Date post: | 25-Jun-2015 |
Category: |
Education |
Upload: | nandan-shandilya |
View: | 624 times |
Download: | 2 times |
Submitted By
Nandan Kumar
2011MT0134
Guided by
Dr. A. K. Mishra
Associate Professor
Dept. of Mining Engineering
Co Guided by
Er. R. D. Dwivedi
Principal Scientist
CSRI-CIMFR
,Regional Centre,
Roorkee
Objective
Study of Classification of Rock Mass according to Q- values
RMR values
GSI values
Calculation of drill blast cycle time which includes Drilling and charging time
Ventilation time
Loading and hauling time
Scaling and rock support time
Investigation of correlations between rock mass
quality and drill blast cycle time
Outline Of Project
Literature survey
Site Selection
Design of Experiment
Field work and Data collection
Data Analysis
Result
Conclusion
Literature Survey Drill Blast Tunnelling Method
The Himalayan Tunnelling
Rock Mass Classification System
Bieniawski’s RMR Classification
Rock Tunnelling Index, Q
Geological Strength Index (GSI)
Drill-Blast Cycle
ROCK MASS RATING: RMR value : It is the geo mechanical classification developed by
Bieniawski (1973)
For application of RMR a given site should be divided into a number of geological structural units.
The following six parameters are determine for each structural unit
UCS (uniaxial Compressive Strength)
RQD (Rock Quality designation)
Joint or Discontinuity Spacing
Joint Condition
Ground Water condition and
Joint Orientation
The rating of six parameters of the
RMR system PARAMETER Assessment of values and Rating
Intact Rock UCS(MPa)
Rating
>250
15
100-250
12
50-100
7
25-50
4
1-25
1
RQD%
Rating
>90
20
75-90
17
50-75
13
25-50
8
<25
3
Mean Fracture Spacing
Rating
>2m
20
0.6-2 m
15
200-600 mm
10
50-200 mm
8
<60 mm
5
Fracture conditions
Rating
Rough tight
30
Open<1 mm
25
Weathered
20
Gouge< 5 mm
10
Gouge>5
0
Groundwater state
Rating
Dry
15
Damp
10
Wet
7
Damping
4
Flowing
0
Fracture orientation
Rating
Very favorable
0
favorable
-2
Fair
-7
Unfavorable
-15
Very unfavorable
-25
Rock Tunnelling Quality Index, Q
Where RQD = Rock Quality Designation 10 - 100
Jn = Joint set number 1 – 20
Jr = Joint roughness factor 1-4
Ja = Joint alteration and clay fillings 1 – 20
Jw = Joint water inflow or pressure 0.1– 1
SRF = stress reduction factor 1 – 20
Range: 0.0001 < Q <1000
SRF
Jw
Ja
Jr
Jn
RQDQ
GSI Hoek and Brown(1997) introduced the GSI both for hard and weak
rock masses
It is based on visual inspection of geological conditions
GSI = RMR -5 for GSI >18 or RMR > 23
= 9 ln Q’ + 44 for GSI < 18
Where Q’ = modified tunneling quality index
=
RMR = rock mass rating according to Bieniawski (1989)
Ja
Jr
Jn
RQD
GSI SHEET
Drill blast cycle
STEPS Unit Operation Time
1 Face mapping, Profile making
2 Face Drilling
3
4
Blasting
Supporting
5 Firing
6 Ventilation
7 Mucking
8 Scaling
Drill – Blast Cycle
Project Overview • Construction of a two lane 9km main
tunnel and parallel one lane escape tunnel, involving major slope cutting and embankment filling works.
• Two bridges of 40 m and 50 m span (two lanes on each bridge).
• Buildings: Two tunnel control buildings, ventilation and power buildings, administrative and maintenance building.
• MEP works: power distribution, ventilation, lighting, fire control system, video surveillance, traffic control, emergency call and communications.
• Approach roads to the Tunnel at both the ends.
Chenani Nashri Tunnel Project,
J&K
North Portal South Portal
Geometrical & Functional characteristics of CHENANI
NASHARI Tunnel Tunnel Name Chenani-Nashri
Length Approx.9000m
Type Single bore, bi-directional double lane with parallel escape tunnel, cross-
passages (pedestrian and vehicular) every 300m
Clearance traffic envelope H = 5m; W = 9.35m;
tolerance 0.05m
Lateral walkways 1.2m (W) x
2.20m (H)
Inner radius 6.65m
Min. curvature radius
300m
Max. overburden Approx.1000m
Profile Tapered with max. slope
0.5%
Excavation method as per Tender documents
D&B (NATM)
Lay-bys Every 600m staggered
Safety and fire niches on both sides
Every 150m
Underground pump rooms
No
Electrical underground substations (technical
rooms)
Every 2400m inside the cross passages
Ventilation Transverse with air ducts above road level
Typical cross section of Escape
Tunnel
Typical cross section of
MainTunnel
NATM(New austrian tunneling method)
NATM is not a method of tunneling but a strategy for tunneling which does have a considerable conformity and sequence
The basic principle of NATM are
1.mobilisation rock mass strength
2. Shotcrete protection to preserve the load carrying capacity of the rock mass
3. monitoring the deformation of the excavated rock mass
4.Providing flexible but active supports and
Correlation among rock class description as per
NATM
and behavioural categories as per Geodata
Engineering approach
Rock class description as per NATM
Qualitative approach
(Geo consult, 1993 )
Geo data Quantitative approach
(Russo & Grasso, 2007)
Class Description Geo structural condition
(typical RMR class)
A1 Stable I
A2 Slightly over breaking II
B1 Friable III
B2 Heavily friable IV
C1 Pressure
exerting/squeezing
III-IV
C2 Heavily pressure
exerting/heavily
squeezing
III-IV-V
L Loose ground/short-
term stable with low
cohesion
V
Drilling Time Data
Boomer XE3 C : Used at Main Tunnel
Drilling time : 70 Minutes ( Hole Depth : 2.5M ) Rock Class : B2 Drilling Time : 100 Minutes ( Hole Depth : 3.5M ) Rock Class : B1 Cross Section Area : 76m No. of hole : 150 Rock Bolting Time : 20 Minutes ( 9 nos. , 5.0 depth Swellex bolt ) Fixing & expansion of bolt : 15 minutes. Machine Navigation : 5-7 Minutes
E2C : Using at Escape Tunnel Drilling Time : 1:30 ( Rock Class : B1 ) Hole Depth : 4.0M Cross Section Area : 36m2 Rock Bolting Time : 15 Minutes ( 6 nos. 3.0 depth Swellex bolt )
Drill Pattern
Escape Tunnel Main
Tunnel
Jumbo
Movement
BLASTING PATTERN PARAMETER
MAIN
TUNNEL(TOP
HEADING)
ESCAPE
TUNNEL
No of Holes
Contour 30 22
Stoping 38 26
Cut 18 16+2(large hole102-
114mm)
Floor 15 6
Total no of holes 101 72
Average round
length
2.3 m 2.3 m
Total
Excavation(m3)
226.71 79.6
Total explosive(Kg) 292.88 115.4
Powder
factor(Kg/m3)
1.29 1.45
Blasting Pattern in
Main Tunnel
Blasting Pattern in Escape Tunnel
Data collection
Under this project data has been collected from Chenani
Nashri Road Tunnel, Jammu
It includes data related to geology and cycle time of different
activities of escape tunnel and main tunnel
Representation of Cycle Time
Main Tunnel Escape Tunnel
GM 4%
SUPP 40%
PROF 3%
FDT 12%
CH T 9%
VENT 3%
MUCK 18%
SCALING 11%
GM
SUPP
PROF
FDT
CH T
VENT
MUCK
SCALING
GM 4%
SUPP 37%
PROF 3%
FDT 14%
CH T 9%
VENT 2%
MUCK 20%
SCALING 11%
GM
SUPP
PROF
FDT
CH T
VENT
MUCK
SCALING
Drill Blast Cycle Time PULL
(M)
Geo
Mapping
(Min)
SUPP.
Time
(Min)
PROF
Making
(Min)
Drilling
Time
(Min)
Charging
Time
(Min)
VENT.
Time
(Min)
Mucking
Time
(Min)
Scaling
Time
(Min)
Cycle
Time
(Min)
4 20 60 15 60 40 10 130 60 395
2.9 20 60 15 60 45 15 180 60 455
3.5 30 185 15 120 75 15 240 45 725
4 30 65 15 115 60 10 170 120 585
3 25 135 40 75 60 15 165 60 575
3 30 90 30 150 75 10 275 30 690
3.5 15 90 15 70 45 25 245 30 535
3 30 60 20 100 75 10 180 60 535
4 20 120 20 130 60 10 200 30 590
4 20 45 15 90 60 10 200 30 470
Lithological Distribution of Rock Type in
Main Tunnel Siltstone,
clayey siltstone, sandy siltstone and sandstone
19%
Sandy siltstone, sandstone
and claystone
3%
Sandy siltstone,
sandstone, claystone and clayey siltstone
12%
Sandstone, claystone and
clayey siltstone 21% Sandstone,
claystone, clayey siltstone and siltstone
7%
Clayey siltstone,
sandstone and sandy siltstone
38%
Lithological Distribution of Rock Type in
Escape Tunnel
Siltstone
11%
Siltstone, intermixed
siltstone and claystone
7%
Siltstone, silty
sandstone,
sandstone 6%
Siltstone, silty
claystone, silty
sandstone, sandstone
6%
Siltstone and
Sandy siltstone
4%
Siltstone and clayey
siltstone, sandysiltstone
2%
Siltstone and clayey
siltstone, sandysiltstone
and Sandstone 20%
Sandstone, siltstone
and a thin strip of
claystone 2%
Sandstone and Siltstone
3%
silty sandstone,
sandstone
21%
Sandstone and clayey
siltstone
9% Sandstone
9%
FACE GEOTEC HNICAL DESCRIPTION ESCAPE TUNNEL
FACE GEOTECHNICAL DESCRIPTION
Main Tunnel
Rock mass quality
FROM TO Q-Value RMR GSI RQD STRENGTH Rock Class
1389.50 1392.50 1.015 47 42 45.7 48 B1
1392.50 1395.10 2.45 46 40 49 45 B1
1395.10 1397.00 2.3 44 40 46 45 B1
1397.00 1399.50 1.015 47 42 45.7 47.5 B1
1399.50 1402.50 2.3 44 40 46 45 B1
1402.50 1405.00 1.08 44 42 49 45 B1
1405.00 1408.00 2.6 50 40 52 45 B1
1408.00 1410.00 1.235 49 45 56 55 B1
1410.00 1412.50 1.235 49 45 55.6 55 B1
1412.50 1415.00 2.6 49 40 52 45 B1
1415.00 1417.70 1.01 46 40 45.7 45 B1
1417.70 1421.00 2.6 48 40 52 45 B1
1421.00 1423.50 0.76 46 40 45.7 45 B1
Ro
ck m
ass Q
ua
lity in
Ma
in
tun
ne
l
00
.5 11.5 22.5 33.5 44
.5 5
1389.50
1408.00
1426.00
1446.50
1465.50
1484.50
1563.20
1577.30
1591.30
1604.50
1625.80
1650.50
Ch
ain
ag
e N
o v
s Q
valu
es
0 10 20 30
40 50
60
1389.50
1408.00
1426.00
1446.50
1465.50
1484.50
1563.20
1577.30
1591.30
1604.50
1625.80
1650.50
Ch
ain
ag
e n
o. v
s RM
R
Va
lue
s
05
101520253035404550
138
9.5
0
140
8.0
0
1426
.00
144
6.5
0
146
5.50
148
4.5
0
156
3.20
1577
.30
159
1.30
160
4.5
0
1625
.80
1650
.50
GSI Values in Main
Tunnel Rock Mass
Quality
Range
Q Values 0.52 to 2.6
RMR Values 42 to 51
GSI Values 35 to 45
Rock mass Quality in Escape
tunnel
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5
216
4.6
219
1.5
2219
.5
224
4
2372
.70
240
8.2
0
244
0.8
0
249
1.5
2533
.2
256
5
2657
.5
Chainage No vs Q values
0
10
20
30
40
50
60
216
4.6
219
1.5
2219
.5
224
4
2372
.70
240
8.2
0
244
0.8
0
249
1.5
2533
.2
256
5
2657
.5
Chainage No Vs RMR Values
0
10
20
30
40
50
60
216
4.6
219
1.5
2219
.5
224
4
2372
.70
240
8.2
0
244
0.8
0
249
1.5
2533
.2
256
5
2657
.5
Chainage No. Vs GSI values Rock Mass
Quality Range
Q Values 1.90 to 4.13
RMR Values 47 to 53
GSI Values 42 to 50
Correlation of data (Main
Tunnel) Correlation between
Cycle time and Q-value in main tunnel
y = -0.3841Q2 + 1.48 Q + 4.73
R² = 0.44
5.0
5.4
5.8
6.2
6.6
0 0.5 1 1.5 2 2.5 3
T0
.33
Q
Main Tunnel Correlation between
Cycle time and RMR-value in main tunnel
CT0.33 = -0.0182(RMR)2 + 1.84(RMR) - 39.9
R² = 0.72
4
5
6
7
42 44 46 48 50 52
T0
.33
RMR
Main Tunnel Correlation between
Cycle time and GSI-value in main tunnel
CT0.33 = 1.13(GSI)0.45
R² = 0.86
4.50
5.00
5.50
6.00
6.50
7.00
30 35 40 45 50
T0
.33
GSI
Correlation of data (Escape
Tunnel) Cycle time vs Q values
(Q < 6)
Cycle time vs Q values (Q>6)
y = -0.0203x + 2.9136 R² = 0.7724
2.72
2.76
2.80
2.84
2.88
2.92
0 2 4 6 8
T0
.2
Q2
y = 0.0131x + 2.5654 R² = 0.9147
2.60
2.64
2.68
2.72
2.76
2.80
0 5 10 15 20
T0
.2
Q2
Correlation of data (Escape
Tunnel) Cycle time vs RMR values
(RMR <49 )
Cycle time vs RMR values (RMR > 49)
CT = 3.305(RMR)2 - 316.5(RMR) + 7750
R² = 0.73
140
160
180
200
220
240
44 45 46 47 48 49
Cy
cle
tim
e p
er m
etre
pu
ll
RMR
CT = 0.216(RMR)3 - 35.36(RMR)2 + 1927(RMR)-
34825
R² = 0.96
100
120
140
160
180
47 49 51 53 55 57
Cy
cle
tim
e p
er m
etre
pu
ll
RMR
Correlation of data (Escape
Tunnel) Cycle time vs GSI value(GSI< 43)
Cycle time Vs GSI value(GSI > 43)
CT = 1.292(GSI)2 - 111(GSI) + 2526
R² = 0.70
100
140
180
220
260
34 36 38 40 42 44
Cycl
e ti
me
per
m p
ull
GSI
CT = -0.246(GSI)2 + 25.76(GSI)- 507.56
R² = 0.89
100
120
140
160
180
30 40 50 60
Cycl
e ti
me
per
pu
ll
GSI
Conclusion From the undertaken study conclusion may be as follows:
1.The change in Rock mass quality direct influence on cycle time of Tunnel which has
been true for both the tunnel(Main & Escape Tunnel).
2.In case of Main Tunnel(Diameter 14.02 m) Cycle time is directly proportional to
Rock mass quality upto a certain range and after that range the cycle time becomes
constant.
3. In case of escape tunnels (diameter 6.55 m), the cycle time is inversely proportional
to rock mass quality
It may be due to change in degree of fragmentation, which influenced the dig rate
as for the lower value of rock mass quality (Q<2.45,RMR values <48.6 and GSI
values < 43 ) degree of fragmentation was good whereas for higher values of rock
mass quality i.e. (Q >√6,RMR >48.6 and GSI >43) the degree of fragmentation
was bad. The specific charge was same for all cases.
Contd……
4. This indicates that the specific charge , design and
sequence need to be changed with change in rock
mass quality to suite the excavator and achieve the
desire efficiency.
5.From the undertaken study it may be concluded that for
varying rock mass quality specific charge, design and
sequence need to be change to keep the same face
advancement and the efficiency of excavation.
Thank You