LTU and Beam Dump Installation April 16, 2007. LTU and Beam Dump Installation. LTU Beamline Design LTU Beamline Overview LTU BTH West Section 72 Installation Drawing Example Quadrupole Support Geometry Quadrupole Support Modal FEA Quadrupole Alignment Stage Geometry - PowerPoint PPT Presentation
20
T. Montagne LTU – Beam Dump Installation Planning [email protected] d.edu April 16, 2007 1 LTU and Beam Dump LTU and Beam Dump Installation Installation April 16, 2007 April 16, 2007
Transcript
Page 1: LTU and Beam Dump Installation  April 16, 2007

T. Montagne

LTU – Beam Dump Installation Planning [email protected]

April 16, 2007 1

LTU and Beam DumpLTU and Beam DumpInstallation Installation

April 16, 2007April 16, 2007

Page 2: LTU and Beam Dump Installation  April 16, 2007

T. Montagne

LTU – Beam Dump Installation Planning [email protected]

April 16, 2007 2

LTU and Beam Dump Installation LTU and Beam Dump Installation

LTU Beamline DesignLTU Beamline OverviewLTU BTH West Section 72 Installation Drawing ExampleQuadrupole Support GeometryQuadrupole Support Modal FEAQuadrupole Alignment Stage GeometryLTU Supports Geometry

LTU Installation SequenceBeam Dump GeometrySafety

Page 3: LTU and Beam Dump Installation  April 16, 2007

T. Montagne

LTU – Beam Dump Installation Planning [email protected]

April 16, 2007 3

LTU Beamline Overview

11 Sections (71-82)27 meter nominal section lengthVAT vacuum valve isolates each sectionTwo 40l/s ion pumps per sectionOne vacuum gauge pair per sectionOne roughing valve/pump out per section

Page 4: LTU and Beam Dump Installation  April 16, 2007

T. Montagne

LTU – Beam Dump Installation Planning [email protected]

April 16, 2007 4

LTU BTH West

BSY Muon Plug - LTU Start

BTH west to BTH Transition

Page 5: LTU and Beam Dump Installation  April 16, 2007

T. Montagne

LTU – Beam Dump Installation Planning [email protected]

April 16, 2007 5

Section 72 Installation Drawing Example

Page 6: LTU and Beam Dump Installation  April 16, 2007

T. Montagne

LTU – Beam Dump Installation Planning [email protected]

April 16, 2007 6

Quadrupole Support Geometry

Mount Plate

Page 7: LTU and Beam Dump Installation  April 16, 2007

T. Montagne

LTU – Beam Dump Installation Planning [email protected]

April 16, 2007 7

Quadrupole Support Modal FEA

Mode # frequency direction

1 113 Z

2 118 X

3 292 X

4 310 X

5 345 Y

6 385 X

7 393 X

8 398 X

9 456 Y

10 505 X

Page 8: LTU and Beam Dump Installation  April 16, 2007

T. Montagne

LTU – Beam Dump Installation Planning [email protected]

April 16, 2007 8

Quadrupole Alignment Stage Geometry

Page 9: LTU and Beam Dump Installation  April 16, 2007

T. Montagne

LTU – Beam Dump Installation Planning [email protected]

April 16, 2007 9

LTU Supports Geometry

Device Support Component Support Drift Support

Page 10: LTU and Beam Dump Installation  April 16, 2007

T. Montagne

LTU – Beam Dump Installation Planning [email protected]

April 16, 2007 10

Device and Quadrupole Support Installation

GROUT

BTH FLOOR

SUPPORTCOLUMN

PRE- ALIGNEDMOUNT PLATE

Page 11: LTU and Beam Dump Installation  April 16, 2007

T. Montagne

LTU – Beam Dump Installation Planning [email protected]

April 16, 2007 11

Core drill support mount hole patterns serially starting at section 71.

Install quadrupole and device mount plates.

Install Component and Drift supports.

Install quadrupole, dipole, and diagnostics supports.

Install Quadrupoles and Dipoles.

Install Diagnostics, collimators, and single beam.

Install vacuum drifts, ion pumps, VAT valves, bellows modules, and vacuum gauges.

Leak check and pump down section by section from 71 through 82.

LTU Installation Sequence

Page 12: LTU and Beam Dump Installation  April 16, 2007

T. Montagne

LTU – Beam Dump Installation Planning [email protected]

April 16, 2007 12

Beam Dump Geometry

BEAM DUMP

BEND MAGNETS

SAFETY DUMP

Page 13: LTU and Beam Dump Installation  April 16, 2007

T. Montagne

LTU – Beam Dump Installation Planning [email protected]

April 16, 2007 13

Beam Dump Geometry

QUARUPOLE MAGNET

Page 14: LTU and Beam Dump Installation  April 16, 2007

T. Montagne

LTU – Beam Dump Installation Planning [email protected]

April 16, 2007 14

Beam Dump Geometry

STOPPER

DUMP BEND MAGNETS

Page 15: LTU and Beam Dump Installation  April 16, 2007

T. Montagne

LTU – Beam Dump Installation Planning [email protected]

April 16, 2007 15

Beam Dump Geometry

SAFETY BEND MAGNETS

QUADRUPOLE MAGNETS

Page 16: LTU and Beam Dump Installation  April 16, 2007

T. Montagne

LTU – Beam Dump Installation Planning [email protected]

April 16, 2007 16

Beam Dump Geometry

DUMP SHIELDING

Page 17: LTU and Beam Dump Installation  April 16, 2007

T. Montagne

LTU – Beam Dump Installation Planning [email protected]

April 16, 2007 17

Beam Dump Geometry

BEND MAGNETS

Page 18: LTU and Beam Dump Installation  April 16, 2007

T. Montagne

LTU – Beam Dump Installation Planning [email protected]

April 16, 2007 18

Beam Dump Geometry

DUMP LINE

SAFETY BEND MAGNETS PROTECTION COLLIMATOR

Page 19: LTU and Beam Dump Installation  April 16, 2007

T. Montagne

LTU – Beam Dump Installation Planning [email protected]

April 16, 2007 19

Beam Dump Geometry

BEAM DUMP

OTR PROFILE MONITOR

Page 20: LTU and Beam Dump Installation  April 16, 2007

T. Montagne

LTU – Beam Dump Installation Planning [email protected]

April 16, 2007 20

Safety

Rigging and Installation will be planned, reviewed, and performed according to SLAC Rigging and Safety Procedures.


Recommended