North Shore Waterfront Liaison Committee
October 22,2015
Lions Gate Secondary Wastewater Treatment Plant
PROJECT UPDATE
Andrea Winkler, Program Manager, Public Involvement
Paul Dufault, P.Eng., Project Manager
3
▶ Update you on Lions Gate Secondary Wastewater Treatment Plant process
▶ Hear how you want to be involved and updated
Purpose
4
Phase 1: Project Definition
● Public meetings● Stakeholder meetings● Door-door survey (businesses)● Public Advisory Committee (LGPAC)
Phase 2: Design and Construction
● LGPAC continued ● Project update (November 2015)● Traffic management and design
presentation (2017)
Public Process
Metro
Vancouver
Liquid Waste
Facilities
5
Lions Gate Wastewater Treatment Plant
1961
8
▶ Integrated Liquid Waste and
Resource Management Plan
(ILWRMP) approved in May
2011
▶ Wastewater Systems
Effluent Regulations – July
2012
Regulatory Drivers
Secondary treatment by
December 31, 2020
New Site
10
Project Objectives
▶ Secondary Treatment
▶ Sustainability
▶ Integrated Resource Recovery
▶ Community Integration
Project Definition and Indicative Design
Wastewater TreatmentThat is Sustainable and Recovers Resources
Provisions for Future Phosphorus Recovery
Reclaimed Water
Biogas Utilization
Provisions for District Energy
LEED® Certification
Envision® Certification
Effluent Heat Recovery
14
▶ Metro Vancouver
Website
● Indicative Design
● Project Definition
Report
● Lions Gate Public
Advisory Committee
About the Design
15
▶ Design & Construction
▶ Performance Period
▶ Handover
▶ Construction Period
Financing
● (~ 30-40 %)
Design Build Finance Delivery
16
▶ Interested Parties to
Submit Responses
▶ Up to 3 Short listed
Proponents to be
invited to submit
Proposals
Request for Qualifications
17
▶ Technical
Specifications
▶ Construction Impact
Mitigation
● Traffic Management
▶ Architectural Design
Guidelines
Moving Forward Specification Development
18
▶ Construction Traffic
● Volume (150 vpd)
● Routing
▶ Lane Closures
● Short term closures for specific activities
▶ Parking
▶ Railways
Traffic Management Planduring Construction
Project Schedule
20
▶ How would you like to be involved?
▶ What is the best way to keep you informed
Moving forward
21
QUESTIONS