LUCI2 Status Report Jochen Heidt, ZAH, Landessternwarte Heidelberg for the LUCI-team
Transcript
Page 1: LUCI2 Status Report

LUCI2 – Status Report

Jochen Heidt, ZAH, Landessternwarte Heidelberg

for the LUCI-team

Page 2: LUCI2 Status Report

The Commissioning-team

J. Heidt, LSW, Heidelberg – Com-lead

W. Seifert, LSW, Heidelberg – PI

P. Buschkamp, MPE, Garching – MOS

K. Polsterer, HITS, Heidelberg – Software

A. Pramskiy, AIRUB, Bochum – Software

M. Edwards, LBTO, Tucson – Support, Scriptor-Queen, Training

D. Thompson, LBTO, Tucson – Support, Detector-King, Training

+ T. Sargent, LBTO, Tucson – TCS

+ D. Kügler, HITS, Heidelberg – Scripting-tool (Scriptor)

+ R. Gredel, MPIA, Heidelberg – PM, Coord with LBTO

+ …more from LUCI-team (LSW, MPIA, MPE, AIRUB, FH Mannheim)

Page 3: LUCI2 Status Report

Timeline

• PPAE: June 2013 in Heidelberg

• Juli 2013 shipment

• Sep/Oct 2013 reintegration and lab-tests

• Nov 2013 – Jan 2014: seeing-limited com

• Mar 2014: Test-run Binocular observing cancelled

• Jun/Jul 2014: Upgrade LUCI2 for AO

• 2014B: LUCI2 AO-commissioning

• 2014B: LUCI2 seeing-limited potentially available for users

• 2015A: LUCI2 AO potentially available for users

Page 4: LUCI2 Status Report

Comparison LUCI1 vs. LUCI2

• Hardware practically identical

• Detector in LUCI2 H2RG, higher and homogenous QE

• New Software (new detector, binocular observing)

scripting via XML-files

• New Observer User Interface

• New RTD

• New (and much faster) LS/MOS-acq. tool

Page 5: LUCI2 Status Report

The highlight – luck with the weather • 3 Runs in 2013B: Nov 9-14, Dec 12-18, Jan 15-21

• 4.25/6, 5/7, 6.25/7 nights 15.5/20 nights!!!

(120/150 nights LUCI1-com dome closed)

• Almost no telescope downtime

• No power outages, no other catastrophies

basically done with the night-time com-activities!!!

Page 6: LUCI2 Status Report

Detector-characteristics

But: LUCI1/2 dichroic cuts off at 0.89/0.95µm

LUCI1 better for z-band, LUCI2 better for H-band and redder

Page 7: LUCI2 Status Report

New Software

Can be started from everywhere

Data go into server + can be downloaded from there

No direct access to the LUCI machine for user!

Page 8: LUCI2 Status Report

Scripting tool - I

Page 9: LUCI2 Status Report

Scripting tool - II

Page 10: LUCI2 Status Report

Scripting tool - III

Page 11: LUCI2 Status Report

Scripting tool - IV

XML-output

Page 12: LUCI2 Status Report

LUCI observation execution panel I

Page 13: LUCI2 Status Report

LUCI observation execution panel - II

Page 14: LUCI2 Status Report

RTD

Page 15: LUCI2 Status Report

MOS acquisition - I

Page 16: LUCI2 Status Report

MOS acquisition - II

Page 17: LUCI2 Status Report

MOS acquisition - III

Page 18: LUCI2 Status Report

Some highlights

W3, K-band, 30min, 0.55“ FWHM

(prepared by D. Thompson)

Comet Lovejoy, K-band, 60sec

MOS-spectra of very faint z > 2 galaxies in MPE-fields

210K, 160min, all galaxies show Hα and [N II] 6583 Å

(prepared by J. Kurk)

Page 19: LUCI2 Status Report

Summary

• LUCI2 in seeing-limited mode basically ready

• Detector/readout SW stable

• Instrument SW stable

• MOS-acq. tool extremely fast (down to 12min) and reliable

• Data processing ongoing

• Some cosmetic instrument SW optimization ongoing

• Manuals pending

Decision board/LBTO if and when LUCI2 may be offered


Recommended