Date post: | 13-Apr-2017 |
Category: |
Documents |
Upload: | tirtham-mukherjee |
View: | 107 times |
Download: | 0 times |
TTRRAAIINNIINNGG IINN
DDIISSTTRRIIBBUUTTIIOONN SSYYSSTTEEMM
((MMAAIINNSS))
CCoommpplltteedd bbyy ----------------
NNAAMMEE:: TTIIRRTTHHAAMM MMUUKKHHEERRJJEEEE
CCOOLLLLEEGGEE:: IINNDDIIAANN IINNSSTTIITTUUTTEE OOFF EENNGGIINNEEEERRIINNGG SSCCIIEENNCCEE
AANNDD TTEECCHHNNOOLLOOGGYY,, SSHHIIBBPPUURR
YYEEAARR:: 33 RRDD
YYEEAARR
UUNNDDEERR SSUUPPEERRVVIISSAATTIIOONN OOFF::
II.. MMrr.. SSiiddhhaarrttaa DDuuttttaa KKhhaassnnaabbiiss
IIII.. MMrr.. PPrraabbhhaass GGhhoorruuii
IIIIII.. MMrr.. AAsshhrruujjiitt DDee
PPAARRTT--11
LLTT SSEECCTTIIOONN
TTRRAAIINNIINNGG PPEERRIIOODD::
0088--1122--22001144 ttoo 1155--1122--22001144
AAUUTTHHEENNTTIICCAATTEEDD BBYY::
PPEERRSSOONN
CCOONNCCEERRNNEEDD DDEESSIIGGNNAATTIIOONN SSIIGGNNAATTUURREE
AABBOOUUTT
TThhee CCaallccuuttttaa EElleeccttrriicc SSuuppppllyy CCoorrppoorraattiioonn oorr CCEESSCC iiss aann IInnddiiaann eelleeccttrriicciittyy
ggeenneerraattiioonn ,, ttrraannssmmiissssiioonn aanndd ddiissttrriibbuuttiioonn ccoommppaannyy sseerrvviinngg tthhee aarreeaa
aaddmmiinniissttrraatteedd bbyy tthhee KKoollkkaattaa MMuunniicciippaall CCoorrppoorraattiioonn,, iinn tthhee cciittyy ooff KKoollkkaattaa,,
aass wweellll aass ppaarrttss ooff HHoowwrraahh,, HHoooogghhllyy,, 2244 PPGGSS ((NNoorrtthh)) aanndd 2244 PPGGSS ((SSoouutthh))
ddiissttrriiccttss iinn tthhee ssttaattee ooff WWeesstt BBeennggaall .. IInn 11997788 tthhee ccoommppaannyy wwaass cchhrriisstteenneedd aass
TThhee CCaallccuuttttaa EElleeccttrriicc SSuuppppllyy CCoorrppoorraattiioonn ((IInnddiiaa)) LLiimmiitteedd.. TThhee RRPPGG GGrroouupp
wwaass aassssoocciiaatteedd wwiitthh tthhee CCaallccuuttttaa EElleeccttrriicc SSuuppppllyy CCoorrppoorraattiioonn ((IInnddiiaa)) LLttdd..
FFrroomm 11998899,, aanndd tthhee nnaammee wwaass cchhaannggeedd ffrroomm CCaallccuuttttaa EElleeccttrriicc SSuuppppllyy
CCoorrppoorraattiioonn ((IInnddiiaa)) LLiimmiitteedd ttoo CCEESSCC LLiimmiitteedd.. TThhrreeee nneeww ppoowweerr ggeenneerraattiinngg
ssttaattiioonnss wweerree ssttaarrtteedd bbyy 11990066.. TThhee ccoommppaannyy wwaass sshhiifftteedd ttoo tthhee VViiccttoorriiaa
HHoouussee iinn DDhhaarrmmaattoollaa iinn 11993333,, aanndd ssttiillll ooppeerraatteess ffrroomm tthhiiss aaddddrreessss..
FFoouurr tthheerrmmaall ppoowweerr ppllaannttss aarree iinn ffuunnccttiioonn ttooddaayy,, ggeenneerraattiinngg 11222255 MMWW ooff
ppoowweerr.. TThheessee aarree BBuuddggee BBuuddggee GGeenneerraattiinngg SSttaattiioonn ((775500 MMWW,, SSoouutthheerrnn
GGeenneerraattiinngg SSttaattiioonn ((113355 MMWW)),, TTiittaaggaarrhh GGeenneerraattiinngg SSttaattiioonn ((224400 MMWW)) aanndd
NNeeww CCoossssiippoorree GGeenneerraattiinngg SSttaattiioonn hhaass bbeeeenn sshhuutt ddoowwnn aanndd sshhiifftteedd ttoo HHaallddiiaa..
TThhee ccoommppaannyy ooppeerraatteess tthhee ttrraannssmmiissssiioonn && DDiissttrriibbuuttiioonn ssyysstteemm tthhrroouugghh wwhhiicchh
iitt ssuupppplliieess eelleeccttrriicciittyy ttoo ccoonnssuummeerrss.. TThhiiss ssyysstteemm ccoommpprriisseess ooff 447744 kkmm cciirrccuuiitt
ooff ttrraannssmmiissssiioonn lliinneess lliinnkkiinngg tthhee CCoommppaannyy’’ss ggeenneerraattiinngg aanndd rreecceeiivviinngg ssttaattiioonnss
wwiitthh 8855 ddiissttrriibbuuttiinngg ssttaattiioonnss,, 33,,883377 kkmm cciirrccuuiitt ooff HHTT lliinneess ffuurrtthheerr lliinnkkiinngg
ddiissttrriibbuuttiioonn ssttaattiioonn wwiitthh LLTT ssuubbssttaattiioonnss,, llaarrggee iinndduussttrriiaall ccoonnssuummeerrss aanndd 99,,886677
kkmmcciirrccuuiitt ooff LLTT lliinneess ccoonnnneeccttiinngg tthhee LLTT ssuubbssttaattiioonnss ttoo LLTT ccoonnssuummeerrss.. CCEESSCC
iiss tthhee ssoollee ddiissttrriibbuuttoorr ooff eelleeccttrriicciittyy wwiitthh iinn aann aarreeaa ooff 556677 ssqq kkmm ooff KKoollkkaattaa
aanndd HHoowwrraahh sseerrvviinngg 22..55 mmiilllliioonn ccoonnssuummeerrss wwhhiicchh iinncclluuddeess ddoommeessttiicc,,
iinndduussttrriiaall aanndd ccoommmmeerrcciiaall uusseerrss..
PPaarrtt11::
PPllaaccee:: 11))NNeettaajjii SSuubbhhaass AAvveennuuee,, SSrreeeerraammppoorree
22))NNiimmaaii TTiirrtthhaa RRooaadd,, BBaaiiddyyaabbaattii
CABLES
Cables from the artery system for the transmission and distribution of Electrical energy. The
residential and industrial loads today have a trend towards their growing density. This
requires rugged construction, greater service reliability, increase safety and better
appearance. This interferences from external disturbances like storms, lighting, ice, trees
etc. should be reduced to minimum. These difficulties are easily overcome by the use of
underground cables and a trouble free service is achieved under a variety of environmental
condition.
Earlier underground cables wire mainly mainly used in or near densely polluted areas and
were operated al low or medium voltages only, but the present day requirements seek to
use them even at extra high voltages for longer distances. The underground system
although more costly as compared with the overhead system for the same voltage, is more
acceptable to public from the point of view of its merits mentioned above.
POWER CABLES
Increased working voltages of the overhead lines require the cables to be insulated for such
voltages in order to meet the requirements of the overhead line.
The possibility of supply interruption due to lighting or other external influences is lesser
with underground cables, but if a fault occurs due to any reason it not easily locate. For
long distance transmission, cables can not be used due to their large charging currents.
Components and Construction of Power Cables
Many types of modern electrical cables have been in use for underground distribution and
transmission of power. They vary greatly in their designed constructional techniques.
However, all power cables consists of three essential components.
CABLE CROSS SECTIONS
44 CCOORREE CCAABBLLEE
33 CCOORREE CCAABBLLEE
SSIINNGGLLEE CCOORREE CCAABBLLEE
1. The metallic conductor which provides and electrical conducting path. 2. The insulation of a cable which prevents direct contact and dangerous proximity
between energized conductor and other objects. 3. the external protection preventing the ingress of moisture, mechanical damage,
chemical or electrochemical attack, fire or any other harmful influences which are detrimental to the cable itself.
Synthetic Dielectrics
The introduction of synthetic dielectrics instead of impregnated paper gained popularity as :
1. The elimination of expansive and rather heavy metallic sheaths due to the non-hygroscopic nature of the synthetic insulants.
2. The simplification of cable jointing and termination as well as repair work coupled with a saving in the cost of labour.
3. Complete freedom from compound drainage troubles, especially in cable terminations. In the recent years, may synthetic or plastic insulants were employed in power cable manufacture, of which the following four dielectrics are most common: a) Polyvinyl Chloride (PVC)
b) Polyethylene (PE) or Polythene
c) Crossed linked Polyethylene (XLPE)
d) Ethylene Propylene Rubber (EPR)
LT CABLE JOINTING
There are three types of cable jointing done.
A). Straight Through Jointing
Here crimping is done when jointing Aluminium conductors MAP OF THE AREA
However, solder basting is also done when Cu & Al conductors are joined
Crimping of Conductors:-
Selection of the Correct Cable Size for Service
The size of cable is selected on basis of load requisitioned by consumer.
The selection of the Cutout to be installed is also dependent on cable size and load.
PPOOLLYYUURREETTHHAANNEE CCAABBLLEE JJOOIINNTTIINNGG
Straight Jointing Cable
Tee Joint Cable
NEW SERVICE INSTALLATION
The procedure of service installation can be divided in to five subgroups namely:
A) Inspection for service; B) Laying of service cable; C) Fixing of meter board; D) Termination of cable at meter board; and E) Tee jointing of cable.
A) Inspection for Service
In Areas Served By Overhead Network:
Selection between Overhead or Underground mode of supply is done weighing both economic and technical parameters.
In O.H. area if consumer insists on U.G. supply then whole cable is chargable.
If width of road is less than 3.0 meters, then U.G. service is given.
If load requisition is more than 15 kW, then U.G. service is provided.
General Requirement:
If consumer’s load requirement is more than 40 kW, then dedicated service through CT metering is done.
A clear space 80 cm wide should be available in front for installation up to 4 way meter board and 1.2 meters for multiway meter boards.
Consumers Main Switch must be within 3 feet from our meter board and always in the same room.
Consumer has to be informed to make meter board wall 10” thick, if not done.
Length of cable required in MP, PCP, and PP chould be clearly defined.
Cable route is kept as short as possible and free from obstructions.
B) Laying of Service Cable
Applicant’s details from paid bill and job slip must be verified.
he meter board position and wall for fixing board must be verified.
Depth of Laying cable is 75 cm.
Cable should be laid inside pipes whenever crossing any installation of other agencies and to be adequately protected.
Precut length of cable is laid in trench prepared and within pipes laid for this purpose.
The service cable should contain a loop in ground below meter board.
This cable must enter meter board through a 75 mm dia PVC pipe 1.0 meter long placed vertically below board.
PPaarrtt:: 22
PPllaaccee:: RRaajjiibb GGaannddhhii NNaaggaarr,, KKoonnnnaaggaarr..
C) Meter Board Installation
The Main Switch of Switches must be identified.
The consumer’s installation/wiring must be verified for completion.
The Main Switch must be in “Off” position.
A 2 way/4 way Meter board is installed on wall by 4 Nos.4”xNo.14 Screws.
The board must be at least 1.0 meter vertically above floor level.
Earthing Brackets must be provided to all meter boards.
In 2 way Meter Boards the Earth Terminal is prefixed.
A connection from our earth is provided to meter board Earth Bracket for consumer’s use.
If requirement is more than a 4 way board size, same is fabricated at site by fitting extra 2/4 way board as necessary.
Asbestos millboards are fixed over the rear wall for fire protection.
These boards must have doors and locking arrangements.
Steel meter board is installed with CT Metering arrangement for load above 40 kW.
D) Termination of Cable at 2 way Meter Board with 25mm2 cable:
MAIN JOBS OF LT DEPARTMENT
o Providing new UG (AC) services to LT consumers
o Shifting and strengthening of existing connection
o Fixing and providing energy meters
o Exchanging with energy meters of better specification
o with increase in load.
o Conversion of overhead service to underground service.
o Detection of underground fault
o Quick restoration of faults
o Installation of new pillar boxes.
o Installation, replacement and repair of distribution
o Transformer and
o Servicing and maintenance
PPaarrtt:: 33
PPllaaccee:: 11)) GGoouurrhhaattii,, HHoooogghhllyy
22)) NNeehhaa jjuuttee BBaagg MMaannuuffaaccttuurriinngg,, CChhaammppddaannii,, BBaaiiddyyaabbaattii
REQUIRED EQUIPMENT FOR DISTRIBUTION
STATION
TRANSFORMER
For transmitting a bulk power over a distance, it is desirable to have high voltage
in order to decrease I’R loses in the conductor. On the other had a
Type of insulation – liquid immersed or dry type
Number of Phases - single phase or three phase
Voltage class
Basic impulse insulation level (BIL)
Parts of Distribution Transformer
Nameplate of transformer. It has details like year of manufacture, kava rating (e.g. 400) HV
and LV volts at no load, current rating for HV and LV sides, phases, frequency, max
temperature rise in oil, winding material (copper), amount of oil, total weight, impedence on
6/11 kV, details of external CT as well as the phasor diagram for better understanding. Also
informs us whether it is dual ratio, tap changing transfer.
LT box (420V): The phase sequence is N,R,B, Y from the right. The parts are bush bearing at
the top followed by the top flexible (made of copper), connected to the current
transformers in each phase except neutral. There are fuses in each phase after that,
followed by two cables from each phase including neutral, which terminate at the bottom of
the LT box and finally join the feeder cables in the pillar box.
HT box (6000/11000 V): Has the phase sequence RYB from the right .
Pillar box: The pillar box has a name, and consists of six unit with bus bars horizontal to
these units. There are also two types of earthing done, namely neutral earth and body earth.
Each unit of the pillar box is connected to an ACPB box or else merely linked without being
energized for future emergencies.
There are different types of pillar boxes:
FEB (Feeder pillar box)
ACPB (AC pillar box)
LPB (Link Pillar Box)
MPB (Meter Pillar Box)
Type of Box: There are two typeof box used in our system
a). 6 Way
This is generally installed as “Feeder” Pillar in conjunction with distribution transformer.
D/S Transformer
A/C PILLER BOX
Here six nos. Of cables may be terminated.
B). 4 Way:
This is generally installed for terminating distributor cables cables and also for achieving network
flexibility.
Here four nos. of cables may be terminated.
Every Pillar Box has two openings;
A) The cable side where the cables are terminated
This is usually towards the road and preferably not less than 300 mm from kerb.
B) The fuse side where the fuses are inserted.
This is usually towards the building.
Feeder cables: These feed power from the LT Box to the pillar box and have 400 mm2 cross
sectional area, made of XLPE (crossed linked poly ethylene).
Ring Main Unit (RMU): this unit consists of three legs usually, and serves the pusposes of
connection, supply and protection of one or more transformers on an open ring network ( A
ring network is a network topology in which each node connects to exactly two other nodes,
forming a single continuous path way for signals through each node – a ring). RMU has in
built fault indicators ammeters, and gas pressure inductors. RMU cab be used to energy or
earth any particular line.
FFUUSSEE AANNDD BBUUSS BBAARR AARRRRAANNGGEEMMEENNTT