+ All Categories
Home > Documents > Madison Elementary School District

Madison Elementary School District

Date post: 10-Jan-2016
Category:
Upload: peyton
View: 31 times
Download: 0 times
Share this document with a friend
Description:
Madison Elementary School District. Mr. Calvin. Bond Project Update August 2013. Solar Update Madison #1. Solar Update Rose Lane Elementary. Solar Update Park Elementary. Solar - Schedule of Completion. Structural and panel set- 8/22/13 - PowerPoint PPT Presentation
Popular Tags:
10
Madison Elementary School District Bond Project Update August 2013
Transcript
Page 1: Madison Elementary School District

Madison Elementary School DistrictBond Project Update August 2013

Page 2: Madison Elementary School District

Solar Update Madison #1

Page 3: Madison Elementary School District

Solar Update Rose Lane Elementary

Page 4: Madison Elementary School District

Solar Update Park Elementary

Page 5: Madison Elementary School District

Solar - Schedule of Completion

• Structural and panel set- 8/22/13• Broken sidewalk replacement- 8/26/13• Installation of turf and DG- 9/16/13• Substantial completion- 9/23/13• First day of generation- 9/26/13• Final Completion- 10/14/13

Page 6: Madison Elementary School District

The Next Step in Solar

Site evaluations later this weekPreliminary design by 8/29Submitting applications to APS for rebates by 8/30

Page 7: Madison Elementary School District

Rose Lane Café Remodel

Page 8: Madison Elementary School District

Madison Heights Café Remodel

Page 9: Madison Elementary School District

Madison Meadows Site Work

Page 10: Madison Elementary School District

Upcoming Projects

• Madison Heights kitchen remodel• Madison Meadows front office remodel• Non-skid surfacing on exterior stairs• Roof replacement at Heights• Daylighting in dining areas at Heights, Park and Rose Lane

Questions:


Recommended