LOR-US 20-22.19 PROJECT MATCHMAKER
2 |
WELCOME
PROJECT REVIEW
DISADVANTAGED BUSINESS ENTERPRISE (DBE)
QUESTIONS
MATCHMAKER EVENT
AGENDA
LOR US 20-22.19 MATCHMAKER
3 |
PROJECT
OVERVIEW
LOR US 20-22.19 MATCHMAKER
4 |
PROJECT OVERSITE
LOR US 20-22.19 MATCHMAKER
BRIAN RAWLINGS: PROJECT ENGINEER
LUKE WYSOCKI: CONSTRUCTION AREA ENGINEER
5 |
PROJECT OVERSITE
LOR US 20-22.19 MATCHMAKER
MIKE FAIR: DISTRICT CONSTRUCTION ADMINISTRATOR
MICHAEL WEILER: PROJECT MANAGER, DESIGN
6 |
PROJECT LOCATION
LOR US 20-22.19 MATCHMAKER
Project No. 170566
LOR-US 20-22.19
PID 82632
Stoney RidgeLear Nagle
7 |
PROJECT LOCATION
LOR US 20-22.19 MATCHMAKER
Project No. 170566
LOR-US 20-22.19
PID 82632
8 |
PROJECT OVERVIEW
LOR US 20-22.19 MATCHMAKER
PROJECT DESCRIPTION:
WIDENING TO 5 LANES FROM STONEY RIDGE ROAD TO
LEAR NAGLE IN THE CITY OF NORTH RIDGEVILLE,
LORAIN COUNTY; REPLACING 2 STRUCTURES;
CONSTRUCTION OF NEW TRAFFIC SIGNALS AND
RELATED WORK
ESTIMATED COST:
$26.5 MILLION
9 |
PROJECT LOCATION
LOR US 20-22.19 MATCHMAKER
Project No. 170566
LOR-US 20-22.19
PID 82632
Structure 1
Structure 2
10 |
PROJECT DESCRIPTION
LOR US 20-22.19 MATCHMAKER
THE PROJECT IMPROVES 2.32 MILES OF US 20/CENTER RIDGE
ROAD IN NORTH RIDGEVILLE BY WIDENING THE ROADWAY
FROM 3 LANES TO 5 LANES; CONSTRUCTING ALL NEW:
PAVEMENT
CURB AND GUTTER
SIDEWALK
SHARED-USE PATH
STORM SEWER
NEW TRAFFIC SIGNALS
11 |
PROJECT DESCRIPTION
LOR US 20-22.19 MATCHMAKER
THE PROJECT WILL RE-ALIGN ROOT ROAD
& RIDGEVIEW BOULEVARD AND REPLACE
THE TWO STRUCTURES CARRYING US 20 &
ROOT ROAD OVER FRENCH CREEK
12 |
PROJECT DESCRIPTION
LOR US 20-22.19 MATCHMAKER
THE PROJECT INCLUDES
IMPROVEMENTS TO SIDE
ROADS,
RECONSTRUCTION OF
GARDEN STREET, AND
CONSTRUCTION OF A
NEW STREET NAMED
SINTA RUN AND NEW
TRAFFIC SIGNALS
SINTA RUN
13 |
PROJECT SCHEDULE
LOR US 20-22.19 MATCHMAKER
SALE DATE: NOVEMBER 30, 2017
AWARD DATE: DECEMBER 11, 2017
CONSTRUCTION START: APRIL 2, 2018
CONSTRUCTION END: OCTOBER 11, 2019
14 |
EXPECTED CONSTRUCTION WORK TYPES
LOR US 20-22.19 MATCHMAKER
ROADWAY
EROSION CONTROL
DRAINAGE
PAVEMENT
WATER WORK
15 |
EXPECTED CONSTRUCTION WORK TYPES
LOR US 20-22.19 MATCHMAKER
SANITARY SEWER, MINOR WORK
LIGHTING
TRAFFIC CONTROL
TRAFFIC SIGNALS & ALTERNATES
16 |
EXPECTED CONSTRUCTION WORK TYPES
LOR US 20-22.19 MATCHMAKER
MAINTENANCE OF TRAFFIC
RETAINING WALLS
STRUCTURE OVER 20 FOOT SPAN
ROOT ROAD – SINGLE SPAN REINFORCED CONCRETE SLAB ON REINFORCED CONCRETE ABUTMENTS
STRUCTURE 20 FOOT SPAN AND UNDER
US 20 - 16’ X 8’ 4 SIDED PRECAST AND C-I-P CONCRETE BOX CULVERT
INCIDENTALS
17 |
UTILITY WORK
LOR US 20-22.19 MATCHMAKER
MOST UTILITIES HAVE OR ARE RELOCATED
SANITARY SEWER REALIGNMENT IS ALREADY
COMPLETED
MOST COMMERCIAL/RESIDENTIAL
STRUCTURES ALREADY REMOVED
18 |
DISADVANTAGED BUSINESS ENTERPRISE (DBE)
LOR US 20-22.19 MATCHMAKER
DBE GOAL 10%
CONTAINS THE PROPOSAL NOTE 013-DISADVANTAGED BUSINESS
ENTERPRISE (DBE) UTILIZATION PLAN AND GOOD FAITH EFFORTS
UPDATED 07/21/2017
ALL BIDDERS SHALL SUBMIT A DBE UTILIZATION PLAN AT THE TIME
OF BID, SETTING FORTH SPECIFIC INFORMATION DEMONSTRATING
HOW THE BIDDER WILL ACHIEVE THE DBE GOAL
19 |
DISADVANTAGED BUSINESS ENTERPRISE (DBE)
LOR US 20-22.19 MATCHMAKER
DBE CERTIFIED FIRMS:
http://www.dot.state.oh.us/Divisions/ODI/SDBE/Pages
/DBE-Directory.aspx
20 |
WHERE TO FIND US
LOR US 20-22.19 MATCHMAKER
ODOT DISTRICT 3
906 CLARK STREET
ASHLAND, OHIO 44805
419-281-0513
HOWARD (BUTCH) HUEBNER
DISTRICT DEPUTY DIRECTOR
21 |
QUESTIONS
LOR US 20-22.19 MATCHMAKER
?
22 |
MATCHMAKER
IMMEDIATELY
FOLLOWING
LOR US 20-22.19 MATCHMAKER