LOGOPROJECT
Regensburg’s Implementation Plan(Part VI of the Management Plan)Barbara Bühler, City of Regensburg
HerO Midterm-Conference in Valletta | 8th-10th November 2009 I Page 2
I. INTRODUCTION
II. IDENTIFYING ISSUES1. Understanding the historic urban area2. Stakeholders and Structure III. APPRAISAL1. Overall vision and objective for the historic urban area2. Field of actions, their principles, objectives and actions3. Organisational and operational structures
IV. IMPLEMENTATION1. Action Plan 2. Continuous monitoring and review
Objective of the Local Implementation Plan
Str
uctu
re M
anag
emen
t P
lan
LOCAL IMPLEMENTATION PLAN “LIP”
Part IV of the “CHIMP” is the “Local Implementation Plan” (LIP) which points out concrete actions and projects in support of the sustainable development and management of the historic urban area including costs, time frame, responsibilities, etc.
In order to facilitate funding for concrete measures on local level, the LIP should be elaborated in close co-operation with the associated Managing Authority.
HerO Midterm-Conference in Valletta | 8th-10th November 2009 I Page 3
During the elaboration process of the ManagementPlan, the LSG conjointly identified 6 “Fields of Action”:
1. Built Cultural Heritage
2. Culture and Tourism
3. Economic Development
4. Urban Development and Urban Planning
5. Environmental Issues and Recreation
6. Awareness Raising and Science
Structure and Content of the LIP
HerO Midterm-Conference in Valletta | 8th-10th November 2009 I Page 4
Structure and Content of the LIP
Done so far:
For each of the six „Fields of Action“ we defined principles and objectives
Next step:
Identification of concrete measures to support these objectives
HerO Midterm-Conference in Valletta | 8th-10th November 2009 I Page 5
Field of Action
Objective Number Measure Priority Responsibleestimated
costs
Financing secured
(Investment Plan)
Funding by / Funding Programme
ScheduleLink to another
objective / measure
1. iv. 10Restoration of the
Stone Bridgehigh Department for … 1.000.000 € x Investitionspaket II: 80% 2010 ….
Field of Action the measure related to
Objective the measure supports
Number
What is it about? (keyword)
Priority
Responsible department / institution
Structure and Content of the LIP
Estimated costs
Financing Secured?
Funded by (Institution/Programme)
Time schedule
Link to another objective / measure
HerO Midterm-Conference in Valletta | 8th-10th November 2009 I Page 6
Additional to the LIP table:
Extra sheet for high priority measures (1-2 pages) with further information such as
- Objective
- Brief description
- Steps for implementation / Time schedule
- expected output
- stakeholders to be involved
- if required: break down of costs
Structure and Content of the LIP
HerO Midterm-Conference in Valletta | 8th-10th November 2009 I Page 7
The next two meetings are dedicated to the elaboration of the LIP:
- Analysis / collecting measures
- Check: still relevant?
- Responsibility
- Requirements for implementation
- Filling in the table
- Check: Is funding secured?
Elaboration Process of the LIP
LOCAL SUPPORT GROUP
HerO Midterm-Conference in Valletta | 8th-10th November 2009 I Page 8
December 2009:
- Information evening
- Information desk
- PR
January 2010:
Civic Participation Process
Discussion of LIP with the public
Participation of all stakeholder groups
Elaboration Process of the LIP
CIVIC PARTICIPATION
HerO Midterm-Conference in Valletta | 8th-10th November 2009 I Page 9
Recommendations / Lessons learnt
Regular information of the political level (City Council) / Approval of important steps and funding for concrete measures
Involvement of the public through Civic Participation Process
PR activities:
- Information during the elaboration process
- Presentation of the results to the public