LINK BOARD PROJECT UPGRADE. Pigi Paolucci and Napoli group. Outline. LB CAD project LVDS suppressor studies LV regulator studies Open questions To be done. LV Regulator LHC4913. LB project schema. Test schema LHC4913. Temperature Tests. Vin = 5V Vout = 3.3V - PowerPoint PPT Presentation
Popular Tags:
20
LINK BOARD PROJECT UPGRADE Pigi Paolucci and Napoli group
Transcript
Page 1: LINK BOARD PROJECT UPGRADE

LINK BOARD PROJECT UPGRADE

Pigi Paolucci and Napoli group

Page 2: LINK BOARD PROJECT UPGRADE

Outline

LB CAD project LVDS suppressor studies LV regulator studies Open questions To be done

Link Board Upgrade Meeting - Dec 20102 Pigi Paolucci

Page 3: LINK BOARD PROJECT UPGRADE

LV Regulator LHC4913

Link Board Upgrade Meeting - Dec 2010Pigi Paolucci3

Page 4: LINK BOARD PROJECT UPGRADE

LB project schema

Link Board Upgrade Meeting - Dec 2010Pigi Paolucci4

Page 5: LINK BOARD PROJECT UPGRADE

Test schema LHC4913

Link Board Upgrade Meeting - Dec 2010Pigi Paolucci5

Page 6: LINK BOARD PROJECT UPGRADE

Vin = 5VVout = 3.3VIout = 1.4A (Load=2.3//2200uF); Ta = 27°C; Td = 91°C

Link Board Upgrade Meeting - Dec 20106 Pigi Paolucci

Temperature Tests

1 volt1 msec

2 msec

Vin

Vout

Page 7: LINK BOARD PROJECT UPGRADE

Link Board Upgrade Meeting - Dec 20107 Pigi Paolucci

Rumping up and down

Vin

Vout

Vin

Vout

Page 8: LINK BOARD PROJECT UPGRADE

Vin=5V; Vout=3.3V

Iout=2.6A (Load=1.2//2200uF); Ta=27°C; Td=135°C

Link Board Upgrade Meeting - Dec 20108 Pigi Paolucci

Temperature Tests

1 volt1 msec Vin

Vout

Page 9: LINK BOARD PROJECT UPGRADE

Link Board Upgrade Meeting - Dec 20109 Pigi Paolucci

Rumping up and down

Vin

Vout

Vin

Vout

Page 10: LINK BOARD PROJECT UPGRADE

Vin=5V; Vout=3.3V

Iout1=1.4A (Load=2.3//2200uF)

Iout2=2.6A (Load=1.2//2200uF)

Link Board Upgrade Meeting - Dec 201010 Pigi Paolucci

Different Loads

Vin

Vout

Page 11: LINK BOARD PROJECT UPGRADE

Vin=5V; Vout=3.3V

Iout1=1.4A (Load=2.3//2200uF)

Spike=5V / Vin=10V Spike su Vout > 10mV

Link Board Upgrade Meeting - Dec 201011 Pigi Paolucci

Vin

Vout

How does react to input spikes

Page 12: LINK BOARD PROJECT UPGRADE

Tmax (junction) = 125°C; Rcase (junction) = 2°C/W (datasheet)

Working caseVin = 5V; Vout = 3.3V; Iout = 1.5A Power to dissipate = (5V - 3.3V) * 1.5A = 2.55W; Tamb=25°C Rtot = /W = (125°C – 25°C)/2.55W = 39°C/W

Rheatsink = Rtot-Rjc = 37°C/W

Worst caseVin=6V; Vout=3V; Iout=3A Power to dissipate= (6V – 3V) * 3A = 9W; Tamb = 40°C Rtot = /W = (100°C - 40°C)/9W = 6.6°C/W

Rheatsink = Rtot-Rjc = 4.6°C/W

Link Board Upgrade Meeting - Dec 201012 Pigi Paolucci

Heat Dissipation

Page 13: LINK BOARD PROJECT UPGRADE

Test Conditions Vin=6V; Vout=3.3V; Iout=2.6A; Tamb=25°C

Temperature on the case: 155°C -:- 135°C

Link Board Upgrade Meeting - Dec 201013 Pigi Paolucci

Max temperature behaviour

Page 14: LINK BOARD PROJECT UPGRADE

Regulator Infrared scan

Link Board Upgrade Meeting - Dec 2010Pigi Paolucci14

Standard condition Worst case – before shutdown

Worst case – after shutdown

Page 15: LINK BOARD PROJECT UPGRADE

Costs

Link Board Upgrade Meeting - Dec 2010Pigi Paolucci15

needed spare PCB + mount + test components cost Total

Crates 12 2   €100,0 €100,0 €1.400,0

ControlBoard 24 4 €430,0 €362,0 €792,0 €22.176,0

Link Board Master 48 5 €200,0 €450,0 €650,0 €34.450,0

Link Board Slave 96 10 €200,0 €400,0 €600,0 €63.600,0

BackPlane 12 2 €337,0 €395,0 €732,0 €10.248,0

Frontplane 24 4 €99,0 €75,0 €174,0 €4.872,0

Mod APA450 24 4 €146,0 €385,0 €531,0 €14.868,0

Mech. 24 4 €37,5 €30,0 €67,5 €1.890,0

€153.504,0

Page 16: LINK BOARD PROJECT UPGRADE

Time schedule

Link Board Upgrade Meeting - Dec 2010Pigi Paolucci16

2011 2012

J F M A M J J A S O N D J F M A M J J A S O N D

LB prototype

LB test

CB prototype

CB test

Lbox

production

Test 904

Installation and commissioning in the 2013

Page 17: LINK BOARD PROJECT UPGRADE

Manpower and tasks

Link Board Upgrade Meeting - Dec 2010Pigi Paolucci17

Napoli is interested in the design of the “up-to-date” system P. Paolucci, S. Buontempo, N. Cavallo (sabbatical year in the 2011) Electronic Service: 6-7 months in the 2010 and 2011 Napoli is now (2010) designing the “up-to-date” LB system including:

LVDS suppressor, LV regulators. First design almost ready (80%). Cost estimation ready

LNF is looking at the test and commissioning of the system L.Benussi, L.Passamonti (Tech.), D.Pierluigi (Tech.) and Electronic

Service: 3-4 months in 2011 Warsaw is in charge for the test, commissioning and installation

of the system Warsaw is the only group having the full expertise of the link

board hardware and firmware system The participation of new groups at the LB project has been

strongly recommended by the CMS management

Page 18: LINK BOARD PROJECT UPGRADE

Manpower needed ?

Link Board Upgrade Meeting - Dec 2010Pigi Paolucci18

Prototypes test at CERN: 1 tech + 1 phys for 3 months (2011) + Warsaw Test at CERN (blg 904): 1 tech + 1 phys for 6 months (2012) + Warsaw Installation: 2 tech + 1 phys for 6 months (2013) + Warsaw Commissioning: 1 phys for 3-4 months (2013) + Warsaw

Page 19: LINK BOARD PROJECT UPGRADE

To be done

Document about the project, schedule, manpower and responsibilities:

Napoli, LNF and Warsaw ?: Napoli and LNF: production Warsaw, Napoli and LNF: prototype test at 904 Warsaw, LNF and Napoli: Production test and commissioning

New design: regulators + heat sink + what else ? LV board: new firmware + what else ? What about the spares ?

Link Board Upgrade Meeting - Dec 2010Pigi Paolucci19

Page 20: LINK BOARD PROJECT UPGRADE

Conclusion

Preliminary conclusions of the Electronic Service in Napoli:1. The present project is very good, complex and sophisticated;

congratulation to our Warsaw/Finland colleagues

2. Two “rad-hard” LV regulators per boards (LB/CB) are suggested – heat dissipation to be studied very carefully

3. Not clear if we really need a set of LVDS protections

4. Spartan III configuration could be double checked

New LB boxes and boards can be produced in Italy but only Warsaw experts can test and commissioning the full system – Napoli and LNF will be part of the business but not the main actors

INFN will discuss and decide about the project in Jan 2011

Link Board Upgrade Meeting - Dec 2010Pigi Paolucci20


Recommended