1 ANNEXURE -1 LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. (Minute) Section affected (with inspection schedule) Brief details of incidence Cause of Failure Responsibility Remedial Action taken to prevent recurrence. 1. 02.10.11 09 11448 12175 12304 12313 12339 13049 13318 15049 18627 154 41 16 82 86 38 125 23 163 BCQ DGR-KPK CRJ-RNPR ASN-PKA MNAE-ASN RNG-ASN DHN ASN-STN ULT-BRR Catenary wire of out of run OHE has been parted under Catenary suspension clamp at loc. no. 227/21 on UP/GC between ULT-BRR. Catenary wire parted due to previous strands cut under suspension clamp. TRD All OHE depots have been advised to pay attention to the Catenary wire under suspension clamp specially at OOR locations. Concerned supervisor, who has last attended the location, was chargsheeted (SF-11). 2. 22.10.11 01 18622 33 TNW-KEE Both JMT and BDME grid failed at 05:28 hrs. Power resumed at 05:38 hrs.. Distance protection relay of “B” phase tripped at Maithon Hydel. Danapur feed could not be availed as MKA grid under E.C. Railway also failed. KMME feed extended up to JAJ Grid Failure -- 3. 29.10.11 09 12023 12369 13021 13049 13105 13185 13320 15047 18603 130 211 55 110 150 54 120 144 80 JSME-JAJ JSME MDP-JAJ MDP-JAJ JSME-JAJ MDP-JAJ MDP-JAJ MDP-JAJ MDP-JAJ Porcelain stay insulator got broken at loc. no. 334/03 on UP/ML between TTN-LHB. The hanging stay tube got entangled with the rearmost VTPN wagon of E/7895/RXL/VTPN and Catenary wire got broken and got under the wheels in last one span. Breakage of porcelain stay insulator is caused by stone pelting at the insulator by miscreants. The site is near cutting. Being elevated with respect to the track gives height advantage to the stone pelters. Miscreant activity There are no flast marks on the stay insulator, bonding between metallic cap and insulator core at both ends was intact. Catenary wire between the two ‘U’ bolts of the suspension clamp wsa healthy.
Transcript
Page 1: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

1

ANNEXURE -1

LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID)

Sl. No.

Date No. of Trains

Train No.

Detn. (Minute)

Section affected (with inspection

schedule)

Brief details of incidence Cause of Failure Responsibility Remedial Action taken to prevent recurrence.

1. 02.10.11 09 11448

12175

12304

12313

12339

13049

13318

15049

18627

154

41

16

82

86

38

125

23

163

BCQ

DGR-KPK

CRJ-RNPR

ASN-PKA

MNAE-ASN

RNG-ASN

DHN

ASN-STN

ULT-BRR

Catenary wire of out of run

OHE has been parted under

Catenary suspension clamp at

loc. no. 227/21 on UP/GC

between ULT-BRR.

Catenary wire parted due to

previous strands cut under

suspension clamp.

TRD All OHE depots have been advised to pay

attention to the Catenary wire under

suspension clamp specially at OOR

locations. Concerned supervisor, who has

last attended the location, was

chargsheeted (SF-11).

2. 22.10.11 01 18622 33 TNW-KEE

Both JMT and BDME grid

failed at 05:28 hrs. Power

resumed at 05:38 hrs..

Distance protection relay of “B”

phase tripped at Maithon Hydel.

Danapur feed could not be

availed as MKA grid under E.C.

Railway also failed. KMME feed

extended up to JAJ

Grid Failure --

3. 29.10.11 09 12023

12369

13021

13049

13105

13185

13320

15047

18603

130

211

55

110

150

54

120

144

80

JSME-JAJ

JSME

MDP-JAJ

MDP-JAJ

JSME-JAJ

MDP-JAJ

MDP-JAJ

MDP-JAJ

MDP-JAJ

Porcelain stay insulator got

broken at loc. no. 334/03 on

UP/ML between TTN-LHB.

The hanging stay tube got

entangled with the rearmost

VTPN wagon of

E/7895/RXL/VTPN and

Catenary wire got broken and

got under the wheels in last one

span.

Breakage of porcelain stay

insulator is caused by stone

pelting at the insulator by

miscreants. The site is near

cutting. Being elevated with

respect to the track gives height

advantage to the stone pelters.

Miscreant

activity

There are no flast marks on the stay

insulator, bonding between metallic cap

and insulator core at both ends was intact.

Catenary wire between the two ‘U’ bolts

of the suspension clamp wsa healthy.

Page 2: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

2

ANNEXURE -1A TRD INCIDENTS REPORTED FROM DIVISIONAL TRAFFIC CONTROL TO HEADQUARTER EMERGENCY CONTROL

Sl. No.

Date No. of Trains

Train No.

Detn. (Minute)

Section affected (with inspection

schedule)

Brief details of incidence Cause of Failure

Responsibility Remedial Action taken to prevent recurrence.

1. 02.1011 09 11448

12175

12304

12313

12339

13049

13318

15049

18627

154

41

16

82

86

38

125

23

163

BCQ

DGR-KPK

CRJ-RNPR

ASN-PKA

MNAE-ASN

RNG-ASN

DHN

ASN-STN

ULT-BRR

Catenary wire of out of run OHE

has been parted under Catenary

suspension clamp at loc. no.

227/21 on UP/GC between ULT-

BRR.

Catenary wire parted due to

previous strands cut under

suspension clamp.

TRD All OHE depots have been advised to pay

attention to the Catenary wire under

suspension clamp specially at OOR

locations. Concerned supervisor, who has

last attended the location, was

chargsheeted (SF-11).

2. 22.10.11 01 18622 33 TNW-KEE

Both JMT and BDME grid failed at

05:28 hrs. Power resumed at 05:38

hrs..

Distance protection relay of

“B” phase tripped at Maithon

Hydel. Danapur feed could not

be availed as MKA grid under

E.C. Railway also failed.

KMME feed extended up to

JAJ

Grid Failure --

3. 29.10.11 09 12023

12369

13021

13049

13105

13185

13320

15047

18603

130

211

55

110

150

54

120

144

80

JSME-JAJ

JSME

MDP-JAJ

MDP-JAJ

JSME-JAJ

MDP-JAJ

MDP-JAJ

MDP-JAJ

MDP-JAJ

Porcelain stay insulator got broken

at loc. no. 334/03 on UP/ML

between TTN-LHB. The hanging

stay tube got entangled with the

rearmost VTPN wagon of

E/7895/RXL/VTPN and Catenary

wire got broken and got under the

wheels in last one span.

Breakage of porcelain stay

insulator is caused by stone

pelting at the insulator by

miscreants. The site is near

cutting. Being elevated with

respect to the track gives height

advantage to the stone pelters.

Miscreant activity There are no flast marks on the stay

insulator, bonding between metallic cap

and insulator core at both ends was intact.

Catenary wire between the two ‘U’ bolts

of the suspension clamp wsa healthy.

Page 3: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

3

ANNEXURE -II GRID SUPPLY FAILURE

Sl. No.

Date Name of GSS/TSS

Supply Athority

From (hh:mm:ss)

To (hh:mm:ss)

Duration in

minutes Cause of failure

Detention of trains due to delay in feed extension

Cause of

delay Action taken

1. 18.10.11 JMT

BDME

JSEB

JSEB

17:15

20:05

17 :40

20 :29

25 :00

24:00

CT burst at JMT/GSS incoming CB tripped at

BDME/GSS due to jumper cut.

-- --

2. 22.10.11 JMT

BDME

JSEB

JSEB

05:28

05:28

05 :37

05 :38

09:00

10:00

132 KV supply tripped through Distance protection

relay of zone “I” at Maithon Hydel. 18622 UP --

3. 22.10.11 JMT

BDME

JSEB

JSEB

12:28

12:28

12 :33

12 :33

05:00

05:00

Distance protection relay of “B” phase tripped at

Maithon Hydel. -- --

4. 29.10.11 JMT

BDME

JSEB

JSEB

03:44

03:44

04 :04

03 :49

20:00

05:00 -- --

5. 29.10.11 JMT

BDME

JSEB

JSEB

23:45

23:45

23 :53

23 :51

Supply failed from JMT and BDME grid due to

CB tripped at Maithon Hydel.(fault in JMT to

Deoghor 132 KV line) -- --

6. 30.10.11 JMT

BDME

JSEB

JSEB

04:42

04:42

04:48

04:55

06:00

13:00 -- --

7. 30.10.11

JMT

JSEB 04:50

04:57

04:53

05:04

03:00

07:00

Both CBs of JMT /GSS and Maithon Hydel

tripped through DPR relay due to fault in JMT-

BDME 132 KV line. -- --

8. 30.10.11

JMT

JSEB 16.35 16.43 08.00

132 KV supply tripped from JMT/GSS due to trial

shot taken by JMT/GSS on JMT-BDME 132 KV

line

-- --

9. 30.10.11

BDME

JSEB 19.14 19.17 03.00 Sultanganj to Deoghar NTPC power failed due to

tripping of Dumka Circuit. -- --

10. 30.10.11

BDME

JSEB 23.28 23.30 02.00 132 KV incoming supply at BDME/GSS failed due

to tripping of CB tripped at Lalmatia/GSS. -- --

11. 31.10.11 BDME JSEB 01:50 01:52 02:00 Sultanganj to Deoghar NTPC supply failed from

Sultanganj end. -- --

Page 4: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

4

TRIPPING DATA RELAY WISE ( NO. OF TRIPPINGS) ANNEXURE -IIA

Auto reclosure action No. of trippings in the month TSS / GSS

Feeder CB No.

Tripping Target

Tripping during the month

Trip & close

Lock out DPR OCR WPC Delta-I Panto flashover

CB-01 -- 10 04 06 07 07 -- 05 Not required. OYR/FP*

CB-02 -- 17 12 05 13 10 -- 03 Not required.

CB-03 -- 31 16 15 27 28 -- 11 Not required. KMME/FP

CB-04 -- 02 -- 02 02 -- -- 02 Not required

CB-121 -- 05 05 -- 05 05 -- 02 Not required. JMT/TSS

CB-123 -- 06 04 02 03 05 -- 04 Not required.

CB-125 -- 01 01 -- -- -- -- 01 Not required SNQ/TSS

CB-127 -- 06 04 02 05 05 -- -- Not required.

TIF 0012 REV 2 PART-II LOG SHEET FOR FAILURES OF SS WIRE ROPE ANNEXURE -II B

FAILURE DUE TO Sl. No.

Section Location Make Month & Year of

Manufacturer

Specification to which

procured & P.O. number

Date of installation

of wire rope

Type of ATD Winch/ Pulley Block/3- pulley/3- pulley

(modified)

Date of last maintenance

Date of

failure

Failure on OHE side/CW

side

Rope snapped

Corrosion/ pitting

marks on rope

Bird caging

loosening of wires

Deformation of wire rope

Date of application of

lubricant “BALMEROL ROPE LUBE-

1000” NIL

ANNEXURE -II C TIF 0012 REV 2 PART-III LOG SHEET FOR FAILURES OF SS WIRE ROPE DUE TO FAILURE OF ATD ONLY

FAILURE DUE TO Sl. No.

Section Location Make Month & Year of

Manufacturer

Specification to which

procured & P.O. number

Date of installation

of wire rope

Type of ATD

Winch/ Pulley Block/3- pulley/3- pulley

(modified)

Date of last maintenance

Date of

failure

Failure on OHE side/CW

side

Seizure of bearing (if failure due to seizure of

bearing mention

bearing No.)

Deformation of pulley groove

Alignment/ gazing of

side walls of pulley/drum

Overriding of wire rope

Date of application of

lubricant “BALMEROL ROPE LUBE-

1000”

NIL

TIF-0014 PART-IV FAILURE REPORTING FORMAT OF THE TRANSFORMER (21.6/30.24 MVA OR 21.6 MVA) ANNEXURE -II D

Sl. No.

Division TSS Location

Make Voltage rating

MVA rating 21.6 or 21.6/30

MVA

Year of manufacture

Year of commissioning

Date of failure

Date and type of last maintenance

Details of failure/ defect including condition i.e. on load or off load

Action taken by Railways

Remarks including details of past failure if any

NIL

Page 5: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

5

TIF--0015 Pt-IV FAILURE REPORTING FORMAT FOR THE SHUNT CAPACITOR BANK ANNEXURE –II/E

Division TSS/FP Make Date of commissioning

Date of failure

Details of failure Probable reasons of

the failure

Action taken by Railway

Corrective and preventive action suggested by the

Railway

Remarks including details of past failures if any

NIL

TIF-0016 Pt-III PROFORMA FOR STATISTICS OF A.C. CIRCUIT BREAKERS ANNEXURE -II/ F

Sl. No.

Division/ Post/ CB

No.

Make Rated Voltage &

Type

Sl. No. & Year of

Manufacture

Date/ Year of Commissioning

Date of failure

No. of operation before failure/

Defect

Details of Failure/ Defect & location on

installation

Action taken by Rly to rectify the

defect

Remarks

NIL

TIF-0016 Pt-IV PROFORMA FOR STATISTICS OF A.C. INTERRUPTORS ANNEXURE -II/G

Sl. No.

Division/ Post/ BM

No.

Make Rated Voltage & Type

Sl. No. & Year of Manufacture

Date/ Year of Commissioning

Date of failure

No. of operation before failure/

Defect

Details of Failure/ Defect & location on

installation

Action taken by Rly to rectify the defect

Remarks

NIL TIF-0018 PART-I FORMAT FOR INSULATOR FAILURE INFORMATION ANNEXURE -II/ H

Zonal Railways

Division Depot Section Location No.

Type of location (whether straight

line, inside curve, outside

curve, out of run, BWA

location, feeder

location or any other

to be specified)

Distance of location

from Anticreep & ATD

Location of

insulator (In Non-polluted zone or Polluted zone)

Type of insulator (Mention whether

Stay Arm/ Bracket Tube/ 9-Tonne/

Sectioning Insulator

Creepage distance/ (850 mm/

1050 mm)

Make of the

Insulator

Month. & Year of

Manufacture

Year of commissioning/

Erection (whether New/

Released insulator)

Date of last maintenance

Date of failure

Weather condition/

clear/ foggy

/stormy/ rainy

Nature of failure

(Flashed, Flashed and Broken, Core broken viz. Mechanical

Breakage into two parts or more, Cap

slipping, Cap broken, any

other abnormality

found)

Apparent cause of failure [(i) SS wire rope/ Contact wire/

Catenary wire broken, (ii) Electrocution of Monkey/ Bird/ Snake etc. (iii) Short circuit due to dropping of stray wire/ foreign object, (iv) Panto

entanglement, (v) tree falling, (vi) Brake block hitting the mast, (vii) Pollutant deposition, (viii) any other reason

(To be specified)

Whether any silicon greases was

applied on the

insulator?

NIL

Page 6: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

6

TIF-0019 REVISION PART-II CONTACT WIRE FAILURE ANNEXURE -II/ I

Particulars of failure Sl. No.

Div Type of failure Date Section Location CC/ Jointed contact wire

Year of Manufactu

re

Make Type of OHE conventional/ Tramway/ unregulated

At OOR/ IR of OHE

Insulated overlap/or uninsulated overlap

Approximate distance From

support

ATD free to move (Y/N)

Whether jumper location (Y/N)

Pollution area (Y/N)

Action taken Reason of failure

NIL

TIF-0024 PART-II FORMAT FOR FAILURE OF TOWER WAGONS ANNEXURE -II/ J

Date of last POH done on equipments Type of wagon

Division Tower wagon no

Make Engine Transmission

System Traction motor/ rectifier/ batteries

Generator/ Alternator

Last POH done on TW/ due date of POH

Recommended Maintenance

schedule followed before or not, with

date

Date of failure and probable

reason of failure

Remedial action taken by Rlys on failure

Details of past failures, if any

Nil

THEFT/ATTEMPTED THEFT ANNEXURE -III

SL No. Date Section Location Theft Item Quantity Gross amount Net amount Joint note details NIL

Page 7: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

7

CORPORATE MASTER ACTION PLAN A. MAINTENANCE ORIENTED WORK

Sl. No.

Item Unit Total Qty. as on 1st April of the current

financial year

Target for current financial

year

Prop. Target up

to the current month

Completed during

the Current month

Completed during the current financial

year

Short fall w.r.t. prop. Target

Balance Cause of shortfall

Action taken for completion

of the balance work

1 2 3 4 5 6 7 8 9 10 11 12 1 AOH of OHE-AC TKM 1335 1335 779 44.866 382.863 (-) 396.137

952.130 -- --

2 AOH of OHE-DC TKM -- -- -- -- -- -- -- -- --

3 Section Insulator (checking) No. 691 536 313 15 106 (-) 207 585 -- --

4 Section Insulator (cleaning) No. 691 536 313 15 106 (-) 207 585 -- --

5 PTFE (Checking & Cleaning) (AF) No. 28 28 16 02 22 (+) 06 06 -- --

6 PTFE (Checking & Cleaning) (BB) No. -- -- -- -- -- -- -- -- --

7 Retenesioning of FTA No. 316 162 95 01 05 (-) 90 311 -- --

8 POH of Regulating Equipment No. 2273 440 257 34 168 (-) 89 2105 -- --

9 AOH of Interrupter. No. 144 134 78 14 68 (-) 16 76 -- --

10 Adjustment of Cross over/Turn out No. 917 772 450 21 184 (-) 266 733 -- --

11 AOH of Isolator No. 415 331 193 16 110 (-) 83 305 -- --

12 AOH of Auxiliary Transformer No. 305 275 160 19 92 (-) 68 213 -- --

13 POH of switching stations. No. 18 18 11 02 06 (-) 05 12 -- --

i) Stay No. -- All -- 20 106 -- -- -- --

ii) Bracket No. -- All -- 35 208 -- -- -- --

14 Replacement of all

broken/flashed over/

erroded insulator. iii) 9-Tonne No. -- All -- 22 198 -- -- -- --

15 Application of Balmerol rope lube on SS wire rope No. 2273 1980 1155 109 755 (-) 400 1518

16 Replacement of catenary ending clamp during alternate POH. No. 4835 500 292 14 79 (-) 213 4756 -- --

Page 8: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

8

1 2 3 4 5 6 7 8 9 10 11 12

17 Replacement of contact ending clamp during alternate POH. No. 3573 500 292 10 32 (-) 260 3541 -- --

18 POH of vacuum interrupter. No. 18 18 11 -- 02 (-) 09 16 -- --

19 POH of engine of 8-wheeler tower wagon. No. 03 03 02 -- -- -- 03 -- --

20 Checking of PG clamp of ‘G’ jumper. No. 15104 All -- 532 4638 -- 10466 -- --

21 Removal of failure prone insulator as per RDSO’s guideline. No. Nil All -- -- -- -- -- -- --

22 Replacement of catenary make ‘C’ jumper by standard jumper. No. 134 134 78 19 107 (+) 29 27 -- --

23 Improvement of steady clearance. No. 1949 All -- 41 201 -- 1748 -- --

i) Stay No. -- -- 896 6458 -- --

ii) Bracket No. -- -- 896 6758 -- --

24

Cleaning of insulators. iii) 9-Tonne No. --

48874

-- 135 1105 --

--

--

-- --

25 Earthing & bonding of OHE structure. No. 7246 All -- 56 624 -- 6622 -- --

26 Continuity of buried rail. No. Nil Nil -- -- -- -- -- -- --

27 Examination of Silica gel of power Transformer and CB/BM. No. 240 240 140 34 144 (+) 04 96 -- --

28 POH of Traction Transformer. No. -- 03 02 -- -- (-) 02 03 -- --

29 Tree trimming. No. All All -- 207 1681 -- -- -- --

30 Visual inspection of SS wire rope during patrolling. No. 2273 All 11880 1871 12217 (+) 337 -- -- --

i) Catenary No. 3715 14 80 3635 -- 31 POH of ending clamps as per SMI No.

TI/MI/0034 (Rev-0). ii) Contact No. 3965 All --

10 47 --

3918 --

32 Provision of double PG clamp on sectioning jumpers/’G’

jumpers.

No. 108 108 63 09 10 (-) 53 98 -- --

33 Bird deterent gel to be provided from 1st Week of February

onward every year.

No. -- All -- -- -- -- -- -- --

34 Live line checking by Tower Wagon. Km 829 829 484 308 644 -- -- -- --

35 Checking of anticreep wire. No. 692 692 404 27 176 (-) 228 516 -- --

36 Measurement of Equivalent salt deposit density(ESDD) -- -- -- -- -- -- -- -- --

37 Replacement of insulators by composite insulators in stone

pelting zone and for ESDD>0.3 No. 4516 3500 2042 10 205 (-) 1837

3295 -- --

38 To check healthiness of the lightning arrester in lightening

prone area. 138 138 81 07 80 (-) 01 58

-- --

39 Joint checking of pantograph by TRD & TRS staff. No. All All -- 133 1007 -- -- -- --

40 Tree branch trimming No. All All -- 1817 20167 -- -- -- --

41 Cutting of trees with Engineering department. No. 465 465 271 12 249 (-) 22 216 -- --

42 Checking of RRA clamp to avoid necking & parting of contact

wire. No. 2235 2235 1304 61 460 (-) 844

1775 -- --

43 Free movement of cantilever. No. 21592 21592 12595 665 6374 (-) 6221 15218 -- --

44 Checking of PG clamps, splices by thermo vision camera. No. 8550 8550 4988 2388 3666 (-) 1322 4884 -- --

45 Checking of all the along/vertical feeders opposite to

TSS/SP/SSP gantries. No. 90 90 53 05 109 (+) 56

-- -- --

Page 9: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

9

B. WORK TO BE DONE WITH MAINTENANCE WORK-ONE TIME PROGRAMME

1 2 3 4 5 6 7 8 9 10 11 12

1 Replacement of worn out contact wire Km 12 10 06 -- 2.970 (-) 3.03 9.03 --

2 Replacement of week and over-aged catenary wire. km 10 10 06 -- 1.720 (-) 4.28 8.28

3 Replacement of conventional type steady arm by BFB steady

arm.

No. 3933 2000 1167 43 188 (-) 979 3745

4 Anti theft jumpers at anti-creep point. No. 2681 500 292 26 89 (-) 203 2592

5 Replacement of pin insulator. No. 100 100 58 -- -- (-) 58 100

6 Mapping of OHE by Oliver G Plus for OHE spark detection. TKM 285 All -- -- 156 -- 129

7 Adjustment of OHE parameters recorded by NETRA Car. No. Nil All -- -- -- -- --

8 Identification of 9-ton insulators having core dia of 72 mm

and appropriate action.

No. All All -- 08 4994 --

--

9 Replacement of G-jumpers/cross feeders of 105 sq. mm with

150 sq. mm size in heavy loading locations.

No. All All -- 05 13 --

--

C. WORKS TO BE DONE THROUGH SANCTIONED WORKS PRIORITY-1 (Required Power Block)

1 2 3 4 5 6 7 8 9 10 11 12

1 Providing guide tubes for counter weight movement. No. 156 80 47 -- 22 (-)25 134

2 Provision of insulated catenary under FOBs/ROBs. No. 29 11 06 02 03 (-) 03 26

3 Replacement of earthing grides at TSSs/FPs. No. 03 03 02 -- -- (-) 02 03

4 Removal of all return conductors. km NIL 02 01 -- -- (-) 01 --

< 2.135 M No. 215 01 10 --

2.136 - <2.16 M No. 129 -- 09 --

2.16 - 2.210 M No. 631 02 19 --

2.211 - 2.36 M No. 1817

300 175

14 41

--

--

2.37 - 2.50 M No. 1729 -- -- -- -- -- --

5

Improvement of tight

implanted masts.

Total No. 4512` -- -- 17 79 -- --

6 Replacement of over aged isolators. No. 32 32 19 -- -- -- --

7 Replacement of over aged Lightning Arrestor. No. -- -- -- 04 06 -- --

8 Replacement of over aged PT. No. -- -- -- -- -- -- --

9 Replacement of Guy Rod Anchor by Dwarf Mast No. 20 -- -- -- 01 -- 19

10 Replacement of Alluminium cross feeder by Copper cross

feeder. No. 33 33 19 -- 01 (-) 18 32

11 Upgradation of Cap Bank. No. 03 03 01 -- 01 -- 02

Page 10: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

10

1 2 3 4 5 6 7 8 9 10 11 12

12 Conversion of fixed tensioning arrangement to auto tensioning

arrangement by providing balance weight anchor in

conventional AC OHE at different locatins.

No. 21 -- -- -- -- -- 21

13 Replacement of soldered type jumper connection to lugs at old

isolator bus connector by new copper bus bar terminal and

connector compression.

No. 64 64 37 -- -- (-) 37 64

14 Replacement of defaced Number Plates for location, isolators

and BM/CB etc.

No. 642 All -- 60 591 -- 51

15 Anticorrosive painting of masts/portals -- -- -- -- -- -- --

16 Provision of PTFE neutral section replacing section insulator

type neutral section.

No. -- -- -- -- -- -- --

17 Replacement of turnbuckle type stay arm by conventional type

Stay arm.

No. 1424 1421 829 -- 06 (-) 823 1418

18 Replacements of earth wire in double track-circuited section. km 4.00 2.00 01 -- 0.440 (-) 0.560 3.56

19 Provision of 250 gms capacity Silica Gel Breathers on 10 KVA

Aux. Transformers.

No. Nil All -- -- -- -- --

20 Replacement of OHE mast at platform with implantation less

than 4.75 m.

No. 63 63 37 -- -- (-) 37 63

21 Provision of drop bracket assembly as per drg No.

ETI/OHE/P/2360 along with steady arm as per Drg. No.

ETI/OHE/P/2390.

No. 3527 2000 1167 29 124 (-) 1043 3403

22 Provision of PTFE Neutral section. No. Nil -- -- -- -- -- --

23 Removal of all (279) OHE structure of implantation less than

2.135 Mtrs as on ASN division.

No. 215 215 125 -- 09 (-) 116 206

24 Shifting of metering point from grid sub-station to traction

sub-station.

No. 02 02 01 -- -- (-) 01 02

25 100 KVA Transformer to be replaced with 10 KVA at Traction

sub-station.

No. 02 02 -- -- -- (-) 01 02

26 Provision of bird & monkey scare measures at portals &

designated locations. No. All -- -- -- 72 --

--

27 Replacement of rusted cantilever assembly 7985 1000 583 05 484 (-) 99 7501

28 Replacement of overhead 11 KV crossing by under ground

cable. No. 27 27 16 -- -- (-) 16 27

D. WROKS TO BE DONE THROUGH SANCTIONED WORKS PRIORITY-I (Required No Power Block)

1 2 3 4 5 6 7 8 9 10 11 12

1 Replacement / renovation of earth pits & provision of earthing

pits at all girder bridges.

No. 47 20 12 08 26 (+) 14 21

2 Replacement of over aged batteries. Set 72 72 42 -- -- (-) 42 72

3 Provision of spare battery charger. No. 05 05 03 -- -- (-) 03 05

4 Painting of Balance weight and regulating equipment. No. 2273 1656 968 08 280 (-) 688 1993

5 Upgradation of sectioning Board. No. -- -- -- -- -- -- --

Page 11: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

11

1 2 3 4 5 6 7 8 9 10 11 12

6 Joint inspection of power line crossing over electrified track. No. 96 81 47 10 47 -- 49

7 Provision of standard height gauge as per RDSOs Drawing. No. All 246 144 -- -- (-) 144 --

Single Masts No. All 6548 All -- -- -- 6548 8 Raising of foundation level and remuffing for

the masts where rail level has been increased

substantially in HWH-BWN-KAN section. Portals Masts No.

All 1076 All -- -- -- 1076

9 Provision of stranded galvanized wire bond in place of M.S.

Flat bond in theft prone areas.

No. 3032 All -- -- 07 -- 3025

10 Provision of screens to 1.83 M height on all FOBs to cover

gaps wherever existing between two lines. No. 17 15 10 -- 08 (-) 02

09

E. WORKS TO BE DONE THROUGH SANCTIONED WORKS-PRIORITY-II

1 2 3 4 5 6 7 8 9 10 11 12

1 Removal of all abandoned OHE structures from along the

track.

No. 38 -- -- 04 16 -- 22

2 Implantation of masts with ATs as per prescribed dimension. Mast 86 86 50 -- -- (-) 50 86

3 Replacement of heavy duty section insulator by standard AC

(light duty) Section Insulator in HWH-BWN main line section. -- -- -- -- --

--

F. SPECIAL WORK

1 2 3 4 5 6 7 8 9 10 11 12

1 Replacement of 16 Nos, 3 track cantilever masts at Srirampore

in HWH division.

No. -- -- -- -- -- -- --

2 Removal of abandoned concrete portals at SHE-TAK section. -- -- -- -- -- --

3 Removal of cross span wire. 03 -- -- -- -- --

G. DEVELOPMENT ORIENTED WORK.

1 2 3 4 5 6 7 8 9 10 11 12

1 Organizing safety seminar by Depot In-Charge. Depot 108 108 63 09 53 -- 55

a) At CKP No. 13 -- 02 11 i) Supervisor

b) At THK No. 33 -- --

01 11 ---

22

ii) Group-C At CKP No. 82 -- -- 07 21 -- 61

2 Training to staff.

iii) Group-D At CKP No. 22 -- -- 03 13 -- 09

3 Time drill once in a month. Depot 84 84 49 02 26 (-) 23 58

Page 12: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

12

FORMAT FOR MONITORING THE STATUS OF TIGHT IMPLANTATION Annexure-IV/III

PRESENT POSITION PROGRESS

Implantation

measured(Mtrs)

New

Implantation

Sl

No.

Depot Section Loc.No. Line

Forward Reverse

SED Value(Mtrs) Type of mast Date/Month

of

replacement

Type of

mast

1 UDL KPK-NMC 190/15A UP/RL 2.32 -- NA NA C-12 October’11 3.03 -- TTU

2 UDL KPK-NMC 189/12A DN/SL 2.19 -- NA NA C-12 October’11 2.74 -- TTU

3 UDL KPK-NMC 190/19A UP/RL 2.36 -- NA NA C-12 October’11 3.02 -- TTU

4 UDL KPK-NMC 190/5A UP/RL 2.35 -- NA NA C-10 October’11 3.07 -- TTU

5 UDL KPK-NMC 190/3A UP/RL 2.36 -- NA NA C-10 October’11 3.00 -- TTU

6 UDL DCOP-OYR 175/21A UP/RL 2.24 -- NA NA Portal

Upright

October’11 2.98 -- B-150

7 UDL UDL-RNG 188/2A DN/SL 2.30 -- NA NA C-10 October’11 2.88 -- TTU

8 UDL UDL-RNG 188/4A DN/SL 2.27 -- NA NA C-10 October’11 2.83 -- TTU

9 UDL RNG-NMC 195/14A DN/SL 2.31 2.20 NA NA C-10 October’11 3.26 -- TTU

10 UDL NMC-KPK 204/1A UP/RL 2.25 -- NA NA C-12 October’11 3.04 -- TTU

11 UDL RNG-NMC 193/18A DN/SL 2.12 2.17 NA NA C-12 October’11 2.80 -- B-150

12 UDL NMC-KPK 204/3A UP/RL 2.23 -- NA NA C-12 October’11 2.91 -- TTU

13 UDL UDL-RNG 190/9A UP/RL 2.31 -- NA NA C-12 October’11 3.00 -- TTU

14 UDL UDL-RNG 190/11A UP/RL 2.30 -- NA NA C-12 October’11 2.98 -- TTU

15 UDL UDL-RNG 188/28A DN/SL 2.34 -- NA NA C-10 October’11 2.98 -- TTU

16 UDL UDL-RNG 188/26A DN/SL 2.35 -- NA NA C-10 October’11 3.14 -- TTU

17 UDL UDL-RNG 188/20A DN/SL 2.36 -- NA NA C-10 October’11 2.90 -- TTU

Page 13: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

13

ANNEXURE -IV/II

CORPORATE RELIABILITY ACTION PLAN FOR TRD ASSETS TO IMPROVE PUNCTUALITY

Sl. No. Item Unit Total Qty. as on 1st

April of the current financial year

Target for current

financial year

Prop. Target up to the current

month

Completed during the Current month

completed during the current

financial year

Short fall w.r.t. prop.

Target

Balance Cause of shortfall

Action taken for completion of the balance work

1. Replacement of worn out contact wire Km 12 10 06 -- 2.870 (-) 3.13 09.130 --

2. AOH of OHE-DC TKM N.A. -- -- -- -- -- -- --

3. AOH of OHE-AC TKM 1335 1335 779 44.866 382.863 (-) 396.137 952.137 --

4. Section Insulator (checking) No. 691 536 313 15 106 (-) 207 585 --

5. Section Insulator (cleaning) No. 691 536 313 15 106 (-) 207 585 --

6. PTFE (Checking & Cleaning) (AF) No. 28 28 16 02 22 (+) 06 06 --

7. PTFE (Checking & Cleaning) (BB) No. N.A. -- -- -- -- -- -- --

8. Retenesioning of FTA No. 316 316 95 01 05 (-) 90 311 --

9. POH of Regulating Equipment No. 2273 2273 257 134 168 (-) 89 2105 --

10. AOH of Interrupter. No. 144 144 84 14 68 (-) 16 76 --

11. Adjustment of Cross over/Turn out No. 917 917 450 21 184 (-) 266 733 --

12. AOH of Isolator No. 415 415 193 16 110 (-) 83 305 --

13. AOH of Auxiliary Transformer No. 305 305 160 19 92 (-) 68 213 --

14. Provision of Hex. Tie Rod on ATD. No. 90 -- -- -- -- -- -- --

Page 14: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

14

ANNEXURE – IV/A AOH OF OHE

Progress in Nos. Progress in ETKM Sl.

No.

Item

Multiplying Factor

Total on line

Yearly target

During the

month

Cumulative up to

current month

Prop. Target

(-) Short fall (+) Excess

During the month

Cumulative up to current month

Prop. target

(-) Short fall

(+) Excess

1 AOH of OHE-DC(TKM) 1.40 Nil NIL -- -- -- -- -- -- -- --

2 AOH of OHE-AC (TKM)

1.00 1335 1335 44.866 382.863 779 (-) 396.137 44.866 382.863 779 (-) 396.137

3 Section Insulator (checking) [No.]

0.22 691 536 15 106 313 (-) 207 3.3 23.7 68.86 (-) 45.16

4 Section Insulator (cleaning) [No.]

0.16 691 536 15 106 313 (-) 207 2.4 16.96 50.08 (-) 33.12

5 (i) PTFE (Cleaning) (Arthur Flury)

0.38 28 28 02 22 16 (+) 06 0.76 7.68 6.08 (+) 01.60

5 (ii) PTFE (Cleaning) (Belfour Beaty)

0.38 Nil -- -- -- -- -- -- -- -- --

6 Retenesioning of FTA [ No.]

0.67 316 162 01 05 95 (-) 90 0.67 3.35 63.65 (-) 60.30

7 POH of Regulating Equipment [No.]

0.33 2273 440 134 168 257 (-) 89 11.56 55.78 84.81 (-) 29.03

8 AOH of Interrupter [No.]

0.16 144 134 14 68 84 (-) 16 2.24 11.88 13.44 (-) 02.56

9 Adjustment of Cross over/turnout [No.]

0.33 917 772 21 184 450 (-) 266 6.93 60.72 149.5 (-) 88.78

10 AOH of Isolator [No.]

0.22 415 331 16 110 193 (-) 83 3.52 24.2 42.46 (-) 18.26

11 AOH of Auxiliary Transformer [No.]

0.16 305 275 19 92 160 (-) 68 3.04 14.72 25.60 (-) 10.88

12 POH of Cantilever [No.]

0.66 24441 150 07 69 88 (-) 19 4.62 45.54 58.08 (-) 12.54

13 "G" jumper

0.30 860 860 25 228 502 (-) 274 7.5 68.40 150.60 (-) 82.20

TOTAL 91.406 714.693 1492.16 (-) 777.367

Page 15: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

15

ANNEXURE – IV/A/I

PROFORMA FOR MONITORING THE PROGRESS OF AOH OF OHE

ETKM (AOH) Sl.

No.

Division

Depot

RKM

TKM Annual Target

Prop. Target

Achievement during the month

Cumulative Progress

Shortfall (-) Excess (+)

1 Panagarh 60 278 419 244 15.947 118.589 (-) 125.411

2 Andal

31 423 760 443 06.146 63.875 (-) 379.125

3 Asansol 30 161 333 194 11.759 60.127 (-) 133.873

4 Barakar

39 122 183 107 11.058 101.646 (-) 05.354

5 Jamtara 44 126 190 111 13.957 96.042 (-) 14.958

6 Madhupur 37 112 148 86 10.031 108.725 (+) 22.725

7 Jasidih

58 113 154 90 11.038 112.304 (+) 22.304

8

ASANSOL

Total 299 1335 2187 1275 79.936 661.308 (-) 613.692

Page 16: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

16

ANNEXURE-IV/B

CLEANING OF PTFE NEUTRAL SECTION

Sl No.

Name of FP/SP

Location

Line

Last date of checking/ Cleaning

Remarks

146/2B DN Line-2 24.08.2011 Provided on 07.06.2009 (Arthur Flurry)

146/2C DN Line-1 04.04.2010 Provided on 11.06.2009 (Arthur Flurry)

146/1B UP Line-2 23.08.2011 Provided on 20.12.2009 (Arthur Flurry)

1.

MNAE/SP

145/27 UP Line-1 23.08.2011 Provided on 24.12.2009 (Arthur Flurry)

177/19 UP Line-1 14.06.2011 Replaced by Arthur flurry type on 21.03.2009

177/19A UP Line- 2 06.05.2011 Replaced by Arthur flurry type on 22.03.2009

178/6 DN Line-1 14.06.2011 Replaced by Arthur flurry type on 15.02.2005 2. OYR/FP

178/4A1 DN Line- 2 13.06.2011 Replaced by Arthur flurry type on 23.03.2009

203/332 UP Line-1 25.12.2010 Provided on 31.12.2003 (Arthur Flurry)

203/33A UP Line-2 27.01.2011 Provided on 29.12.2003 (Arthur Flurry)

203/34 1 DN Line-1 09.09.2010 Provided on 17.01.2004 (Arthur Flurry) 3. KPK/SP

203/34A1 DN Line-2 06.05.2010 Provided on 18.01.2004 (Arthur Flurry)

232/13 UP/GC 03.05.2011 Replaced by Arthur flurry type on 02.12.03 4. KMME/FP

232/18 DN/GC 25.06.2011 Replaced by Arthur flurry type on 17.04.2007

244/11 UP/GC 08.04.2010 Replaced by Arthur flurry type on 07.04.2007 5. KAO/SP

245/6 DN/GC 11.03.2011 Replaced by Arthur flurry type on 09.04.2007

235/41 UP/ML 28.06.2010 Provided on 10.09.2004 (Arthur Flurry) 6. CRJ/SP

235/42 DN/ML 11.05.2011 Provided on 11.10.2004 (Arthur Flurry)

250/19 UP/ML 15.03.2011 Replaced by Arthur flurry type on 05.04.2007 7. JMT/TSS

250/20 DN/ML 01.03.2011 Replaced by Arthur flurry type on 10.7.2004

281/25 UP/ML 03.04.2010 Provided on 10.03.2004 (Arthur Flurry) 8. JRW/SP

281/26 DN/ML 03.04.2010 Provided on 25.11.2004 (Arthur Flurry)

313/5 UP/ML 24.04.2011 Replaced by Arthur flurry type on 12.04.2007 9. SNQ/TSS

313/6 DN/ML 24.04.2011 Replaced by Arthur flurry type on 11.04.2007

335/23 UP/ML 14.09.2011 Provided on 19.12.2003 (Arthur Flurry) 10. LHB/SP

335/24 DN/ML 09.08.2011 Provided on 22.12.2003 (Arthur Flurry)

260/1 UP/GC 14.07.2011 Provided on 22.07.2007 (Arthur Flurry) 11. PKA/FP

260/2 DN/GC 17.07.2011 Provided on 25.07.2007 (Arthur Flurry)

Page 17: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

17

REPLACEMENT OF 9 TON INSULATOR BY TESTED 9 TON INSULATOR ANNEXURE –IV/D

LOCATION SECTION MAKE OF INSULATOR REPLACED BATCH OF INSULATOR REPLACED REPLACED BY – MAKE REPLACED BY- BATCH JB05/8N-9 BDME Line M-India 03/94 AESPL 2011

JB06/01 BDME Line M-India 10/94 AESPL 2011

338/36 TTN-LHB M-India 10/94 AESPL 2011

323/22 JSME-TTN M-India 03/94 AESPL 2010

352/8 STL-GHN M-India 10/94 GTSL 04/09

325/18 JSME-TTN M-India 03/94 AESPL 2011

325/24 JSME-TTN M-India 03/94 AESPL 2011

364/8 NRGO-JAJ M-India 10/94 MCPL 2011

170/53-57 DCOP-DGR WSI 03/89 Deccan 11/07

122/13-15 KAN-GLI M-India 03/88 Deccan 04/11

125/10 KAN-GLI BHEL 1987 MCPL 08/09

121/3-5 KAN-GLI WSI 03/89 Deccan 08/08

121/5-7 KAN-GLI WSI 03/89 Deccan 07/09

127/5 KAN-GLI M-India 07/04 Deccan 10/08

395/11 MUW-SNQ M-India 05/95 MCPL 11/07

295/5 MDP-MUW M-India 05/95 Deccan 2006

254/28 CAM-KAO -- -- Deccan 2008

251/21 KAO-CAM -- -- Deccan 07/09

180/21 OYR-UDL -- -- GTSL 2009

180/24A-26A OYR-UDL -- -- MCPL 04/09

ANNEXURE -IV/E REPLACEMENT OF FAILURE PRONE INSULATOR

Insulator replaced New insulator provided Sl No.

LOCATION

SECTION MAKE BATCH MAKE BATCH

NIL

Page 18: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

18

ANNEXURE -IV/F REPLACEMENT OF BROKEN/FLASHED OVER INSULATOR

1 360/28 STL-JAJ Bracket Insulator -- -- MCPL 2009

2 315/37 MUW-SNQ Bracket Insulator -- -- GIL 10/10

3 227/19 ULT-KMME Bracket Insulator -- -- MCPL 03/10

4 326/14 SNQ-JSME Bracket Insulator -- -- MCPL 2009

5 327/20 SNQ-JSME Bracket Insulator -- -- MCPL 2010

6 228/12 CRJ-SLS Bracket Insulator -- -- M-India 2004

7 360/34 STL-JAJ Bracket Insulator -- -- MCPL 2010

8 362/2 STL-JAJ Bracket Insulator -- -- MCPL 2010

9 362/12 STL-JAJ Bracket Insulator -- -- MCPL 2010

10 362/16 STL-JAJ Bracket Insulator -- -- MCPL 2010

11 289/5 JRW-VDS Bracket Insulator -- -- GIL 2010

12 363/10 STL-JAJ Bracket Insulator -- -- MCPL 2009

13 226/17 SLS-CRJ Bracket Insulator -- -- Deccan 10/10

14 225/43 SLS-CRJ Bracket Insulator -- -- Deccan 10/10

Insulator replaced New insulator provided Sl No. LOCATION

SECTION

Type of insulator (9-T, BKT, Stay) MAKE BATCH MAKE BATCH

1 231/28 SLS-CRJ 9-Ton Insulator -- -- Deccan 07/09

2 323/22 SNQ-JSME 9-Ton Insulator -- -- AESPL 2010

3 180/24A UDL-OYR 9-Ton Insulator -- -- MCPL 04/09

4 351/8 LHB-STL 9-Ton Insulator -- -- GTSL 04/09

5 325/18 LHB-JSME 9-Ton Insulator -- -- AESPL 2011

6 325/24 LHB-JSME 9-Ton Insulator -- -- AESPL 06/10

7 364/8 STL-JAJ 9-Ton Insulator -- -- MCPL 2011

8 305/11 SNQ-JSME 9-Ton Insulator -- -- MCPL 11/07

9 JB06/1 BDME Line 9-Ton Insulator -- -- AESPL 2011

10 JB05/8N-9 BDME Line 9-Ton Insulator -- -- AESPL 2011

11 125/10 GLI-KAN 9-Ton Insulator -- -- MCPL 04/09

12 125/10 KAN-GLI 9-Ton Insulator -- -- MCPL 08/09

13 224/30 STN-ULT 9-Ton Insulator -- -- Deccan

14 295/5 MDP-NPZ 9-Ton Insulator -- -- Deccan 2006

15 121/3-5 KAN-GLI 9-Ton Insulator -- -- Deccan 08/09

16 121/5-7 KAN-GLI 9-Ton Insulator -- -- Deccan 07/09

17 127/5 KAN-GLI 9-Ton Insulator -- -- Deccan 10/08

18 204/3A KPK-ASN 9-Ton Insulator -- -- Deccan 2007

19 160/25 PAN-RBH 9-Ton Insulator -- -- Deccan 04/11

20 121/3 KAN-GLI 9-Ton Insulator -- -- Deccan 04/10

21 231/15 SLS-RNPR 9-Ton Insulator -- -- MCPL 10/07

22 221M20-2L ASN-BCQ 9-Ton Insulator -- -- MCPL 2008

Page 19: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

19

15 327/17 SNQ-JSME Bracket Insulator -- --- MCPL 07/10

16 126/11 KAN-GLI Bracket Insulator -- -- Deccan 07/10

17 126/13 KAN-GLI Bracket Insulator -- --- Deccan 07/10

18 RNPR/1040 SLS-CRJ Bracket Insulator -- -- GIL 07/10

19 CLW/1/8 SLS-CRJ Bracket Insulator -- -- MCPL 2010

20 143/25A MNAE-PAJ Bracket Insulator -- -- Deccan 07/10

21 125/12 KAN-GLI Bracket Insulator -- -- Deccan 07/10

22 224/30 STN-ULT Bracket Insulator -- -- Deccan 10/08

23 181/18 UDL-OYR Bracket Insulator -- -- MCPl 08/09

24 295/31 MDP-NPZ Bracket Insulator -- -- GIL 07/10

25 289/3 JRW-MDP Bracket Insulator -- -- GIL 07/10

26 357/16 GHN-NRGO Bracket Insulator -- -- MCPL 2010

27 228/18 SLS-RNPR Bracket Insulator -- -- Deccan 07/10

28 358/30 GHN-NRGO Bracket Insulator -- -- MCPL 2010

29 358/32 GHN-NRGO Bracket Insulator -- -- MCPL 2010

30 250/16 BM-JMT Bracket Insulator -- -- Deccan 10/10

31 256/6 CRJ-JMT Bracket Insulator -- -- Deccan 10/10

32 286/24 MDP-MUW Bracket Insulator -- -- GIL 07/10

33 279/17 JRW-MDP Bracket Insulator -- -- M-India 10/10

34 151/30 MNAE-PAN Bracket Insulator -- -- Deccan 07/10

35 266/28 KEE-VDS Bracket Insulator -- -- BHEL 11/08

36 327/6 SNQ-JSME Bracket Insulator -- -- MCPL 2009

37 327/10 SNQ-JSME Bracket Insulator -- -- MCPL 10/10

38 240/28 JMT-CRJ Bracket Insulator -- -- GTSL 07/10

39 215/20A ASN-BCQ Bracket Insulator -- -- MCPL 2010

1 177/24A OYR-UDL Stay Insulator -- -- MCPL 06/08

2 170/60-62 OYR-DCOP Stay Insulator -- -- MCPL 2009

3 194/14A UDL-OYR Stay Insulator -- -- GTSL 04/09

4 220/7A BCQ-STN Stay Insulator -- -- MCPL 2007

5 136/12 PAJ-GLI Stay Insulator -- -- MCPL 10/08

6 361/8 STL-JAJ Stay Insulator MCPL 2010

7 362/4 STL-JAJ Stay Insulator -- -- MCPL 2010

8 362/16 STL-JAJ Stay Insulator -- --- MCPL 2010

9 319/11 SNQ-JSME Stay Insulator -- -- GTSL 05/08

10 315/3 SNQ-JSME Stay Insulator -- -- GTSL 05/08

11 JSME/1027 JSME Yard Stay Insulator -- -- MCPL 2010

12 JSME/1021 JSME Yard Stay Insulator -- -- MCPL 2009

13 174/26 OYR-DCOP Stay Insulator -- -- MCPL 2010

14 RNPR/1040 SLS-CRJ Stay Insulator -- --

Insulator replaced New insulator provided Sl No. LOCATION

SECTION

Type of insulator (9-T, BKT, Stay) MAKE BATCH MAKE BATCH

Page 20: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

20

15 CLW/1/8 SLS-CRJ Stay Insulator -- --

16 178/14 DCOP-OYR Stay Insulator -- -- MCPL 2009

17 131/18 UDL-OYR Stay Insulator -- -- BHEL 11/08

18 295/31 MDP-NPZ Stay Insulator -- -- MCPL 06/08

19 181/30 MNAE-PAN Stay Insulator -- -- BHEL 11/08

20 161/34 RBH-PAN Stay Insulator -- -- MCPL 04/10

SURVEY OF INSULATOR DURING AOH ANNEXURE -IV/G

9-Ton Stay Bracket Others

Numbers Numbers Numbers Numbers

AOH done in no. of

locations

Make Batch Porc. Compo

Make Batch Porc. Compo

Make Batch Porc. Compo

Type

Make Batch Porc. Compo

JB05/8N-9 2011 AESPL 04/09 01 AESPL 2008 01

JB06/01 2011 AESPL

338/36 2011 AESPL

323/22 2011 AESPL

325/18 2010 AESPL

325/24 04/09 AESPL

CGEC 1964 01 BHEL 10/87 02 BHEL 2008 05

Deccan 2007 04 BHEL 05/87 02 BHEL 01/87 01

Deccan 07/09 01 BHEL 12/86 02 BHEL 12/86 05

Deccan 2008 04 BHEL 12/87 01 CGEC 1963 31

Deccan 04/11 04 BHEL 11/08 01 CGEC 1959 114

Deccan 2007 11 BHEL 2008 14 CGEC 1964 24

IEC 09/02 01 Deccan 2007 10 Deccan 2007 19

IEC 07/03 02 Deccan 2009 06 Deccan 2009 13

IEC 05/03 01 Deccan 2006 08 Deccan 2006 02

JSI 06/92 01 CGEC 1963 29 IEC 03/08 01

JSI 07/92 02 CGEC 1961 01 IEC 11/04 02

JSI 03/94 05 GTSL 2010 01 IEC 11/05 04

JSI 04/93 03 GTSL 2008 26 GTSL 2010 02

JSI 05/94 01 GTSL 2007 06 GTSL 2006 12

JSI 07/94 01 GTSL 2009 12 GTSL 2007 06

JSI 08/94 01 GTSL 2006 08 GTSL 2008 05 JSI 05/92 02 IEC 10/08 11 GIL 03/10 02 JSI 06/94 02 IEC 11/08 08 GIL 2009 04 JSI 01/93 01 GIL 06/10 04 JSI 02/93 04

M-India 10/94 JSI 03/94 20 JSI 10/94 02 M-India 03/94 05 JSI 09/94 02 JSI 09/93 03

826 Nos.

M-India 01/01 01 JSI 04/92 03 JSI 03/96 11

Insulator replaced New insulator provided Sl No. LOCATION

SECTION

Type of insulator (9-T, BKT, Stay) MAKE BATCH MAKE BATCH

Page 21: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

21

9-Ton Stay Bracket Others

Number Number Number Number AOH done in no. of

locations

Make Batch Porc. Compo

Make Batch Porc. Compo

Make Batch

Type

Make Batch Porc. Compo

M-India 05/94 04 JSI 04/96 04 JSI 10/93 11 M-India 12/94 01 JSI 02/93 02 JSI 04/96 19 M-India 02/88 03 JSI 03/96 39 JSI 05/94 86 M-India 07/03 04 JSI 10/94 0134 JSI 06/94 32 M-india 07/00 01 JSI 06/94 52 JSI 04/94 90 M-india 04/95 14 JSI 05/94 54 JSI 11/94 02 M-india 08/05 01 JSI 04/94 64 JSI 02/93 23 M-india 03/95 11 JSI 06/94 23 JSI 02/94 11 M-india 12/95 02 JSI 02/96 03 JSI 05/92 28 M-india 10/94 12 JSI 09/93 30 JSI 06/92 03 M-india 01/95 01 JSI 05/93 02 JSI 03/94 83 M-india 09/01 02 JSI 08/93 01 JSI 04/92 02 M-india 03/08 01 JSI 10/99 01 JSI 08/89 02 GTSL 2008 08 JSI 03/93 03 JSI 03/95 02 GTSL 2010 01 JSI 10/93 187 JSI 03/92 01 GTSL 2006 01 JSI 01/94 01 JSI 02/95 02 MCPL 2007 02 JSI 03/94 65 JSI 01/94 05 MCPL 2009 04 JSI 02/94 07 JSI 09/93 01 MCPL 08/09 04 JSI 04/93 05 JSI 06/93 01 MCPL 04/09 02 JSI 06/93 03 JSI 03/93 49 W.Ger 05/82 01 M-India 06/08 01 JSI 12/93 01 W.Ger 1982 01 M-India 10/08 05 JSI 05/93 08 NGK 1978 02 M-india 04/88 03 MCPL 07/10 04

N 1959 01 M-india 04/00 02 MCPL 2009 02

WSI 1986 01 M-india 03/08 23 MCPL 2010 09

WSI 06/88 01 M-india 02/08 01 MCPL 2008 04

WSI 02/82 02 M-india 08/04 07 M-India 10/99 01

WSI 03/52 01 M-india 05/00 02 M-India 12/07 02 Portugal 1989 01 M-india 06/03 02 M-India 06/08 02

UT 1988 01 M-india 06/06 01 M-India 05/00 03 SIEM 1983 03 M-india 01/08 01 M-India 02/08 19

SIEM 12/87 01 M-india 04/08 05 M-India 03/99 02 SIL 07/76 01 M-india 07/00 01 M-India 01/99 07

AESPL 2010 04 M-india 09/06 04 M-India 11/99 02

M-india 07/08 02 M-India 08/03 09

M-india 02/98 01 M-India 11/09 01

M-India 09/07 05 M-India 07/08 02

Page 22: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

22

9-Ton Stay Bracket Others

Number Number Number Number AOH done in no. of

locations

Make Batch Porc. Compo

Make Batch Porc. Compo

Make Batch

Type

Make Batch Porc. Compo

M-India 09/05 02 M-India 03/08 35 M-India 09/00 01 M-India 07/00 02 M-India 02/07 02 M-India 08/08 01 M-India 01/00 03 M-India 08/02 01 M-India 09/08 01 M-india 09/06 02 M-India 11/08 05 M-india 01/00 06 M-India 06/00 12 M-india 11/04 05 M-India 01/09 01 M-india 05/06 03 M-India 10/94 01 M-india 12/98 20 M-India 11/00 01 M-india 09/09 01 M-India 07/03 04 M-india 11/04 01 M-India 01/07 09 M-india 08/08 01 M-India 07/08 04 M-india 07/03 03 MCPL 04/11 08 M-india 01/04 01

MCPL 2010 11 M-india 04/08 13

MCPL 2007 20 M-india 01/07 09 MCPL 2009 26 M-india 07/00 03 MCPL 02/08 07 M-india 12/04 01

NGK 1980 09 M-india 03/07 01

NGK 1988 08 WSI 02/83 01 N 1959 80 OKT 1963 08

NGK 1980 08 YU 1987 02 NGK 1979 02 SEP 1963 11

N 08/59 03 NGK 1986 02

WSI 12/88 02 NGK 1978 08

WSI 08/85 01 Portugal 09/79 01

N 10/59 14 Portugal 1989 02

N 11/59 01

N 07/59 01

Page 23: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

23

ATTENTION TO DEFECTS/DEFICIENCIES RECORDED BY NETRA CAR ANNEXURE -V

Category ‘A’ Stg>450 mm Category ‘B’ Stg <450mm and >350 mm Category ‘C’ Stg <350mm >300 mm Sl No. Section Total TKM run Total

location (as on 01.04.11)

Location attended during the month

Cumul attended

Balance Total location (as on

01.04.11)

Location attended during the month

Cumul attended

Balance Total location (as on

01.04.11)

Location attended during

the month

Cumul attended

Balance

NIL

TESTING DETAILS OF FEEDER PROTECTION RELAY ANNEXURE -VI

Type of Relay

Name of FP/TSS/GSS

CB No.

Date of Last testing

2010-11-12

Testing done during

current month

Testing done during current Financial Year

Balance

Cause of Non Testing

Action taken for testing

CB-01 -- -- -- -- OYR/FP

CB-02 -- -- -- --

Feeder circuit breakers with protective

relays were commissioned on 18.06.11

CB-03 -- -- -- -- KMME/FP

CB-04 -- -- -- --

Feeder circuit breakers with protective

relays were commissioned on 18.02.11

CB- 121 27.03.11 March’11 Nil -- Not due JMT/TSS

CB- 123 27.03.11 March’11 Nil -- Not due CB- 125 09.03.11 March’11 Nil -- Not due

Feeder Protection Relay

SNQ/TSS CB- 127 11.03.11 March’11 Nil -- Not due

Auto Reclose Relay Integrated with Feeder protection relay

CB-01 -- -- -- -- OYR/FP

CB-02 -- -- -- --

Feeder circuit breakers with protective

relays were commissioned on 18.06.11

CB-03 -- -- -- -- KMME/FP

CB-04 -- -- -- --

Feeder circuit breakers with protective

relays were commissioned on 18.02.11 CB- 121 27.03.11 March’11 Nil -- Not due

JMT/TSS CB- 123 27.03.11 March’11 Nil -- Not due

CB- 125 09.03.11 March’11 Nil -- Not due

Delta – I Relay

SNQ/TSS CB- 127 11.03.11 March’11 Nil -- Not due

Panto Flashover Relay Not required

Page 24: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

24

Annexure -VII MAINTENANCE PROGRESS OF OTHER OHE ITEMS

AVAILABILITY OF POWER BLOCK ANNEXURE -VIII

Power Block Granted OHE

Maintenance/ Construction

Depot

Power Block Demanded For Maintenance Work

Schedule ETKM done as per Annexure-IVA

Power Block Granted for other than Maintenance Work

Total Power Block Granted

Panagarh 87.00 hrs (maint) + 35.00 hrs. (Spl) 38 hrs 30 mts. 15.947 26 hrs 35 mts. 63 hrs 05 mts.

Andal 114.00 hrs (maint) + 40.00 hrs. ( Spl) 14 hrs 10 mts. 06.146 32 hrs 45 mts. 46 hrs 55 mts.

Asansol 104.00 hrs (Maint) + 25.00 hrs. (Spl) 19 hrs 50 mts. 11.759 22 hrs 45 mts. 42 hrs 35 mts.

Barakar 96.00 hrs.(maint) + 25.00 hrs. (Spl) 22 hrs 25 mts. 11.058 15 hrs 40 mts. 38 hrs 05 mts.

Jamtara 94.00 hrs. (maint) + 34.00 hrs. (Spl) 29 hrs 00 mts. 13.957 17 hrs 15 mts. 46 hrs 15 mts.

Madhupur 86.00 hrs (maint) + 35.00 hrs. (Spl) 23 hrs 35 mts. 10.031 22 hrs 00 mts. 45 hrs 35 mts.

Jasidih 93.00 hrs (maint) + 27.00 hrs. (Spl) 23 hrs 05 mts. 11.038 14 hrs 50 mts. 37 hrs 55 mts.

Construction 00.00 hrs (maint) + 24.00 hrs. (Spl) 00 hrs 00 mts -- 24 hrs 00 mts. 24 hrs 00 mts.

Total 674.00 hrs (maint) + 245.00 hrs. (Spl) 168 hrs 35 mts 79.936 175 hrs 50 mts. 344 hrs 25 mts.

Sl No Item Done during the month Cumulative during 2011-12

1. No. of turnouts (M/L) 04 65

2. No. of turnouts (Y/L) 16 77

3. No. of trees cut (Engg.) 12 477

4. No. of trees trimmed 207 1681

5. No. of tree branch trimmed 1817 20167

6. No. of kites / kite threads removed 14 64

7. No. of bird nest removed 80 1699

8. No. of Flashed / Broken insulator replaced. 77 511

(i) Checked 4064 21648 9. No. of muffs of OHE structure

(ii) Repaired 35 35

10. No. of Winch type ATD replaced by pulley type ATD. -- --

11. No. of special drive for joint panto checking by TRD and RSO/ RS staff. 19 MEMU + 38 Loco (133 Nos. Pantos) 144 MEMU + 192 Loco (1007 Nos. Pantos)

(i) Stay Insulator 832 6473

(ii) Bracket Insulator 831 6540

12. Identification of Insulators for various

Makes & Batches.

(iii) 9-Tonne Insulator 151 1144

13. Replacement of damaged droppers. 115 720

14. Replacement of corroded cantilever assembly. 07 486

Page 25: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

25

INTEGRATED BLOCK ANNEXURE VIII/A

Integrated Power Block Sl.

No. Date

Section

Demanded (Mts) Granted (Mts) % Granted

Work done

Attended by

Nil

INSPECTION DONE BY OFFICERS / SUPERVISORS ANNEXURE IX

Sr.DEE/TRD/ASN AEE/TRD/MDP AEE/TRD/ASN AEE/TRD/UDL SR. SUPERVISORS Sl No.

Item Quota Actual Quota Actual Quota Actual Quota Actual Quota Actual

1.1 OHE depots 01 -- 04 04 04 01 04 03 04 --

1.2 Tower Wagon inspections 01 02 03 -- 03 -- 03 01 04 62

1.3 Push trolley/motor trolley inspections 01 -- 02 -- 02 -- 02 -- 04 --

1.4 Inspections by Loco Cab 01 -- 02 -- 02 01 02 02+01* 02 22

1.5 Station inspection/Level X-ing gates 01 01 02 -- 02 01 02 02 04 32

1.6 Ambush checks of working gangs/TPC Once in

2 month 01 01 -- 01 -- 01 01 02 16

1.7 Current collection test Once in

6 month -- Once in

2 month -- Once in

2 month -- Once in

2 month -- Once in

2 month 01

1.8 PSI depots 01 -- 04 -- 04 01 04 -- -- --

1.9 Traction Sub-Station 01 -- 02 01 02 -- 02 -- 04 04

1.11 Switching Stations 01 02 03 -- 03 02 03 02 04 12

1.12 Grid Sub-Station 2 in a

year

01 02 -- 02 01 02 -- 01 04

1.13 Remote Control centre Once in

6 month -- Once in

2 month -- Once in

2 month -- Once in

2 month -- 01 01

1.14 Office inspection 01 -- 01 -- 01 -- 01 01 01 --

2.00 Foot Pattrolling -- -- -- -- -- 01 -- 01 -- 28

* including 01 No. Night foot plate inspection.

INSPECTION CARRIED OUT BY DIVISIONAL OFFICERS DURING THE MONTH ANNEXURE –IX/1

No of inspections during the month

No of inspections during the year Sl No.

Division

Due Done Prop. Due up to the month Done up to the month Arrear

Remarks

1 Asansol 48 34 336 315 21

Page 26: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

26

FAILURE OF REMOTE CONTROL SYSTEM /SCADA ANNEXURE –X/A

Date & time of failure Date & time of Rectification Sl No

Switching Post Date Time ( hrs.) Date Time (hrs.)

Duration in minutes.

Type of failure

Responsibility

01 LHB/SP 10.10.11 14:35 10.01.11 21.45 430 BM-239 not executed from RCC/ASN RC

02 KAO/SP 11.10.11 16:34 11.10.11 18:05 91 Post out due to modem card not working. RC

FAILURE OF COMMUNICATION ANNEXURE –X /B

Date & time of failure Date & time of Rectification Sl No

Switching Post

Date Time (hrs.) Date Time (hrs.)

Duration in minutes.

Type of failure Responsibility

Nil

GRID WISE ENERGY CONSUMPTION ( MONTH :AUGUST ’’’111111 ) ANNEXURE –XIA

Name of GSS/TSS

Contract Demand (MVA)

Recorded Maximum demand (MVA)

Energy consumption (KWH)

Status of Capacitor Bank

Power Factor

Remarks

DTPS/GSS 25.00 23.062 7236000 OK 0.90 -- KMME/GSS 20.50 17.168 5920000 OK 0.94 --

JMT/TSS 12.00 11.305 2368813 OK 0.969 --

SNQ/TSS 14.00 10.620 2806380 OK 0.876 --

TOTAL ENERGY CONSUMPTION VIS-À-VIS GTKM ANNEXURE- XIB

Energy Consumption (KWH) Month

2010-11 2011-2012

Excess (+) Saving (-)

Variation (%) Variation in GTKM (10-11 over 09-10)

(%)

October’11 17724041 18331193 607152 03.42 -- PENALTIES PAID TO SUPPLY AUTHORITY ANNEXURE –XII

Penalty Paid Name of GSS/TSS

Low Power factor

Exceeding Contract

Demand Minimum Guaranteed

Energy

Cause

Action taken

Nil

Page 27: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

27

STAFF POSITION AND VACANCY ANNEXURE –XIII/A

E. SUPERVISOR Sl No Category Pay Band (`) Grade Pay (`) Sanctioned On Roll Vacancy Remarks 1. Sr. Section Engg. 9300-34800/- 4600/- 33 30 03

2. Junior Engg. Gr.-I 9300-34800/- 4200/- 27 24 03

3. Junior Engg./Drg. 9300-34800/- 4200/- 01 01 --

TOTAL 61 55 06

B. TECHNICIAN

Sl No Category Pay Band (`) Grade Pay (`) Sanctioned On Roll Vacancy Remarks 8. MCM/Sr.Tech(TW Driver) 9300-34800/- 4200/- 01 01 Nil

9. TW Driver-I 5200-20200/- 2800/- 22 18 04

10. TW Driver-II 5200-20200/- 2400/- 00 01 +01

12. MT Driver-I 5200-20200/- 2800/- 02 00 02

13. MT Driver-II 5200-20200/- 2400/- 02 03 (+) 01

14. MT Driver-III 5200-20200/- 1900/- 02 05 (+) 03

15. Sr.Tech 9300-34800/- 4200/- 22 18 04

16. Tech-I 5200-20200/- 2800/- 113 101 12

17. Tech-II 5200-20200/- 2400/- 68 61 07

18. Tech-III 5200-20200/- 1900/- 59 48 11

Crane Driver-III 5200-20200/- 1900/- 01(wc) 01(wc) --

TOTAL 291+01(wc) 256+01(wc) 35

C. GROUP-‘D’

Sl No Category Pay Band (`) Grade Pay (`) Sanctioned On Roll Vacancy Remarks 32. Helper-I 5200-20200/- 1800/- 99 55 44

34. Helper-II 5200-20200/- 1800/- 12 46 (+) 34

35. Substitute 5200-20200/- 1800/- -- 00 (+) 01

36. Chowkidar 5200-20200/- 1800/- 18 15 03

37. Hd. T/Man -- -- -- -- --

38. T/Man -- -- -- -- --

37. Sr. MCP -- -- -- -- --

38. MCP -- -- -- -- --

39. Sweeper -- -- -- --

TOTAL 129 116 13

Page 28: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

28

D. MINISTRIAL & DRAWING

+Sl No Category Pay Band (`) Grade Pay (`) Sanctioned On Roll Vacancy Remarks 40. Ministerial -- -- 22 21 01

41. Draftsman -- -- -- -- Nil

42. Steno -- -- 01 01 Nil

43. Gr. ‘D’ Staff (Office) -- -- 03 03 Nil

TOTAL 26 25 01

SUMMARY OF STAFF POSITION AND VACANCY

Sl No Category Sanctioned Strength Man on Roll Vacancy 1 A 61 55 06

2 B 291+01(wc) 256+01(wc) 35

3 C 129 116 13

4 D 26 25 01

TOTAL 507+01 (wc) 452+01 (wc) 55

STAFF TRAINING DURING 2010-11 ANNEXURE –XIII/B

Traction Distribution Course Categories Total No. of staff

Completed during the month

Total completed

Remarks

Supervisor -- -- 01 --

Artisan -- -- 03 -- Initial

Unskilled -- 03 13 --

Supervisor 54 -- 01 -- Refresher

Artisan 228 07 16 --

Supervisor 54 -- -- --

Artisan 228 -- -- -- Special

T/W Driver -- -- 01 --

AICTC, Chakradharpur,

South Eastern Railway

Total 312 05 25 --

Supervisor 54 01 09 --

Artisan -- -- -- -- CETI, Thakurli,

Central Railway Total 54 -- 08 --

Tower Wagon Driver (promotional) -- -- 02 -- ZRTI, Bhuli,

Eastern Railway Tower Wagon Driver (refresher) 20 01 02 --

Disester management -- --

Page 29: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

29

Annexure –XIV

FINANCIAL MANAGEMENT (ALLOTMENT AND EXPENDITURE AGAINST VARIOUS DEMANDS) DEMAND 7-100 ( Fig. In `̀̀̀ Thousand)

Particulars Primary Units Spending limit (2011-12) Proportionate grant up to August’ 11 Expenditure incurred up to August’11 Salary 01 7856 3273 4998

DA 02 4646 1936 2613

PLB 03 315 131 --

HRA 04 775 323 520

CCA 05 -- -- --

Interim Relief 06 -- -- --

Conveyance Allowance 07 557 232 319

KM-Allowance 10 -- -- --

OT 11 51 21 28

NDA 12 108 45 69

Other Allowance 13 101 42 30

Fees & Honourium 14 -- -- --

Transfer Allowance 15 -- -- 37

TA 16 377 157 145

Leave encashment 20 42 18 26

Children education 25 -- -- --

Office expences 18-24 967 403 593

TOTAL 15795 6581 9377 DEMAND 7-400 ( Fig. In `̀̀̀ Thousand)

Particulars Primary Units Spending limit (2011-12) Proportionate grant up to August’11 Expenditure incurred up to August’11

Salary 01 57076 23781 21053

DA 02 29502 12293 11051

PLB 03 3103 1293 09

HRA 04 4469 1862 1581

CCA 05 -- -- --

Interim Relief 06 -- -- --

Conveyance Allowance 07 4700 1958 1776

KM- Allowance 10 1292 538 559

OT 11 1941 809 626

NDA 12 1933 805 783

Other Allowance 13 90 805 275

Fees & honourium 14 -- 38 --

Transfer Allowance 15 404 -- 72

TA 16 2064 168 1508

Leave encashment 20 161 860 --

Office expences 18-24 -- 67 38

Children education 25 -- --

Page 30: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

30

Particulars Primary Units Spending limit (2011-12) Proportionate grant up to August’11 Expenditure incurred up to August’11 Stock material 27 10629 4429 13760

Non stock material 28 6279 2616 1481

Contractual payment 32 11278 4699 1011

Transfer Dr./Cr. 33 2726 1136 184

Sale Tax 38 -- -- --

TOTAL 137627 58157 55768 --

DEMAND No. – 10 (Fig. In `̀̀̀ Thousand)

Primary Units Spending limit (2011-12) Proportionate grant up August’11 Expenditure incurred up to August’11 32 1113494 463956 416849

DEMAND 08E611 (Fig. In `̀̀̀ Thousand)

Particulars Primary Units Spending limit (2011-12) Proportionate grant up to August’11 Expenditure incurred up to August’11 Salary 01 5263 2193 223

DA 02 3000 1250 127

PLB 03 300 125 --

HRA 04 250 104 29

CCA 05 -- -- --

Conveyance Allowance 07 40 17 09

OT 11 10 04 --

NDA 12 65 27 --

Other Allowance 13 109 45 06

Transfer Allowance 15 -- -- --

TA 16 200 83 09

Leave encashment 20 214 89 --

Children education 25 -- -- --

Total 9451 3937 404

DEMAND 03-700 ( Fig. In `̀̀̀ Thousand)

Particulars Primary Units Spending limit ( 2011-12) Proportionate grant up to August’11 Expenditure incurred up to August’11 Salary 01 5705 2377 1527

DA 02 3251 1355 773

PLB 03 -- -- --

HRA 04 585 244 125

CCA 05 -- -- --

Conveyance Allowance 07 463 193 94

OT 11 -- -- --

NDA 12 -- -- --

Other Allowance 13 62 26 02

14 50 21 --

Page 31: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

31

Particulars Primary Units Spending limit ( 2011-12) Proportionate grant up to August’11 Expenditure incurred up to August’11 Transfer Allowance 15 26 11 --

TA 16 117 49 34

Leave encashment 20 40 17 --

Children education 25 -- -- --

Office Contigency 18-24 60 25 --

Total 10359 4318 2556 Annexure –XV/1

PROGRESS OF COMPLETION REPORT OF SANCTIONED PINK BOOK WORKS

Pink Book / 11-12

PH-16 PH-17 PH-29 PH-36 PH-42 PH-52 PH-53 PH-64 Total No. of works

Work-in-progress -- -- -- 05 -- -- -- -- 05

New Works (10-11) -- -- -- -- -- -- -- -- --

WORKS COMPLETED

Month Sl.No. Description of work P.B. ref. Works ref. (Plan Head) March’11 -- -- -- --

Annexure –XV/I1

PROGRESS OF COMPLETION REPORT OF SANCTIONED LAW BOOK WORKS

Law Book / 11-12 PH-16 PH-17 PH-29 PH-36 PH-42 PH-52 PH-53 PH-64 Total No. of works Work-in-progress 01 -- -- 17 -- -- -- -- 18

New Works (11-12) 01 -- -- 02 -- -- -- -- 03

WORKS COMPLETED

Month Sl.No. Description of work L.B. ref. Works ref. (Plan Head) March’11 -- -- -- --

Page 32: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

32

ANNEXURE –XV/A

Progress of Sanction Works above 1 Cr. (Under Pink Book & LAW Book Pt..-I) (Figures in `̀̀̀ 1000/-)

Sl. No

Yr. O

f San

ction

Item

No. of

curren

t yr

. Name of works

Current Cost / Allocation

Exp. Upto last financial

Yr. 2010-11

Outlay for

current Fin. Yr.

Exp. Upto

current month during current Fin.Yr. 2011-12

Fund required during current Fin. Yr.

Fund required in next Fin. Yr.

Plan App.

( Y/N

)

Date of Sanctionin

g of detailed estimate

Ten

der

open

ing date

LOA date

Tar

get da

te

% Fin. Prog

% Phy. Prog.

Progress of work

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 1 07-08 PB No.

507 of

11-12

Khana – Pradhankhunta –

Replacement of corroded

Cantilever Assemblies. Phase-

III. (1750 Nos)

35021

DRF 31332 1000 0 1500 2956 NA 0 24.08.07 10.01.08 31.03.12 89.48

%

60 % All materials received &

1615 Nos. cantilever

assemblies replaced

2 09-10 PB No.

516 of

11-12

Replacement of mast at critical

implantation (Phase-VI). (300

Nos)

82253

DRF

1548 10000 2244 18000 60000 NA 15.09.09 22.01.10 -- 31.07.12 3.98 % 5 %

Tender finalised and

LOA issued on 30.06.10

against M/s Master

Engineering Concern,

Asansol. 47 Nos foundation

casting completed.

3 10-11 PB No.

528 of 11-12

KAN-PKA- Replacement of

cntilever assemblies (Phase-IV) (2000 Nos.)

37043

DRF

0 5000 0 5000 20000 -- 29.04.11 20.09.11 19.08.12 -- -- Estimate sanctioned.

Requisition sent to HQ on

06.01.11. TCM under process

4 10-11 PB No.

529 of

11-12

Asansol Division-Replacement

of catenery wire (40 km) 19656

DRF

0 5000 38 19000 656 -- -- -- -- -- -- Estimate sanctioned. Reqn.

Sent to HQ on 15.02.11.

5 06-07 LB No.

996

Replacement of Mast at critical

implantation PH-IV

(117 Nos)

21961

DRF (LOA

cost:

19044)

17028 100 03 2772 650 -- 0 27.07.06 04.07.07 Completed

89.42

%

80 % 119 Nos. critically

implanted masts already

removed. Work physically completed.

6 07-08 PB No.

508 of

11-12

Asansol Division-

Replacement of Mast at critical

Implantation.

Phase –V (143 Nos.).

25342

DRF

20298 2995 1856 2400 2000 -- 0 24.08.07 06.03.08 31.12.11 80.10 % 55 % Material received. 103 nos

critically implanted masts

also removed.

7 09-10 LB No.

993 of

11-12

Replacement of leaning portals

in KAN-UDL section of ASN

Division (29 Nos).

18350

DRF

623 200 383 6000 11727 -- 04.09.09 22.01.10 30.06.10 31.07.12 5.48

%

5% LOA issued against M/s

Master Engineering Concern,

Asansol.

8 08-09 LB No.

992 of

11-12

Replacement of old and

overaged failure prone

catenary wire in industrially

polluted area. (Reqn. No.

351050179 dt. 30.07.08)

(20 Km).

12912

DRF

10785 838 170 1430 1338 0 08.07.08 16.10.08 28.01.09 Complete 83.89 % 60 % i) 5391 Mtr Catenary wire

replaced in 2008-09 & 14543

Mtrs replaced in 2009-10.

ii) Material received on

04.08.10. iii) 1st on A/cs bill passed on

12.04.10.

Page 33: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

33

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 9 08-09 LB No.

1008 of

11-12

Replacement of failure prone –

underground cable between

Durgapur Thermal Power

Station & Waria/FP.

(Reqn. No. 351050225 dt.

13.11.08 for 1850 Mtrs HT

cable)

9221

DRF

9162 58 15 15 1500 -- 0 25.03.09 18.12.09 31.07.11 99.52

%

40% 1843 Mtrs HT cable received

from M/s Hindusthan Vidyut

Products Ltd, New Delhi on

12.01.10.

ii) Cable laying completed.

Feeder-2 connection

completed. Cable fault during

process on.

ANNEXURE –XV/B Progress of Sanction Works below 1 Cr. (Under LAW Book Pt.-II) (Figures in ` ` ` ` 1000/-)

Sl

No

Item

No. of

Current

Yr.

Name of works Qty Year

Sanc.

Current cost/

Allocation

Exp

upto

last

Fin.

Yr.

2010-

11

Outlay

for

current

Fin.

Yr.

Exp up to

current

month

during

current

Fin. Yr.

2011-12

Fund

required

during

current

Fin. Yr

Fund

required

during

nextFin

Yr

Target

date

%

Fin.

Prog

%

phy.

Prog

Progress of work

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 1 LB No.

995 of

11-12

Replacement of Steel

Anticreep by copper

Catenary wire.

(Requisition no. 351050117

dtd.30.06.06)

8.5 km 06-07 1801

DRF 47 1454 0 100 1754 -- 2.60% 25 % i) Total 15 Nos. damaged steel

anticreep wire replaced with

conventional copper catenery

wire during 09-10.

ii) P.O has been issued. 2 LB No.

994 of

11-12

Provision of 2nd CB with

associated equipments at

SNQ/TSS and provision of

DP isolator at JSME/SSP

-- 06-07 3374

DF3

2980 394 0 394 0 31.07.11 88.38 % 55 % CB, LA, CT all erection work

completed and commissioned at

SNQ/TSS. DP isolator at

JSME/SSP has been ereceted.

3 LB No.

1001 of

11-12

Raising of muffing of OHE

structures in KAN-PKA

Section.

1800 Nos 07-08 1725

DF3

643 1038 0 1 0 31.07.11 37.27 % 35 % Tender opened on 13.12.07. LOA

issued on 21.04.08.

567 Nos. muffing have been

completed. 1st on A/c bill passed.

4 LB No.

1007 of

11-12

Provision of new SP at

Sitarampur

01 No 08-09 3319

DF3

1238 150 02 150 1931 31.03.12 37.33% 25% Tender opened on 16.01.09. LOA

issued on 20.08.09. 1st on A/c bill

passed. All material received.

5 LB No.

1009 of

11-12

Provision of circuit

breakers at Kumardhubi &

Waria feeding posts to

enhance the reliability of

power supply

-- 08-09 7092

DRF

4366 1706 05 2726 0 31.07.11 61.56% 30% All equipments erected. Work

completed at KMME/FP. All

erection completed at OYR/FP.

Testing due. Circuit breaker have

been commissioned at KMME & OYR/FP.

6 LB No.

1010 of

11-12

ASN Divn-Shifting of mast

below 4.75mtrs at Platform

area in ASN division.

30 Nos 09-10 6041

DRF

28 200 129 2000 4013 31.07.12 2.58 % 5 % LOA issued on 30.06.10 against

M/s Master Engineering

Concern, Asansol. 03 nos. mast

and 04 nos. dwarf mast

foundation completed.

Page 34: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

34

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

7 LB No.

1011 of

11-12

ASN Divn-Replacement of

failure prone underground

cable between DTPS-

OYR/FP in phase-II Reqn

No. 351050030 dt. 03.11.09.

1850

Mtrs

09-10 9925

DRF

22 200 0 8695 1208 31.12.11 0.22 % 5 % i) Tender opened on 17.12.09.

LOA issued on 20.05.10 against

M/s Sabitri Enterprises, Asansol.

ii) Retender under process.

8 LB No.

1013

ASN Divn-Replacement of

existing old SCADA system

of STN-JAJ section by new

at Remote Control Centre at

Asansol

14 Nos 09-10 9875

DRF

8133 200 322 420 0 Completed 85.62 % 25 % Tender opened on 17.12.09.

LOA issued on 31.03.10.

9 LB No.

1014

Replacement of broken

insulators by composite

insulators in polluted/

vandalism prone areas. (Reqn

No. 351050035 dt. 19.11.09).

Stay

(1200)

Bkt (6000)

09-10 5432

DRF

46 200 3659 5000 386 2011-12 68.20 % 5% i)Tender opened on 23.12.10.

Briefing note under process.

ii) P.O has been issued for

stores.

10 LB No.

1006 of

11-12

Renovation of Burried Rail

and earth pit of TSS/FP at

JMT, SNQ.OYR & KMME.

-- 09-10 3535

DF3

1039 164 02 2496 0 Completed 29.44% 25 % Tender opened on 16.01.09.

LOA issued on 20.08.09.

Work physically completed..

1st on A/c bill passed.

11 LB No.

1012 of

11-12

ASN Divn-Supply of drop

out fuse unit complete set

with solid core pedestal

insulators (Rating-25 KV)

90 Nos 09-10 3508

DF3

2485 100 0 100 923 31.12.11 70.83% 25% 10 nos DO fuse have been

already been erected.

12 LB No.

23

STN-Provision of OHE on

pre-weighment line No.2 to

yard lines with full wiring

of yard line No.11

-- 09-10 5105

DF3

1466 750 394 3639 0 31.07.11 36.48 % 100 % Tender opened on 24.12.09. LOA

issued on 07.04.10. Work

physically completed.

13 LB No.

1016 of

11-12

POH of Traction Transformer

at JMT/TSS.

02 Nos 10-11 7860

DF 0 100 0 100 7760 -- 0% 0% Estimate vetted by Sr.DFM/ASN

and sanction is under process.

14 LB No.

1017 Restoration of damage

/deficient traction bonds

10-11 8858

DRF

0 100 0 7000 1858 -- 0% 0% Estimate sanctioned on 07.12.10

& requisition is on process.

Vetted copy sent to HQ on

12.01.11.

15 LB No.

1019

Conversion of cross type

OHE to Overlap type OHE

for running at 140 Kmph in

ASN Divn.

10-11 9802

DF-3

0 100 0 1500 8302 -- -- -- Original estimate vetted &

sanctioned on 03.03.11 and

revised estimate vetted. Tender

will be opened on 01.12.11.

16 LB No.

132

Provision of full OHE of line

no. 8, 9, 11 at receiving yard

at Andal

10-11 9743

DF-3

0 2000 0 500 9243 -- -- -- Tender open on 25.10.11 and

briefing note sent to A/Cs on

31.10.11.

Page 35: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

35

PROGRESS OF M&P ANNEXURE –XV/C (Figures in ` 1000/-

PROGRESS OF RSP ANNEXURE –XV/D

(Figures in `̀̀̀ 1000/-)

Annexure –XV/E

MONTHLY AND CUMULATIVE EXPENDITURE UNDER VARIOUS PLAN HEADS FOR THE YEAR 2010-11

(Figures in thousand of `̀̀̀ ) PH-16 PH-29 PH-36 PH-41 PH-42 PH-52 PH-53 PH-64 Total

Budget allotment for 2010-11

Actual expenditure 1171 -- 49517 1636 -- -- -- -- 52324

For 0 -- -- -- -- -- -- -- -- April ’11 Upto 0 -- -- -- -- -- -- -- --

For 0 -- 0 0 -- -- -- -- 0 May’11 Upto 0 -- 0 0 -- -- -- -- 0

For 0 -- 0 0 -- -- -- -- 0 June’11 Upto 293 -- 337 0 -- -- -- -- 630

For 101 -- 5960 0 -- -- -- -- 6061 July’11 Upto 394 -- 6297 0 -- -- -- -- 6691

For 0 -- 2028 0 -- -- -- -- 2028 August’11 Upto 394 -- 8325 0 -- -- -- -- 8719

For 0 -- 157 0 -- -- -- -- 157 September’11 Upto 394 -- 8482 0 -- -- -- -- 8876

For 0 -- 346 0 -- -- -- -- 346 October’11 Upto 394 -- 8828 0 -- -- -- -- 9222

Sl.

No Description of works Qty Year

Sanction/

Item No.

Unit Book Item

No of

11-12

Alloc. Sanction

cost

Expn.

Upto last

financial

year

OA/

Current

year

Expn.

During

curren

financial

year

Fund

required

during

current

Fin. Yr

Fund

required

during

next Fin

Yr

Present status

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

01 On line leakage current monitor

for Lightning Arrester.

(Reqn No. 351050180)

01 08-09

(LS)

No. LB 1836 DF3 1428 694 744 0 3 0 P.O No. 08.08.6359.1.41370 dt.

18.06.09 against M/s SCOPE

T&M Pvt. Ltd., Mumbai.

Material has been received.

Sl.

No

Description of works Qty Year

Sanction/

Item No.

Unit Book Item

No of

Current

Yr.

Alloc. Sanction

cost

Expn.

Upto last

financial

year

OA/

Current

year

Expn.

During

curren

financial

year

Fund required

during current

Fin. Yr

Fund

required

during next

Fin Yr

Present status

01 Supply, erection, testing and

commissioning of Diesel Hydraulic

Rail Crane on suitable Railway

Wagon.

10-11 No. LB 1707 4922 0 01 0 1 4921 Estimate is under

preparation.

Page 36: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

36

STORE PURCHASE ITEMS AGAINST SANCTIONED ESTIMATE ANNEXURE –XVI

Sl No

Name of sanctioned work

Estimate No. Description of Material Unit Quantity Total cost (in `̀̀̀)

Requisition No & date

COS Case No.

Remarks

1 Electrification of extension of shunting neck (250 M)

at UDL UP Yard and UDL Yard modification.

Estt. No. 29 TRD/ASN/05-06 &

22/TRD/ ASN/ 05-06.

Copper catenary wire (65 sq. mm) Size-19/2.1 mm.

m 2400 4,64,568/- 351050089 dt. 03.03.06.

15.06.6264

P.O. has been issued.

2 Electrification of LPG

siding at DGR & ASN

Division-TTR-27 set.

52/TRD/ASN/05-06

25/REV/TRD/ASN/

05-06

Copper catenery wire (65 Sq.mm)

Size-19/2.1 mm.

km 2.3 4,45050/- 3510500103

dt. 23.03.06

15.06.6383

P.O No. 16.10.6030.1.41695 dt.09.11.10.

3 Electrification of FSD

siding at DGR. & Replace

ment of Girder of Bridge

no. 509 in M/L section of

ASN Division.

51/TRD/ASN/05-06

&

40/TRD/ASN/05-06.

Cadmium copper catenery wire (65

sq. mm) size-19/2.1 mm.

km. 2.3 4,45,211/- 351050108

dt. 25.05.06

15.06.6382

club with

reqn. No.

351050103

dt. 23.03.06.

P.O. has been issued. P.O. No.

16.10.6030.1.41695 dt.09.11.10

54 Raising of Rail level

platform at DGR, RNG, JSME, CRJ, MDP &

Extension of platform at

PAN, MNAE, RNG &

OYR.

70/2nd Rev/TRD/C/

ASN/05-06 & 71/2nd Rev/ TRD/C/

ASN/05-06

Galvanised TTC/ Portal/Rolled/

Febricated Traction Mast.

MT. 19 MT for

reqn. No. 351050002

& 08 MT

for

351050010

15,02,874/- 351050002

dt. 04.03.10 &

351050010

dt. 26.06.10

vice Requn No.

351050106

dt. 05.04.06.

15.06.6433 After TR the case sent to COS/KKK

by CEE/KKK on 19.09.11. Final

TCM is under process.

5 i) ASN Divn. –

Replacement of steel

anticreep by Cu atenary

wire.

ii) Electrification of DD

line and shunting neck

with top wiring at RNG.

iii) Electrification of

Chunch colliery siding at

KMME, Damaguria

siding at JMT & SCOB

siding at Hirapur.

Club Estt. No.

16, 17, 18/

TRD/ASN/06-

07,

38/TRD/C/05-06

& 32/TRD/ASN/

06-07

Cadmium copper catenary

wire

(65 Sq.mm).

km 13.8 26,13,195/- 351050117

dt.

30.06.06.

15.06.6411

P.O. has been issued. P.O. No.

16.10.6030.1.41695 dt.09.11.10.

6 Electrifcation of chunch

at Kumardubi,

Mugma colliery &

Burnco (BCME) siding

at Hirapur.

Estt.No.41, 42

& 43/Rev/TRD/

ASN/06-07.

Cadmium copper catenary

wire

(65 Sq.mm)

km 5000 967850/- 351050142

dt.

18.10.06.

15.07.6020

Requisition not traceable at

HQ/KKK vide CEE/KKK’s letter

No. dt. 16.03.10.

7 STN-Provision of top

wiring at HWH end of

L/No. 22 to 24 at UDL

top wire of L/No. 7 at

KLK end at DN Dep.

Yard.

Estt.No.

28/TRD/ASN/06

-07.

25 KV AC Copper cadmium

catenary wire 19/2.10 mm.

km 0.9 174213/- 351050133

dt.

22.09.06.

15.07.6157 P.O. has been issued. P.O. No.

16.10.6030.1.41695 dt.09.11.10.

Page 37: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

37

Sl No

Name of sanctioned work

Estimate No. Description of Material Unit Quantity

Total cost (in `̀̀̀)

Requisition No & date

COS Case No.

Remarks

8 Electrification of

Departure Line No. 3 in

UP Departure yard at

UDL setion.

Estt.No.

Club. Estt. No.

54/TRD/ASN/

05-06.

Galvanized TTC structure

complete with 8 mtrs.

Boom with fastner.

MT. 5.5 306141/- 351050159

dt. 11.12.07.

16.09.6024

Main case No.

16.08.0163

After TR the case sent to COS/KKK

by CEE/KKK on 19.09.11.Final

TCM is under process.

9 Replacement of old and

overaged failure prone

catenery wire in industrial

polluted area 20KM

Estt No.

12/TRD/ASN/08-09

Hard drawn round copper wire

(5mm) dia small dropper wire

confirming to IS-282,1982

Make: RDSO / CORE/Appvd

source.

kg 3000 1143000/- 351050186

dt. 11.08.08

16.08.6098

Main case

No.

16.08.0117

P.O has been -ssued vide P.O No.

16.09.1606.1.41620 dt. 11.10.10

against M/s Surender Palimer,

Bikaner, Rajasthan.

10 Replacement of old and

overaged failure prone

catenery wire in industrial

polluted area 20KM

Estt No.

12/TRD/ASN/08-09

Contact wire splice (tooth

type) complete confirming to

RDSO Spn No.

ETI/OHE/P/1080 of 1081-1

Mod-C.

Nos. 400 435868 /- 351050204

dt. 14.08.08

16.08.6110

Main case

no.

16.08.0077

P.O has been issued against M/s

Eastern Works/KKK. P.O No.

16.08.6095.1.41774 dt. 13.12.10.

11 Replacememt of failure

prone under ground cable

between DTPS-OYR/FP

Estt. No.

36/TRD/ASN/09-10 Single Core 800/1000 Sq.

mm. Copper conductor,

XLPE insulated.

km 1850 86,95,000 /- 351050030

dt.03.11.09.

08.10.6021 TR done & under negotiation to

lowest offerer.

12 i) Replacement of leaning

Portals at KAN-UDL

section in Asansol Division.

ii) Shiftting of mast below

4.75 M at Platfrom.

iii) Replacement of mast at

critical implantation.

Estt. No. 16/TRD/

ASN/09-10

Estt. No. 38/TRD/

ASN/09-10

Estt. No. 37/TRD/

ASN/09-10

25 KV Composite 9 –

Tonne insulator.

Nos. 280 9,66,000 /- 351050021

dt.08.10.09

16.10.6014

Clubbing

T.C NO.

16.09.0177

TCM is under finalisation. P.O is

under A/Cs vetting.

13 Provision/on pre-

weighment line No. 2 yard

lines with full wiring of

yard line No. 2.

Estt. No. 41/TRD/

ASN/09-10 Hard drawn dropper

contact wire

m 1900 7,12,500/- 351050026

dt.03.11.09 16.10.6022

Main case

no.

16.09.0114

P.O. issued. P.O will be released on

30 % of opposition basis after issue

of main P.O.

14 Provision/on pre-

weighment line No. 2 yard

lines with full wiring of

yard line No. 2.

Estt. No. 38/TRD/

ASN/09-10

Estt. No. 37/TRD/

ASN/09-10

Galvanised rolled /

fabricated traction mast/

Gantry mast

MT 139.5 7,60,046/- 351050031

dt.03.11.09

16.10.6041 After TR the case sent to COS/KKK

by CEE/KKK on 19.09.11. Final

TCM is under process.

Page 38: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

38

Sl No

Name of sanctioned work

Estimate No. Description of Material Unit Quantity Total cost (in `̀̀̀)

Requisition No & date

COS Case No.

Remarks

15 Provision/on pre-

weighment line No. 2 yard

lines with full wiring of

yard line No. 2.

Estt. No. 38/TRD/

ASN/09-10

Estt. No. 37/TRD/

ASN/09-10

Galvanised TTC’s /Portal

Structure complete with

fasterners.

MT 5 3,30,455 351050022

dt.03.11.09

16.10.6042

Main case

No.

16.10.0160

After TR the case sent to COS/KKK

by CEE/KKK on 19.09.11. Final

TCM is under process.

16 Provision/on pre-

weighment line No. 2 yard

lines with full wiring of

yard line No. 2.

Estt. No. 41/TRD/

ASN/09-10 Copper catenery wire m 380 99,560/- 351050027

dt.03.11.09 16.10.6020 TCM is under finalisation. P.O will

be released on 30% option basis

after issue of main P.O.

17 PAN –Provision of OHE on

3rd Loop with direct

reception facilities on UP

direction.

Estt. No. 52/TRD/

ASN/09-10

Hard drawn grooved copper

contact wire 107 sq, mm m 400 1,50,000/- 351050032

dt. 19.11.09

15.09.6063 P.O has been issued.

18 PAN –Provision of OHE on

3rd Loop with direct

reception facilities on UP

direction

Estt. No. 52/TRD/

ASN/09-10

Galvanised rolled /

fabricated traction mast/

Gantry mast

MT 3 1,98,273/- 351050034

dt. 19.11.09

16.10.6043 After TR the case sent to COS/KKK

by CEE/KKK on 19.09.11. Final

TCM is under process.

19 PAN –Provision of OHE on

3rd Loop with direct

reception facilities on UP

direction.

Estt. No. 52/TRD/

ASN/09-10

Catenery wire 65 sq. mm. M 400 1,04,800/- 351050038

dt. 19.11.09

16.10.6023 After current fund certification, the

case has been sent to HQ on

23.08.10. P.O will be released on

30% option basis after issue of main

P.O.

20 Romoval of diamond

crossing by 1 in 12 points

and crossing man east cabin

at Asansol.

Estt. No. 39/TRD/

ASN/08-09

Hard drawn grooved copper

contact wire of 107 sq. mm.

m 750 2,78,250/- 351050001

dt: 04.03.10

In vice of

351050007

dt: 29.06.09

16.10.6057

Main Case

No.

16.10.0115

After local vetting the case has been

sent to CEE/KKK on 24.05.10. P.O

will be released on 30% option basis

after issue of main P.O.

21 Romoval of diamond

crossing by 1 in 12 points

and crossing man east cabin

at Asansol.

Estt. No. 39/TRD/

ASN/08-09

Copper catenary wire of 65

sq. mm

m 750 1,64,490/- 351050004

dt: 04.03.10

In vice of

351050008

dt: 29.06.09

16.10.6083 Sent to COS/KKK on 08.11.2010

CEE/KKK. P.O will be released on

30% option basis after issue of main

P.O.

22 Madhupur- development of

direct dispatch line for

goods traffic.

Estt. No. 74/TRD/

ASN/09-10

Hard drawn grooved copper

contact wire of 107 sq. mm.

m 300 1,12,500/- 351050002

dt: 12.04.10

16.10.0115 After local vetting the case has been

sent to CEE/KKK on 27.09.10.

Opening date of tender fixed on

09.09.11 P.O will be released on 30%

option basis after issue of main P.O.

23 Extension of platform to

accommodate 16 coach

trains with foot over bridge

at 06 station i.e: KEE,

KBQ, SNQ, JRW, Rajla

halt and Telwa.

Estt. No. 67/TRD/

ASN/09-10

Galvanized rolled fabricated

traction mast/gantry mast

MT 18 11,89,638/- 351050004

dt: 12.04.10

16.10.6030 P.O has been issued. P.O. No.

16.10.6036.2.46325 dt. 28.12.10.

Page 39: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

39

Sl No

Name of sanctioned work

Estimate No. Description of Material Unit Quantity

Total cost (in `̀̀̀)

Requisition No & date

COS Case No.

Remarks

24 Extension of platform to

accommodate 16 coach

trains with foot over bridge

at 06 station i.e: KEE,

KBQ, SNQ, JRW, Rajla

halt and Telwa.

Estt. No. 67/TRD/

ASN/09-10

Galvanized TTC/Portal

structure complete set.

MT 15 9,91,365/- 351050003

dt: 13.09.10

16.09.6036 After TR the case sent to COS/KKK

by CEE/KKK on 19.09.11. P.O will

be released on 30% option basis after

issue of main P.O.

25 Replacement of atenary

wire 40 Km

24/TRD/ASN/

10-11

25 Kv uninsulated copper

cadmium atenary wire

19/2.10 mm 65 sq. mm

MT 23.89 1,15,16,318/ 351050011

dt: 28.09.10

16.10.6072 Tender is under process. P.O will be

released on 30% option basis after

issue of main P.O.

26 Replacement of catenary

wire 40 Km

24/TRD/ASN/

10-11

Stranded annealed copper

jumper wire(105 sq. mm)

19/1.016 mm

kg 1500 4,83,660/- 351050012

dt: 28.09.10

16.10.6074 Tender under process. Tender opening

date not yet been fixed up.

27 Replacement of catenary

wire 40 Km

24/TRD/ASN/

10-11

Stranded annealed copper

jumper wire(50 sq. mm)

19/1.80 mm

kg 1000 4,99,000/- 351050013

dt: 28.09.10

16.10.6075 Tender is under finalization. Tender

opening date not yet been fixed up.

28 Replacement of catenary

wire 40 Km

24/TRD/ASN/

10-11

Hard drawn copper wire

(5mm dia) small dropper

wire

kg 5000 20,40,000/- 351050014

dt: 28.09.10

16.10.6088 Sent to COS/KKK on 29.12.10.

Tender is under process.

29 Replacement of catenary

wire 40 Km

24/TRD/ASN/

10-11

Contact wire parallel clamp

(large) assembly with all

fasteners.

Nos. 3000 10,07,400/- 351050021

dt: 28.09.10

16.10.6071 Tender date not fixed up. Tender is

under process.

30 Replacement of catenary

wire 40 Km

24/TRD/ASN/

10-11

Contact wire dropper

clip(107)

Nos. 16000 2,49,108/- 351050024

dt: 28.09.10

16.10.6087 Sent to COS/KKK on 15.12.10 TCM

is under process.

31 Replacement of catenary

wire 40 Km

24/TRD/ASN/

10-11

Catenery wire dropper clip

(107)

Nos. 10000 4,57,000/- 351050025

dt: 28.09.10

16.10.6088 Sent to COS/KKK on 29.12.10 P.O is

under A/Cs vetting.

32 Replacement of catenary

wire 40 Km

24/TRD/ASN/

10-11

Catenery ending clamp (65) Nos. 1000 4,50,450/- 351050028

dt: 28.09.10

16.10.6076 Sent to HQ on 29.12.10. P.O is under

A/Cs vetting.

33 Replacement of catenary

wire 40 Km

24/TRD/ASN/

10-11

Suspension clamp complete

with all accessories.

Nos. 1000 3,18,200/- 351050030

dt: 28.09.10

16.10.6077 Sent to HQ on 15.12.10. TR done on

15.09.11.

34 Replacement of catenary

wire 40 Km

24/TRD/ASN/-

10-11

Contact splice(tooth type) Nos. 600 11,88,468/- 351050031

dt: 28.09.10

16.10.6070 P.O has been issued against M/s

Kumar Fastener. P.O No.

16.10.6070.1.41393 dt. 05.09.11 P.O

is under A/Cs vetting.

35 Replacement of catenary

wire 40 Km

24/TRD/ASN/

10-11

Insulated atenary wire

(19/2.10 mm) 65 sq. mm

m 500 5,35,000/0 351050033

dt: 28.09.10

16.10.6086 Sent to HQ on 20.12.10. Retender is

under process.

36 Replacement of catenary

wire 40 Km

24/TRD/ASN/

10-11

Stay insulator (composite) Nos. 500 6,72,600/- 351050034

dt: 28.09.10

16.11.6001 TCM is under finalization.

37 Replacement of catenary

wire 40 Km

24/TRD/ASN/

10-11

Bracket insulator

(composite)

Nos. 500 7,08,000/- 351050035

dt: 28.09.10

16.11.6002 TCM is under finalization.

Page 40: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

40

Sl No

Name of sanctioned work

Estimate No. Description of Material Unit Quantity

Total cost (in `̀̀̀)

Requisition No & date

COS Case No.

Remarks

38 Replacement of catenary

wire 40 Km

24/TRD/ASN/

10-11

Pedestal insulator Nos. 200 7,80,000/- 351050037

dt: 28.09.10

16.10.6078 Tender is under process. TR done on

25.10.11

39 Replacement of cantilever

assembly at KAN-PKA

section (Ph- iv)

01/TRD/ASN/

10-11

Composite Stay insulator Nos. 2500 33,60,000 /- 351050038

dt: 28.09.10

16.11.6001 TCM is under finalization.

40 Replacement of cantilever

assembly at KAN-PKA

section (Ph- iv)

01/TRD/ASN/

10-11

Composite bracket insulator Nos. 2500 33,40,000 /- 351050039

dt: 28.09.10

has

cancelled &

clubbed with

reqn. No.

351050035

dt. 28.09.10

16.11.6002 TCM is under final procession.

41 Replacement of overaged

lighting arrester at various

switching station at OYR-

STN section

44/TRD/ASN/

10-11

42 kv 10 KVA lighting

arrester with surge monitor

& insulating base as per RDSO Spn No.

ETI/PSI/71/Rev-1 (1/87) with

A & C slip no. 5/9/2005.

Nos. 27 6,79,050 /- 351050040

dt: 09.12.10

16.11.6004 P.O. has been issued.

42 Replacement of over aged

25 kv /240 volts. 10 KVA

AT with associated

assembly at various station

& level crossing

43/TRD/ASN/

10-11

25 kv/240 volts 10 KVA AT

with associated assembly

Nos. 11 8,14,000 /- 351050041

dt: 09.12.10

16.11.6014 Oepning date of tender not fixed up.

43 Restoration of damaged

Traction bond

50/TRD/ASN/

10-11

Galvanised steel feexible

wire bond for traction with

lug duly crimped on both

ends

Nos. 1260 14,70,420 /- 351050042

dt: 22.12.10

16.11.6008 Re-tender is under process. Opening

date has not yet been fixed .

44 Restoration of damaged

Traction bond.

50/TRD/ASN/

10-11

Galvanised steel feexible

wire bond for traction with

lug duly crimped on both

ends (each 2.05 mtrs. Long)

Nos. 1270 15,67,180 /- 351050043

dt: 22.12.10

16.11.6009 Re-tender is under process. Opening

date has not yet been fixed .

45 Restoration of damaged

Traction bond

50/TRD/ASN/

10-11

Galvanised steel feexible

wire bond for traction with

lug duly crimped on both

ends (each 2.75 mtrs. Long)

Nos. 500 6,51,000 /- 351050044

dt: 22.12.10

16.11.6005 Re-tender is under process. Opening

date has not yet been fixed .

46 Restoration of damaged

Traction bond

50/TRD/ASN/

10-11

Galvanised steel feexible

wire bond for traction with

lug duly crimped on both

ends (each 3.00 mtrs. Long)

Nos. 1100 15,07,000 /- 351050045

dt: 22.12.10

16.11.6011 Re-tender is under process. Opening

date has not yet been fixed .

47 Restoration of damaged

Traction bond

50/TRD/ASN/

10-11

Galvanised steel feexible

wire bond for traction with

lug duly crimped on both

ends (each 3.50 mtrs. Long)

Nos. 760 11,45,320 /- 351050046

dt: 22.12.10

16.11.6010

Re-tender is under process. Opening

date has not yet been fixed .

Page 41: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

41

Sl No

Name of sanctioned work

Estimate No. Description of Material Unit Quantity

Total cost (in `̀̀̀)

Requisition No & date

COS Case No.

Remarks

48 Restoration of damaged

Traction bond

50/TRD/ASN/

10-11

Galvanised steel feexible

wire bond for traction with

lug duly crimped on both

ends (each 5.25 mtrs. Long)

Nos. 200 3,96,800 /- 351050047

dt: 22.12.10

16.10.6006 Re-tender is under process. Opening

date has not yet been fixed .

49 Restoration of damaged

Traction bond

50/TRD/ASN/

10-11

Galvanised steel feexible

wire bond for traction with

lug duly crimped on both

ends (each 7.00 mtrs. Long)

Nos. 200 4,92,200 /- 351050048

dt: 22.12.10

16.10.6007 Re-tender is under process. Opening

date has not yet been fixed .

50 Restoration of damaged

Traction bond

50/TRD/ASN/

10-11

M.S. flat bond size 40mm x

6 mm

kg. 8000 3,76,000 /- 351050050

dt: 22.12.10

07.11.9004 P.O has been issued. P.O. No.

07.11.9004.1.41349 dt. 27.07.11. 51 Stabling line for MEMU

rake at Asansol.

28/TRD/ASN/09-10 Hard drawn grooved copper

contact wire(107sq.mm)

MT 1.153 4,50,000/- 351050053

dt: 07.01.11

16.11.6019 P.O will be released on 30 % option

basis. 52 Replacement of 1100Volt, 40

Ah battery charger by

110Volt, 200Ah battery

chargerfor improvement of

DC backup supply of

reliability of train operation

reliability of

56RD/ASN/10-11 Battery charger suitable for

110V D.c 200Ah lead acid

battery.

Nos 04 8,43,600/- 351050056

dt: 28.01.11

16.11.6021 Tender is under process.

53 Development of Railway

yard facilities under ISP’s

expansion plan at Hirapur.

31RD/ASN/10-11 Hard drawn grooved copper

contact wire(107 sq.mm)

MT 2.306 9,36,000/- 351050054

dt: 28.01.11

16.11.6022 After TR the case sent to COS/KKK

on 01.08.11 by CEE/KKK. P.O will

be released on 30 % option basis.

54 Development of Railway

yard facilities under ISP’s

expansion plan at Hirapur.

31RD/ASN/10-11 Catenery wire 65 sq. mm MT 1.552 8,21,600 351050055

dt: 28.01.11

16.11.6023 After local vetting the case sent to HQ

on 04.03.11. Tender is under process..

55 Provision of additional retro-

reflective structure number

plate and OHE drop arm on

UP and DN main line for

guidance of running staff in

Kan-STn quadruple section.

55RD/ASN/10-11 Retro-reflective structure

number plate

Nos. 900 4,45,500/- 351050060

dt: 17.02.11

16.11.6025 P.O has been issued. P.O No.

16.11.6025.1.41436 dt. 19.09.11.

56 Coversion of cross type

OHE to overlap type OHE

for running at 140 Kmph in

ASN division of KAN-

PKA section.

61/TRD/ASN/10-11 Galvanised TTC /portal

structure complete with

fastners.

MT 23 11,60,005/- 351050062

dt: 24.03.11

16.11.6038

Main case

no.

16.10.0160

Final TCM is under process.

57 Coversion of cross type

OHE to overlap type OHE

for running at 140 Kmph in

ASN division of KAN-

PKA section.

61/TRD/ASN/10-11 Galvaninesd rolled

fabricated Traction

mast/gantry mast.

MT 13 6,55,655/- 351050063

dt: 24.03.11

-- Final TCM is under process.

Page 42: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

42

Sl No

Name of sanctioned work

Estimate No. Description of Material Unit Quantity

Total cost (in `̀̀̀)

Requisition No & date

COS Case No.

Remarks

58 Coversion of cross type

OHE to overlap type OHE

for running at 140 Kmph in

ASN division of KAN-

PKA section.

61/TRD/ASN/10-11 Small parts steel other than

mast including drop arm,

dwarf mast, gantry mast.

MT 10 7,89,330/- 351050064

dt: 24.03.11

-- Sent to HQ on 24.05.11 but returned

back to Division and advised to make

separate requisition for separate items

on 25.05.11

59 Coversion of cross type

OHE to overlap type OHE

for running at 140 Kmph in

ASN division of KAN-

PKA section.

61/TRD/ASN/10-11 Cantiliver assembly without

insulator .

Nos 80 6,56,000/- 351050064

dt: 24.03.11

Sent to HQ on 24.05.11 but returned

back to Division and advised to make

separate requisition for separate items

on 25.05.11

60 Coversion of cross type

OHE to overlap type OHE for running at 140 Kmph in

ASN division of KAN-

PKA section.

61/TRD/ASN/10-11 Regulating equipment of 3

pulley modified type.

Nos 16 7,77,936/- 351050070

dt: 24.03.11

-- The case sent to HQ on 24.05.11.

TCM is under process.

61 Coversion of cross type

OHE to overlap type OHE

for running at 140 Kmph in

ASN division of KAN-

PKA section.

61/TRD/ASN/10-11 Hard drawn grooved copper

contact wire of 107 sq, mm

MT 1.441 5,85,000/- 351050074

dt: 24.03.11

16.11.6042 The case sent to HQ on 24.05.11. P.O

will be released on 30 % option basis

62 Coversion of cross type

OHE to overlap type OHE

for running at 140 Kmph in

ASN division of KAN-

PKA section.

61/TRD/ASN/10-11 Catenery wire of 65 sq. mm. MT 0.895 4,74,000/- 351050075

dt: 24.03.11

16.11.6041 The case sent to HQ on 24.05.11. P.O

will be released on 30 % option basis

63 Coversion of cross type

OHE to overlap type OHE

for running at 140 Kmph in

ASN division of KAN-

PKA section.

61/TRD/ASN/10-11 Large span wire 130 sq. mm

of 37/2.10 mm cadmium

copper.

Mtrs 1000 6,46,000/- 351050075

dt: 24.03.11

16.11.6040 The case sent to HQ on 24.05.11. TC

is under process but opening date has

not yet been fixed.

CRITICAL STORE ITEMS ANNEXURE –XVII

Sl. No.

Description Unit Qty. Approximate Cost (in `̀̀̀)

Requisition No. & date

C.O.S case No.

Remarks

1 Battery charger including associated for 110 volt, 200AH 0-30

Amp. Trickle mode function.

No. 03 1,31,040/- 361100339

dt. 22.08.06.

16.07.6042 P.O has been issued.

2 Overhauling kit for pole column/TSS4-720002-RI for 25 KV

SF-6 interrupter type EDF-SKI-1.

Set. 21 113720/- 361100306

dt.25.07.06

16.08.6009 P.O. No. 16.08.6009.1.41747 dt. 17.11.09 against M/s

Bhandari Enterprises, Kolkata.

3 Vacuum bottle suitable for 25 KV vacuum circuit breaker of

Alind Make type-VSE-5/20, part No.4 Rating 1600 Amps.

No. 01 173361/- 361100379

dt.15.12.06

16.07.6031 P.O issued (P.O no. 16.07.6031.1.41499) against M/s

Alluminium Industries Ltd., Kolkata.

Page 43: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

43

ANNEXURE -XVII A

POSITION OF P.I. STOCK ITEM OF AC OHE COMPONENTS /FITTINGS RECEIVED FOR TRD/ASN

Year of 09-10 Year of 10-11 Year of 11-12 Sl. No

P.L No

Description of Store

RDSO’s Drawing No

Unit Yearly

P.I Quota Qty. Recd.

% Recd.

Yearly P.I Quota

Qty. Recd.

% Recd.

Yearly P.I Quota

Qty. Recd.

% Recd.

1 46-13-0019 SS bolt with nuts, L/nuts

Size 10x35/30 mm.

No. 1000 800 80 1000 1300

1000

130

77

1000 -- --

2 46-13-0100 SS bolt with nuts, L/nuts

Size 10x65/30 mm No.

1000

200

20

1000

450 45

1000

20 02

3 46-13-0202 SS bolt with nuts, L/nuts

Size 12x45/30 mm

No. 100

05 05 100

100 100 100

-- --

4 46-13-0251 SS bolt with nuts, L/nuts

Size 12x55/30 mm old

& obsolate (item modified

size 12x60/30 mm)

No. 100 100 100 100 10 10 100

5 46-13-0305 SS bolt with nuts +L/nuts size

12x75x30mm

No. -- -- -- 200 -- -- 200

6 46-13-0408 GS bolt with nuts, L/nuts

Size 16x50/38 mm.

No. 4000 3000 75 4000

2000

50 4000 250 6.25

7 46-13-0500 GS bolt with nuts + L/nuts size

16x65x38mm.

No. 200 200 100 200 60 30 200

8 46-13-0550 GS bolt with nuts + L/nuts size

16x75x38 mm.

No. 125 125 100 125 125 100 125

9 46-13-0603 GS bolt with nuts + L/nuts

size16x260x100 mm.

No. 200 150 75 200 200 100 200

10 46-13-0652 GS bolt with nuts + L/nuts

Size 16x360/100 mm

No. -- -- -- -- -- -- -- -- --

11 46-13-0706 GS bolt with nuts +L nuts

Size 20x65/46 mm.

Nos. 200 150 75 200 50

25

200

12 46-13-0809 GS bolt with nuts +L nuts

Size 20x85/46mm.

No. 75 75 100 75 -- -- 75 30 40

13 46-13-0858 GS bolt with nuts +L nuts

Size 20x260/100mm

No. 50 100 100 50 03 06 50

14 46-13-0901 GS bolt with nuts + L nuts

Size 20x360/100mm

No. 50 20

30

40

60

50 -- -- 50

15 46-13-0950 GS bolt with nuts + L nuts

size 24x85/55mm (old and

obsolate item) modified

24x70/54mm

ETI/C/007

3, MOD-

“A” &

RDSO

Specn No-

ETI/OHE/

18(4/84)

with latest

rev. ETI/OHE/

P/150

No. 50 50 100 50 -- -- 50

Page 44: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

44

Year of 09-10 Year of 10-11 Year of 11-12 Sl. No

P.L No

Description of Store

RDSO’s Drawing No

Unit Yearly

P.I Quota Qty. Recd.

% Recd.

Yearly P.I Quota

Qty. Recd.

% Recd.

Yearly P.I Quota

Qty. Recd.

% Recd.

16 46-13-1309 SS Hex head stud bolt size

12x50/50mm

No. 25 25 100 25 -- -- 25

17 46-13-2454 SS 'U' Bolt size 10 mm dia

1153 (s)

No. 20 20 100 20 20 100 20 20 20

18 46-13-2508 SS "U" bolt - 10 mm dia

1162 (s)

No. 500 500 100 500 50 10 500

19 46-13-2557 SS "U" bolt - 10 mm dia

1173 (s)

No. 100 100 100 100 -- -- 100

20 46-13-2650 SS 'U- Bolt - 10 mm dia

6034 (s)

ETI/C/0073,

MOD-“A” &

RDSO

Specn No-

ETI/OHE/18

(4/84) with

latest rev. ETI/OHE/

P/150

No. 500 300 -- 500 -- -- 500 500 100

21 46-19-0053 Anti wind Clamp for

Circular tube.

RE/33/P/

2500

No. -- -- -- 100 750 750 100

22 46-19-0077 Standard Anti wind Clamp

with ID No 2251-1, 2502 &

2503.

ETI/OHE/P/2550-

1/2 MOD-L

No. 1000 1000 10

90

1000 --

1000

--

100

1000

23 46-19-0107 18 mm bus Terminal

Multiple Bolt.

ETI/OHE/P/

6310-1MOD-A

No. -- -- -- 20 -- -- 20

24 46-19-0156 18 mm bus Tee Joint. ETI/OHE/

P/6330-1

MOD-C

No. -- -- -- 20 -- -- 20

25 46-19-0302 Contact wire PG clamp

(large)

ETI/OHE/

P/1030-2

MOD-D

No. 1000 800 60

20

1000 800 80 1000

26 46-19-0351 Contact wire PG clamp

(small)

ETI/OHE/P/ 1040-2

MOD-E

No. 500 680 225 500 600 120

500 500 100

27 46-19-0405 Contact wire Dropper Clip RE/33/P/1180

MOD-F with ID

Nos. 1182 MOD-C

No. 1000 1000 100

1000 1000 100

1000 1000

100

28 46-19-0454 Catenary Dropper Clip ETI/OHE/

P/1192 MOD-C

No. 500 430 86

500 300

200

67

40

500 50 10

29 46-19-0508 Contact wire swivel clip ETI/OHE/

P/1220 MOD-E

with ID No.-1222

MOD-C

Set 300

300 100

300

300 101

300 300 100

30 46-19-0752 Double suspension clamp (65

x 65)

RE/33/P/1170-

MOD-K with 1D

Nos. 1172 MOD-C & 1174 MOD-B

Set 10

10 100

10

10 100

10

Page 45: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

45

Year of 09-10 Year of 10-11 Year of 11-12 Sl. No

P.L No

Description of Store

RDSO’s Drawing No

Unit Yearly

P.I Quota Qty. Recd.

% Recd.

Yearly P.I Quota

Qty. Recd.

% Recd.

Yearly P.I Quota

Qty. Recd.

% Recd.

31 46-19-0934 Contact wire ending

clamp (107 wedge type) ETI/OHE/

P/1110-2MOD-D No. 300

50 17 300

100 33 300

32 46-19-0958 Ending clamp catenary

(65)

ETI/OHE/

P/1120 MOD-B No. 300

250

83

300 300 99

300 300 100

33 46-19-1033 Ending clamp steel wire

(90)

ETI/OHE/

P/1360 MOD-B

No. 10 10 100

10 10 100

10

34 46-19-1057 Feeder Ending Clamp ETI/OHE/

P/1130

No. 25 25 100

25 25 100

25 25 100

35 46-19-1100 Earth Pipe Clamp ET/10 ref Drg No.

RE/33/P/7022

No. 20 20 100

20 --

20

--

100

20 - --

36 46-19-1252 Earth Wire strain Clamp. ETI/OHE/

P/7050 MOD-D

No. 05 -- --

05 -- --

05 -- --

37 46-19-1409 Knuckle Tube Clamp &

Jaw.

ETI/OHE/

P/1216 MOD-D

No. 10 -- --

10 10 100

10 -- --

38 46-19-1458 Large span wire ending

clamp (130)

ETI/OHE/

P/1140 MOD-B

Set 20 20 100

20 20

100

20 -- --

39 46-19-1653 Dropper clip (38mm) ETI/OHE/

P/2274-1 MOD-D No. 250

250 500 250

-- -- 250 -- --

40 46-19-1859 Backing angle RE/33/

P/3076 ID

No-3076-1.

No. 10 10 100 10 10 100 10 -- --

41 46-19-1872 Backing angle RE/33/

P/3076 ID

No-3076-2.

No. 20 20 100 20 20 100 20 -- --

42 46-19-1896 Backing angle RE/33/ P/3076 ID

No-3076-3.

No. 10 10 100 10 --

10

--

100

10 -- --

43 46-19-1914 Backing angle RE/33/

P/3076 ID

No-3076-4.

No. 10 10 100 10 -- -- 10 -- --

44 46-19-1926 Backing angle RE/33/

P/3076 ID

No-3076-5.

No. -- 05 50 10 -- -- 10 -- --

45 46-19-2050 Parallel Clamp

(Modified)

ETI/OHE/

P/1050-3

Set 100 -- -- 100 200 200 100 100

100

46 46-19-2207 Parallel clamp double

contact wire

ETI/OHE/

P/6170 MOD-C

No. -- -- -- 200 200 100 200 150 75

47 46-19-2256 Raised register Arm

clamp.

ETI/OHE/

P/1370-1 MOD-E

Pair 10 10 100 10 10 100 10 100 100

Page 46: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

46

Year of 09-10 Year of 10-11 Year of 11-12 Sl. No

P.L No

Description of Store

RDSO’s Drawing No

Unit Yearly

P.I Quota Qty. Recd.

% Recd.

Yearly P.I Quota

Qty. Recd.

% Recd.

Yearly P.I Quota

Qty. Recd.

% Recd.

48 46-19-2359 Dropper clip (34mm) ETI/OHE/

P/2461-1 MOD-F

No. 200 -- -- 200 200 100 200 20 10

49 46-19-2402 Dropper clip (25mm) ETI/OHE/

P/2471-1 MOD-E

No. 20 20 40 20 510

20

2505

100

20 10 50

50 46-19-2505 Suspension (65mm) ETI/OHE/

P/1160 MOD-J

Set 50 -- -- 50 100

50

200

100

50 50 100

51 46-19-2554 Suspension clevis (18mm) ETI/OHE/

P/1270-1 MOD-F

No. 10 -- -- 10 -- -- 10 10 100

52 46-19-2657 25mm steady arm Clamp. ETI/OHE/

P/2490-2 MOD-E Set 200 -- -- 200 200 100 200 -- --

53 46-19-2955 18 mm single Clevis. ETI/OHE/

P/5040 MOD-B No. -- 10 -- 10 -- -- 10 -- --

54 46-19-3406 ‘U’ clamp (50/50) ETI/OHE/

P/1320 MOD-B

No. 50 20 40 50 -- -- 50 -- --

55 46-19-4289 Large Suspension Clamp

with all accessories

(20mm)

ETI/OHE/

P/1580 MOD-F .ID

No-1581,1582,1580

(Ref:10,11)

No. -- -- -- 10 --

10

--

100

10 -- --

56 46-19-4400 Post Insulator jumper

Clamp

ETI/OHE/

P/6094 MOD-B Nos. 50 50

50

100

100

50 -- -- 50 -- --

57 46-23-0014 Contact wire splice

(Tooth type).

ETI/OHE/

P/1080-1 MOD-B

& 1081-1 MOD-C

Set 75 70 127 75 10 13 75 -- --

58 46-23-0051 Catenary splice (65) ETI/OHE/

P/1090 No. 1000 600 60 1000 400 40 1000 1000 100

59 46-23-0154 Double contact wire

splice.

RE/33/

P/1280MOD-C -- -- -- -- 20 -- -- 20 -- --

60 46-23-0506 Mast fitting for hook

insulator.

TI/DRG/OHE

TGEF/RDSO/00005/04

/0,ID No3021-1

No. 50 50 100 50 25 50 50 -- --

61 46-23-0555 Mast bracket fitting assly

(150)

ETI/OHE/

P/3070-1D MOD-H No. 25 25 100 25 25

25

100

100

25 -- --

62 46-23-0579 Mast bracket fitting assly

(200)

ETI/OHE/

P/3070-2 MOD- D No. 25 01 04 25 -- -- 25 -- --

63 46-23-0658 Mast anchor fitting

welded

ETI/OHE/

P/3231 MOD-C No. 25 25 100 25 10 40 25 -- --

64 46-23-0750 Mast guy rod fitting

welded.

ETI/OHE/

P/3232- MOD-C No. 10 10 100 10 -- -- 10 -- --

65 46-23-0956 Multiple cantilever cross

arm assly. RE/33/

P/3120 MOD-H No. 05 -- -- 05 --

200

-- 05 -- --

Page 47: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

47

Year of 09-10 Year of 10-11 Year of 11-12 Sl. No

P.L No

Description of Store

RDSO’s Drawing No

Unit Yearly

P.I Quota Qty. Recd.

% Recd.

Yearly P.I Quota

Qty. Recd.

% Recd.

Yearly P.I Quota

Qty. Recd.

% Recd.

66 46-23-1158 Counter weight guide tube

assly. ETI/OHE/

P/0560- MOD-C

with ID No-5067

& 2053-1

No. 100 40 100 100 125 250 100 -- --

67 46-27-0024 SS stud bolt with L/nuts

/ size 10x3530mm ETI/OHE/

P/2404- MOD-C No. 300 50 50 300 150 50 300 300 100

68 46-29-0450 Tube cap 25mm ETI/OHE/

P/2423-1 MOD-A No. 400 -- -- 400 40 10 400 20 5

69 46-29-0503 Tube cap 40mm ETI/OHE/

P/2104-1 MOD-A No. 50 -- -- 50 52 104 50 50 100

70 46-29-0655 Tubuler stay sleeve ETI/DRG/OHE/FIGF

E/RDSO/00004/03/

0 & RDSO Spec.No

ETI/OHE/49/

(09/09) with A&C

No. 50 -- -- 50 50 100 50 20 40

71 46-35-1309 Washer flat G.S for 16

mm dia bolt. ETI/C/0075

No. 200 -- -- 200 200 100 200 -- --

72 46-50-0017 Anchor bolt (1.6 mtrs)

long ETI/OHE/

P/6001-1 MOD-D No. 50 50 500 50 50 100 50 -- --

73 46-50-0108 Anchor double strap assly. ETI/OHE/

P/6030 MOD-C Set 50 -- -- 50 50 100 50 -- --

74 46-50-0200 Guy rod double strap

assly. ETI/OHE/

P/6220 Set 15 15 100 15 115 100

100 15 --

--

75 46-51-0308 Counter weight assembly complete (ID No.

5091,5092 & 5093)

ETI/OHE/

P/5901 MOD-B Set -- -- -- 05 -- -- 05 -- --

76 46-52-0703 SS wire rope for pully

block type RE.

RDSO’s specn No. TI/SPC/OHE/WR/10

60 No. 50 30 60 50 50 100 50 50 100

77 46-52-0752 SS wire rope for winch

block type RE.

No. -- -- -- -- -- -- -- --

--

78 46-53-0101 Earth contact assembly

for 25KV SP Isolator-

1600Amps

RDSO’s Specn No.

ETI/OHE/16(1/94) No. 10 10 100 10 -- -- 10 05 50

79 46-53-0204 Earth pipe 3100 mm.

long. ETI/OHE/

P/7021 MOD-A No. 100 -- -- 100 50 166 100 -- --

Page 48: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

48

Year of 09110 Year of 10-11 Year of 11-12 Sl. No

P.L No

Description of Store

RDSO’s Drawing No

Unit Yearly

P.I Quota Qty. Recd.

% Recd.

Yearly P.I Quota

Qty. Recd.

% Recd.

Yearly P.I Quota

Qty. Recd.

% Recd.

80 46-53-0307 Single pole isolator 25

KV, 1250 amp. ETI/OHE/16(01/94)

Rev-2(March-04) No. 04 04 100 04 04 100 04

81 46-54-0039 Guy rod stirrup. ETI/OHE/

P/5002 MOD-B No. 10 10 100 10 10 100 10 10 100

82 46-54-0155 Equalising plate. No. 05 -- -- 05 01 20 05 04 80

83 46-54-0209 Compensating plate.

ETI/OHE/

P/5191 MOD-B No. 05 5 100 05 -- -- 05

84 46-54-0404 Raised register Arm

adjuster 25mm. ETI/OHE/

P/2432 MOD-E No. 05 5 100 05 02 40 05 05 100

85 46-54-0556 Tubular stay adjuster ETI/OHE/

P/2402 MOD-A No. 10 -- -- 10 10 100 10 05 50

86 46-55-0010 Large jumper wire (105 sq

mm) (19/7/1.016) ETI/OHE/3

(2/94) rev-1 Kg 300 200 66.6 300 300 100 300 -- --

87 46-55-0100 Stranded annealed copper

jumper wire (50 sq.mm)

(19/1.80mm)

ETI/OHE/3/

(2/94) rev-1 Kg 1000 -- -- 1000 -- -- 1000 -- --

88 46-55-0306 Contact wire

(107 Sq.mm) ETI/OHE/76/(06/97)

with A & AC Slip 1&3 m 3500 -- -- 3500 6164 176 3500 -- --

89 46-55-0409 Catenary wire

(65 sq.mm) ETI/OHE/50/(06/97)

with A&C slip No. 1 m 3000 3000 100 3000 7786 6153 3000 -- --

90 46-55-0604 Large dropper wire (7mm

dia) IS-282/1982 Kg 100 97 388 100 -- -- 100 -- --

91 46-55-0800 Small dropper wire (5mm IS-282/1982 Kg 400 382.9 95 400 300 100 400 380.7 95.175

92 46-56-0014 Ball eye I.D No. 6068 ETI/OHE/P/6068

Mod-B -- -- -- -- -- -- -- -- -- --

93 46-56-0105 Bent steady Arm, swivel

ID. No 2352

ETI/OHE/P/2352

Mod-A No.

25 25 100 25 -- -- 25 -- --

94 46-56-0208 Double eyes distance rod

(20mm x 1m) ETI/OHE/P/5183

Mod-C No.

100 85 85 100 95

100

100

100 100

-- --

95 46-56-0403 Eye rod for balance

weight ETI/OHE/P/5094-

5095Mod-F No.

30 30 100 30 30 100 30 -- --

96 46-56-0609 Normal bent steady arm

eye piece ETI/OHE/P/2522

Mod-B No.

05 -- -- 05 -- -- 05 -- --

97 46-56-0907 Register Arm eye piece TI/DRG/OHE/

RDSO/FTGFE/

0002/00/0 & RDSO’s

specn No.

ETI/OHE/94/ (09/95)

with A&C-1

No.

100 100 100 100 50

100

50

100 100 -- --

98 46-56-1201 BFB steady arm eye piece.

ID. No. 2541 ETI/OHE/P/2541

Mod-E

No. 200 -- -- 200 200 100 200 -- --

Page 49: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

49

Year of 09-10 Year of 10-11 Year of 11-12 Sl. No

P.L No

Description of Store

RDSO’s Drawing No Unit Yearly

P.I Quota Qty. Recd.

% Recd.

Yearly P.I Quota

Qty. Recd.

% Recd.

Yearly P.I Quota

Qty. Recd.

% Recd.

99 46-56-1304 BFB steady arm

swivel. ID. No. 2542

ETI/OHE/P/2542

Mod-C

No.

500 200

430

40

86 500 200 40 500

100 46-56-1456 BFB steady arm

(32*31x3mm)

(0.72mtr long)

ETI/OHE/P/2540Mo

d-B ID NO 2544-1

No.

250 50 20 250 250 100 250

101 46-56-1500 BFB steady arm

(32*31x3mm)

(0.92mtr long)

ETI/OHE/P/2540

Mod-B ID NO 2544-2

No.

500 500 100 500 -- -- 500 500

100

102 46-57-0019 BFB steady arm

(40x30mm)

ID. No. 2521

ETI/OHE/P/2520

MOD-B ID No 2544-2

RDSO’s Spec No –

ETI/OHE/9/74 or

latest.

No.

25 25 100 25 -- -- 25

103 46-57-0100 Large Bracket tube

(40/49)

ETI/OHE/P/2081

MOD-E& RDSO

Spec No –

ETI/OHE/11/5/89 or

latest.

m

150 300

200 150

150

25

100

17 150 300 200

104 46-57-0305 Stay Tube RE/33/P/2401

MOD-C & RDSO

Spec No

ETI/OHE/11

(5/89) or latest.

m

200 -- -- 200 198 99 200

105 46-57-0500 Standard Bracket Tube

(30/38 mm)

ETI/OHE/P/2041

MOD-D & RDSOSpec

No –ETI/ OHE /

11/5/89or latest.

No.

-- -- -- 50 -- -- 50

106 46-58-0130 Large Register Arm

hook

ETI/OHE/P/2160-1 &

MOD-E

Set

100 100 100 100 100

100

100

100 100

107 46-58-0700 Standard Register Arm

hook

ETI/OHE/P/2150-1 &

MOD-E

No. 100 02 04 100 -- -- 100

108 46-58-0402 Normal bent Steady

Arm Hook ID. No.

2523

ETI/OHE/P/2523 &

MOD-B

No.

-- -- -- 20 -- -- 20

Page 50: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

50

Year of 09-10 Year of 10-11 Year of 11-12 Sl. No

P.L No

Description of Store

RDSO’s Drawing No

Unit Yearly

P.I Quota Qty. Recd.

% Recd.

Yearly P.I Quota

Qty. Recd.

% Recd.

Yearly P.I Quota

Qty. Recd.

% Recd.

109 46-58-0694 Steady Arm hook (BFB

Forged)

ID. No. 2391-1

ETI/DRG/OHE/FTG

EE/RDSO/OOOO3/

00/0 & RDSO Spec

No –ETI/OHE/49

(9/95)WITH A&C-

1 (3/97).

No.

750 -- -- 750 750 100 750

110 46-59-0055 Bracket insulator

assembly ETI/OHE/P/6030 No.

250 255 102 250 -- -- 250

111 46-59-0109 Large suspension bracket ETI/OHE/P/2130

MOD-B

No. 30 30 100 30

30

30

100

100 30

112 46-59-0158 Standard Catenary

suspension bracket Complete

ID. No. 2110

ETI/OHE/P/2110

MOD-B

No. -- -- -- -- -- -- --

113 46-59-0201 Bracket Insulator assembly

(Polluted zone) ETI/OHE/15/(9/91)

with Slip No1 to 6. No.

100 -- -- 100 100 100 100

114 46-61-0753 Section insulator assembly

without insulator (RI 6100) ETI/OHE/27 (08/84)

rev-1 (Oct-92)

No. -- -- -- 10 10 100 10 10 100

115 46-61-0806 Section Insulator (RI 6100)

(850 mm CD) CORE ETI/OHE/15 (09/91)

with A&C-1to 6

No. 10 -- -- 10 10 100 10

116 46-61-0984 Porcelain stay arm insulator

(polluted zone) No.

100 -- -- 100 30 34 100 75 75

117 46-61-1010 Porcelain 9 Ton insulator

(polluted zone) (RI-6020-2)

1050mm CD

No. 100 -- -- 100 -- -- 100

118 46-61-1022 Operating insulator for 25KV

Isolator (RI-6260) No.

-- -- -- 10 10 100 10

119 46-61-1034 Post insulator for 25KV

isolator and bus bar (RI-

6090)

No. 25 25 100 25 10 40 25

120 46-61-0303 Porcelain 9 Ton

insulator(RI-6020) (850 mm

CD)

300 -- -- 300 300

81

100

27 300

121 46-61-0704 Porcelain Stay Arm

Insulator. (RI-6000) 850

mm CD

ETI/OHE/15

(09/91) with

A&C-1to 6

200 200 66 200 250

60 83

30 200

122 46-62-0011 Register arm extension

frame ETI/OHE/P/2110

05 -- -- 05 -- -- 05

123 46-62-0102 Stay arm/bracket chair RDSO’s Drg No

ETI/OHE/P/3050

Mod-B 05 -- -- 05 -- -- 05 01 20

Page 51: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

51

Year of 09-10 Year of 10-11 Year of 11-12 Sl. No

P.L No

Description of Store

RDSO’s Drawing No

Unit Yearly

P.I Quota Qty. Recd.

% Recd.

Yearly P.I Quota

Qty. Recd.

% Recd.

Yearly P.I Quota

Qty. Recd.

% Recd.

124 46-63-0016 9.5Mtrs long drilled and

galvanized RSJ masts (WB-

022) 52 Kg./Mtr (203 x152

mm) as per IS: 808 IS:2062

gr. A. SK driiled scheduled.

ETI/OHE/g/00144

sheet-3 Rev-C type

of mast-F & Spec

No. ETI/OHE/13

(1/84) & A&C-1 to 3.

No.

-- -- -- 05 -- -- 05

125 46-63-0107 9.5Mtrs long drilled and

galvanized BFB masts

ETI/OHE/g/00144

sheet-3 Rev-C type

of mast-F & Spec

No. ETI/OHE/13

(1/84) & A&C-1 to 3.

No.

10 08 80 10 -- -- 10

126 46-63-0156 Galvanised standard Traction

masts (fabricated with batten

plate) 9.5 Mtrs long,

B-200.

No. -- 03 -- 05 -- -- 05

127 46-63-0259 Galvanised standard

Traction masts (fabricated

with batten plate) 9.5 Mtrs

long, B-175.

No. -- -- -- 05 -- -- 05

128 46-63-0302 Galvanised standard Traction

masts (fabricated with batten

plate) 9.5 Mtrs long, B-150.

ETI/C/0071/MOD-E

& RDSO’s specn

No.

ETI/OHE/13(04/84

0 A&C 1 to 3

No. -- -- -- 05 -- -- 05

129 46-64-0014 Guy Rod (25mm dia) 9.3

Mtrs long ID No. 5004

RDSO’s specn No.

ETI/OHE/P/5004/5/

6-1 MOD-G

No. -- -- -- 10 -- -- 10

130 46-90-0366 Discharge/ Earthing rod

complete with all accessories

for OHE (preferably fibre

glass type)

ETI/OHE/51/

(09/87) Rev-1

(Oct’92)

No. 50 06 12 50 50 100 50

131 46-98-7812 SS bolt with nuts, L/nuts

size 10/40/26mm ETI/C/0073

MOD-A No. 500 300

60 500 300 60 500

132 46-98-7824 Adjuster 9 tonne (Eye and

Clevis type) ETI/OHE/P/

5021-1 No. 500 90 18 500 300 60 500

133 46-99-0057 Bond (Transverse) with 40x6

mm of MS flat 4 Mtr length

complete with fastner

ETI/OHE/G/

0525 MOD-A No. 500 -- -- 500 -- -- 500

200 40

134 46-99-0069 40x6 mm of M.S. flat

structure bond 2.5 m length

complete with fastner

ETI/OHE/P/7000

MOD-E

No. 500 500 100 500 500 100 500

135 46-99-0094 Silicon composite 9

Tonne insulator

(Standard)

No. 200 -- -- 200 125 62.5 200

136 46-99-0100 Silicon Composite 9

Tonne Insulator (polluted

Zone)

TI/SPC/OHE/

INSCOM/1070 No. 300 300 99 300 278 92.67 300

100 34

Page 52: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

52

Year of 09-10 Year of 10-11 Year of 11-12 Sl. No

P.L No

Description of Store

RDSO’s Drawing No

Unit Yearly

P.I Quota Qty. Recd.

% Recd.

Yearly P.I Quota

Qty. Recd.

% Recd.

Yearly P.I Quota

Qty. Recd.

% Recd.

137 46-99-0112 25 KV Silicon composite

stay arm insulator

(Polluted Zone)

TI/SPC/OHE/

INSCOM/1070

No. 200 250 125 200 200 100 200 210 105

138 46-99-0124 25 KV Silicon Composite

bracket tube Insulator

(Polluted Zone)

No. 200 200 100 200 30 15 200 100 50

139 46-99-0136 Regulating equipment 3

pully type 3:1 ratio

(Modified)

TI/SPC/SSWR/

1061

No. 25 -- -- 25 25 100 25 25 100

140 46-99-0150 SS wire rope for 3 pulley

RE (3:1 ratio)

TI/SPC/SSWR/

1060

No. 30 -- -- 30 30 100 30

141 46-99-0161 SS wire Rope for

modified 3 pully R.E. TI/SPC/OHE/WR/

1060 No. 50 50 100 50 55 110 50

142 46-99-0173 Silicon composite bracket

insulator (Stranded).

TI/SPC/OHE/

INSCOM/1070

No. 500 -- -- 500 -- -- 500

143 46-99-0185 Public caution board retro

reflective type.

RE/33/P/7551 No. 100 -- -- 100 100 100 100

144 46-99-0197 Staff caution board retro

reflective type

RE/33/P/7531

Mod-B

No. 200 -- -- 200 200 100 200

145 46-99-0203 25KV danger board retro

reflective type

ETI/OHE/P/7531

MOD-B

No. 100 100 100 100 50 50 100 100 100

146 46-99-0215 Silicon composite stay

arm insulator (stranded)

TI/SPC/OHE/INS

COM/1070

No. 500 400 240 500 350 70 500

147 46-99-7213 Angular contact ball

bearing double row

As per ID No

SKF 3205

No. -- -- -- -- -- -- --

148 46-99-0318 Drop bracket PUI suit

33.7mm register arm tube

Drg

No.ETI/OHE/P/

2360(Mode I)

Pl No. 2361

No.

-- -- -- 1200 -- -- 1200

149 85-99-7328 Bearing SKF 8305 RSI or

MBC 6305LLU

SKF 6305 2RSI

or MBC 6305

LLU

No.

-- -- -- 600 -- -- 600

150 46-99-0537 Counter weight eye rod

(1.55 Mtr long) for 3

pulley

ETI/OHE/P/

5090-5 (Mod-A

ID 5099)

No.

-- -- -- 25 25 100 25

25 100

151 46-99-0549 Guy rod 25mm length

5.35 mtrs for dwarf mast

ETI/OHE/G/

01402 ref-3

No. -- 27 -- 50 50 100 50

152 46-99-0550 Anchor bolt 0.85 mtr long

dia 20 mm

ETI/OHE/G/

01402 ref-5

No. -- -- -- 40 40 100 40

Page 53: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

53

Year of 09-10 Year of 10-11 Year of 11-12 Sl. No

P.L No

Description of Store

RDSO’s Drawing No

Unit Yearly

P.I Quota Qty. Recd.

% Recd.

Yearly P.I Quota

Qty. Recd.

% Recd.

Yearly P.I Quota

Qty. Recd.

% Recd.

153 46-99-0562 Attachment for dwarf

mast

ETI/OHE/G/

01402 ref-6 No.

-- -- -- 50 50 100 50 50 100

154 46-99-0460 PTFE type neutral section

(phase break)

TI/SPC/OHE/SN

S/0000

No. -- 1 -- 05 04 26 05

155 46-99-0860 Tension insulator rod 2500

of neutral section GF 25

spare part(one set

consisting of 4pieces

OEMID No. 659.500.013

TI/SPC/OHE/SN

S/0000

Set -- -- -- 05 -- -- 05

156 46-99-0872 Cleaning paste for

insulator rods (for PTFE

short neutral section

assembly phase break)

TI/SPC/OHE/SN

S/0000 OEM’s ID

No. 655.188.000

No.

-- -- -- 15 -- -- 15

157 46-99-0884 Set of right sidd to SI

655.167.666 (one set

consisting of 04 pieces)

TI/SPC/OHE/SN

S/0000 OEM’s ID

No. 659.500.127

Set

-- -- -- 10 -- -- 10

158 46-99-0896 Set of left sidd to SI

655.167.666 (one set

consisting of 04 pieces)

TI/SPC/OHE/SN

S/0000 OEM’s ID

No. 659.500.126

Set

-- -- -- 10 -- -- 10

ANNEXURE-XVII/B EAC QUOTA FOR 2009-10 FOR PSI ITEM & ADDITIONAL FOR OHE ITEMS FOR 2009-10 IN ASANSOL DIVISION

Year of 09-10 Year of 10-11 Year of 11-12 Sl. No

P.L. No Description of Store RDSO’s Drawing No/ Specn. No.

Unit

Yearly P.I

Quota

Qty. Recd.

% Recd.

Yearly P.I

Quota

Qty. Recd.

% Recd

.

Yearly P.I

Quota

Qty. Recd.

% Recd

. 1 46-99-0320 25KV/240V single phase oil filled

Auxiliary Transformer/10 KVA.

ETI/PSI/15 (03/2003) or

latest

No. 45 -- -- 45 21 47 45

2 46-99-0331 25 KV single pole Vacuum Circuit

Breaker

TI/SPC/PSI/ CB/00000

with A& C slip No:04 or

latest

No. 02 -- -- 02 -- -- 02

3 46-99-0343 25 KV single pole Vacuum Inturreptor ETI/PSI/67(9/97) with

A & C slip: 1 or latest

No. 09 -- -- 09 08 88 09

4 46-99-0355 25 KV potential transformer type-I TI/SPC/PSI/PTS/0992

(Aug.)

No. 10 01 10 10

02

10

20

100

10

5 46-99-0367 25 KV Potential transformer type-II TI/SPC/PSI/ PTS/0992

(Aug.05 or latest)

No. 04 02 20 04 04 40 04

6 46-99-0379 25 KV single phase oil cooled current

transformer ratio 1500-750/5A Class-

P.S.

ETI/PSI/90(06/95) with

A & C slip 1,2,3,4 or

latest

No. 04 -- -- 04 04 100 04

Page 54: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

54

Year of 09-10 Year of 10-11 Year of 11-12 Sl. No

P.L. No Description of Store RDSO’s Drawing No/ Specn. No.

Unit Yearly P.I

Quota

Qty. Recd.

% Recd.

Yearly P.I

Quota

Qty. Recd.

% Recd

Yearly P.I

Quota

Qty. Recd.

% Recd

7 46-99-0380 Vacuum bottle for 25KV Circuit

Breaker type VSE-5/20 make-BHEL

TI/SPC/PSI/ CB/0000 with

A & C slip 1 to 4 or latest No.

02 -- -- 02 01 50 02

8 46-99-0392 Vacuum bottle for 25 V iterruptor type

VSE 5/8

ETI/PSI/167(9/97) with

A & C slip :1 No.

20 -- -- 20 -- -- 20

9 46-99-0409 Drop out fuse switch assembly (W/O

insulator)

ETI/PSI/4 (1/66) Rev:1

April 87 No.

50 -- -- 50 30

20

60

40 50

10 46-99-0410 Battery Lead Acid 40 AH-LM Set 03 -- -- 03 03 100 03

11 46-99-0422 Battery Lead Acid 200 AH-LM

RDSO/PE/SPEC/TL/

0040-2003 (Rev-0) Set

03 -- -- 03

03

01

(Jan’10)

100

34 03

12 46-99-0434 Battery charger Lead Acid

40 AH-LM

ETI/PSI/1 (6/81) No. 03 -- -- 03 04 121 03

13 46-99-0446 Battery charger Lead Acid

200 AH-LM

ETI/PSI/24 (6/81) No. 02 -- -- 02

--

02 -- 100

02 03 133

14 46-99-0471 18 mm Copper Bus Bar RE/30/OHE/5 (11/60)

18-613-2000

M 12 -- -- 12 -- -- 12

15 46-99-0483 36 mm Tubular Al Bus Bar GR GIE

to IS:5082-1998

IS: 2673-2002 M 36 -- -- 36 -- -- 36

16 46-99-0495 36mm Al Tubular connector

a) 36mm Al Bus TEE Connector

ID No.6501 Mod B. & 6492 Mod C

a) 36/20mm all terminal connector

ID No. 6482, 6592 & 6531

GR 91E to IS 5082-1998

2673-2002

No.

No.

No.

10

10

10

-- -- 10

10

10

-- -- 10

10

10

17 46-99-0501 Copper Cable 2x2.5 Sq mm (LT for

PT)

IS: 1554 PT-1 1998 M 200 -- -- 200 -- -- 200

18 46-99-0513 Copper Cable 2x4 Sq mm (LT for

CT)

IS: 1554 PT-1 1998 M 200 -- -- 200 -- -- 200

19 46-99-0525 Copper Cable 7x2.5 Sq mm

(LT for Interruptor/CB)

IS: 1554 PT-1 1998 M 45 -- -- 200 -- -- 200

20 46-99-0574 Fuse carrier fibre tube for DO fuse

25KV outer dia 32mm length 53mm

ETI/PSI/032 No. 02 -- -- 50 50 100 50

21 42-99-1171 Fuse wire element for (DO fuse) AT 1

Amp

ETI/PSI/14(1/06) No. 09 -- -- 900 -- -- 900

22 46-99-0598 End fitting for DO fuse 25 KV

Dia 32mm

ETI/PSI/14(1/86) No. 10 -- -- 50 50 100 50

23 46-99-0616 Swivel with hook for DO fuse 25 KV

dia-32mm

ETI/PSI/14(1/86) No. 04 -- -- 50 30 60 50 50 100

Page 55: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

55

Year of 09-10 Year of 10-11 Year of 11-12 Sl. No

P.L. No Description of Store RDSO’s Drawing No/Specn. No.

Unit Yearly

P.I Quota Qty. Recd.

% Recd.

Yearly P.I

Quota

Qty. Recd.

% Recd.

Yearly P.I

Quota

Qty. Recd.

% Recd.

24 46-99-0630 Jaw with terminal connector for DO fuse 25

KV dia-32mm

ETI/PSI/14(1/86) No. 04

50 08 30 -- -- 30 50 165

25 46-99-0653 Horn link for DO fuse 25 KV dia 32mm. ETI/PSI/14(i/86) No. 02 20 1000 50 30 60 50

26 46-99-0689 36/15 mm Al Bus to centenary tap

connector

ETI/OHE/P/6660 Mod-B No. 20

-- -- 20 20 100 20 20 100

27 46-99-0677 36 mm Al Bus to PAD terminal connector

for 25 KV isolator

ETI/OHE/P/6480 Mod -C No. 50

-- -- 20 20 100 20

28 46-99-0690 PAD to Al conductor terminal connector ETI/OHE/P/6830-01 Mod C No. 03

-- -- 20 30

20

150

100

20

29 46-99-0458 Operating Rod (Pole) ETI/PSI/14 (1/86) No. 03 -- -- 10 -- -- 10

30 46-99-0586 Fuse carrier fibre tube for DO fuse 25 KV

outer dia 32mm length 53mm.

-- No. 03

-- -- -- -- -- --

31 46-99-0604 End fitting for DO fuse 25 KV dia-25mm -- No. 02 -- -- -- -- -- --

32 46-99-0628 Swivel with hook for DO fuse 25KV dia-

25mm

-- No. 12 -- -- -- -- -- --

33 46-99-0641 Jaw with terminal connector for DO fuse

25KV dia 25mm

-- No. 36 -- -- -- -- -- --

34 46-990665 Horn link or DO fuse 25KV dia-25mm. -- No. 10

-- -- -- -- -- --

35 46-99-0707 Micro processor based for feeder protection TI/SPC/PSI/PROTECT/507

0 (05/07) No. 200 -- -- 02 02 100 02 02 100

36 46-99-0719 Delta-I type fault selective relay for 25 KV

single phase traction system

TI/SPC/PSI/PROTECT/198

2 No. 200 -- -- 02 02 100 02

37 46-99-0720 HT capacitor cell 220KV AC 8KV ETI/PSI/67(11/96) with

A & C slip 1-6 No. -- -- -- 15 -- -- 15

38 46-99-0732 42KV 10KA metal oxide gapless type

lightning arrestor

ETI/PSI/71(Rev-1) 1/87

with A & C slip 1& 5 (8/94) No. -- -- -- 15 -- -- 15

39 46-99-0744 Single pole high speed based differential

relay of make- Alind/ Ashida

ETI/PSI/65 (1/97) with

A & C slip. 1 (3/99) &

2 (04/02)

No. 02 02 100 02 -- -- 02

40 46-99-0756 IDMT single pole over current relay

Make- Alind/ Ashida

ETI/PSI/65 (1/97) with

A & C slip. 1 (3/99) &

2 (04/02)

No. 03 -- -- 03 02 67 03

41 46-99-0768 IDMT single pole over current relay with

instantaneous tripping.

Make- Alind/ Ashida

ETI/PSI/65 (1/97) with

A & C slip. 1 (3/99) &

2 (04/02)

No. 02 -- -- 02 02 100 02

Page 56: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

56

Year of 09-10 Year of 10-11 Year of 11-12 Sl. No

P.L. No Description of Store RDSO’s Drawing No/Specn. No.

Unit Yearly P.I

Quota

Qty. Recd.

% Recd.

Yearly P.I

Quota

Qty. Recd.

% Recd.

Yearly P.I

Quota

Qty. Recd.

% Recd.

42 46-99-0770 Instantaneous high stability restricted

earth fault relay for HV/LV.

Make- Alind/ Ashida

ETI/PSI/65 (1/97) with

A & C slip. 1 (3/99) &

2 (04/02)

No. 04 04 100 04 -- -- 04

43 46-99-0781 Single pole voltage polarized, inverse

time, over voltage relay for Capacitor

bank. Make- Alind/ Ashida

ETI/PSI/65 (1/97) with

A & C slip. 1 (3/99) &

2 (04/02)

No. 01 -- -- 01 -- -- 01

44 46-99-0793 Single pole voltage polarized, inverse

time under voltage relay for

Capacitor bank. Make- Alind/ Ashida

ETI/PSI/65 (1/97) with

A & C slip. 1 (3/99) &

2 (04/02)

No. 01 -- -- 01 -- -- 01

45 46-99-0800 IDMT single pole over current relay

for capacitor bank. Make- Alind/

Ashida

ETI/PSI/65 (1/97) with

A & C slip. 1 (3/99) & 2

(04/02)

No. 02 -- -- 02 -- -- 02

46 46-99-0811 Unbalanced current protection relay

for capacitor bank. Make- Alind/

Ashida

ETI/PSI/65 (1/97) with

A & C slip. 1 (3/99) &

2 (04/02)

No. 02 -- -- 02 -- -- 02

47 46-99-0823 Silica gel breather clear vision

transparent, oil seal type threaded

terminal to suit with 25 KV Alind

Vacumm Interruptor, Alind vacumm

CB & AT

Capacity to contain 250

gm. of Silica Desiccant

Model DTO-B or

similar.

No. 210 -- -- 210 250 119 210

48 46-99-0835 Feeder wire splice (150 sqmm) (ID-1100) RDSO’S Drg.

No RE/33/P/1100

(Assembly of ID-

1101,1102,1103,1104)

Set 140 -- -- 140 -- -- 140

49 46-99-0847 Alluminium alloy revets, size

6x36mm for fabrication of BFB

steady arm.

RDSO’S Drg. No

ETI/OHE/P/2540 item

No 7,IS Span No 2907.

No. 1400 -- -- 1400 1500 107 1400

50 46-99-0859 Alluminium copper Bi-metallic strip,

size-600x300x1mm

RDSO’s Spn. No

ETI/OHE/55 (4/90)

No. 220 100 22 220 150 68.18 220 120 54.55

Page 57: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

57

ANNEXURE-XVIII

AVAILABILITY OF CRITICAL STORE ITEM

Asansol Depot Madhupur Depot Sl. No.

Item Population Spare Population Spare

Total Remarks

1. Auxiliary

Transformer

100 KVA-NIL

10 KVA -193 Nos.

5 KVA –01 No.

10 KVA – 02 Nos. 100 KVA-02 Nos.

10 KVA-75 Nos.

NIL

01 No.

NIL

01 Nos.

2. Interrupter Vacuum-95 Nos.

SF6(ABB)-02 Nos.

Vacuum-02 Nos.

ABB-01 No.

SF6(ABB)-19 Nos.

Vacuum-12 Nos.

SF6(CGL)-06 Nos.

NIL 03 Nos.

3. 132 KV Circuit

Breaker NIL NIL

SF6 (BHEL)-01 No.

SF6 (CGL)-02 Nos. NIL NIL

4. 25 KV Circuit

Breaker

Vacuum-04 Nos.

SF6(ABB)-01 No.

Vacuum-01 No.

SF6-01 No.

SF6-03 Nos.

Vacuum-06Nos. NIL 02 No.

5. Current

Transformer

132 KV -Nil

25 KV–09 Nos.

25 KV-02 Nos.

132 KV CT-06 Nos.

25 KV CT-14 Nos.

02 Nos.

02 Nos.

02 Nos.

06 Nos.

6. Potential

Transformer

Type- 1 –55 Nos.

Type- II - 09 Nos.

Type- 1-01 No.

(released)

Type-1 – 19 Nos.

Type- II - 06 Nos.

01 nos.

03 Nos.

04 Nos.

03 Nos.

7. 120 KV LA NIL NIL 08 Nos NIL NIL

8. 42 KV LA 104 Nos. 02 Nos. 48 Nos. 07 Nos. 12 Nos.

9. Capacitor Bank 2 FPs 02 Cells 02 TSSs 18 Cells 05 Cells

SCRAP MANAGEMENT ANNEXURE -XIX

Achieved during the year in MT Target for year

in MT During the

month in MT Cumulative

in MT Sl No Material Description

2008-09 2009-10 2010-11 2011-12 October’11 2011-12

Credit received

Remarks

1. Ferrous 29.896 94.106 143.482 100.00 1.553 20.839 --

Copper 14.889 19.152 16.791 20.00 0.540 8.172 --

Alluminium 0.750 0.721 2.383 2.00 -- 0.242 -- 2. Non-ferrous

Brass 0.801 -- 1.773 -- -- 1.094 --

Page 58: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

58

ANNEXURE -XX

STOCK SHEETS, ACCOUNTS INSPECTION REPORTS & AUDIT INSPECTION REPORTS

Description Opening balance as on 01.06.10

Accretion Closed as on 30.07.10

Closing balance as on 01.08.10

Initial reply not submitted

Cases require further clarification

Cases pending with audit

Cases pending with accounts

Audit inspection report (Part-I)

-- -- -- -- -- -- -- --

Audit inspection report (Part-II)

-- 02 -- NIL -- -- 02 --

Accounts inspection Report-I

NIL -- -- NIL -- -- -- --

Accounts inspection Report-II

NIL -- -- NIL -- -- -- --

Stock sheets 01 -- 01 NIL -- -- -- --

ANNEXURE –XXI

AVAILABILITY OF TOWER CARS AT VARIOUS DEPOTS AND POH POSITION

Sl. No.

Tower wagon no

Type of Tower Wagon

DEPOT RKM TKM Km Run Year of

Coms

LAST POH

POH DUE

Age as on 01.04.2010

Return from POH

Remarks

1 ER-839 Mark-II JMT 45 126.64 1305 1981 09/2010 09/2014 30 Yrs. 09.09.2010 Working.

2 ER-843 Mark-II PAN 56.3 278.3 910 1988 05/2010 05/2014 23 Yrs. 24.05.2010 Working.

3 ER-774 Mark-III PAN 56.3 278.3 -- 1992 03/2004 03/2008 19 Yrs. 05.03.2004 Working`

4 ER-782 Mark-III BRR 39 122.1 510 1998 08/2011 08/2015 13 Yrs. 13.08.2011 Working

5 ER-869 Mark-IV JSME -- -- 1450 03/2010 New recd. 03/2014 New -- Working

6 ER-816 Mark-II UDL -- 423.184 620 1964 10/2010 10/2014 47 Yrs. 28.10.10 Working

7 ER-832 Mark-II MDP 50 112 872 1975 01/2011 01/2015 36 Yrs. 29.01.11 Working

8 RU 02901 8-Wheeler JSME 49 112.5 -- 02/2003 10/2011 10/2015 08 Yrs. -- Taken over from KPA on 15.10.11

after POH.

9 RU 00905 8-Wheeler ASN/CON -- -- 805 11/2001 03/2010 03/2016 09 Yrs. -- Working

10 RU-814 8-Wheeler ASN 21 160.6 405 06/1999 05/2009 05/2015 11 Yrs. 11.05.2009 Working

Page 59: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

59

DETAILS OF MAINTENANCE OF TOWER WAGONS ANNEXURE –XXI/A

Tower Wgon No. Sl. No.

Date of last Maintenance ER-839 ER-843 RU-814 ER-782 ER-816 ER-832 ER-774 RU-2901 RU-00905 ER-869

1 Weekly 30.01.11 16.11.10 14.01.11 29.11.10 10.04.10 16.08.10 21.01.11 01.04.10 24.07.09 --

2 Fortnightly 25.04.10 22.08.10 22.03.10 25.03.10 28.04.10 20.08.10 29.01.11 -- 06.01.08 --

3 Monthly 30.09.11 02.09.11 09.09.11 05.01.11 03.10.11 27.10.11 03.08.11 12.05.11 09.08.11 24.10.11

4 Six Monthly 27.03.11 11.10.11 27.08.11 29.04.09 04.04.11 29.08.11 02.05.11 20.10.10 14.10.11 --

5 Yearly 17.01.06 25.07.07 24.09.10 23.12.09 07.10.09 13.08.09 07.08.07 18.12.10 10.08.07 --

6 Two Yearly 02.06.07 05.01.06 15.09.05 27.06.07 21.08.07 04.08.07 25.05.06 24.06.05 18.03.06 --

Remarks -- -- -- -- -- -- -- -- -- --

STAFF TAKEN UP FOR FAILURE / BREAKDOWN ANNEXURE –XXII

Sl. No. Name Designation Head quarter

Description of failure/Breakdown Action taken Reference letter No.

1. Sri D.C. Marandi SSE/OHE/BRR BRR Catenary wire of out of run OHE has been

parted under Catenary suspension clamp at

loc. no. 227/21 on UP/GC between ULT-

BRR. Catenary wire parted due to previous

strands cut under suspension clamp.

SF-11 has been issued. Sr. DEE/TRD/ASN’s letter no.

ACOE/20/DCM/2269 dated 18.10.11.

ANNEXURE –XXIII/A

Minutes of CEEs conference held at Railway Board on 30th & 31st Aug’07 at Railway Board

Item No. Item Status Remarks RE CRB

1.1 While addressing the CEEs, CRB mentioned that composite/porcelain insulator could be used in

non-polluted areas. However, for polluted zones, only composite insulators to be used. The detailed

instructions have already been issued by Board.

Being followed. Total 8079 Nos. Composite

Insulators have already been provided in this

Division up to April’11.

1.2 To facilitate the running of Garib Rath trains in the minimum OHE height above rail level to be kept

as 4.69 meters. RDSO has been advised to revise the SOD Revised 2004 accordingly. The power of

CEEs to reduce the height of contact wire has been frozen.

SS Wire rope parted due to lack of

lubrication and rubbing with the pulley

groove.

Pertains to RDSO

1.3 Rehabilitation of OHE should be planned particularly where life of OHE is more than 40 years old.

The life of other OHE components is under consideration in Board’s office.

Division to give reply of Railway Board’s letter No

2007/Elect(G)/ 220/2/Pt.I dated 17.11.2009 on

Codal life of TRD assets

Reply under preparation.

Page 60: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

60

Item No. Item Status Remarks 1.4 For facilitating BCM and other engineering P.Way machines working’ the foundations may be

redesigned so that the clearance towards track could be enhanced without infringing the concrete block

of foundations. RDSO may examine.

-- Pertains to RDSO

1.5 The failure of core insulators in section insulators where potential difference is on higher side may be

taken care by replacing the core insulators on section insulator after some time or use section insulator

with double core insulators. RDSO may examine.

-- Pertains to RDSO

2.0 Discussion on Agenda Items.

2.1 TRD : AML and EDRE complimented Zonal Railways for reduction of 36.5% in punctuality loss cases

on account of TRD during the period April to July 2007.

Punctuality loss

2010-11 (Upto

current month)

2011-12 (Upto

current month)

64 33

2.2 On detailed analysis of TRD failures due to insulators in Board’s office, it was noticed that from

April’2007 to 23.08.07, out of 17 cases, 11 cases of failures of 9 Tonne porcelain insulators have been

reported, leading to loss of punctuality of trains,. It shows the trend that 9 tonne insulators are more

failure prone. RDSO may undertake the batch wise analysis of 9- tonne failure prone insulator and given

recommendations to contain the failures. RDSO was advised to issue guidelines incorporating cheek

checklist to identify failure prone in service insulators. RDSO was also advised to identify the batches, if

any, which is more failure prone.

There is no identified failureprone insulators

in this division. However, Make & Batch of

the following insulators are yet to be identified

or invisible.

Depot Stay Bkt 9-tonne

PAN -- -- 135

UDL 08 22 --

ASN 18 34 05

2.3 AM/L also emphasized that the proper inspection should be carried out while procuring insulators. It

was also mentioned that the new specification of porcelain /composite insulators have been issued and

have been frozen for five years. The 9 –tonne insulators of revised specifications are also likely to give

improved performance in the filed.

There is no failure of composite insulator of new

specification No. TI/SPC/OHE ISCOM/1070 and

porcelain insulator of new specification No.

TI/SPC/OHE INS/0070 till date.

3.0 Sidings.

3.1.1 CRS & ME had emphasized upon early completion of electrification of sidings. NIL 3.1.2 AML stressed that the target for completion of electrification of sidings of December’ 07 should be

strictly adhered to as Hon’ble MR is closely monitoring the progress.

NIL

3.1.3 CEE/ECR raised the issue of non availability of contact and catenary wire and other materials for

completion of sidings works from CORE/ALD and it was suggested that one of the Zonal Railways may

be nominated other than RE for centralized procurement of materials like contact and catenary wire.

Contact & catenary wires are being procured

through CMM/KKK.

3.1.4 Pertaining to SECR and EcoR. -- 3.1.5 Zonal Railways represented that the targets of electrification of sidings are difficult to be met since a lot

of items are centralized for procurement by CORE and CORE is not supplying these items timely,

therefore, electrification of siding works, is delayed. It was decided that the proposal for decentralization

of stores items shall be processed again in Boards office.

Procurement process has already been

decntralised.

3.1.6 AML directed that the proposal regarding decentralization of procurement of materials could again be

processed and a meeting can be convened between AM/L and AM/Stores to sort out the issue.

Procurement process has already been

decntralised.

Page 61: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

61

Item No. Item Status Remarks 4.0 Standard Implantation

As deliberated in the last ESC meeting held at Nainital, Board has issued revised instructions vide letter

No. 2002/RE/161/11 dt. 10.08.2007 as under :

(i) Implantation of 2.8 m for lines will be adopted for electrification of main lines, new gauge –

conversion works where formation is adequate and track centers of 5.9 m (min) is available. Where

these track centers are not available implantation on Main lines will be 2.50 hrs. (ii) Existing Main lines – implantation of 2.5m will be adopted wherever track centers are not 5.9m. (iii) For all yard lines implantation of 2.36 m will be followed.

Details of removal of critically implanted

OHE masts are given below.

2010-11

2011-12

(up to

September’11)

145 nos. 54 nos.

ANNEXURE –XXIII/B

Compliance of CEDE’s Conference held on 05.05.09

Item No

Item Status Remarks

1.0 Review of CR -- Pertaining to CR 2.0 Review of ER

2.1 Performance - Target is fixed as 4.8 per one thousand TKM for 2009-10 Cumulative performance up to current

month. (in per thousand TKM)

Prop. Target 2010-11 2011-12

2.80 5.01 2.99

2.2 Mast hit by open door wagon. ER shall plan this work on priority. More emphasis shall be given for

removing infringement on routes where empty movement is frequent.

Removal of infringements is in progress. Total

nos. of infringements already removed are given

below.

1010-11

2011-12

(up to October’11)

145 nos. 79 nos.

2.3

(i)

Grid supply failure- Close liaison with supply authority and checked how redundancy can be built in

system

Close liaision is being maintained with the supply

authorities to improve reliability of power supply.

2.3

(ii)

SCADA maintenance shall be monitored and Isolation of any activity from SCADA shall be monitored

by CEDE and reported to RB.

AMC of SCADA has been given to the OEM and

is valid up to 2011. No activity has been isolated

from SCADA in this division.

3.0 Review of ECR. -- Pertaining to ECR.

4.0 Review of EcoR. -- Pertaining to EcoR.

5.0 Review of NR -- Pertaining to NR.

6.0 Review of NCR -- Pertaining to NCR.

7.0 Review of SR -- Pertaining to SR.

8.0 Review of SCR -- Pertaining to SCR.

9.0 Review of SER -- Pertaining to SER.

Page 62: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

62

Item Status Remarks 10.0 Review of SECR -- Pertaining to SECR.

11.0 Review of SWR -- Pertaining to SWR.

12.0 Review of WR -- Pertaining to WR.

13.0 Review of WCR -- Pertaining to WCR.

14.0 SCADA

14.1 RDSO successfully completed trial at Umbala division of N.Rly. for “High speed data transfer

communication system” to achieve 9.6 KBPS data transfer speed with existing SCADA system and

modified communication scheme. Rly. Shall take necessary steps for upgrading the SCADA system for

high speed communication system. RDSO to issue modification sheet in this regard.

Modification sheet yet to be received by this

division.

14.2 All Zonal Railways were advised to send compliance of Inspection note of Member Electrical of BRC

– BCT division on 29.11.08. In inspection note, SCADA system operating on quad-cables must be

transferred to OFC cables in all Railways including small patches between “cable hut to switching

stations” . In this connection, it was advised to make the action plan and to send the target date

completion of work in co-ordination with S & T deptt. For ML”s Perusal. Railways have not sent the

same in proper format, hence Railways must send the compliance by format given at Annexure’A’

Compliance of ML’s inspection Note of BRC-

BCT division regarding SCADA has already

been sent to HQ as per prescribed annexure.

Though OFC cables are available on main line

sections, quad-cables are till existing on the

small patches between cable huts to all the

switching stations in this division.

S&T department has

already been requested to

supply the cost estimate

and action plan for

conversion of the existing

small patches quad-cables

between cable huts to all

the switching stations into

OFC cables.

14.3 Railways shall plan AMC of SCADA on regular basis Being followed.

14.4 RE & RVNL shall ensure in all Projects the SCADA shall have optical fibre as discussed in para2 of

the letter.

-- Pertaining to RE & RVNL.

14.5 RDSO shall finalize the specification of SCADA on TCP/IP open protocol for future procurement.

There shall be provision video wall. RDSO shall send the specification by 30.05.09.

Specification yet to be received.

15.0 Insulator 15.1 Board have issued the policy regarding provision of composite insulators in Vandalism Prone areas as

well as polluted zones.

Railway Board’s policy for provision of

composite insulators in Vandalism Prone areas

as well as polluted zones has been received

and is being followed.

Total 3193 Nos. Composite

Insulators have already

been provided in this

Division up to Mar’10.

15.2 In this connection Board also advised Zonal Railways vide letter No. 2008/Elect(G)/161/1/Pt dated

17.03.09 to identified the polluted zones & Vandalism prone locations (with personnel approval of

CEE of the Zonal Railways). The position shall be complied by Railways within week’s time and

summarized position shall be sent as per format ’C’.

List of poluuted zones and vandalism prone

locations have already been sent to HQ.

15.3 Board have issued a letter regarding Testing Machine for OHE Insulator testing which are portable,

easier to handle and does not require any foundation. RDSO have also issued the specification for this

machine. All divisions and construction organization shall have one such machine in OHE depot.

Procurement will be initiated through M&P.

15.4 All Railways must send the picture of insulator failure to RDSO through E-mail. Insulators shall also

be sent to RDSO on the request of RDSO. RDSO shall make standard pictorial view to identify

different cause of failures.

Will be ensured.

Page 63: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

63

Item No

Item Status Remarks

16.0 Predictive maintenance. 16-+

Board have issued a letter regarding on line monitoring of hard spots (Flashes) by adopting OLIVER-G

vide letter No. 2004/RE/220/4/pt dated 29.11.2005. in which Zonal Railways were advised to

introduce initially at least one OLIVER system for current Collection Test. Vide Board’s letter No.

2004/RE/220/4/Pt dated 16.02.06 to send the progress of same along with field experience to be

communicated for Board’s perusal in PCDO.

Mapping of OHE in STN-JAJ section has

already been completed during 2008-09.

Current collection in the above section is

being conducted.

16.2 All electrified Railways mast have one Oliver ‘G’ plus equipment per Division. Target-30.12.09 Procurement was initiated through M&P.

16.3 All electrified Railways must have Thermo vision camera per electrified division. Target-30.12.09 01 No. Thermo vision camera has already

been procured in this division.

16.4 All Railways shall send the GPS data sheet to RDSO for better monitoring to RDSO. GPS mapping

data should be sent to RDSO by 30.09.09.

GPS data sheet of OHE for STN-JAJ section

will be sent to HQ shortly.

17.0 Others issue 17.1 M/S ABB has modified BM/CB 05.05.09 SCR. The failures in modified CBs shall be monitored by

RDSO and SCR

-- Pertaining to RDSO &

SCR

17.2 The work of Transmission line in SECR, NCR, NR has been fixed as March’2011. RE and Railways shall

study that where demand charges are more than Rs.150/- per KVA lying Transmission line is economical for

reducing Traction tariff. For all new sub-station on existing electrified tariff, Railways shall explore the

option of constructing transmission line from Existing connection.

-- Pertaining to SECR, NCR,

NR

17.3 Trails for corrosion resistant paint shall be completed by identified railways by 30.7.09. Corrosion resistant paint has been applied on

50 Nos. rusted OHE masts up to a heght of

75cm above the top of muff during the month

of Sep’09.

17.4 ECR must practice of joint Checking of Pantograph in Loco shed with TRD staff. -- Pertaining to ECR

17.5 ER must study the reason for high DVC tariff, as tariff in ECR is 3.69/- while in ER it is 4.10/- ER unit.

During 2008-09 DVC tariff was 3.72/- per

unit, in 2009-10 DVC tariff was 4.49/- per

unit and in 2010-11 DVC tariff was 3.05/-

per unit (provisional).

Increase in tariff is due to

adjustment of arrear fuel

surcharge with effect from

Apr’08 to Apr’09 due to

increase of fuel surcaharge

from 80.71 paisa/KWH to

138.45 paisa/KWH with

effect from Apr’08.

17.6 SER shall plan OHE replacement work in big way as assets are of 1955-1965. -- Pertaining to SER

17.7 ECoR has not finalized the SCADA work. This needs to be expedited -- Pertaining to ECoR

17.8 NR has given the PDC for conducting trials for modular OHE fitting – March’2010 and for motorized

isolator – March’2010. NR shall monitor it in close coordination with RDSO.

-- Pertaining to NR

17.9 NCR should prepare the action plan for power exchange and fix the target. -- Pertaining to NCR.

17.10 WCR pointed out the difficulty in maintenance of power transformer. RDSO shall collect the

information from all zonal railways for making STR.

-- Pertaining to WCR.

17.11 RDSO must comprehensive action plan for improving reliability of OHE. -- Pertaining to WCR.

18.0 Power exchange. -- Pertaining to NCR.

Page 64: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

64

19.0 DRPC Item No

Item Status Remarks

19.1 CORE and RVNL were advised to provide DRPC on all new substations. -- Pertaining to CORE and

RVNL.

19.2 RDSO will advise the suggested ratings for new substation. -- Pertaining to RDSO.

19.3 CORE/RVNL must ensure that area of room shall be such provided so that it can meet future

requirement. RDSO shall standardize the size of room.

-- Pertaining to CORE and

RVNL.

ANNEXURE-XXIII/C

Implementation of Recommendation No. 1.1 made in Part-I of Report of Railway Safety Review Committee-98 (Khanna Committee)

ItemNo./Para No.

Item Status Remarks

7.10

2.14.11

A register to drivers observation during his run must be maintained in all lobbies and this information should be conveyed to

Traction /Power Controller under exchange of private numbers. PRC/TLC should in turn convey this to concerned departments

who would rectify the defects and the same should be conveyed to lobby for information of driver.

N.A. This is related to Traction

Rolling Stock (Operation)

deapartment.

25.1

3.5.1(ii)

For the guidance of the inspecting officials, detailed checklists for various types of inspections need to be made out. For inspection

checklists are

available.

25.2

3.5.1(ii)

Each item of checklist to be covered after a specified period by designated levels and record maintained. Noted Being followed.

25.3

3.5.2

Apart from these detailed inspections, other field visits of the inspecting officials should be focused on random check of some

items out of the checklist, in addition to action taken on previously noticed shortcomings.

Noted Being followed.

ANNEXURE-XXIII/D

Implementation of Recommendation No. 1.1 made in Part-II of Report of Railway Safety Review Committee –98 (Khanna Committee)

Item No. Item Status Remarks 9

2.9.9

Purely on grounds of enhancing the safety of the system, creation of adequate infrastructure for maintenance (both for fixed and moving

assets) and line/terminal capacity must get the highest priority in the investment planning process on par with replacement and renewal of

over-aged assets.

Noted Shall be ensured.

12

2.11.5(ii)

A reassessment of the coadal life of major assets on IR should be done by a small disciplinary team of Railway and outside expert on the

basis of past performance of the assets, extent of use and other related factors.

Noted --

2.11.5(iii) IR must introduce a proper prioritization for the renewal of major assets based on the importance of the route, the extent of wear and tear, the

extent of use and most importantly, the performance of the assets from the safety angle and the cost of maintenance.

Noted --

21

3.1.2

The committee reiterates in the strongest possible terms that IR needs to improve its implantation of safety items by planning each-with

physical/financial benchmark spread over several years.

Noted --

65

4.11.2

A detailed divisional plan for arrangements to execute scheduled work involving line blocks be made for a week in advance covering all

departments and thereafter adhered to.

Being

followed.

--

95

3.10.03

On all Divisions concerned officers and supervisors should be provided with mobile breathalyzer equipment for testing running staff on the

footplate on a regular basis.

Not

available.

--

Page 65: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

65

ANNEXURE –XXIII/E OHE Reliability :

Sl. No.

Item

Total on line

Progress During the

month

Progress up to

the month

No. of locations observed where

adjustment required during the month

No. of locations observed where

adjustment required, up to the month

Location attended during the month

Location attended up to the month

Remarks

1. Live line checking of OHE

by 8 wheeler tower wagon

in TKM

828.5 308 644 -- 48 -- 29 --

2. Checking of free movement

of ATDs

2273 1657 11166 30 57 13 21 --

3. Re-tensioning of FTAs 316 01 17 -- 01 -- 02 --

4. Checking and adjustment of

cross-over & turn-out

917 21 184 09 57 09 57 --

5. Checking and adjustment of

regulating equipment

2273 909 3973 31 121 08 38 --

6. Cleaning of Insulators

Total No. of Insulators No. of Insulators cleaned during the month Cumulative No. of Insulators cleaned up to the month

Remarks

53997 1927 14023 --

7. Lead Sealed Insulators, if exist

Total No. of Insulators No. of Lead Sealed Insulators replaced during the month

Cumulative No. of Lead Sealed Insulators replaced up to the month

Remarks

2431 -- 56 --

ANNEXURE –XXIII/F Minutes of the Performance Review meeting held in Railway Board on 28.09.2010.

Item No.

Item Status Remarks

4.0 Electrical Energy Management 4.1 Panto Entanglement in serious concern and needs to analyses the each case in depth at

higher level.

Analysis of Panto entanglement cases are being sent to HQ as per prescribed

Annexure 9.03 of ACTM Vol-III.

4.2 Insulator cleaning in polluted/corroded area needs special focus specially in CR. Progress during the month 236 Nos.

Cumulative : 420 Nos.s

--

4.3 Training of staff by conducting mock drill at model OHE in OHE depots after setting

target time for each maintenance activity shall be ensured.

-- --

Page 66: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

66

Item No.

Item Status Remarks

4.4 Lightning arresters should be checked by Third Harmonic Distortion (THD)

measurement equipment. LA failures and OHE failures due to bad weather can be

avoided by use of this equipment. RDSO should issue the instruction for provision of

LA at alternate AT location. CORE should ensure the quality of the new LA.

Progress during the month : Nil

Cumulative : 07 Nos.

4.5 Current collection and use of Thermo vision camera should be ensured for checking of

hot spot.

Current collection test is being conducted in main lines quarterly. One no. thermo

vision camera has been procured by the division in 2010-11. Checking of hot spots

in TSS and switching stations are being done using thermo vision camera.

4.6 To reduce the breakage of insulators, it shall be ensured during maintenance that

cantilevers are having free movement to avoid failures due to bending stresses.

-- --

4.7 Railway should avoid the high voltage traction supply, which increases the Specific

energy consumption.

There are four take off points in the division. 123kV supply received at

BDME/GSS & JMT/GSS and 25 kV supply receiced at DTPS/GSS &

KMME/GSS.

4.8 Railway should ensure regular calibration of energy meter for correct recording of

energy consumption.

DVC & JSEB authorities has been requested for joint checking & calibration of

energy meters.

4.9 AM/L in his address emphasized the need of maintenance & stated as under : 4.9.1 Pantograph entanglement cases continue to be routinely ascribed to storms while

maintenance of stagger and gradients are not getting checked. Unsettled disputes of

tracks slewed/lifted may lead to acceptance of tolerance beyond specified limits.

Instructions are wherever track is attended implantation is to be honoured.

Being followed

--

4.10 Traction energy consumption has increased in SWR, WR. Railways to investigate in

details and correct entry of data at base level to be ensured.

-- Pertains to SWR & WR.

4.11 Railways shall plan for different means of energy conservation and optimum

manpower utilization. The effort made by NCR for “Automation of pumps by remote

operation & fault logging features” was appreciated.

1)Cold stand by of Traction transformers are being maintained.

2) Paralleling of double line feeders to TSS, where double line is available is being

done.

3) Proposal for upgradation at two Cap Bank sent for inclusion.

4.12 CR should prepare the proposal of solar based generating station. -- Pertains to CR.

ANNEXURE – XXIV REPORT OF NEW EQUIPMENT UNDER TRIAL

A. SS wire rope with Specification No. TI/SPC/OHE/WR/ 1060 (6/06) with A&C No. 1&2 Total Population of Modified 3

Pulley type ATD with modified Pulley Groove. Nos. received Nos. distributed to OHE Depots Nos. installed in Modified 3 Pulley

type ATD with modified Pulley Groove

Failure if any

388 198 171 86 Nil

B.

Total No. of Lightning Arrestor Total No. of Surge Counter provided Action taken for provision of Surge Counter

THRC Action taken for procurement of THRC

176 40 Procurement for remaining is under

process.

01 Leakage current monitor procured by

the division & the material received

on 06.05.10.

Page 67: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

67

ANNEXURE –XXV 1.0 Special drive & inspection of OHE Sl. No.

Works Quantity of works

Works completed

Target of remaining work Action plan for remaining work

A) Action plan as per D.O. letter no. 2008/Elect. (G) / 161 / 8 / Punct. dated 08.09.2010 1. A drive to check turnouts /cross over OHE for its

proper adjustment / alignment and furnish

compliance in next 3 months.

917 nos. 184 nos. 31.03.12 --

2. Identification of 9-Tonne insulators having core

dia of 72 mm and approprite action .

5290 nos. 4942 nos.

31.03.12 GO-NOGO gauges mounted on Operating rod have been made

and given to the depot to identify 9-tonne insulators with 72

mm core diameter. Total 3262 nos. 9-tonne insulator with 72

mm core diameter have been identified.

3. Updated compilation of SMIs / MIs of RDSO in

every depot

13 depots 13 depots. All TRD Depots of the Division have been provided with a compilation of all SMIs/MIs

of RDSO four years back. Also copies of RDSO’s SMIs/MIs are being circulated to all

field Officers and maintenance Depots as and when received by the Division. Bound updated compilation of SMIs/MIs has been prepared by the division and circulated to all

TRD Depots in January’11.

4. Provision of screens to 1.83 M height on all FOBs

to cover gaps wherever existing between two line.

15 nos. 08 -- The same will be taken up with the Engineering

Department and complied with.

B) 1. Live line checking by TW 828.5 TKM 644 TKM 31.03.12 --

2. Checking of anti-creep wire 602 nos. 176 nos. 31.03.12 --

3. Checking of buried rail connections 04 nos. -- completed. --

4. Provision of missing structure bonds / Rail bonds 16157 nos. 624 nos. -- --

5. The progress of seasonal cleaning of insulators. 53997 nos. 14023 nos. 31.03.12 --

6. Replacement of Insulators by composite / antifog

insulators in polluted zones specially in NR &

NCR

4576 nos. 214 nos. The requisition for 2522 nos. composite insulator (Reqn Nos. 351050036 & 351050035 dt.

19.11.09) .has been resent to HQ with reduced rate on 23.08.10 against existing sanctioned work for

replacement of broken insulators by composite insulators in polluted/ vandalism prone areas.

P.O.has been issued.

7. To check the healthiness of the lightning arrester

in lightning prone area

138 nos. 80 nos. 31.03.12 --

8. Attention of critical implantation (< 2.36 M +

curve allowance) mast on main line

2727 nos. 54 nos. Another 356 nos. can be

removed through existing

works. Target date : 31.07.12

--

9. Joint checking of pantograph by TRD & TRS staff All 1007 -- Joint checking of Pantograph is being conducted

regularly in the Division.

Page 68: LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS … · LOSS OF PUNCTUALITY OF MAIL/EXPRESS TRAINS (OHE & GRID) Sl. No. Date No. of Trains Train No. Detn. ... 132 KV supply tripped from

68

Sl. No.

Works Quantity of works

Works completed

Target of remaining work

Action plan for remaining work

10. Provision of bird & monkey scare measures at

portals & designated location

-- 72 -- PVC pipes are being provided inside portal/TTC drop arms

to prevent bird nesting. PVC pipes have already been

provided at 1608 nos. locations up to the month.

11. Tree branch trimming All 20167 nos. -- --

12. Cutting of trees with Engineering department 465 nos. 249 nos. -- --

13. Replacement of rusted cantilever assembly 7985 nos. 486 nos. Another 2712 nos. can be replaced through existing sanctioned work.

14. Checking of RRA clamp to avoide necking &

parting of contact wire

2235 nos. 460 nos. 31.03.12 --

15. Free movement of cantilever 21592 nos. 6732 nos. 31.03.12 --

16. Checking of P.G. clamps, splices by thermo vision

camera

8550 nos. 3666 nos. 31.03.12 --

17. Checking of all the along / vertical feeders

opposite to TSS / SP/ SSP gantries

90 nos. 140 nos. -- --

18. Replacement of G - Jumpers / cross feeders of 105

sq. mm with 150 sqmm size in heavy loading

locations

-- 13 There is no cross feeder of 105 sqmm exist on line in this division. RDSO specification

for 150 sqmm ‘G’ jumper yet to be received by the division.

19. Replacement of silver brazing joint in Contact

wire

-- -- No records available regarding silver brazing joints in Contact wire.

20. Provision of anti theft Jumper in OOR OHE and

anticreep wire in theft prone area

2820 nos. 90 nos. For provision of anticreep jumpes, existing steel anticreep wires are required to be

replaced by copper catenary wire for which there is no sanctioned work.

2.0 Progress of Netra Car run : Sl. No.

Section Running date Nos. of bad location Total Nos. of location rectified

Targrt date for remaining location

Action Plan

NIL

3.0 Population of predictive Maintenance Tools :

Sl. No.

Division OLIVER-G Thermo Vision Camera GPS mapping for Netra Car

1. Asansol NIL 01 no. GPS mapping of 606 TKM OHE completed by OLIVR-G up to the month.


Recommended