+ All Categories
Home > Documents > Lifting Good and Bad Practice Book

Lifting Good and Bad Practice Book

Date post: 12-Dec-2015
Category:
Upload: michael-nelson
View: 24 times
Download: 11 times
Share this document with a friend
Description:
Great resource for good rigging practice
Popular Tags:
40
2 3 Contents Introduction Section 1 Cargo Carrying Units (CCU’s) Design Section 2 Slings & Shackles Section 3 Supply Base Checks Section 4 Loading and Securing CCU Contents Section 5 Slinging of Tubulars Section 6 Loads Requiring Special Attention Section 7 Positioning of Loads on Vessels Section 8 Sea Fastening (Adverse Weather Conditions) Section 9 Positioning of Loads on Trucks Section 10 Security and Safety of Loads for Road Transport good l bad l
Transcript
Page 1: Lifting Good and Bad Practice Book

2 3

Contents

Introduction

Section 1 Cargo Carrying Units (CCU’s) Design

Section 2 Slings & Shackles

Section 3 Supply Base Checks

Section 4 Loading and Securing CCU Contents

Section 5 Slinging of Tubulars

Section 6 Loads Requiring Special Attention

Section 7 Positioning of Loads on Vessels

Section 8 Sea Fastening (Adverse Weather Conditions)

Section 9 Positioning of Loads on Trucks

Section 10 Security and Safety of Loads for Road Transport

good l bad l

Page 2: Lifting Good and Bad Practice Book

4 5

Cargo Carrying Units (CCU’s) Design

As from 1st May 2004, all Cargo Carrying Units (CCU’s) must be designed, built and tested in accordance with BS EN 12079 or DNV 2.7.1. However, you will still come across CCU’s constructed before this time which should comply with the previous design code, BS 7072.

You probably wont be able to tell the difference visually, but the design standard WILL be stamped on the Data Plate.

NO DESIGN CODE - DON’T SHIP!

This Data Plate should also contain the relevant certification details (see typical Data Plate below).

REMEMBER, VISUAL / NDT INSPECTIONS ARE ONLY VALID FOR 6 MONTHS.

LESS THAN 1 MONTHS CERTIFICATION REMAINING - DON’T SHIP!

The main problem we have with cargo handling, is that we receive cargo for onward-shipping from various suppliers with varying standards of competence when it comes to preparation, packing and slinging of loads. In other words, they are not experts in mechanical handling.

We don’t expect you to be an expert, but you should be able to recognise unsafe loads, poor slinging practices or defective CCU’s so that the items can be made safe or replaced to enable safe onward-shipping.

The safety of the loads can be compromised by:

Poor design of CCU

Impact damage to CCU

Excessive corrosion

Poor slinging practices

Undersized rigging

Excessively worn slings

Inadequately packaged freight, etc

Loose items becoming dropped objects

This pocket book is designed to help you recognise these faults and also demonstrate good practice.

Introduction

Page 3: Lifting Good and Bad Practice Book

6 7

Cargo Carrying Units (CCU’s) DesignCargo Carrying Units (CCU’s) Design

Features:

4 point lift

Padeyes angled towards centre

Solid sheet steel construction

Protected door handles

Protected hinges

Information square

Date plate

Forklift pockets

Good condition, no impact damage, little / no corrosion

Defects:

Impact damage

Damage door

Faulty door seal

Damaged door lock

Broken door handle

Data plate missing

Illegible markings

Excessive corrosion

Holes in container fabric

OK TO SHIP DON’T SHIP!

typical container : good substandard container : bad

Page 4: Lifting Good and Bad Practice Book

8 9

Cargo Carrying Units (CCU’s) Design

The material used in the construction of containers has more or less been standardised as sheet steel. However, cargo baskets and boxes come in all shapes and sizes using a range of materials such as wire mesh and expanded sheet metal (expamet). The suitability of these units for transporting cargo will depend on the actual cargo.

Typical cargo basket with expamet sides. It’s advisable (though not essential) to have 6 inch / 150mm kicker plates around the bottom of the sides to prevent dropped objects

Note that the padeyes are angled towards the centre of the lift to avoid side loading!

The basket is not suitable for this particular cargo as there is no weather protection. (How many other problems can you identify?)

Answer : 1. fragile item (control panel and hoses) packed alongside heavy steel items 2. load not secured in basket 3. all 4 legs of wire rope sling onto 1 link

While it is acceptable to use wire mesh / expamet on the sides of a basket, it should not be used as floor material. Can you give three reasons why it is not suitable?

Cargo Carrying Units (CCU’s) Design

Expament / wire mesh / open grating are NOT suitable as floor material!

Answer : 1. Expamet is generally not strong enough 2. it is easily pierced by sharp heavy objects 3. the possibility of smaller items falling through the mesh, i.e. dropped objects

basket : good

packing : bad

floor design : poor

Page 5: Lifting Good and Bad Practice Book

10 11

Cargo Carrying Units (CCU’s) Design

Cargo boxes are generally a safer option to cargo baskets, as they are comparably stronger and there is a reduced risk of dropped objects.

When storing these units, although stacking is acceptable onshore, it should be avoided where possible offshore. If there is a lack of space offshore, CCU’s can be stacked (maximum two boxes high), but only if they are designed for that purpose and a Job Safety Analysis (JSA) has been carried out. Below is a typical example of a stacking bracket which locates and holds the upper basket in position while at the same time, protecting the slings.

On this particular basket, you will notice that the padeyes are NOT angled towards the centre. With baskets that are longer than they are wide, this can be acceptable as long as the padeyes are robust enough to withstand the side loadings that they would incur under normal working conditions. Obviously, the longer the basket in relation to its width, the lesser the side loading on the padeyes.

Cargo Carrying Units (CCU’s) Design

padeyes : acceptable

floor design : poor

cargo box : good

suitable for stacking : good

Generally, if the padeye thickness is 75% or more of the shackle jaw gap (and correctly proportioned), it will be sufficient to withstand the bending.

Page 6: Lifting Good and Bad Practice Book

12 13

When it comes to Tote tanks, i.e. tanks for handling aviation fuel, oils, chemicals, etc, the majority are single skinned. This means they are susceptible to impact damage. If the impacts are made by sharp objects, there is a danger of them piercing the tanks and spilling the contents. These tanks should either be “double skinned”, or more practically, protected by a crash / protection frame.

Cargo Carrying Units (CCU’s) Design

typical vertical tank crash / protection frame : good

tank design : bad

Here we have a typical crash / protection frame for a verticle tank. Other important features are protection of the valves, grating on the roof (to prevent slings falling through and becoming entangled) and a ladder for access.

Cargo Carrying Units (CCU’s) Design

Apart from the lack of a crash frame, what other poor design can you see here?

Answer : lifting padeye welded directly onto the skin of the tank. padeye design not very good, e.g. hole too big, plate too narrow for shackle

typical valve protection : good

Page 7: Lifting Good and Bad Practice Book

14 15

Cargo Carrying Units (CCU’s) Design

Gas bottle racks are a popular method of shipping gas bottles to and from the worksite. Depending on quantity of gas bottles being shipped and the corresponding size of the racks, they can be fitted with four, two, or even one single padeye. As there is no safety back-up with a single padeye, it is advisable to have an increased factor of safety.

bottle rack : good

Cargo Carrying Units (CCU’s) Design

Here is an example of a horizontal tank with crash / protection frame.

typical horizontal tank crash / protection frame : good

Note : All bottle racks should have a primary and a secondary method of securing the bottles for transit.

Warning : Partially filled tanks can be hazardous to handle due to the fluid movement of the contents shifting the centre of gravity. For this reason, it is preferable to use cranes as the lifting appliance. However, if forklift trucks are used, extra care must be exercised to prevent the tanks toppling off the forks or even worse, over-turning the forklift truck when cornering.

Note : All valves should be secured and locked to prevent inadvertent opening in transit.

Page 8: Lifting Good and Bad Practice Book

16 17

Cargo Carrying Units (CCU’s) Design

Padeyes on CCU’s

At present there are neither national nor international standards relating to padeye design. The following information / guidance is based on industry good practice.

Padeyes that have been flame cut must have all cutting marks ground out to eliminate stress points. The holes should always be drilled or bored and not flame cut. If cheek plates are fitted, they should be line bored after fitting.

smooth profile, hole correct size, hole bored / drilled, adequate thickness. adequate material left around hole, good quality welding

flame-cut outer profile, flame-cut hole, hole too near top of padeye, padeye plate inadequate thickness

Cargo Carrying Units (CCU’s) Design

Padeyes should always be designed to suit specific shackles i.e:

i) Minimum hole size: To avoid point loading, the holes should be equal to the diameter of the shackle pin plus 10%

ii) Maximum plate thickness: To ensure a neat fit in the shackle jaw, the maximum width of the padeye should be equal to the jaw gap of the shackle less 10%

pin dia.jaw gap

pin dia. +10%jaw gap -10%

padeye : good

padeye : bad

padeye : good

iii) Maximum hole size: Ideally, the padeye hole should not be greater than 125% times the shackle pin diameter

iv) Minimum plate thickness: Ideally, the padeye width (including cheek plates where applicable) should not be less than 75% of the shackle jaw gap

Note : If percentages at iii) and iv) are exceeded, check with your supervisor as to their suitability for shipping.

Page 9: Lifting Good and Bad Practice Book

18 19

Cargo Carrying Units (CCU’s) Design

If the knuckle of the shackle can fit through the hole, the hole is definately too big. (1) In this particular case, what else is wrong?

Answer (1) : the padeye plate is far too narrow, and there is substantial impact damage.Answer (2) : Purple (the Red paint on the pin is the manufacturer’s mark)

(2) What is the colour code of this shackle, Red or Purple?

Cargo Carrying Units (CCU’s) Design

When the padeye plate is too narrow, the shackle doesn’t seat properly and causes undue stresses.

If narrow plate is used to fabricate the padeye, cheek plates should be welded on (prior to boring the hole for the shackle pin) to fill the shackle jaw gap.

another typical example : bad

another typical example : bad

padeye : bad

padeye : good

Page 10: Lifting Good and Bad Practice Book

20 21

Cargo Carrying Units (CCU’s) Design

Be aware that narrow padeyes are much more susceptible to bending and impact damage.

Answer : there was obviously too much heat used which caused substantial undercutting

Pay particular attention to the welding as quality can vary between suppliers. Can you see the problem with this weld?

!!

Cargo Carrying Units (CCU’s) Design

This padeye (hole too big for pin) is starting to show signs of wear / stretch due to point loading.

padeye too narrow : bad

padeye weld : bad

hole too big for pin : bad

This padeye does not have enough material around it i.e. bored to close to the edge of the plate, therefore would not last long in service.

hole too close to edge : bad

Page 11: Lifting Good and Bad Practice Book

22 23

Cargo Carrying Units (CCU’s) Design

Apart from the hole being too big and the plate being too narrow, what else is wrong with this padeye?

Answer : the padeye is too long, this makes it more susceptable to bending and puts excessive load on the weld.

padeye : bad

Cargo Carrying Units (CCU’s) Design

Padeyes should be orientated in such a direction as to eliminate, or at least reduce out-of-plane loading. This is normally achieved by angling the padeyes towards the centre of the load and is common on most containers and square baskets. However, with long narrow baskets, e.g. tool baskets, this is not always the case.

As long as the padeye plates are robust enough to withstand the slight side loading (transverse bending), this design is acceptable.

padeye orientation : good

padeye orientation : acceptable

Page 12: Lifting Good and Bad Practice Book

24 25

Once you have established that the padeye material is adequate, you have to consider the suitability of its connection to the CCU. Can you spot the problems with the following design?

Cargo Carrying Units (CCU’s) DesignAnswer : although the padeye has a doubler base plate, the angle iron frame it is welded to is not adequately supported to prevent bending

padeye design : bad

padeye design : bad

Cargo Carrying Units (CCU’s) Design

The parent material that both these padeyes are welded to is more slender than the actual padeye, i.e. not strong enough to take the loadings. What else can you see wrong with the bottom padeye?

Answer : padeye is at the wrong orientation for the sling angle.

deformed due to load through padeye

padeye design : bad

padeye design : bad

Page 13: Lifting Good and Bad Practice Book

26 27

padeye design : bad

In this example, the padeye looks OK, although a bit narrow, but the method of attaching to the CCU, e.g. a mixture of welding and bolting leaves a lot to be desired.

Cargo Carrying Units (CCU’s) Design

The padeye base plate, although welded at the back, is only bolted to a thin steel flat bar at the front which, A) does not appear strong enough to support the load, and B) will allow water or moisture to get between the plates causing corrosion which cannot be readily monitored.

padeye design : bad

In this example, the padeye has been welded directly to the skin of the tote tank.

Finally, you may often come across ISO type corner castings. These are primarily designed to be lifted using special twist locks, however, it is acceptable to use ordinary shackles with them. The dimensions of the openings and the surrounding material determines the maximum shackle size that can be used.

Cargo Carrying Units (CCU’s) Design

Although safety pin shackles are normally preferred, with ISO corners, it is difficult if not impossible, to fit the split pin. For this reason it is better to use screw pin shackles, with the fully tightened pin moused / wired / tie-wrapped back to the body of the shackle to prevent the pin unscrewing in service.

What can you see wrong with this particular arrangement?

iso corner casting : good (if split pin is fitted)

Answer : incorrect orientation of the twist lock (lifting eye)

Page 14: Lifting Good and Bad Practice Book

28 29

If a smaller shackle is fitted, i.e. the knuckle of the shackle can fit through the hole in the ISO corner casting, It is acceptable to use safety shackles upside down as the split pin can be fitted in this position.

Cargo Carrying Units (CCU’s) Design

Screw pin shackle moused / wired / tie-wrapped back to body of shackle.

moused or tie wrapped to prevent backing off

iso corner casting : good

iso corner casting : good

Cargo Carrying Units (CCU’s) Design

Words fail me with this one !!!!!

What do you think, good or bad ?

Answer : abysmal!

!!! : bad

good or bad : ??

Page 15: Lifting Good and Bad Practice Book

30 31

Slings and Shackles

Container slings are generally four-leg assemblies more often than not, fitted with a fifth leg (top lifting leg) designed to hang down the side of the CCU to prevent personnel having to climb up to attach rigging.

To avoid “out of plane” forces no more than 2 legs should be fitted to a master link, therefore a quadruple assembly should be used in the manufacture. In addition, to improve the bend ratio and durability of the sling eyes, thimbles (hard eyes) should be fitted throughout.

typical thimble

quadruple assembly

fifth leg

quad assembly : good

Slings and Shackles

Four legs onto quadruple assembly - CORRECT!

Four legs onto single master link - NOT ACCEPTABLE!

masterlink assembly : good

single masterlink link : bad

Page 16: Lifting Good and Bad Practice Book

32 33

Slings and Shackles

One of the most common faults with new slings is not leaving enough “tail” protruding from the standard ferrule / talurit.

rope tail must be flush to protruding

picture of rope eye with tail

Ideal length of tail is 1/3 rope diameter.

Note: if it is too long, it snags, bends and tends to cause hand injuries.

Note : Be aware that there are also slightly longer talurits where the wire does NOT protrude, but these are evident by their; tapered end.

rope tail : bad

rope tail : good

Slings and Shackles

If the eyes have not been pulled tight enough during the manufacturing process, the thimbles can be dislodged in service.

Alternatively, if the eyes are pulled too tight, they can interfere with the pressing process.

thimbles : bad

thimbles : bad

Page 17: Lifting Good and Bad Practice Book

34 35

Slings and Shackles

In the majority of cases, safety pin shackles are the preferred option (bolt, nut and split pin).

There are exceptions, e.g. as mentioned earlier, screw pin shackles with pin secured to body are preferred for use with ISO corner castings

safety shackle : good

screw pin shackle : good

bow safety shackle

dee safety shackle

dee screw pin shackle

bow screw pin shackle

Slings and Shackles

Make sure you know what the proper pin should look like, as they are sometimes replaced with ordinary bolts if lost.

shackle with bolt

Finally, just because an item appears to be new, don’t assume it is safe to use!

This one managed to get through FIVE separate quality checks and actually got into service!

shackle with bolt : bad

manufacturing : bad

Page 18: Lifting Good and Bad Practice Book

36 37

Supply Base Checks

Outwith your suppliers’ inspections, it’s also a legal requirement (and common sense) to check every container, sling and shackle before you use it.

For this reason, it is important to have a checking system when receiving equipment at the base.

Unfortunately, at some locations, examination or inspection of lifting equipment has dwindled to purely a paperwork exercise ... in other words, checking that the certification matches the identification numbers stamped on the items while scant attention is paid to the actual physical condition of the Cargo Carrying Unit (CCU) or slings. As a result of this, many defects are only picked up if they are glaringly obvious or even worse, after an incident occurs!

what about the corrosion?

The “goods in” inspection check lists for the various types of gear expected should enable the inspector to pin-point any defects. (see the following checklists).

Supply Base Checks

Page 19: Lifting Good and Bad Practice Book

38 39

Supply Base Checks

Containers / Cargo Boxes

Check data plate for standard of manufacture

Check certification date and make sure that there is at least 1 month’s certification remaining

Check capacity of the CCU and ensure its not overloaded

Ensure correct hazard labels are affixed if applicable

Ensure old hazard labels are removed

Check structure and general condition of CCU

Check condition of door locks and seals

Check that heavier cargo is at the bottom

Make sure there are no sharp items next to soft skinned drums

Ensure there is adequate packing between the items of freight

Check the cargo is lashed down or wedged in place

In open top units, check drainage holes are clear

Check door safety nets are fitted where possible

Ensure there are no loose items on the roof of the CCU

Check condition of slings and shackles (see checklist following)

Check the weight is as manifested

Inspection Checklist

Supply Base Checks

Check Door Seals

Check Legs for Twists

Check Slings

Check for Mechanical Damage

Check Certification

Check Door Locking

Page 20: Lifting Good and Bad Practice Book

40 41

Supply Base Checks

Check data plate for standard of manufacture

Check certification date and make sure that there is at least 1 month’s certification remaining

Check structure and general condition of tank

Check condition of protection frame

Ensure correct hazard labels are affixed if applicable

Ensure old hazard labels are removed

Check that valves are locked shut and there are no leaks

Ensure there are no loose items on the roof of the tank

Check all bolt-on covers are secure

Check condition of slings and shackles (see checklist following)

Check gross weight of the tank and ensure it’s not overloaded

Inspection ChecklistFuel / Chemical Tanks

Supply Base Checks

Check Condition of Frame

Check Condition of Tank Check

Certification

Check Gross Weight for Overload

Check Valves are Locked Shut

Check Correct Hazard Labels Fitted

Page 21: Lifting Good and Bad Practice Book

42 43

Slings:

Check the colour coding (where applicable) is current and the sling has a plant number/ID mark

Check sling legs for wear, corrosion, abrasion, mechanical damage and broken wires.

Check that the sling is correctly fitted, ie no twists in the legs

Check the SWL is adequate for the load

Shackles:

Check the colour coding (where applicable) is current and the shackle has a plant number/ID mark

Check shackle for wear, corrosion, abrasion and mechanical damage.

Check that the pin is the correct one for that shackle

Ensure that safety pin shackles are fitted with split pins or that shackles with screw pins have their pins secured to the body, e.g. with cable ties

Check the SWL is adequate for the loading in the sling legs

Supply Base Checks

Inspection ChecklistSlings and Shackles

Supply Base Checks

more than 2 legs - must have quadruple assembly all terminations -

hard eyes / thimbles

safety shackles or screw pin tie wrapped

permanent bends

brocken wirs

kinks

bird caging (opening up)

Page 22: Lifting Good and Bad Practice Book

44 45

Supply Base Checks

Dropped Objects

The final check on any cargo should be for any loose items which may fall off and become a dropped object, e.g. Can you think of 5 typical examples of a dropped object.

Answer : 1 debris such as gravel and stones in forklift pockets, 2 tools such as hammers, pliers left on top of containers, 3 Loose data plates, 4 padlocks, 5 valve handles from tanks

loose debris : bad

components in fork pockets : bad

This stone found on the roof of a CCU doen’t look big or dangerous, but if it falls any substancial height, even your helmet wouldn’t protect you!

Supply Base Checks

loose debris : bad

you wouldn’t like to be the victim of a dropped of a dropped object ...

... try to make sure no one else is!

Page 23: Lifting Good and Bad Practice Book

46 47

Loading and Securing Contents

Packing of Containers and Open Top Units

Certain chemicals and materials which, when combined (possibly through transit damage), can become toxic, highly flammable or explosive. It is imperative that such material are kept apart. There is a document known as the International Maritime Dangerous Goods (IMDG) code for handling, and shipping dangerous goods which gives guidance on this subject.

Once your cargo has been separated and segregated according to compatibility, the next thing to establish is the weight of the individual items of cargo to allow you to select the capacity of your CCU. If the items are not marked or manifested, then you will have to weigh them using a loadcell or crane weigher to ensure the CCU is not overloaded. These must have an accuracy of plus or minus 4% and be checked for calibration at least once a year.

Initially, the aim when packing a CCU is to distribute the load or contents evenly over the floor to keep it balanced. This will prevent unequal loading on the slings and to keep the CCU level when lifting.

The second most important action is to secure the load inside the container to prevent it moving around in transit.

Note : Think about the safety of the people at the receiving end.

Loading and Securing Contents

A common cause of injury is unsecured cargo spilling out from containers when the doors are opened.

If you suspect the cargo has moved in transit, e.g. you can feel the pressure on the door handle, you can use door safety straps or even a rope to control the opening of the doors remotely.

unsecured cargo : bad

Page 24: Lifting Good and Bad Practice Book

48 49

Loading and Securing Contents

Typical examples of improperly secured cargo.

Large or heavy unsecured objects left loose in the container, can move around and damage other cargo.

unsecured heavy cargo : bad

Loading and Securing Contents

There are fundamental rules based on common sense that will help to protect your cargo and they are as follows:

Always

Place heavier cargo at the bottom with the lighter goods on top

Use packing to prevent damage between items of cargo

Lash down or wedge cargo to prevent movement in transit

Where applicable, use door safety nets

Remove old hazard labels

Where necessary, attach relevant new hazard labels

Where applicable, check drainage holes are not blocked

Fit waterproof covers where necessary

Ensure no loose items have been left on the roof of the CCU

Check final weight of CCU for manifest purposes

Never

Ship a CCU with less than one month’s certification remaining

Ship cargo in a damaged or sub-standard CCU or with damaged slings

Place heavy cargo on top of fragile cargo

Ship cargo loose or unsecured in the CCU

Pack sharp items next to soft skinned drums

Guess or estimate the weight of the loaded CCU for the manifest

Let cargo protrude over the side or be in a position to roll or fall off an open top container

Overload the CCU

NOTE : These rules apply whether you are shipping out from the shore base or returning goods from offshore.

consequence of unsecured heavy cargo : bad

“Victim” of loose cargo no longer fit for service, can cause costly operational delays.

Page 25: Lifting Good and Bad Practice Book

50 51

Loading and Securing Contents

Always be prepared to get something repacked if it arrives in a condition that you don’t think is good enough. As mentioned previously, suppliers are not always expert in cargo handling.

High value and / or fragile cargo can often merit purpose built transportation units.

This may seem a costly solution, but it could cost a lot more if it arrived damaged!

Page 26: Lifting Good and Bad Practice Book

52 53

Din 1142 type wire rope grips are preferred for this purpose.

Only bundle together tubulars of the same diameter. If you mix them up, the smaller ones will slide out if the bundle gets jarred or tilted (the same applies to bundles of materials with different cross-sections).

Because the slings will be in choke hitch and operating at an angle, each sling must be rated at the total weight of the bundle, for example, two six tonne slings will be needed for a six tonne lift.

Never hammer down the choke hitch to tighten it. This will increase the ef fec tive sling angle and weaken the sling.

This hitch compressesthe load and prevents it from slipping out of the sling

Slinging of Tubulars

Included Angle not to exceed 120º

The slinging of tubulars is a very common lifting operation. The slings ideally should be positioned approximately 25% (of the total length) in from either end.

The slings must be double wrapped with a choke hitch taking care not to cross over the wires on the underside of the pipe or tube bundle. The choke hitch should be pulled tight to contain the bundle and secured using an ASBRO WireClamp™ (preferred) or a bulldog grip. If using a bulldog grip, a tie wrap should then be fi tted to prevent the reeved eye slipping over the bulldog should the bundle loosen in transit.

Each sling should have a SWL approximately equal to the gross weight of the load.

Included Angle not to exceed 90º

25% 25%

Slinging of Tubulars

ASBRO WireClampTM

Bulldog Grip

Page 27: Lifting Good and Bad Practice Book

54 55

The ASBRO WireClamp™ is a recently developed alternative to the Bulldog Grip. It is a relatively simple piece of equipment consisting of three components:

ASBRO WireClamps™ may have already been examined and certified fit for use, but if not, they must be visually inspected before each use as follows:

Check the clamp is the correct size for the wire rope (size is hard stamped on the “U” hoop).

Inspect the “U” hoop for excessive wear, cracks, deformity and impact damage.

Inspect the claw for excessive wear, cracks, deformity and impact damage.

Inspect the wedge for excessive wear, cracks, deformity and impact damage and check that the wedgelock is free to move.

Rejection Criteria

The clamp should be rejected when there is any obvious excessive wear, cracks, deformity or impact damage or if the clamp allows the rope to slip through when landing the bundle thus allowing the bundle to become slack.

Care and Maintenance

The clamps must be inspected for damage after removing from sling. The wedgelock should be greased if required and the clamp reassembled and stored in a box marked with the correct size / diameter for future use. They should be stored in a dry atmosphere.

Reusability

ASBRO WireClamps™ can be safely re-used as long as they pass the pre-use visual inspection. The amount of times they can be re-used will depend on the treatment they receive in service.

Fit the ASBRO WireClamp™ using the appropriate tools as follows:

Note : After landing load on the truck or supply vessel, check that the bundle remains secure and there is no back slippage of the rope through the clamp. Should any back slippage be apparent and / or the bundle becomes slack, the clamps must be replaced with new ones.

Step 1 : Dismantle ASBRO WireClampTM and position “U” Hoop on sling wire just above the choke eye. Slide up / down if required to clear thin assembly wire.

Step 4 : Lightly tap the wedge from the left to ensure the wedgelock is properly engaged. The wireclamp is now fitted and secure.

Step 3 : With the claw component towards you, introduce the wedge from the right ensuring it passes through both sides of the “U” Hoop and the hole in the claw and hammer wedge until the wedgelock clicks into the locked position.

Step 2 : Fit the claw into the “U” Hoop and ensure the claw captures the wire of the sling eye.

Slinging of Tubulars Slinging of Tubulars

claw

“U” hoop

open wedge socket

Page 28: Lifting Good and Bad Practice Book

56 57

Although the British Standard indicates that it is acceptable to single wrap and choke INDIVIDUAL tubulars, this is only recommended under ideal conditions. In all other cases where outside influences can affect the safety of the lift, eg offset centre of gravity, lifting on a vessel where the load is liable to swing, lifting in windy conditions, lifting in confined spaces, lifting excessive heights, etc. it is recommended that these tubulars are also double wrapped. If the tubular or load is being lifted and laid down more than once, it may also be advisable to lock the choke with an ASBRO WireClamp™ or a wire rope grip (bulldog) secured with a tie-wrap.

Always : Prepare your landing site to enable the bundles to be landed without crushing the slings.

If using Bulldogs only DIN1142 type are acceptable for this particular purpose.

Typical examples:

16 mm for 3 tonne slings

19/20 mm for 4.8 tonne slings

22 mm for 5 tonne slings

Warning : Do not over-tighten the grip as this could damage the wire rope.

Step 6 : Push and hold in the wedgelock with the ASBRO tool and hit the wedge at the narrow end to disassemble the ASBRO WireClamp™.

Step 5 : Hit the wide end of the wedge to ensure the wedgelock is free to be depressed with the ASBRO tool.

Arrival at destination to remove clamps (with the weight of bundle still supported by the crane) do as follows:

Eye of sling

Fit withthreadedportion tothis side

To crane hook

When lowering off with the crane, beware of tubulars rolling out to flat position. There may be a danger of limbs being trapped.

Slinging of Tubulars Slinging of Tubulars

Page 29: Lifting Good and Bad Practice Book

58 59

Loads Requiring Special Attention

There will on occasion, be loads which are out of the ordinary and require special attention, eg loads that are quite small but extremely heavy. In this case, it is imperative that spreaders or pallet bars are used to distribute the weight over the load bearing members in the floor of the CTU. This is to prevent the load falling through in the event of dynamic/shock loading.

If the load is extremely heavy, possibly nearing the maximum capacity of the crane on the offshore installation, there will have to be additional planning required to ensure the lift can proceed, eg questions to ask:

Is the weather forecast favourable?

Can the vessel manoeuvre to within the cranes safe operating radius for that load?

Will the crane be correctly reeved up to perform the lift?

Does it have adequate hoisting speed when fully reeved?

Is there adequate space on the installation’s deck to receive the load?

Is the load bearing capacity of the deck (both vessel and installation) adequate?

Will the load exert excessive point loading and is special packing required to protect the decks?

It may be advisable to involve the services of an engineer who will indicate the maximum sea state/radius in which the lift can be made without the load re-impacting on the deck as the vessel rises on the next wave. This information would then be passed on to the installation. You may also prefer an engineer’s input if the load is fragile or if it is an expensive piece of equipment.

If the load has a high centre of gravity and is unstable, it may be preferable to ship it in the horizontal position for upending once it is landed on the installation. This being the case, additional rigging may be required to perform the upending operation.

If the cargo is contained in a wooden box, it must be put into a CTU for transportation, ie do not sling the box itself as it may collapse under load and/or the cargo could fall out of the bottom.

Note : The exception is boxes which have been specifically designed for lifting

Always : When stacking tubulars, insert timber packing or similar to prevent damaging the slings.

Never :

Sling tubes of different diameters.

Sling a mixture of tubulars, angle, flat bar, etc. (in both cases the smaller items will slip out).

Tighten the choke by hammering as this will increase the effective sling angle thus weakening the sling.

Angle

Flat bar

Large bore pipe

Differentsize tubes

Sling in choke bight.Do Not knock down bight

Slinging of Tubulars

Page 30: Lifting Good and Bad Practice Book

60 61

Positioning of Loads on Vessels

The positioning of loads on a vessel is very important and can make the difference between whether or not they can be offloaded at their destination especially if the weather conditions are marginal for lifting operations.

Obviously, this is more critical for the heavier loads but even lighter loads positioned in the middle of the vessel can cause problems if the vessel cannot manoeuvre close enough to the installation. For that reason, cargo must be prioritised and positioned on the vessel accordingly.

If the vessel is shared between Installations or Operating Companies which is often the case, the positioning of cargo will be affected by the order in which it will be taken off. However, there are other considerations such as each individual crane’s ability to handle loads.

A crane’s lifting capacity decreases as the radius increases therefore heavier loads or priority containers (food for example), should always be placed towards the side of the vessel that will be along side the installation. This is to allow the vessel to maintain an acceptable distance from the installation when manoeuvring the load to within the cranes working radius for that particular load.

and these will have been tested and marked accordingly.

Once the cargo has arrived at the destination and has been removed from the CTU, it should be handled using cargo nets. Alternatively, the cargo could be removed from the box and have slings attached directly to it for further handling.

If the load has an offset centre of gravity you will have to arrange for special slings with varying leg lengths to compensate. Alternatively, a fabricated lifting beam or frame can be used.

If a lifting beam or frame is being used, it is important to lash it down to the item of cargo once it is loaded onto the vessel to prevent it damaging the cargo in transit if the weather gets rough.

If the load is fragile, or extremely valuable, it may be necessary to have a container specially made to waterproof, protect and transport it to its destination.

Loads Requiring Special Attention

Page 31: Lifting Good and Bad Practice Book

62 63

Positioning of Loads on Vessels

The positioning of standard containers and open top containers next to each other does not usually present problems but consideration is required when placing other types of loads together on the vessel. The aim is to prevent any load snagging against another load when being lifted off again. A typical example of poor vessel loading would be the positioning of bundles of tubulars in close proximity to fuel or oil tanks where there is the possibility that they could get tangled up in the tank protection frame or even pierce the tank should the bundle swing.

The preparation of a deck plan for the supply vessel can save a lot of time by reducing the amount of double handling and consequently lessen the

Positioning of Loads on Trucks

Page 32: Lifting Good and Bad Practice Book

64 65

The security and safety of loads coming into the base is the responsibility of the supplier but they must be aware of the minimum standards acceptable to the base.

Loads being returned to the supplier however, are the total responsibility of the base. If trucks are carrying a variety of equipment for different suppliers, the first thing to consider is the order in which they will be taken off. The driver can then be given a route map and suppliers can be contacted in advance to be advised of deliveries. Forward planning and the resultant positioning of loads on

the truck will reduce double handling to a minimum and hence reduce the potential for accidents.

The actual securing of loads on the transport will depend on what the load is, but in general, there are accepted practices for handling standard cargo, eg when transporting containers on trailers, you must make sure the doors are locked and secure. A minimum of two cargo restraints per container are required to lash it down.

Don’t forget to secure the link

The material for the lashings will depend on the weight of the load, eg Polyester cargo restraints will be sufficient for the majority of cargo but extremely heavy loads will have to be secured using high tensile chains and loadbinders.

Security & Safety of Loads for Road Transport

Page 33: Lifting Good and Bad Practice Book

66 67

Always remember to secure the 5th leg of container slings to prevent them swinging into the path of other vehicles on corners.

When transporting tubulars, when each bundle is landed, the slings should be laid along the length of the bundle to prevent them being crushed by the next bundle. (This makes it easier for offloading at the supplier’s yard). Samson posts should be in place along the sides of the trailer and wedges should be used where necessary to stabilise the load.

The weight of any particular load or bundle should be known and if on the heavy side, for safety reasons, this information should be relayed in advance to the suppliers to allow them to organise suitable cranage or forklift trucks.

Security & Safety of Loads for Road Transport

Sea fastening is the tying down and securing of cargo to prevent it moving around the vessel’s deck in bad weather. All cargo should be restrained in the three directions of movement, eg forward to aft, port to starboard and against upward movement.

For the majority of containers positioned along the side of the vessel, it is common practice to use winches on the deck to secure them.

Most vessels have eyeplates or rings sunk into the decks to which various types of lashing equipment can be attached. The most popular and easy to use are polyester cargo ratchet lashings. For heavier duty restraint, there are loadbinders which are used with chain and rigging screws.

Cargo Restraint Assembly Load Binder, Chain & Turnbuckle

Note : Hold down capacity = 1/3 of breaking strain.

Support stools are normally secured to the deck for shipping large pipes. These pipes are then lashed down onto them for stability during transit.

Larger loads can actually have transportation frames to both support the load and also spread the load over the strong points of the vessel’s deck.

Sea Fastening

Duty Breaking Strain

Standard 5,000 kg

Heavy 10,000 kg

Duty Breaking Strain

Std. 10mm dia. 7,360 kg

Hvy. 13mm dia. 11,800 kg

X. Hvy. 16mm dia. 16,800 kg

Deck Deck

Page 34: Lifting Good and Bad Practice Book

68 69

Sea Fastening

WARNING : Securing a load by welding directly to the vessel deck is to be avoided at all costs due to the danger of some of the welds still being intact as the lift takes place.

This could severely overload your crane!

If any special sea fastening arrangements have been made, it is vitally important that the supply vessel crew is instructed as to the removal procedure once the load has arrived at the destination.

Depending on the complexity of the project, procedural documents, job packs or even specialised personnel may have to be onboard to assist with the offloading.

If the load is of a substantial height, ladders may be required to allow the deck crew access to hook up the rigging when offloading.

Adverse Weather Conditions

In section 12 we have dealt in depth with adverse weather conditions restricting crane operations but obviously, they also have a bearing on cargo handling operations.

The first and most important task is to evaluate the priority of cargo against the chances of it being damaged in transit. There is no point in shipping it out if it arrives at the destination damaged and possibly unusable, it will only get sent back again at great cost to all concerned. It would be more efficient to ship it a few days late as opposed to shipping it on time, then having to wait weeks to have it repaired!

If the cargo is essential and has to be shipped, consideration must be given to packaging it more securely due to the possibility of it shifting within the CTU in transit, and becoming a hazard at the other end when its opened.

It may also be necessary to waterproof it because...

...although it’s calm in the harbour, it could be rough at sea!

In severe weather conditions, there is the added possibility of the cargo breaking loose on deck which can be very hazardous to the deck crew when they try and re-secure it on a pitching and heaving deck. There is the obvious risk of them being trapped and crushed between loads or the load and the side of the vessel.

Consider the use of additional or stronger sea lashings to compensate for rough weather.

Page 35: Lifting Good and Bad Practice Book

70 71

Communications

Communications in this context is about letting everyone know in advance, what is happening with regards to cargo movements to allow them to make any special arrangements. It is also about issuing specific instructions where required, to ensure the cargo is handled in the safest possible manner.

For outward bound cargo, manifests and any special instructions should be relayed to both the vessel Master/crew and the relevant personnel at the destination. This is the opportunity to give any special instructions to the vessel crew with regards to releasing sea fastenings etc. Failure to do this can have serious consequences, eg:

Loads being lifted off with the transportation steel work still attached

Sea fastenings still attached when the lift begins

WARNING : By far, the most dangerous oversight is failing to remove all sea fastenings and the crane ends up trying to lift the whole vessel.

For inward bound cargo, advance notification to the relevant personnel at the base allows them to make sure they have enough personnel to cope with the offloading. It also allows them to organise any special activities such as toxic waste disposal, onward transportation, give advance notification to all relevant suppliers to make them aware of returning cargo, eg ensure they have adequate lifting capacity available.

When sending goods from the base back to suppliers, if possible, organise the drop-offs first and plan the route for the trucks to take to minimise the double handling of loads.

NOTE : A short phone call or fax is all it takes to alert everyone as to what’s happening. This can and will save a lot of time and money and eliminate a lot of stress on the part of the recipient.

Imagine how you would feel if you had just finished work for the day, organised a game of golf and six fully laden trucks arrive at your yard!

Page 36: Lifting Good and Bad Practice Book

72 73

Can the vessel manoeuvre to within the cranes safe operating radius for that load?

One of the most important aspects in dealing with returning cargo is the accurate weighing and manifesting of returning cargo. The fact that most of the returns are scrap items of unknown weight makes it essential that they are weighed as they are loaded into the CTU. If this is not possible, then as a minimum, the gross weight should be checked against the crane’s weighload to ensure the CTU is not overloaded and to gain accurate information for the manifests.

NEVER JUST GUESS THE WEIGHT - WEIGH IT ACCURATELY

Make sure the contents of the CTU are secure and not just crammed in to maximise any free space in the CTU.

Think about the handler at the receiving end!

Remember to remove all previous hazard warning labels if they no longer apply but do affix new ones if applicable, eg LSA warnings

WARNING : Remove any loose items from the top of cargo transport unit

A copy of the manifest must be given to the vessel’s Master with whom the crane operator will

liaise regarding the order in which the cargo is loaded back onto the

vessel. It is the vessel Master’s responsibility to position them safely on deck.

Prior to crane operations commencing, the vessel is to be manoeuvred to within the crane’s safe operating radius and to a position where the crane operator has an unobstructed view of the deck.

Back Loading Cargo

Page 37: Lifting Good and Bad Practice Book

74 75

Back Loading Cargo

All loads should be lowered over open sea, ie clear of the vessel in case of rigging failure. When the load is approximately 8 to 10 metres above the height of the vessel’s deck, the operator will slew the load over the deck, and lower off under the instructions of the signaller onboard the vessel. The operator will use his judgement for the final lay down of the load.

For heavier loads, the vessel may have to pull away prior to the load being lowered until it is approximately 6 to 8 metres above the vessel’s deck level. The crane should then cease lowering and the vessel should then manoeuvre its deck below the load, thus maintaining the crane within its safe working radius. The load will be finally landed under direction from the vessel’s signaller and at the discretion of the crane operator.

Once the landing operation is completed the vessel’s signaller will ensure the crane is unhooked and clear of all obstructions before giving the instruction to hoist the hookblock.

Crane / Hoist

Crane / Hoist pre-use inspected

Certification of crane / hoist is current

Adequate capacity for lifts

Adequate boom length / height of lift

Set up correctly for lifts (correct radius / adequate number of falls)

Set up correctly (level, on firm ground)

Set up correctly (outriggers fully extended and pinned)

Set up correctly (load spreaders / sleepers used under outriggers if required)

Set up correctly (clear of O/head power lines)

Set up correctly (clear of underground services)

Set up correctly (far enough away from excavations)

Certification of ancilliary equipment current (e.g. chain slings, hook blocks etc.)

Crane / Hoist operator

Qualified / experienced to operate crane / hoist

In good health / reasonably fit

Eyesight satisfactory

Knowledge of basic slinging

Knowledge of hand signals / radio comms.

Checklist for lifting equipment / rigging arrangement / competence (before you lift):

Page 38: Lifting Good and Bad Practice Book

76 77

Banksman

Qualified / experienced to direct crane / lifting operation

In good health / reasonably fit

Eyesight satisfactory

Knowledge of basic slinging

Knowledge of hand signals / radio comms

Slingers

Qualified / experienced to slings loads / check rigging on loads

In good health / reasonably fit

Eyesight satisfactory

Knowledge of basic slinging

Knowledge of hand signals / radio comms

Load carriers (Containers, baskets, half heights etc.)

Load carrier is of sound construction

Load carrier has data plate - SWL, Payload, max. gross weight, test date, insp. date etc.

Pad eyes properly constructed (not flame cut)

Pad eyes properly constructed (holes to suit shackle pin dimensions)

Pad eyes properly constructed (width / thickness to suit shackle jaw gap )

Pad eyes properly mounted (normally welded and NDT’d)

Pad eyes mounted / welded to substantial base (not on to sheet steel)

Pad eyes angled towards centre (preferable)

Payload centred as much as possible to keep C of G central

Payload lashed down / wedged / secured to prevent movement in transit

Door nets fitted / tarpaulins fitted as required

Door seals intact

Door locks functioning correctly

Doors secured for transit e.g. padlocked / tie-wrapped etc.

No cargo protruding over edge of baskets / half heights

Old shipping labels removed (e.g. hazardous warnings etc.)

New shipping labels attached to reflect contents

Unit checked for possible dropped objects

Gross weight checked to ensure NO overload

Page 39: Lifting Good and Bad Practice Book

78 79

Load (Tubulars)

Correctly stacked for bundling

Thread protectors fitted where applicable

Casing checked for possible dropped objects

Each sling rated same as load (e.g. 5 tonne load - use 2 x 5 tonne slings)

Slings inspected prior to use (including colour code if applicable)

Slings positioned 25% in from either end

Slings double wrapped, choked, bulldogged and tie-wrapped (also applies to singles).

Bundle tight and secure but NOT with slings hammered down

Loads (various)

Load is of sound construction

Weight of load is known

Pad eyes / temporary lifting eyes currently certified

Pad eyes / temporary lifting eyes correctly installed

Load has central C of G or special slings to compensate

Load is balanced

Any wrap-around slings will remain in place during lifting operation

Wire rope sling sets

Slings / shackles are pre-use inspected

Certification in date

maximum 2 legs per link (unless third one is a top lifting leg)

Correct SWL for load to be lifted

Fitted correctly (no twists in legs etc)

Free to lift (not snagged on any part of load)

Shackles are correctly fitted - safety pin type shackles preferred with split pins fitted

Screw pin shackles must have pins wired / tie-wrapped to shackle body

Route / Lay-down area

Route load to be travelled clear of obstacles

Lay-down area adequate load-bearing capacity

Lay-down area within crane’s safe working radius for load

Work area cordoned off to uninvolved personnel

POSITION HOOK DIRECTLY OVER THE CENTRE OF GRAVITY

CLEAR PERSONNEL FROM AREA / RETREAT TO SAFE AREA

TRIAL-LIFT LOAD JUST CLEAR OF GROUND TO CHECK BALANCE AND STABILITY PRIOR TO LIFTING

Page 40: Lifting Good and Bad Practice Book

80


Recommended