+ All Categories
Home > Documents > Lightning Calculations

Lightning Calculations

Date post: 04-Apr-2018
Category:
Upload: buntysurat
View: 234 times
Download: 1 times
Share this document with a friend

of 48

Transcript
  • 7/29/2019 Lightning Calculations

    1/48

    LIGHTNING CALCULATION

    CLIENT : ACC WADI LIMITED REV/DATE : 0/18.07.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE :LIGHTNING CALCULATION SHEET : Page 1 of 48

    CONTENTS

    SL.NO. DESCRIPTION SHEET NO.

    1.0 PURPOSE 2

    2.0 REFERENCES DOCUMENTS 2

    3.0 ASSUMPTIONS 2

    4.0 RISK FACTOR CALCULATION 7

    5.0 STRIP SIZE CALCULATION 32

    6.0 RESULT 46

  • 7/29/2019 Lightning Calculations

    2/48

    LIGHTNING CALCULATION

    CLIENT : ACC LIMITED REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTINING CALCULATION SHEET : Page 2 of 48

    1.0 PURPOSE

    The calculations are done for the following purposes :

    a) Lightning protection requirement for Old wadi Cement plant,Power plant andColony Area.

    b) To estimate the number of Lightning electrodes required at the above area.c) To prove that the maximum value of resistance of the earthing system shall not be

    more than 3 ohms as per 12.3.1 of IS 2309:1989 .

    2.0 REFERENCE DOCUMENTS, CODES AND STANDARDS

    a) IS: 2309-1989-Indian Standard Code of Practice for Protection against Lightning.&NFPA78.

    ASSUMPTIONS & RECOMMENDED DESIGN PROCEDURE.

    a) Soil resistively is equal to 312 ohm-m , which is assumed to be uniform throughout

    the plant.b) Pipe electrode in contact with earth is 300 cm and the diameter of the pipe

    electrode is 3.8 cm .c) The effect of interconnection and links between other earthing grids is ignored for

    the purpose of this calculation.

    3.1 Protected StructureCommon structures are structures used for ordinary whether commercial, Industrial,

    institutional or research.

    3.2 Need for Protection

    3.2.1Desirability of providing lightning protection shall be assessed either by calculating the riskindex or by judgement. Structures with inherent explosive risks like factories, fuel tanks etc.

    need the highest possible class of lightning protection system. Other structures where largenumber of people congregate, essential public services are concerned, tall/isolated structures,

    structures of historic and cultural importance should be provided with lightning protectionsystem irrespective of risk index.

    3.2.2 Risk Index Weighting Factors

    Indian standard recommends the following factors which form the basis of calculating the risk

    index.

    a) Weighting factor A Use of structure (Table 1 A).b) Weighting factor B Type of Construction (Table 1 B)

    c) Weighting factor C Contents or consequential effects (Table 1C)d) Weighting factor D Degree of Isolation (Table 1D)

    e) Weighting factor E Type of Country (Table 1E)

    Depending upon the characteristic features of above factors, various weighting factors are give

    in Table 1A to 1E of IS:2309. The probability of the structure being struck by lightning in one

  • 7/29/2019 Lightning Calculations

    3/48

    LIGHTNING CALCULATION

    CLIENT : ACC LIMITED REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTINING CALCULATION SHEET : Page 3 of 48

    year is the product of lightning flash density and the effective collection area of the

    structure to be protected.

    The probable number of strikes/year (Risk) is:

    P = Ac * Ng * 10 6

    Ng = Number of lightning flashes to ground per Km 2 per year.

    Ac = Effective area of collection of the structure.Risk, P, multiplied by weighting factors A to E gives the risk index.

    3.2.3 If the value of risk index is less than 10 -5, then in the absence of other Overriding

    consideration, protection shall not be necessary.3.2.4 If the risk index is more than 10 -5 then sound reasons shall be necessary to

    Support the decision of not providing the lightning protection.

    3.3 Size and Material of Conductors

    3.3.1 The materials of air termination network, down conductors and earth terminals shall be GI as

    per Table 3 of IS 2309:1989.

    3.3.2 Lightning currents have very short duration. Therefore, thermal factors are of little consequen

    in deciding the cross-section of the conductor. The minimum size of the various components o

    the system are given below:

    Sl.No Item Material Size

    1. Vertical Air Terminations Copper 20 mm dia,1000 mm Long

    G.S 20 mm dia,1000 mm Long

    2. Horizantal air Terminations copper 20 X 3 mm Flat

    G.S 25X 6mm Flat.

    3. Down Conductors Same as Horizontal Air Terminations.

    4. Earth Terminations

    a) Horizontal conductors Cu. Strip 32 X 6 mm

    G.S Strip 50 X 6 mmb) Rod Electrodes Cu 20mmDia, 3000 mm Long.

    Steel 20mmDia, 3000 mm Long.c)Pipe Electrode Steel 40mmDia, 3000 mm Long.

  • 7/29/2019 Lightning Calculations

    4/48

    LIGHTNING CALCULATION

    CLIENT : ACC LIMITED REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTINING CALCULATION SHEET : Page 4 of 48

    3.4 Air termination Systems

    Air Terminations: The vertical and horizontal conductors or combination of both, installed oveor near the structure to attract the lightning stroke to themselves are called air terminations

    3.4.2 Protective Zone : The space around the air terminations in which there is almost no

    probabilityDirect lightning discharge is called the protective zone of air termination. Protective zones of

    various arrangements shall be as given in IS: 2309 - 1989 etc. for correctness.

    3.4.3 The angle between vertical line passing through the conductor and side of protective zone iscalled protective angle.

    3.4.4 Horizontal air terminations: Arranged along the contours such as parapets, ridges and edges

    the roof and wherever necessary, over the flat surfaces, horizontal air termination networkform basic protection arrangement, if roof of the building has large horizontal dimensions.

    3.4.5 Protective angle of horizontal air termination is 45 for normal protection and upto 30 if high

    protection is needed.

    3.4.6 Protective angle for two horizontal air terminations, spaced at a distance not greater than twic

    the height, shall be used within the space between conductors and 45 and 30 respectively if

    higher protection is needed.

    3.4.7 The spacing, between adjacent horizontal air terminations shall not be more than 10 metres

    and no part of the roof shall be more than 5 metres away from the nearest horizontal

    conductor.

    3.4.8 Layout of Horizontal Air Terminationsa) A horizontal air termination shall run along the periphery of the roof.

    b) Additional parallel horizontal conductors shall be provided if spacing between theconductors is more than 10 metres or any part of the roof is more than 5 metres

    away from the nearest horizontal conductor.C) Conductors shall be interconnected to form a closed loop.

    3.4.9 Vertical Air Terminations

    a) Vertical air terminations shall be used for very high structures with small base area.b) Protective angles of vertical air terminations shall be same as given for horizontal air

    terminations under clause 3.4.5/.6.

    c) Vertical air terminations shall project at least 300 mm above the protected structure.d) All the vertical air terminations provided on the same structure shall be interconnected.e) All the air termination network shall be effectively secured to the roof against

    overturning. The fasteners shall be of the same material as the conductor to avoid

    bimetallic corrosion.

    3.4.10 Where a structure has two elevations, out of which lower is projecting outside the high

    elevation such that the network in higher elevation does not protect the lower elevation, both

    networks shall be interconnected by connecting the higher elevation down conductors to thelower network.

  • 7/29/2019 Lightning Calculations

    5/48

    LIGHTNING CALCULATION

    CLIENT : ACC LIMITED REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTINING CALCULATION SHEET : Page 5 of 48

    3.4.11 If a particular small portion in the structure is projecting above the level of horizontal

    conductors by more than 1000 mm, a separate network shall be formed for the same.

    3.4.12 All the metal piping, railing, etc. on the roof shall be bonded to the protective network

    with a bolted connection.

    3.5 Down ConductorsThe conductors which connect air terminations to earth terminations are called down

    Conductors.

    3.5.1 Size and material of the down conductors shall be given under clause 3.3.

    3.5.2 Number

    a) As per IS.2039, a structure having a base area less than 100 sq. mtr shall be provided with

    only one down conductor. Chimneys, whose over all width at the top or diameter is less than1.5 metres shall be provided with only one down conductor.

    b) For buildings having base area more than 100 m 2 , the number of down conductors shall be

    smallerthe number obtained by the following two criteria

    i) one down conductor for first 100 m 2 area plus one for every additional 300 m 2 area or part

    thereofii) one down conductor for every 30 metres of periphery

    Non-conducting chimneys whose overall width at the top or diameter is more than 1.5 metres sha

    be provided two down conductors. Structures on rocky terrain where testing and inspection is

    difficult shall be provided with minimum two down conductors.

    As per BS: 6651 1999 at least one down conductor should be provided for each 20 mtr or part

    thereof of the perimeter at roof level. Structures greater than 20-mtr height, shall have a downconductor per 10 mtr or part thereof.

    3.5.3 Route of Down Conductors

    a) Unless aesthetic and architectural considerations prohibit, down conductors shall be uniformlydistributed around the outside walls of the structure.

    b) The path between the air terminations and earth terminations shall be as direct as possible an

    shall avoid sharp bends upturns and kinks.

    c) No deep re-entrant loop, in which length of the conductor forming the loop is more than 8 timthe width of open side of the loop, shall be recommended. This is shown in Figure-1 and is

    avoided to prevent large inductive voltage drop across the open side of the loop.

    d) In a building cantilevered from first storey onwards, the down conductors shall not follow thecontour of the building as shown in Figure-2.

    e) Down conductors shall not be attached to lift shafts.

  • 7/29/2019 Lightning Calculations

    6/48

    LIGHTNING CALCULATION

    CLIENT : ACC LIMITED REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTINING CALCULATION SHEET : Page 6 of 48

    f) When suitable external route for down conductors is not possible or advisable, the conductors

    may run in air space provided by non-metallic, non-combustible ducts not smaller than 75 x 15 mor in any vertical, service duct running through the height of the building, provided it does not

    contain any unarmoured, non-metal sheath cable.

    g) Down conductors may be embedded in the wall of the structure. In such case, reinforcing bars

    shall be bonded to the down conductor.

    h) In case metallic object such as pipes, structures etc. exists in the vicinity of down conductors,there is a risk of side flash over between the down conductor and these objects. In such

    cases, the object shall be bonded to or installed on the basis of the recommendations givenunder

    Clause3.7.1.

    Each down conductor shall be provided with testing point as discussed in Clause 3.7.2 (f)

    j)Holes in cornice and parapet walls shall be used for the passage of down conductors,wherever possible.

    3.6Earth Terminations

    3.6.1 Earthing conductors embedded in the soil and designed for the safe discharge of lightning

    currents into the soil are called earth terminals.3.6.2 Down conductor shall be provided an earth electrode and all earth electrodes shall be intercon

    nected.

    3.6.3 Earthing resistance of earth terminations shall be such that the combined resistance is not mothan 3 ohms. In case, the earthing resistance is not within limits, the earth electrodes shall belocated in treated earth pit.

    3.6.4 Disconnecting facility shall be provided in some of the earth electrodes so that it is possible tomeasure the earthing resistance.

    3.6.5 Lightning protective earthing system may be interconnected with operational and safety

    earthing system.

    3.6.6 Earthing conductors shall not be more than 1.5 to 2.0 metres away from the structure except

    when high temperatures are likely to be encountered in subsoil or when sufficient space near

    the structure is not available.3.6.7 Metal pipes and other structures buried in earth shall be bonded to or isolated from the

    earthing conductors on the basis of the recommendation given under clause 3.7.1.

    3.6.7 Earth Electrodes

    a) The use of rod/pipe/plate electrodes is permissible. their choice will depend upon the siteconditions, soil resistivity and economic considerations. In general, the use of pipe electrodes

    recommended.

    b) The material of earth electrodes shall be either galvanised steel or copper. The choice willdepend upon the material of the air termination, down conductors and soil resistivity. It is

    preferable to use the same material throughout the system.

  • 7/29/2019 Lightning Calculations

    7/48

  • 7/29/2019 Lightning Calculations

    8/48

    LIGHTNING CALCULATION

    CLIENT : ACC LIMITED REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTINING CALCULATION SHEET : Page 8 of 48

    BULK LOADING SILO:

    Diameter(D) : 11 M

    Height (H) : 49.5 M

    Lightning Flashes/Sq.Km / year(Ng) : 3.284 (AS CALCULATED ABOVE)-Rating factor for Wadi

    Weighing Factors

    A : 1.0

    B : 0.8

    C : 0.8

    D : 1.0

    E : 0.3

    Overall weighing Factors : A x B x C x D x E

    : 1.0 x 0.8 x 0.8 x 1.0 x 0.3

    : 0.192

    Collection Area AC : H2

    : (49.5)2

    : 7693.785 m2

    Probable no.of strikes for the : Ac x Ng x 10-6

    structure per year P : 7693.785 x 3.284 x 10-6

    : 2.526 x 10-2

    Therefore, the overall risk Factor : P x Overall Weighing Factor

    : 2.526 x 10-2 x 0.192

    : 4.84 x 10-3

    which is greater than 10-5

    Therefore for Bulk loading Silo Lightning Protection is essential.

    CEMENT STORAGE SILO:

    Diameter(D) : 10 M

    Height (H) : 29.8 M

    Lightning Flashes/Sq.Km / year(Ng) : 3.284

    - Rating factor for Wadi

    Weighing Factors

  • 7/29/2019 Lightning Calculations

    9/48

    LIGHTNING CALCULATION

    CLIENT : ACC LIMITED REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTINING CALCULATION SHEET : Page 9 of 48

    A : 1.0

    B : 0.8

    C : 0.8

    D : 1.0

    E : 0.3

    Overall weighing Factors : A x B x C x D x E

    : 1.0 x 0.8 x 0.8 x 1.0 x 0.3

    : 0.192

    Collection Area AC : H2

    : (29.8)2

    : 2788.45 m2

    Probable no.of strikes for the : Ac x Ng x 10-6

    structure per year P : 2788.45 x 3.284 x 10-6

    : 9.157 x 10-3

    Therefore, the overall risk Factor : P x Overall Weighing Factor

    : 9.157 x 10-3 x 0.192

    : 1.75 x 10-3

    which is greater than 10-5

    Therefore for Cement storage Silo Lightning Protection is essential.

    KILN NO.3 PREHEATER:

    Length (L) : 19.2 M

    Width ( W) : 16 MHeight (H) : 106 M

    Lightning Flashes/Sq.Km / year(Ng) : 3.284

    - Rating factor for Wadi

    Weighing Factors

    A : 1.0

    B : 0.8

    C : 0.8

  • 7/29/2019 Lightning Calculations

    10/48

    LIGHTNING CALCULATION

    CLIENT : ACC LIMITED REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTINING CALCULATION SHEET : Page 10 of 48

    D : 1.0

    E : 0.3

    Overall weighing Factors : A x B x C x D x E

    : 1.0 x 0.8 x 0.8 x 1.0 x 0.3

    : 0.192

    Collection Area AC : (L x W) + 2(L x H) + 2(W x H) + 2

    : (19.2x16)+2(19.2x106)+2(16x106)+ (107.5)2

    : 1290105.505 m2

    Probable no.of strikes for the : AC x Ng x 10-6

    structure per year P : 1290105.505 x 3.284 x 10-6

    : 4.236

    Therefore, the overall risk Factor : P x Overall Weighing Factor

    : 4.236 x 0.192

    : 0.8133 which is greater than 10-5

    Therefore Lightning Protection is essential for Kiln No.3 Preheater.

    CEMENT MILL BUILDING :

    Length (L) : 34 M

    Width ( W) : 36 M

    Height (H) : 11.5 M

    Length (L) : 22 M

    Width ( W) : 36 M

    Height (H) : 16.5 M

    Lightning Flashes/Sq.Km / year(Ng) : 3.284

    - Rating factor for Wadi

    Weighing Factors

    A : 1.0

  • 7/29/2019 Lightning Calculations

    11/48

    LIGHTNING CALCULATION

    CLIENT : ACC LIMITED REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTINING CALCULATION SHEET : Page 11 of 48

    B : 1.0

    C : 0.8

    D : 1.0

    E : 0.3

    Overall weighing Factors : A x B x C x D x E

    : 1.0 x 1.0 x 0.8 x 1.0 x 0.3

    : 0.24

    Collection Area AC : (L x W) + 2(L x H) + 2(W x H) + 2

    : (12x36)+2(12x11.5)+(36x11.5)+

    (22x36)+2x(22x16.5)+(36x16.5)+ (16.5)2

    : 4088.86 m2

    Probable no.of strikes for the : AC x Ng x 10-6

    structure per year P : 4088.86 x 3.284 x 10-6

    : 1.44 x 10-2

    Therefore, the overall risk Factor : P x Overall Weighing Factor

    : 1.34 x 10-2 x 0.24

    : 3.22 x 10-3 which is greater than 10-5

    Therefore Lightning Protection is essential for Cement Mill Building.

    CEMENT MILL 4 & 5 BUILDINGS:

    Length (L) : 34 M

    Width ( W) : 36 M

    Height (H) : 16.5 M

    Lightning Flashes/Sq.Km / year(Ng) : 3.284

    - Rating factor for Wadi

    Weighing Factors

    A : 1.0

  • 7/29/2019 Lightning Calculations

    12/48

    LIGHTNING CALCULATION

    CLIENT : ACC LIMITED REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTINING CALCULATION SHEET : Page 12 of 48

    B : 1.0

    C : 0.8

    D : 1.0

    E : 0.3

    Overall weighing Factors : A x B x C x D x E

    : 1.0 x 1.0 x 0.8 x 1.0 x 0.3

    : 0.24

    Collection Area AC : (L x W) + 2(L x H) + 2(W x H) + 2

    : (34x36)+2(34x16.5)+2(36x16.5)+ (16.5)2

    : 4388.86 m

    2

    Probable no.of strikes for the : AC x Ng x 10-6

    structure per year P : 4388.86 x 3.284 x 10-6

    : 1.44 x 10-2

    Therefore, the overall risk Factor : P x Overall Weighing Factor

    : 1.44 x 10-2 x 0.24

    : 3.46 x 10-3 which is greater than 10-5

    Therefore Lightning Protection is essential for Cement Mill 4 & 5 Buildings .

  • 7/29/2019 Lightning Calculations

    13/48

    LIGHTNING CALCULATION

    CLIENT : ACC LIMITED REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/MK

    TITLE : LIGHTINING CALCULATION SHEET : Page 13 of 48

    CEMENT MILL CONTROL ROOM:

    Length (L) : 16 M

    Width ( W) : 7.5 M

    Height (H) : 11.5 M

    Lightning Flashes/Sq.Km / year(Ng) : 3.284- Rating factor for Wadi

    Weighing Factors

    A : 1.0

    B : 1.0

    C : 0.8

    D : 1.0

    E : 0.3

    Overall weighing Factors : A x B x C x D x E

    : 1.0 x 1.0 x 0.8 x 1.0 x 0.3

    : 0.24

    Collection Area AC : (L x W) + 2(L x H) + 2(W x H) + 2

    : (4x16)+(3.5X6)+(5.25x7.5)+(5.25x13)+ (6X5.25)

    +(7X5.25)+2X(11.5X3.5)+(11.5X4)+5/4 (11.5)2

    : 552.32 m2

    Probable no.of strikes for the : AC x Ng x 10-6

    structure per year P : 552.32 x 3.284 x 10-6

    : 1.81 x 10-3

    Therefore, the overall risk Factor : P x Overall Weighing Factor

    : 1.81 x 10-3 x 0.24

    : 4.3526 x 10-4 which is greater than 10-5

    Therefore Lightning Protection is essential for Cement Mill Control room .

  • 7/29/2019 Lightning Calculations

    14/48

    LIGHTNING CALCULATION

    CLIENT : ACC LIMITED REV/DATE :

    0/24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD: LB/MK

    TITLE : LIGHTINING CALCULATION SHEET : Page 14

    of 48

    PACKING PLANT:

    Length (L) : 36.9 M

    Width ( W) : 27 M

    Height (H) : 24.75 M

    Lightning Flashes/Sq.Km / year(Ng) : 3.284- Rating factor for Wadi

    Weighing Factors

    A : 1.0

    B : 1.0

    C : 0.8

    D : 1.0

    E : 0.3

    Overall weighing Factors : A x B x C x D x E

    : 1.0 x 1.0 x 0.8 x 1.0 x 0.3

    : 0.24

    Collection Area AC : (L x W) + 2(L x H) + 2(W x H) + 2

    :

    (23.4x27)+(13.5X15.5)+(24.75x27)+(24.75x11.5)+

    (8.5X13.5)+(8.5X15.5)+(36.9X8.5)+

    (15.5X8.5)+5/4 (24.75)2

    : 4890.132 m2

    Probable no.of strikes for the : AC x Ng x 10-6

    structure per year P : 4890.132 x 3.284 x 10-6

    : 1.6 x 10-2

    Therefore, the overall risk Factor : P x Overall Weighing Factor

    : 1.6 x 10-2 x 0.24

    : 3.85 x 10-3 which is greater than 10-5

    Therefore Lightning Protection is essential for Cement Packing plant.

  • 7/29/2019 Lightning Calculations

    15/48

    LIGHTNING CALCULATION

    CLIENT : ACC LIMITED REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/MK

    TITLE : LIGHTINING CALCULATION SHEET : Page 15 of 48

    CEMENT SILO EXPANSION AND PACKING PLANT:

    CEMENT SILO:

    Diameter(D) : 12 M

    Height (H) : 34.5+2.5=37 M

    Lightning Flashes/Sq.Km / year(Ng) : 3.284- Rating factor for Wadi

    Weighing Factors

    A : 1.0

    B : 0.8

    C : 0.8

    D : 1.0

    E : 0.3

    Overall weighing Factors : A x B x C x D x E

    : 1.0 x 0.8 x 0.8 x 1.0 x 0.3

    : 0.192

    Collection Area AC : H2

    : (37)2

    : 4298.66 m2

    Probable no.of strikes for the : Ac x Ng x 10-6

    structure per year P : 4298.66 x 3.284 x 10-6

    : 1.41 x 10-2

    Therefore, the overall risk Factor : P x Overall Weighing Factor

    : 1.41 x 10-2

    x 0.192

    : 2.71 x 10-3

    which is greater than 10-5

    Therefore for Cement Silo Lightning Protection is essential.

  • 7/29/2019 Lightning Calculations

    16/48

    LIGHTNING CALCULATION

    CLIENT : ACC LIMITED REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/MK

    TITLE : LIGHTINING CALCULATION SHEET : Page 16 of 48

    PACKING PLANT:

    Length (L) : 14 M

    Width ( W) : 16 M

    Height (H) : 30 M

    Lightning Flashes/Sq.Km / year(Ng) : 3.284- Rating factor for Wadi

    Weighing Factors

    A : 1.0

    B : 1.0

    C : 0.8

    D : 1.0

    E : 0.3

    Overall weighing Factors : A x B x C x D x E

    : 1.0 x 1.0 x 0.8 x 1.0 x 0.3

    : 0.24

    Collection Area AC : (L x W) + 2(L x H) + 2(W x H) + 2

    : (14x16)+2(14X30)+2(16x30)+ (30)2

    : 2024 m2

    Probable no.of strikes for the : AC x Ng x 10-6

    structure per year P : 2024 x 3.284 x 10-6

    : 6.646 x 10-3

    Therefore, the overall risk Factor : P x Overall Weighing Factor

    : 6.646x 10-3 x 0.24

    : 1.59 x 10-3 which is greater than 10-5

    Therefore Lightning Protection is essential for Cement Packing plant.

  • 7/29/2019 Lightning Calculations

    17/48

    LIGHTNING CALCULATION

    CLIENT : ACC -WADI REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTNING CALCULATION SHEET : Page 17 of 48

    KILN NO. 1 & 2 PREHEATER:

    Length (L) : 11 M

    Width ( W) : 24 M

    Height (H) : 69.36 M

    Lightning Flashes/Sq.Km / year(Ng) : 3.284- Rating factor for Wadi

    Weighing Factors

    A : 1.0

    B : 0.8

    C : 0.8

    D : 1.0

    E : 0.3

    Overall weighing Factors : A x B x C x D x E

    : 1.0 x 0.8 x 0.8 x 1.0 x 0.3

    : 0.192

    Collection Area AC : (L x W) + 2(L x H) + 2(W x H) + 2

    : (11x24)+2(11x69.36)+2(24x69.36)+ (69.36)2

    : 20225.142 m2

    Probable no.of strikes for the : AC x Ng x 10-6

    structure per year P : 20225.142 x 3.284 x 10-6

    : 6.64 x 10-2

    Therefore, the overall risk Factor : P x Overall Weighing Factor

    : 6.64 x 10-2 x 0.192

    : 1.27 x 10-2 which is greater than 10-5

    Therefore Lightning Protection is essential for Kiln No.1 & 2 Preheater.

  • 7/29/2019 Lightning Calculations

    18/48

    LIGHTNING CALCULATION

    CLIENT : ACC -WADI REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTNING CALCULATION SHEET : Page 18 of 48

    RAW MILL 4& 5:

    Length (L) : 60.1 M

    Width ( W) : 36 M

    Height (H) : 31.35 M

    Lightning Flashes/Sq.Km / year(Ng) : 3.284- Rating factor for Wadi

    Weighing Factors

    A : 1.0

    B : 1.0

    C : 0.8

    D : 1.0

    E : 0.3

    Overall weighing Factors : A x B x C x D x E

    : 1.0 x 1.0 x 0.8 x 1.0 x 0.3

    : 0.24

    Collection Area AC : (L x W) + 2(L x H) + 2(W x H) + 2

    : (60.1x36)+2(60.1x31.35)+2(36x31.35)+ (31.35)2

    : 11275.132 m2

    Probable no.of strikes for the : AC x Ng x 10-6

    structure per year P : 11275.132 x 3.284 x 10-6

    : 3.7 x 10-2

    Therefore, the overall risk Factor : P x Overall Weighing Factor

    : 3.7 x 10-2 x 0.192

    : 7.1 x 10-3 which is greater than 10-5

    Therefore Lightning Protection is essential for Raw mill 4 & 5.

  • 7/29/2019 Lightning Calculations

    19/48

  • 7/29/2019 Lightning Calculations

    20/48

    LIGHTNING CALCULATION

    CLIENT : ACC -WADI REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTNING CALCULATION SHEET : Page 20 of 48

    POWER PLANT AREA :

    DG SET BUILDING:

    Length (L) : 52 M

    Width ( W) : 20 M

    Height (H) : 15 M

    Lightning Flashes/Sq.Km / year(Ng) : 3.284

    - Rating factor for Wadi

    Weighing Factors

    A : 1.0

    B : 0.4

    C : 1.0

    D : 1.0

    E : 0.3

    Overall weighing Factors : A x B x C x D x E

    : 1.0 x 0.4 x 1.0 x 1.0 x 0.3

    : 0.12

    Collection Area AC : (L x W) + 2(L x H) + 2(W x H) +

    2

    : (52x20)+2(20x15)+ (15)2

    : 2346.5 m2

    Probable no.of strikes for the : AC x Ng x 10-6

    structure per year P : 2346.5 x 3.284 x 10-6

    : 7.705 x 10-3

    Therefore, the overall risk Factor : P x Overall Weighing Factor

    : 7.705 x 10

    -3

    x 0.12: 9.247 x 10-4 which is greater than 10-

    5

    Therefore Lightning Protection is essential for DG Set Building .

  • 7/29/2019 Lightning Calculations

    21/48

    LIGHTNING CALCULATION

    CLIENT : ACC -WADI REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTNING CALCULATION SHEET : Page 21 of 48

    3 NOS. OF 1 X 25 MW TG BUILDING :

    Length (L) : 52.5 M

    Width ( W) : 26.7 M

    Height (H) : 23.56 M

    Lightning Flashes/Sq.Km / year(Ng) : 3.284

    - Rating factor for Wadi

    Weighing Factors

    A : 1.0

    B : 0.4

    C : 1.0

    D : 1.0

    E : 0.3

    Overall weighing Factors : A x B x C x D x E

    : 1.0 x 0.4 x 1.0 x 1.0 x 0.3

    : 0.12

    Collection Area AC : (L x W) + 2(L x H) + 2(W x H) + 2

    : (8x52.5)+(18.7x37.5)+(14.5x12.2)+2(8x14.86)

    +(52.5x14.86)+2(18.7x23.56)+2(14.5x15.26)+ (23.56)

    2

    : 5382.67 m2

    There are 3 Nos of 1x25 MW Generator

    Areas. Therefore Total collection area is : 3x5382.67 m2

    : 16146 m2

    Probable no.of strikes for the : AC x Ng x 10-6

    structure per year P : 16146 x 3.284 x 10-6

    : 5.3 x 10-2

    Therefore, the overall risk Factor : P x Overall Weighing Factor

    : 5.3 x 10-2 x 0.12

    : 6.36 x 10-3 which is greater than 10-5

    Therefore Lightning Protection is essential for TG Building .

  • 7/29/2019 Lightning Calculations

    22/48

    LIGHTNING CALCULATION

    CLIENT : ACC -WADI REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTNING CALCULATION SHEET : Page 22 of 48

    CHIMNEY -1

    Diameter(D) :4 M

    Height (H) : 113 M

    Lightning Flashes/Sq.Km / year(Ng) : 3.284-Rating factor for Wadi

    Weighing Factors

    A : 1.0

    B : 0.4

    C : 1.0

    D : 2.0

    E : 0.3

    Overall weighing Factors : A x B x C x D x E

    : 1.0 x 0.4x 1.0 x 2.0 x 0.3

    : 0.24

    Collection Area AC : H2

    : (113)2

    : 40094.66 m2

    Probable no.of strikes for the : Ac x Ng x 10-6

    structure per year P : 40094.66 x 3.284 x 10-6

    : 13.16x 10-2

    Therefore, the overall risk Factor : P x Overall Weighing Factor

    : 13.16 x 10-2 x 0.24

    : 3.16 x 10-2 which is greater than 10-5

    Therefore for Chimney Lightning Protection is essential.

  • 7/29/2019 Lightning Calculations

    23/48

  • 7/29/2019 Lightning Calculations

    24/48

  • 7/29/2019 Lightning Calculations

    25/48

    LIGHTNING CALCULATION

    CLIENT : ACC -WADI REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTNING CALCULATION SHEET : Page 25 of 48

    WATER TANK (227000 LITRES) 2 Nos:

    Diameter(D) :9.4 M

    Height (H) : 24.55 M

    Lightning Flashes/Sq.Km / year(Ng) : 3.284-Rating factor for Wadi

    Weighing Factors

    A : 0.7

    B : 0.4

    C : 0.8

    D : 1.0

    E : 0.3

    Overall weighing Factors : A x B x C x D x E

    : 0.7 x 0.4x 0.3x 1.0 x 0.3

    : 0.0252

    Collection Area AC : H2

    : (24.55)2

    : 1892.485 m2

    Probable no.of strikes for the : Ac x Ng x 10-6

    structure per year P : 1892.485 x 3.284 x 10-6

    : 6.21x 10-3

    Therefore, the overall risk Factor : P x Overall Weighing Factor

    : 6.21 x 10-3 x 0.0252

    : 1.568 x 10-4 which is greater than 10-5

    Therefore for Water tank Lightning Protection is essential.

  • 7/29/2019 Lightning Calculations

    26/48

    LIGHTNING CALCULATION

    CLIENT : ACC -WADI REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTNING CALCULATION SHEET : Page 26 of 48

    KAGINA GUEST HOUSE:

    Length (L) : 40 M

    Width ( W) : 15 M

    Height (H) : 10 M

    Lightning Flashes/Sq.Km / year(Ng) : 3.284- Rating factor for Wadi

    Weighing Factors

    A : 1.2

    B : 0.4

    C : 1.7

    D : 0.4

    E : 0.3

    Overall weighing Factors : A x B x C x D x E

    : 1.2 x 0.4 x 1.7 x 0.4 x 0.3

    : 0.0979

    Collection Area AC : (L x W) + 2(L x H) + 2(W x H) + 2

    : (40x15)+2(40x10)+2(15x10) + (10)2

    : 2014 m2

    Probable no.of strikes for the : AC x Ng x 10-6

    structure per year P : 2014 x 3.284 x 10-6

    : 6.613 x 10-3

    Therefore, the overall risk Factor : P x Overall Weighing Factor

    : 6.613 x 10-3 x 0.0979

    : 6.47 x 10-4 which is greater than 10-5

    Therefore Lightning Protection is essential for Kagina Guest House .

  • 7/29/2019 Lightning Calculations

    27/48

    LIGHTNING CALCULATION

    CLIENT : ACC -WADI REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTNING CALCULATION SHEET : Page 27 of 48

    MANAGEMENT TRAINEE HOSTEL:

    Length (L) : 17 M

    Width ( W) : M

    Height (H) : 10 M

    Lightning Flashes/Sq.Km / year(Ng) : 3.284- Rating factor for Wadi

    Weighing Factors

    A : 1.2

    B : 0.4

    C : 1.7

    D : 0.4

    E : 0.3

    Overall weighing Factors : A x B x C x D x E

    : 1.2 x 0.4 x 1.7 x 0.4 x 0.3

    : 0.0979

    Collection Area AC : (L x W) + 2(L x H) + 2(W x H) + 2

    : (40x15)+2(40x10)+2(15x10) + (10)2

    : 2014 m2

    Probable no.of strikes for the : AC x Ng x 10-6

    structure per year P : 2014 x 3.284 x 10-6

    : 6.613 x 10-3

    Therefore, the overall risk Factor : P x Overall Weighing Factor

    : 6.613 x 10-3 x 0.0979

    : 6.47 x 10-4 which is greater than 10-5

    Therefore Lightning Protection is essential for Management Trainee hostel .

  • 7/29/2019 Lightning Calculations

    28/48

    LIGHTNING CALCULATION

    CLIENT : ACC -WADI REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTNING CALCULATION SHEET : Page 28 of 48

    V. P BUNGALOW:

    Length (L) : 22.76 M

    Width ( W) : 15.25M

    Height (H) : 6.80 M

    Lightning Flashes/Sq.Km / year(Ng) : 3.284- Rating factor for Wadi

    Weighing Factors

    A : 1.2

    B : 0.4

    C : 1.7

    D : 0.4

    E : 0.3

    Overall weighing Factors : A x B x C x D x E

    : 1.2 x 0.4 x 1.7 x 0.4 x 0.3

    : 0.0979

    Collection Area AC : (L x W) + 2(L x H) + 2(W x H) + 2

    : (10x22.76)+(5.58x14.11)+(10x4.1)+2(8.65X4.1)

    +(5.58X6.8)+2(14.11X6.8)+(15.25X6.8)+ (6.8)2

    : 861.53 m2

    Probable no.of strikes for the : AC x Ng x 10-6

    structure per year P : 861.53 x 3.284 x 10-6

    : 2.829 x 10-3

    Therefore, the overall risk Factor : P x Overall Weighing Factor

    : 2.829 x 10-3 x 0.0979

    : 2.76 x 10-4

    which is greater than 10-5

    Therefore Lightning Protection is essential for Vice president Bungalow .

  • 7/29/2019 Lightning Calculations

    29/48

  • 7/29/2019 Lightning Calculations

    30/48

    LIGHTNING CALCULATION

    CLIENT : ACC -WADI REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTNING CALCULATION SHEET : Page 30 of 48

    QUARY CRUSHER:

    Length (L) : 24 M

    Width ( W) : 12M

    Height (H) : 15 M

    Lightning Flashes/Sq.Km / year(Ng) : 3.284- Rating factor for Wadi

    Weighing Factors

    A : 1.0

    B : 0.8

    C : 0.8

    D : 1.0

    E : 0.3

    Overall weighing Factors : A x B x C x D x E

    : 1.0 x 0.8 x 0.8 x 1.0 x 0.3

    : 0.192

    Collection Area AC : (L x W) + 2(L x H) + 2(W x H) + 2

    : (24x12)+2(24x15)+2(12x15)+ (15)2

    : 2074.9 m2

    Probable no.of strikes for the : AC x Ng x 10-6

    structure per year P : 2074.9 x 3.284 x 10-6

    : 0.6812 x 10-2

    Therefore, the overall risk Factor : P x Overall Weighing Factor

    : 0.6812 x 10-2 x 0.192

    : 1.3 x 10-4 which is greater than 10-5

    Therefore Lightning Protection is essential for Quary crusher .

  • 7/29/2019 Lightning Calculations

    31/48

  • 7/29/2019 Lightning Calculations

    32/48

    LIGHTNING CALCULATION

    CLIENT : ACC -WADI REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTNING CALCULATION SHEET : Page 32 of 48

    5.0Resistance of Pipe Electrode (Ref. 9.2.2 of IS: 3043-1987)

    Re = 100 x loge 4 x l

    2 x x l d

    Where l = length of the rod or pipe = 300 cm.

    d = diameter of the rod or pipe = 3.8 cm.

    = resistivity of soil = 312 -m assumed uniform.

    Re = 100 x 312 loge 4 x 300

    2 x x 300 3.8

    = 16.55 loge 315.789

    = 41.36 .

    Resistance of the Earth Strip 50 x 6 G.I Flat

    Old Wadi plant

    5.1.1 Bulk loading silo

    Rs = 100 Log e 2L2

    2 L wt

    L=Estimated Length Strip : 12500 cm

    Width of the Strip (t) : 50 x 6 mm

    Depth of the Buried Strip (W) : 60 cm

    Rs = 100 x 312 Loge 2 x 125002 = 2.38

    2x3.14x12500 60x5

    There are 3 Nos of earth pits are used, therefore

    Re = Re/3 = 41.36 / 3 = 13.78

    Rt = Re xRs = 13.78 X 2.38 = 2.03

    Re +Rs 13.78+2.38

    Thus the Total resistance is less than 3 ohms .

    50x6 G.I Flat strip is selected for vertical down conductor and horizondal earthconductor.

  • 7/29/2019 Lightning Calculations

    33/48

    LIGHTNING CALCULATION

    CLIENT : ACC -WADI REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTNING CALCULATION SHEET : Page 33 of 48

    5.1.2 Cement storage silo

    Rs = 100 Loge

    2L2

    2 L wt

    L=Estimated Length Strip : 14640 cm

    Width of the Buried Strip (t) : 50 x 6 mm

    Depth of the Buried Strip (W) : 60 cm

    Rs = 100 x 312 Loge 2 x 146402 = 2.0

    2x3.14x14640 60x5

    There are 2 Nos of earth pits are used, therefore

    Re = Re/2 = 41.36 / 2 = 20.68

    Rt = Re xRs = 20.68 X 2 = 1.8

    Re +Rs 20.68+2.

    Thus the Total resistance is less than 3 ohms .

    50x6 G.I Flat strip is selected for vertical down conductor and horizondal earth

    conductor.

    5.1.3 Kiln No:3 Preheater

    Rs = 100 Log e 2L2

    2 L wt

    L=Estimated Length Strip : 30160 cm

    Width of the Buried Strip (t) : 50 x 6 mm

    Depth of the Buried Strip (W) : 60 cm

    Rs = 100 x 312 Loge 2 x 301602 = 1.1172

    2x3.14x30160 60x5

    There are 2 Nos of earth pits are used, therefore

    Re = Re/2 = 41.36 / 2 = 20.68

  • 7/29/2019 Lightning Calculations

    34/48

    LIGHTNING CALCULATION

    CLIENT : ACC -WADI REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTNING CALCULATION SHEET : Page 34 of 48

    Rt = Re xRs = 20.68 X 1.1172 = 1.054

    Re +Rs 20.68+1.1172.

    Thus the Total resistance is less than 3 ohms .

    50x6 G.I Flat strip is selected for vertical down conductor and horizondal earth

    conductor.

    5.1.4 Cement Mill Building

    Rs = 100 Log e 2L2

    2 L wt

    L=Estimated Length Strip : 20405.6 cm

    Width of the Buried Strip (t) : 50 x 6 mm

    Depth of the Buried Strip (W) : 60 cm

    Rs = 100 x 312 Loge 2 x 20405.62 = 1.568

    2x3.14x20405.6 60x5

    There are 2 Nos of earth pits are used, therefore

    Re = Re/2 = 41.36 / 2 = 20.68

    Rt = Re xRs = 20.68 X 1.568 = 1.4469

    Re +Rs 20.68+1.568.

    Thus the Total resistance is less than 3 ohms .

    50x6 G.I Flat strip is selected for vertical down conductor and horizondal earthconductor.

  • 7/29/2019 Lightning Calculations

    35/48

    LIGHTNING CALCULATION

    CLIENT : ACC -WADI REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTNING CALCULATION SHEET : Page 35 of 48

    5.1.5 Cement Mill Building 4 & 5

    Rs = 100 Log e 2L2

    2 L wt

    L=Estimated Length Strip : 20405.6 cm

    Width of the Buried Strip (t) : 50 x 6 mm

    Depth of the Buried Strip (W) : 60 cm

    Rs = 100 x 312 Loge 2 x 20405.62 = 1.568

    2x3.14x20405.6 60x5

    There are 2 Nos of earth pits are used, therefore

    Re = Re/2 = 41.36 / 2 = 20.68

    Rt = Re xRs = 20.68X 1.568 = 1.4469

    Re +Rs 20.68+1.568.

    Thus the Total resistance is less than 3 ohms .

    50x6 G.I Flat strip is selected for vertical down conductor and horizondal earth

    conductor.

    5.1.6 Cement Mill Control Room

    Rs = 100 Log e 2L2

    2 L wt

    L=Estimated Length Strip : 10394.8 cm

    Width of the Buried Strip (t) : 50 x 6 mm

    Depth of the Buried Strip (W) : 60 cm

    Rs = 100 x 312 Loge 2 x 10394.82 = 2.799

    2x3.14x10394.8 60x5

    Only one earth pit is used, therefore

    Re = Re/1 = 41.36 / 1 = 41.36

  • 7/29/2019 Lightning Calculations

    36/48

    LIGHTNING CALCULATION

    CLIENT : ACC -WADI REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTNING CALCULATION SHEET : Page 36 of 48

    Rt = Re xRs = 41.36 X 2.799 = 2.6

    Re +Rs 41.36+2.799.

    Thus the Total resistance is less than 3 ohms .

    50x6 G.I Flat strip is selected for vertical down conductor and horizondal earth

    conductor.

    5.1.7 Packing Plant

    Rs = 100 Log e 2L2

    2 L wt

    L=Estimated Length Strip : 17730 cm

    Width of the Buried Strip (t) : 50 x 6 mm

    Depth of the Buried Strip (W) : 60 cm

    Rs = 100 x 312 Loge 2 x 177302 = 1.77

    2x3.14x17730 60x5

    There are 2 Nos of earth pits are used, therefore

    Re = Re/2 = 41.36 / 2 = 20.68

    Rt = Re xRs = 20.68 X 1.77 = 1.68

    Re +Rs 20.68+1.77.

    Thus the Total resistance is less than 3 ohms .

    50x6 G.I Flat strip is selected for vertical down conductor and horizondal earthconductor.

    5.1.8 Cement silo Expansion

    Rs = 100 Log e 2L2

    2 L wt

    L=Estimated Length Strip : 32033 cm

    Width of the Buried Strip (t) : 50 x 6 mm

    Depth of the Buried Strip (W) : 60 cm

  • 7/29/2019 Lightning Calculations

    37/48

    LIGHTNING CALCULATION

    CLIENT : ACC -WADI REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTNING CALCULATION SHEET : Page 37 of 48

    Rs = 100 x 312 Loge 2 x 320332 = 1.07

    2x3.14x32033 60x5

    There are 2 Nos of earth pits are used, therefore

    Re = Re/2 = 41.36 / 2 = 20.68

    Rt = Re xRs = 20.68 X 1.07 = 1.0

    Re +Rs 20.68+1.07.

    Thus the Total resistance is less than 3 ohms .

    50x6 G.I Flat strip is selected for vertical down conductor and horizondal earthconductor.

    5.1.9 Kiln No:1& 2 Preheater

    Rs = 100 Log e 2L2

    2 L wt

    L=Estimated Length Strip : 25672 cm

    Width of the Buried Strip (t) : 50 x 6 mm

    Depth of the Buried Strip (W) : 60 cm

    Rs = 100 x 312 Loge 2 x 256722 = 1.285

    2x3.14x25672 60x5

    Only one earth pit is used, therefore

    Re = Re/1 = 41.36 / 1 = 41.36

    Rt = Re xRs = 41.36X1.285 = 1.240

    Re +Rs 41.36+1.285.

    Thus the Total resistance is less than 3 ohms .

    50x6 G.I Flat strip is selected for vertical down conductor and horizondal earthconductor.

  • 7/29/2019 Lightning Calculations

    38/48

    LIGHTNING CALCULATION

    CLIENT : ACC -WADI REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTNING CALCULATION SHEET : Page 38 of 48

    5.1.10 Raw Mill 4 & 5

    Rs = 100 Log e 2L2

    2 L wt

    L=Estimated Length Strip : 56730cm

    Width of the Buried Strip (t) : 50 x 6 mm

    Depth of the Buried Strip (W) : 60 cm

    Rs = 100 x 312 Loge 2 x 567302 = 0.64

    2x3.14x56730 60x5

    There are 2 Nos of earth pits are used, therefore

    Re = Re/2 = 41.36 / 2= 20.68

    Rt = Re xRs = 20.68X0.64 = 0.62

    Re +Rs 20.68+0.64.

    Thus the Total resistance is less than 3 ohms .

    50x6 G.I Flat strip is selected for vertical down conductor and horizondal earth

    conductor.

    5.1.11 Coal Mill

    Rs = 100 Log e 2L2

    2 L wt

    L=Estimated Length Strip : 52000cm

    Width of the Buried Strip (t) : 50 x 6 mm

    Depth of the Buried Strip (W) : 60 cm

    Rs = 100 x 312 Loge 2 x 520002 = 0.64

    2x3.14x52000 60x5

    There are 2 Nos of earth pits are used, therefore

    Re = Re/2 = 41.36 / 2= 20.68

  • 7/29/2019 Lightning Calculations

    39/48

    LIGHTNING CALCULATION

    CLIENT : ACC -WADI REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTNING CALCULATION SHEET : Page 39 of 48

    Rt = Re xRs = 20.68X0.64 = 0.62

    Re +Rs 20.68+0.64.

    Thus the Total resistance is less than 3 ohms .

    50x6 G.I Flat strip is selected for vertical down conductor and horizondal earth

    conductor.

    5.1 Power plant

    5.2.1 DG Set

    Rs = 100 Log e 2L2

    2 L wt

    L=Estimated Length Strip : 63800cm

    Width of the Buried Strip (t) : 50 x 6 mm

    Depth of the Buried Strip (W) : 60 cm

    Rs = 100 x 312 Loge 2 x 638002 = 0.578

    2x3.14x63800 60x5

    There are 3 Nos of earth pits are used, therefore

    Re = Re/3 = 41.36 / 3= 13.78

    Rt = Re xRs = 13.78X0.578 = 0.55

    Re +Rs 13.78+0.578

    Thus the Total resistance is less than 3 ohms .

    50x6 G.I Flat strip is selected for vertical down conductor and horizondal earth

    conductor.

    5.2.2 T.GCPP Building

    Rs = 100 Log e 2L2

    2 L wt

  • 7/29/2019 Lightning Calculations

    40/48

    LIGHTNING CALCULATION

    CLIENT : ACC -WADI REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTNING CALCULATION SHEET : Page 40 of 48

    L=Estimated Length Strip : 81802.2cm

    Width of the Buried Strip (t) : 50 x 6 mm

    Depth of the Buried Strip (W) : 60 cm

    Rs = 100 x 312 Loge 2 x 81802.22 = 0.588

    2x3.14x81802.2 60x5

    There are 3 Nos of earth pits are used, therefore

    Re = Re/4 = 41.36 / 4= 10.34

    Rt = Re xRs = 10.34X0.588 = 0.5532

    Re +Rs 10.34+0.588

    Thus the Total resistance is less than 3 ohms .

    50x6 G.I Flat strip is selected for vertical down conductor and horizondal earth

    conductor.

    5.2.3 Chimney-1

    Rs = 100 Log e 2L2

    2 L wt

    L=Estimated Length Strip : 23659cm

    Width of the Buried Strip (t) : 50 x 6 mm

    Depth of the Buried Strip (W) : 60 cm

    Rs = 100 x 312 Loge 2 x 236592 = 1.379

    2x3.14x23659 60x5

    There are 2 Nos of earth pits are used, therefore

    Re = Re/2 = 41.36 / 2= 20.68

  • 7/29/2019 Lightning Calculations

    41/48

  • 7/29/2019 Lightning Calculations

    42/48

  • 7/29/2019 Lightning Calculations

    43/48

    LIGHTNING CALCULATION

    CLIENT : ACC -WADI REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTNING CALCULATION SHEET : Page 43 of 48

    Rs = 100 x 312 Loge 2 x 13329.22 = 2.26

    2x3.14x13329.2 60x5

    There are 2 Nos of earth pits are used, therefore

    Re = Re/2 = 41.36 / 2= 20.68

    Rt = Re xRs = 20.36X2.26 = 2.0

    Re +Rs 20.36+2.26.

    Thus the Total resistance is less than 3 ohms .

    50x6 G.I Flat strip is selected for vertical down conductor and horizondal earth

    conductor.

    Kagina Guest house

    Rs = 100 Log e 2L2

    2 L wt

    L=Estimated Length Strip : 22100cm

    Width of the Buried Strip (t) : 50 x 6 mm

    Depth of the Buried Strip (W) : 60 cm

    Rs = 100 x 312 Loge 2 x 221002 = 1.46

    2x3.14x22100 60x5

    There are 2 Nos of earth pits are used, therefore

    Re = Re/2 = 41.36 / 2= 20.68

    Rt = Re xRs = 20.36X1.46 = 1.35

    Re +Rs 20.36+1.46.

  • 7/29/2019 Lightning Calculations

    44/48

    LIGHTNING CALCULATION

    CLIENT : ACC -WADI REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTNING CALCULATION SHEET : Page 44 of 48

    Thus the Total resistance is less than 3 ohms .

    50x6 G.I Flat strip is selected for vertical down conductor and horizondal earthconductor.

    V.P Bungalow

    Rs = 100 Log e 2L2

    2 L wt

    L=Estimated Length Strip : 14194m

    Width of the Buried Strip (t) : 50 x 6 mm

    Depth of the Buried Strip (W) : 60 cm

    Rs = 100 x 312 Loge 2 x 141942 = 2.14

    2x3.14x14194 60x5

    There are 2 Nos of earth pits are used, therefore

    Re = Re/2 = 41.36 / 2= 20.68

    Rt = Re xRs = 20.36X2.14 = 1.925

    Re +Rs 20.36+2.14.

    Thus the Total resistance is less than 3 ohms .

    50x6 G.I Flat strip is selected for vertical down conductor and horizondal earthconductor.

  • 7/29/2019 Lightning Calculations

    45/48

  • 7/29/2019 Lightning Calculations

    46/48

    LIGHTNING CALCULATION

    CLIENT : ACC -WADI REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTNING CALCULATION SHEET : Page 46 of 48

    6.0 RESULTS

    a) 38 mm ID,3 M long pipe suggested for earth pit refer drg. No. E-ECB-A565-LTNG-001(Sheet 2 of 4).

    b) 50 x 6 G.I flat strip suggested for down conductors and burried conductor.

    c) The No.of Lightning conductors and earth pits required are as shown in thedrawing.

    d) The Lightning conductor shall be placed at the topmost height of everyBuilding.

    e) The Location of Earthpits shall be fixed as per the site conditions.f) The Earthing Resistance shall be maintained below 3 ohms.

    g) The down conductors shall be insulated from the metal structures inorderto reduce the leakage current.

    h) All the down conductors shall have a test Link arrangement between thearrestor and Earthpit.

    Old Wadi plant Area:

    Location of theLightning

    Conductor

    No.ofLightnin

    gConduct

    or.

    No.ofEarth Pits

    Remarks

    KilnNo-1&2

    Preheater

    2 2

    Bulk loading cement

    silo

    2 3 One Arrestor at

    each silo.

    Packing plant 1 2 Shall be placedat the topmost

    structure.

    Cement storage silo 2 2 Arrestor Shall beplaced at the

    topmoststructure.

    Cement mill building

    4&5

    2 2 Arrestor Shall be

    placed at

    topmoststructure.

    Raw mill 4&5 2 2 Arrestor Shall beplaced at the

    topmoststructure.

    Coal mill 2 2 Arrestor Shall be

    placed at thetopmost

  • 7/29/2019 Lightning Calculations

    47/48

  • 7/29/2019 Lightning Calculations

    48/48

    LIGHTNING CALCULATION

    CLIENT : ACC -WADI REV/DATE : 0 /24.06.05

    PROJECT : LIGHTNING ARRESTOR REQUIREMENT CALCULATION PRE/CHKD : LB/ MK

    TITLE : LIGHTNING CALCULATION SHEET : Page 48 of 48

    Power plant Area

    Note: The Horizotal Air terminations to be Placed as marked in the drawing forD.G set building & T.G building.

    As the Chimneys are provided with the 2 nos of 25x3 GI Flat as downconductor, the same shall be retained as it is and the required earth value

    of less than 3 ohms should be confirmed.

    Description No.of

    Arrestor

    No.of Earth

    Pit

    Remarks

    D.G Set 2 3 Two Arrestor is

    existing. No needto provide.

    T.G CPP building 10 4 7 Arrestor is

    already existingremaining 3

    should be placedas per drawing.

    Chimney 2Nos 2 4 One Arrestor is

    existing in each

    chimney. No needto provde.

    River pump Area

    a) There are three Tank in this area ,in each Tank one Arrester shall be

    placed.

    c) In quary crusher area one Arrestor and Two nos. of earth pits shall be placed as

    marked in the drawing.


Recommended