Terri Denise Taylor July, 2016
OSU Health Plan, Inc. Fiscal Year Licensed Massage Therapist
Contracting Cycle Time Reduction
Six Sigma Green Belt Project Final Tollgate Presentation
2
Define Phase Charter signed via champion: Stefanie Morrow
Start date: April 5, 2016 with compliance standards checks and 8 executed LMT contracts prior to July 1st.
3
Measure Phase
Outcome Measure: Contractor contract execution cycle reduction time to total cycle time of >30 days by 6/30/16.
Process Measure: Compliance standards verified and contracts execution time reduction, execution cycle reduction time to total cycle time of >30 days with completion by 6/30/16.
FY ’16 CheckSheet Tallies Sum wrong email address
health assessment delay 1 1 background check delay 1111111111 10 professional licensure delay
malpractice insurance delay 11111 5 receipt after deadline 111111111 9 follow up required 1 1 Unplanned resignation 1111 4
4
Analyze Phase
5
Improve Phase Best Solutions: contract in phases, use spreadsheet for tracking, engage decision makers for approvals.
Decrease cycle time Com
mun
icatio
n
Mai
ntai
n Co
mpl
ianc
e
Redu
ce re
-wor
k
Tota
l
Tracking spreadsheet 5 10 3 18Agenda based meetings 10 1 5 16Engage decision makers 10 10 10 30
Implementation Plan Description
Responsible Status Tentative/Final Completion Date
Champion approval Denise Taylor; Stefanie Morrow Complete 04/04/2016 Current process & proposed
discussion and approval Denise Taylor; Stefanie Morrow Complete 4/12/2016
Champion phase update & input Denise Taylor; Stefanie Morrow Complete 4/18/2016 Pre-phase Meeting with contract
review; and compliance agreements Team Complete 4/27/2016
Contract revisions, compliance standards communication creation
Denise Taylor Complete 4/28/2016
Launch Denise Taylor Complete 4/29/2016 Completion Team Complete 5/10/2016 Wrap up Team Complete 5/13/2016
Contracting Fiscal year
total days for contract cycle
Number of contracts
Days per contract
Hours per contract
Goal Hours: 30% cycle time reduction
Goal Days: reduction by 30%
Contracting cycle hard costs
Project ROI
15-16 82 9 9.11 218.67 $5,000.91actual 16 - 17 6 8 0.75 18.00 153.07 6.38 $411.66
$4,589.25