Lost Creek Drive Road Rebuild Project Fall 2018 Public Works – Street Division
Transcript
Page 1: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

WWW.Columbia.SC.Gov/Engineering

Lost Creek Drive Road Rebuild

Project

Fall 2018

Public Works – Street Division

Page 2: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Public Works – Street Division

Page 3: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Overview

● Why Road Work is Needed

● Reclamation Method

● Project Schedule

● Lane Closures & Delays

● Things to Consider

● Resources Available to You

Public Works – Street Division

Page 4: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Why Road Work is Needed

● Road is in need of repairs due to major base failures

● Normal method is pothole repair

● Soil under Lost Creek Drive is currently not stable

enough for long term pothole patching or standard

overlay

Public Works – Street Division

Page 5: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Method for Reclamation

Public Works – Street Division

Page 6: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Method for Reclamation

● Full depth reclamation with cement

○ Recycle existing roadway

○ Added cement stabilizes road base

● Steps in process

○ Pulverize existing base

○ Mix in-place with water & cement

○ Grade & Compact Base

○ Wet Cure – Strength & Dust

○ Pave

Public Works – Street Division

Page 7: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Project Schedule

● Bid Contract – Complete

○ – Awarded to Armstrong Contractors, LLC

● Construction Schedule

○ – Construction Phases

● Will Take Approximately 15 weeks

● Milling Phase

● Cement (CMRB) Phase

● Paving Phase

Public Works – Street Division

Page 8: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Milling Phase

Public Works – Street Division

Page 9: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Cement Phases

Public Works – Street Division

Page 10: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Paving Phases

Public Works – Street Division

Page 11: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Traffic by Hour in Chestnut Hill

Public Works – Street Division

Page 12: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Lane Closures & Delays

○ The Contractor will enforce traffic control

○ Access to entrances

○ Efforts to control dust

○ Cure period of CMRB “Reclaimed” roadway (Wet Cure)

○ Construction will take place between the hours of 7:30 a.m.-5:30 p.m.,

Monday morning to Friday evening

Public Works – Street Division

Page 13: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Stationary Construction Signs 500’ from Intersections

Page 14: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Flagger and Pilot Cars

● Flaggers and possibly a pilot car will be used during

construction operations to assist with guiding residents

through the construction zone

● Please forgive the delays for these measures/procedures

are in place to provide continuous safe travel to

Chestnut Hill residents within the construction zone

Public Works – Street Division

Page 15: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Public Works – Street Division

Is It Ok To Pave In The Rain?

Page 16: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Considerations

● Weather Restrictions

● Rain

● If Temperature < 55 °F – cannot pave

● Utilities

○ Although utilities are supposed to be marked there is a high probability that

something is underground that is unknown.

○ Not uncommon to have depths above expected levels

● Other Considerations

○ Murphy’s Law

Public Works – Street Division

Page 17: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Social Media

● Posts Will be each Friday at 7:30 p.m.● Facebook

○ Construction status reports weekly

○ Updates on lane shifts and progress

● www.facebook.com/COCPublicWorks● Twitter

○ Construction status reports weekly

○ Updates on lane shifts and progress

● www.twitter.com/COCPublicWorks

Public Works – Street Division

#LostCreekPaving

Page 18: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

WWW.Columbia.SC.Gov/Engineering

Questions

Public Works – Street Division

Fall 2018