Date post: | 18-Nov-2014 |
Category: |
Technology |
Upload: | chandan-kumar |
View: | 1,314 times |
Download: | 4 times |
MAJOR BLACKOUT IN THE WORLD
By:
Chandan Kumar
ET ,WRLDC
MAJOR BLACKOUT IN THE WORLD
NAME OF BLACKOUT
MILLIONS OF
PEOPLE
AFFECTED
REGION DURATION
NORTHEAST BLACKOUT 1965 30NORTH EASTERN PART OF NORTH
AMERICA,
SOUTH-EASTERN PART OF CANADA
09-11-1965
12 Hours
SOUTHERN BRAZIL BLACKOUT
199997
SOUTH AND SOUTH-EASTERN
BRAZIL
11-03-1999
30 Hours
NORTH EASTERN REGION OF 14-08-2003/15-08-2003
NORTHEAST BLACKOUT 200355
NORTH EASTERN REGION OF
NORTH AMERICAAMERICA
14-08-2003/15-08-2003
16 Hours
ITALY BLACKOUT 2003 55ITALY,
PARTS OF SWITZERLAND
28-09-2003
3 Hours
JAVA BALI BLACKOUT 2005 100 INDONESIA18-08-2005
7 Hours
BRAZIL AND PARAGUAY
BLACKOUT 200987
CENTRAL, SOUTH AND SOUTH-
EASTERN BRAZIL AND ALL
PARAGUAY
10-11-2009/11-11-2009
5 Hours
NORTH EAST BLACKOUT 1965THE EVENT
� It all started with the tripping of single transmission line from Niagara generatingstation .
� Within 2.5 seconds, four other transmission lines became overloaded and tripped,isolating 1,800 MW of generation at Niagara Station.
� After their isolation, the generators became unstable and tripped off-line.
� The northeast power system became unstable and separated into isolated powersystems (islands) within 4 seconds.
CAUSECAUSE
� Human Error lead to Incorrect setting of relay at Niagara generator leading to linetripping
� Line overloading on rest of four 230KV line leading to their outage..
� Earlier no study was done on Reliability of Interconnected system
LESSON LEARNT
� Planning for Unexpected Events.
� Commissioning of NERC,NYPP,NPCC to develop industry standards for equipmenttesting and reserve generation capacity, as well as preventative measuresgoverning interconnection and reliability .
� Introduction of SCADA/EMS And Auto-Reclosure of CB.
NORTH EAST BLACKOUT 1965
SOUTHERN BRAZIL BLACKOUT 1999
THE EVENT
� Bus fault at the 440 kV Bus bar of Bauru substation due to Lightening .Due toFailure of Bus-Bar protection remote transmission line protection systems wereactivated.
� Six 440 kV circuits were tripped which initiated a process of oscillation that endedwith the cascading shutdown and loss of 2300 MW of Generation.
� 500 kV lines in the Southern system tripped, activating the SPS in the region whichresulted in the HVDC link loss due to voltage collapse in sao-paulo area.
� In the same manner, the North/South interconnection was tripped by its out-of-step protection. The total interrupted load reached 25,000 MW.
LESSON LEARNT
� Modifications in the physical arrangements of many EHV substations as well as inthe protection and control systems.
� Greater detailing in maintenance planning to avoid exposure to the higher risks ofblackouts.
� Improvement in the information systems in view of the new environment of theelectric industry as a whole.
� Investment to modernize the operation control centers.
� Better SPS to cope with multiple contingency analysis process.
CAUSE
� Inadequate Situational Awareness of First Energy ‘s System.
� Lack of Investments into the Grids (high Cost-Pressure for the Asset-Owners due to Deregulation), leading to Bottlenecks in Transmission
� Lack of Communication among the Operators
� Need for more Regulatory Works (Rules, Grid Code etc.) for the Operation of Transmission Systems and Power Plants in Case of Cascading Events.
� Weak Points in System Protection, Energy and Demand Side Management - EMS, DSM
NORTHEAST BLACKOUT 2003
LESSON LEARNT
� Make reliability standards mandatory and enforceable, with penalties fornoncompliance
� Develop a regulator-approved mechanism for funding NERC and the regionalreliability councils, to ensure their independence from the parties they oversee
� For More Reliable Grid Operation PMU and WAMPAC was introduced .
NORTHEAST BLACKOUT 2003
ITALY BLACKOUT 2003
EVENTS
� Trip of the Swiss 380 kV line Mettlen-Lavorgo (also called the “Lukmanier” line) at
03:01 caused by tree flashover.
� Load was reduced on the overloaded Sils-Soazza line but that also tripped after a
tree flashover.
� Created overloads on the remaining lines in the area became intolerable and
almost simultaneous and automatic trip of the remaining interconnectors towards
Italy occurred
� The Italian system was isolated from the European network about 12 seconds after
the loss of the line Sils-Soazza.
LESSON LEARNT
� Counter measures must be identified and prepared at each moment and for each
single incident.
� ROW Maintenance practice
� Operator training for emergency procedures.
� System should withstand after loss of N-1 security.
JAVA-BALI BLACKOUT 2005
CAUSE
� A transmission line between Cilegon and Saguling lead to cascading failure.
� two units of the Paiton plant in East Java and six units of the Suralaya plant in West
Java
� Loss of 2300 MW of generation that is roughly half of the supply.
� Deficit of Power due to Low Generation
LESSON LEARNT
� Adequate Generation to meet the needs
� Adequate Transmission line to withdraw power if N-1 Security fails.
� Configuring the Renewable Energy with the grid
BRAZIL AND PARAGUAY BLACKOUT 2009
CAUSE
� Tripping of all the three lines of 765 kV at Itaipu dam due to Phase to ground fault
due to heavy rain and strong wind.
� Loss of 5600MW at Itaipu Generation Plant tripped due to load rejection.
� Cascade tripping of remaining lines in the South-Southeast Brazil which caused
additional load rejection of 2,950Mw
� Then HVDC system tripped causing a total interruption of Approximately
24,500Mw
LESSON LEARNT
� Transmission system equipment should be rated to consider severe environmental
conditions that could occur.
� Maintenance of infrastructure is critical to prevent or minimize the effect of
outages
� Need to enhance it’s transmission system to help prevent cascading outages to
re-route the power in case of tripping of Lines.
BRAZIL AND PARAGUAY BLACKOUT 2009
THANK YOU