LQ Coil Fabrication at BNL. Jesse Schmalzle, BNL CM12 – 4/9/09. LQ Coil Status. LQ04 (practice coil) Completed and shipped 4/2/09. LQ07 Completed and shipped 4/2/09. LQ09 Reaction complete. Prep for impregnation in progress. LQ07 - Reaction. LQ07 - Reaction. - PowerPoint PPT Presentation
9
April 9, 2009 J. Schmalzle – CM12 1 Superconductin g Magnet Division LQ Coil Fabrication at BNL Jesse Schmalzle, BNL CM12 – 4/9/09
Transcript
Page 1: LQ Coil Fabrication at BNL

April 9, 2009 J. Schmalzle – CM12 1

Superconducting Magnet Division

LQ Coil Fabrication at BNL

Jesse Schmalzle, BNLCM12 – 4/9/09

Page 2: LQ Coil Fabrication at BNL

April 9, 2009 J. Schmalzle – CM12 2

Superconducting Magnet DivisionLQ Coil Status

– LQ04 (practice coil)• Completed and shipped 4/2/09.

– LQ07• Completed and shipped 4/2/09.

– LQ09• Reaction complete.• Prep for impregnation in progress.

Page 3: LQ Coil Fabrication at BNL

April 9, 2009 J. Schmalzle – CM12 3

Superconducting Magnet DivisionLQ07 - Reaction

0

50

100

150

200

250

300

350

400

450

500

550

600

650

700

0 24 48 72 96 120 144 168 192 216 240

Elapsed Time (hours)

Tem

pera

ture

(C)

T1T2T3T4T5T6T7T8T9T10

Page 4: LQ Coil Fabrication at BNL

April 9, 2009 J. Schmalzle – CM12 4

Superconducting Magnet DivisionLQ07 - Reaction

– BNL site wide power failure completely shut down reaction cycle after 40 hours at 640C.

– Coil had cooled to 555C before Argon flow was manually restarted.

– Coil had cooled to 520C over 5.5 hours before power was restored.

– Coil was brought back to 640C and held for 8 hours to complete the 48 hour step.

– Temperature at 640C step was a little low, adjustment made for next coil.

202

204

206

208

210

212

214

216

4 10 16 22 28 34 40 46 52 58 64 70 76 82 88

Elapsed Time (hours)

Tem

pera

ture

(C)

72 hours

392

394

396

398

400

402

404

406

84 90 96 102 108 114 120 126 132 138 144

Elapsed Time (hours)

Tem

pera

ture

(C)

48 hours

630

632

634

636

638

640

642

644

136 142 148 154 160 166 172 178 184 190 196 202 208

Elapsed Time (hours)

Tem

pera

ture

(C)

T5 - Sample Can

40 hours 8 hrs

Page 5: LQ Coil Fabrication at BNL

April 9, 2009 J. Schmalzle – CM12 5

Superconducting Magnet DivisionLQ07

– Impregnation quality looks good.

– Electrical checks:• Coil shorted to outer layer LE brass

saddle – use as is.• Heater shorted to LE outer layer

brass saddle – repaired• Heater shorted to outer layer NL

brass saddle – use as is.• Extra insulation being added for

next coil.

Page 6: LQ Coil Fabrication at BNL

April 9, 2009 J. Schmalzle – CM12 6

Superconducting Magnet DivisionLQ07

– Coil size measurements.• Coil clamped in form blocks.• Measured using portable CMM.

– Variations from nominal shown by arrows on plots.

• Data fit to coil OD.• Measured variations on midplane are

from .002” (.05mm) small to .005” (.13mm) large.

10”, -.0025 to +.0024

40”, -.0023 to +.0054

65”, -.0024 to +.0049

90”, -.0068 to +.0041115”, -.0026 to +.0025

Page 7: LQ Coil Fabrication at BNL

April 9, 2009 J. Schmalzle – CM12 7

Superconducting Magnet DivisionLQ09 - Reaction

0

50

100

150

200

250

300

350

400

450

500

550

600

650

700

0 24 48 72 96 120 144 168 192 216 240

Elapsed Time (hours)

Tem

pera

ture

(C)

T1T2T3T4T5T6T7T8T9T10

Page 8: LQ Coil Fabrication at BNL

April 9, 2009 J. Schmalzle – CM12 8

Superconducting Magnet DivisionLQ09 - Reaction

– Signal interference abruptly stopped mid way through 210C step.

• Will investigate cause before next reaction.

202

204

206

208

210

212

214

216

4 10 16 22 28 34 40 46 52 58 64 70 76 82 88

Elapsed Time (hours)

Tem

pera

ture

(C)

72 hours

392

394

396

398

400

402

404

406

84 90 96 102 108 114 120 126 132 138 144

Elapsed Time (hours)

Tem

pera

ture

(C)

48 hours

630

632

634

636

638

640

642

644

139 145 151 157 163 169 175 181 187 193 199

Elapsed Time (hours)

Tem

pera

ture

(C)

T5 - Sample Can

48 hours

Page 9: LQ Coil Fabrication at BNL

April 9, 2009 J. Schmalzle – CM12 9

Superconducting Magnet DivisionLQ Coil Plans

– LQ09:• Complete impregnation and wiring.• Ship to LBNL at beginning of May

– LQ11:• Start reaction at beginning of May• Ship to LBNL in July

– LQ12:• Start reaction at beginning of FY10.