required for R M Dsystem via Temp Work procedureC Frame.
Ensure there are no loops or knotsin operating line. Keep tag lines asshort as practicable.
Main FrameSteelwork
Columns,beams, bracing
Not yetknown
To be advised Delivery vehicles Final position To be confirmedprior tocommencement
All offloading to be carried outwithin site boundaries.
7/28/2019 lift plan 2
20/26
IDENTIFICATION AND ASSESSMENT OF LIFTING OPERATIONS
Operation * Items to beLifted
MaxWeight
Crane Used Lifted From Lifted To EquipmentUsed
Comments
Plant andmachinery
CompressorsWeldingmachine
3.0 t All Cranes(crawler crane)
Site location Final position Web sling Plant and machinery to be lifted bytheir designated lifting points only.Slinger Signaller to be inattendance.
Sheds forDA,OXYGEN
CYLINDERSetc
Scaffolding pipes 1t Mobile Crane /Crawler crane
Delivery vehicle Final position Web sling Lifting points to be clearly definedin the method statement andapproved by Principal Contractor
Formed plates 13 t Crawler crane Delivery vehicle Final position Slings 5t Slinger signaller to be inattendance.
Saddles 9t Crawler crane Delivery vehicle Final Position Slings 5t Slinger Signaller to be inattendance
* as itemised in works programme Issue No.:
Date:
7/28/2019 lift plan 2
21/26
IDENTIFICATION AND INITIAL ASSESSMENT OF LIFTING OPERATIONS
Operation * Items to beLifted
MaxWeight
Crane Used Lifted From Lifted To EquipmentUsed
Comments
Walls Dish polar 2 t Crawler crane Delivery vehicle Final position 4 leg 6.7t chains Slinger signaller to be inattendance.
* as itemised in works programme Issue No.:
Date:
7/28/2019 lift plan 2
22/26
SCHEDULE OF COMMON LIFTS
Load Method
Concrete or muck skip. Skip chain 8tEnsure that any rope fixed to skip is ofsingular construction and is free of allknots and loops.
Boat Skip /Rollover skip Skip chain 8tBundles of tubes, bars or other similar materials,e.g.. scaffold tubes, bars, small diameter pipes,lengths of timber, etc. whether banded or not.
4 leg 6.7t chains, load to be doublewrapped using 2 legs of the chains
Reinforcement Bar Wrapped 4 leg chain slings. Ensurethat bars to be lifted are of equallength
Flying Table Platforms Four leg chains passed through preprepared holes on top of platform andwrapped around upper platform alumsor steel supports. Use C frame wherepossible.
Palletised materials. Crane forks with cage or net. Fork LiftTruck.
Web Slings will be used for palletisedmaterial
Stillages 4 leg chain slings wrapped around
7/28/2019 lift plan 2
23/26
SCHEDULE OF COMMON LIFTS
Load Method
Small plant ie compressors, bowsers etc Chains to be attached to certifiedlifting eyes only 8t drop chain.
Prefab Re Bar Cages Chains to be attached to double tiedremovable thickened re bar special
care must be taken to ensure integrityof the load.
7/28/2019 lift plan 2
24/26
Record of lifting appliances and accessories
Lifting Appliances (e.g.Cranes)
Description ID No. Supplier: Test Cert.Expiry Date:
12 MonthlyThorough
ExaminationExpiry Date:
Used for lifting persons?Y/N.
(If so, 6 MonthlyThorough Examn?)
WeeklyInspections
carried out by:
Lifting Accessories (e.g. lifting gear)Description ID No. Owner S.W.L (t) Test Certificate
Y/N6 Monthly Thorough Examination Y/N?
Expiry Date
Issue No.:01
Date:
7/28/2019 lift plan 2
25/26
Crane team appointment and certification
Position Name Date Appointed
Appointed Person*(Lifting Operations)
Deputy appointedPerson
Crane Co-ordinator
Crane Operators*
Signallers/Slingers*
* Must hold appropriate CPCS CardsIssueNo.:
01
Date:
7/28/2019 lift plan 2
26/26