Date post: | 24-Oct-2014 |
Category: |
Documents |
Upload: | mohammed-faiz |
View: | 47 times |
Download: | 9 times |
ABSTRACT FOR NEWCONSTRUCTION OF MAJOR BRIDGE
Item No. Item Description Quantity Unit Rate Amount
SACRIFICIAL WELL
1
A
(As per Rate Analysis Attached) 4.000 Nos 528041.00 2112164.00
2
(As per Rate Analysis Attached) 64.500 Rmt 6951.00 448340.00
3
(As per Rate Analysis Attached) 2.375 MT 61249.00 145469.00
4
(As per Rate Analysis Attached) 6.909 CUM 4170.00 28810.00
5
(As per Rate Analysis Attached) 45.380 MT 61249.00 2779498.00
6
(As per Rate Analysis Attached)
Well steining
PCC M20 Grade 453.803 CUM 4073.00 1848340.00
7
(As per Rate Analysis Attached)
A. Sandy Soil
upto 3m 9.000 Rmt 1497.00 13473.00
Beyond 3m upto 10m depth 21.000 Rmt 2059.00 43239.00
Beyond 10m upto 20m depth 4.090 Rmt 2161.95 8842.00
B. Hard rock 0.000 Rmt 57966.00 0.00
Dewatering 42.270 Rmt 831.00 35126.00
8
(As per Rate Analysis Attached) 0.424 MT 61249.00 25963.00
9
(As per Rate Analysis Attached)PCC Grade M20 50.868 CUM 4073.00 207185.00
Providing and Constructing Temporary Island 16 m diameter for Construction of Well Foundation for 8m dia. Well.
Assuming depth of water 4.0 m and height of island 4.5 m.
Providing and constructing one span service road
to reach island location from one pier location to
another pier location
Providing and Laying Cutting Edge of Mild Steel weighing 40 kg per metre for Well Foundation complete as per Drawing and Technical Specification.
Plain/Reinforced Cement Concrete, in Well Foundation complete as per Drawing and Technical Specification. Well curb RCC Grade M20
Providing and Laying Well steining of Mild Steel weighing 100 kg per cum for Well Foundation complete as per Drawing and Technical Specification.
Plain/Reinforced Cement Concrete, in Well Foundation complete as per Drawing and Technical Specification.
Sinking of 6m external diameter well (other than pneumatic method of sinking) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is rekoned from bed level.
Providing and Laying Bottom plug of Mild Steel weighing 5 kg per sqm for Well Foundation complete as per Drawing and Technical Specification.
Plain/Reinforcement concrete in Bottom plug complete as per Drawing and Technical Specifications.
Item No. Item Description Quantity Unit Rate Amount
10 1175.713 CUM 1147.00 1348543.00
FOUNDATION
1
(As per Rate Analysis Attached)
I Ordinary Soil
i) Upto 3 m depth 542.758 Cum 41.00 22253.00
ii) 3m to 6m depth 408.864 Cum 47.00 19217.00
iii) Above 6m depth 1094.594 Cum 57.00 62392.00
II Ordinary rock (not requiring blasting)
i) Depth upto 3 m 201.187 Cum 52.00 10462.00
III Hard rock (requiring blasting) 0.000 Cum 745.00 0.00
2
(As per Rate Analysis Attached)I Ordinary Soili) Upto 3 m depth 542.758 Cum 2.00 1086.00ii) 3m to 6m depth 408.864 Cum 3.00 1227.00iii) Above 6m depth 1094.594 Cum 5.00 5473.00
II Ordinary rock (not requiring blasting)i) Depth upto 3 m 201.187 Cum 4.00 805.00
III Hard rock (requiring blasting) 0.000 Cum 21.00 0.00
3
(As per Rate Analysis Attached) 14.742 Tonne 47778.00 704355.00
4
PCC Grade M15
(As per Rate Analysis Attached) 33.139 Cum 3484.00 115455.00
5
RCC Grade M30 133.225 Cum 4068.00 541959.00
(As per Rate Analysis Attached)
Sand Filling in Foundation Trenches as per Drawing & Technical Specification
Earth work in excavation for foundation of
structures as per drawings and technical
specifications, including setting out, construction
of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and
bottom and backfilling with approved material.
Add Extras as follows in the rates of the above items if dewatering is resorted to
Supplying, fitting and placing uncoated TMT bar
Reinforcement in foundation complete as per
drawing and Technical Specifications.
Plain/Reinforcement concrete in Open Foundation complete as per Drawing and Technical Specifications.
Plain/Reinforcement concrete in Open Foundation complete as per Drawing and Technical Specifications.
Item No. Item Description Quantity Unit Rate Amount
SUBSTRUCTURE
6
(As per Rate Analysis Attached) 78.068 Tonne 47883.00 3738142.00
7
(As per Rate Analysis Attached) 4.000 Each 385.00 1540.00
8
(As per Rate Analysis Attached)
A Abutment
RCC Grade M30
a) Height upto 5m 140.798 Cum 4287.00 603602.00
b) Height beyond 5m and upto 10m 77.967 Cum 4392.00 342432.00
c) Height above 10m 94.680 Cum 4540.00 429848.00
B Pier
RCC Grade M30
a) Height upto 5m 47.100 Cum 4287.00 201918.00
b) Height beyond 5m and upto 10m 47.100 Cum 4392.00 206863.00
c) Height above 10m 49.455 Cum 4540.00 224526.00
C Return wall
PCC Grade M20
a) Height upto 5m 78.667 Cum 4073.00 320411.00
9
(As per Rate Analysis Attached)
In Cap RCC Grade M30 118.234 Cum 4287.00 506868.00
10
(As per Rate Analysis Attached)
In Pedestal RCC Grade M40 4.194 Cum 4402.000 18464.00
11
(As per Rate Analysis Attached) ### Cu.Cm 0.304 155868.00
Supplying, fitting and placing TMT bar
Reinforcement in substructure complete as per
drawing and Technical Specifications.
Providing weep holes in brick masonary/Plain/reinforced concrete abutment, wing wall/ return wall with 100 mm dia AC pipe, extending through the full width of the structures with slope of 1V:20H towards drawing foce. Complete as per drawing and Technical Specifications.
Plain/Reinforced cement concrete in substructure complete as per Drawing and Technical Specifications.
Plain/Reinforced cement concrete in substructure complete as per Drawing and Technical Specifications
Plain/Reinforced cement concrete in substructure complete as per Drawing and Technical Specifications.
Supplying, fitting and fixing in position true to line and level elastomeric bearing conforming to IRC: 83 (Part-II) section IX and clause 2005 of MoRTH specifications complete including all accessories as per drawing and Technical Specifications.
Item No. Item Description Quantity Unit Rate Amount
SUPERSTRUCTURE
12
(As per Rate Analysis Attached) 95.772 Tonne 49161.00 4708257.00
13
Dirt Wall in RCC M30
(As per Rate Analysis Attached) 23.702 Cum 4800.00 113769.00
14
(As per Rate Analysis Attached) 1856.342 Cum 547.00 1015419.00
15
(As per Rate Analysis Attached) 42.000 Each 3570.00 149940.00
16
(Provisional Rates) 62.112 Metre 9160.00 568946.00
17
Girder & Slab in RCC M30
(As per Rate Analysis Attached) 522.213 Metre 4800.00 2506624.00
18
(As per Rate Analysis Attached) 12.165 Cum 3370.00 40996.00
19
(As per Rate Analysis Attached) 23.987 Cum 6424.00 154093.00
Supplying , Fitting and placing TMT bar
reinforcement in superstructure complete as per
drawing and Technical Specifications
Furnishing and placing reinforced/prestressed
cement concrete in superstructures as per drawing
and Technical Specifications
Backfilling behind abutment, wing wall and return wall complete as per drawing and Technical Specifications.
Providing Drainage Spouts complete as per
drawing and Technical specification and as per
clause 2705 of specifications.
Providing and laying of an elastomeric slab seal expansion joint, catering to right or skew (less than 20 deg., moderately curved with maximum horizontal movement upto 50 mm, complete as per approved drawings and standard specifications to be installed by the manufacturer/supplier or their authorised representative ensuring compliance to the manufacturer's instructions for installation and clause 2606 of MoRTH specifications for road & bridge works.
Furnishing and placing reinforced/prestressed
cement concrete in superstructures as per drawing
and Technical Specifications
PCC M15 Grade levelling course below approach slab complete as per drawing and Technical Specifications.
Reinforced cement concrete Approach slab including reinforcement and formwork complete as per drawing and Technical Specification. RCC M25
Item No. Item Description Quantity Unit Rate Amount
20
Crash barrier RCC Grade M30
(As per Rate Analysis Attached) 197.660 RMT 2643.00 522415.00
21
(As per Rate Analysis Attached) 86.363 Cum 7695.00 664565.00
22
(As per Rate Analysis Attached) 1079.540 Sq.m. 508.00 548406.00
TOTAL FOR NEWCONSTRUCTION OF MAJOR BRIDGE = 28273588.00
Provision of an Reinforced cement concrete crash barrier at the edge of road, approaches to bridge structures and medians, constructed with M30 grade concrete with HYSD reinforcement conforming to IRC:21 and dowel bars 25mm dia. 450mm long at expansion joints filled with premoulded asphalt filler board , keyed to the structure on which it is built and installed as per design given in the enclosure to MOST circular No. RW/NH -33022/1/94-DO III dated 24 june 1994 as per dimensions in the approved drawing and at locations directed by engineer, all as specified etc. complete.
Providing and laying Bituminous Concrete on prepared surface with specified graded crushed stone aggregates premixed with bituminous binder as per job Mix formula and 2% filler lime or cement by weight of total aggregate as per job mix. Transporting the mix to the work site, laying with a hydrostatic paver finisher to the required grade level and alignment, rolling with roller to achieve the desired compactions per MORT &H specification complete in all respect excluding cost of tack coat. (The Rate is for Bitumen Content @ 5.0% by weight of total mix)
Providing & laying 25 mm thick Mastic Asphalt wearing course with paving grade bitumen 14% by wt. of mix , filler, fine & coarse aggregate , meeting the requirements given in table 500-29 of MORT&H specifications, prepared by using mastic cooker and laid to required level and slope after cleaning the surface, including providing antiskid surface with bitumen precoated fine grained hard stone chipping of 13.2 mm nominal size at the rate of 0.005 cum per 10 sqm and at an approximate spacing of 10 cm center to center in both directions, pressed into surface when the temperature of surface is not less than 1000C, protruding 1mm to 4mm over mastic surface etc. complete, excluding tack coat . (Mix design is required for each case).
NEWCONSTRUCTION OF MAJOR BRIDGE AT CH.- 539+800.00
DATA
Abutment (L) Abutment (R) Pier Return
GL 276.605 277.060 272.398 278.725 Overall Span 21.50 No of Spans 4.0
RTL 279.870 279.870 279.870 279.870 LBL 270.530 Pier RCC
Soffit 277.475 277.475 277.475 Cap Top Width 1.24
FL 259.705 262.160 258.375 275.308 Pier Top Width 2.3
Soft Rock RL 262.605 Length of Return (Left) 3.600 Side slopes 1: 0
Hard Rock RL 259.605 262.060 257.898 266.725 Length of Return (Right) 3.600 No. of Abutment 2
265.805 268.260 264.675 280.608 276.925 No. of Pier 3
Deck Slab (C) 0.225
270.805 273.260 269.675 285.608 (E) 0.200
Top of Left Abt. Cap Level 276.975 Pier Foundation Bottom 0.4
Dia of Pier 2.000 Skew = Top of Right Abt. Cap Level 276.975 Sloping Portion Ht. 0.9
Length of Abutment 12.422 Skew Factor 1.035 Diameter of sacrificial well ( r ) 6.0
MEASUREMENTSItem Description No. Length Breadth Depth Unit Quantity Remarks
No. (m) (m) (m)
A) SACRIFICIAL WELL
1 Temporay Island 4.0 - - Nos 4.000
Total Nos 4.000
2 Service Road
for 1st Pier 1.000 = 21.500 RMT 21.500
for 2nd Pier 1.000 = 21.50+ 21.50 RMT 43.000
for 3rd Pier 1.000 = 43 + 21.50 RMT 64.500
Total RMT 64.500
3
Circumference = 2 * p * r = 56.549 MT 2.262
Add 5% for wastage or for Dowel bar 0.113
Total MT 2.375
4 Well Curb (RCC M20)
0.3 Area 0.045 0.122 6.909
0.077
0.15 Circumfernce 56.549
0.64
0.015
angle
Total 6.909
5 Well Steining Quantity of Well Steining = m3 453.803
R/F @ 100 kg/cum
R/F @ 100 kg/cum = MT 45.380
MT 45.380
6 Well Steining (PCC M20)
0.5
height of P1 17.940 Circumfernce 56.549 453.803
height height of P2 16.115 Area 8.03
height of P3 14.095
Avg height 16.050
453.803
7 Sinking of wellA. In Sandy Soil 3 height of P1 15.5 RMT 14.090
height of P2 13.27
height of P3 13.5
Avg height 14.090 Depth below bed level upto 3m 3.000Beyond 3m upto 10m depth 7.000Beyond 10m depth 4.090
upto 3m RMT 9.000
3 to 10m RMT 21.000
Above 10m RMT 4.090B. In Hard rock 3 height of P1 0.000 RMT 0.000
height of P2 0.000
height of P3 0.000
Avg height 0.000
RMT 0.000
Dewatering 3 14.090 RMT 42.270
Level at 5m From Foundation Top
Top of Pier Cap Level
Level at 10m From Foundation Top
15 0
Cutting edge of mild steel weighing 40 kg per metre
m2 m3
m3
m3
m3
Item Description No. Length Breadth Depth Unit Quantity Remarks
No. (m) (m) (m)
Item Description No. Length Breadth Depth Unit Quantity Remarks
No. (m) (m) (m)
8 Bottom Plug Quantity of Bottom Plug = 84.780
R/F @ 5 kg/Sqm
R/F @ 5 kg/Sqm = MT 0.424
MT 0.424
9 Bottom plug (PCC M20)
2 3 Area 28.260 50.868
0.9Sacrificial well
0.4
4
50.868
10 Sand Filling 3 Area 28.260 1360.719Avg Height 16.050
Deduction for Pier
Area foundation block 16.000 19.200
9.923 26.791
Pier 3.142 139.015
1175.713
ROAD TOP LEVELAPPROACH SLAB 279.870
CROSS GIRDERLEVELLINGCOURSE OF SOFFIT LEVELAPPROACH POT PTFE BEARING 277.475SLAB 276.975 WITH RCC PEDESTRAL
600 mm THK.FILTER MEDIA
259.705LEVELLING COURSE
( PCC M15 )258.375
A) FOUNDATION
Abutment (Left) Abutment (Right) Pier Return
Soil = 14.000 15.000 14.500 3.418
Soft Rock = 3.000 0.000 0.000 0.000
1 Earthwork in Excavation Hard Rock = 0.000 0.000 0.000 0.000
a) Abutment (L)
Height Upto 3 m
1.0 12.629 5.310 3.000 201.187 Soil
1.0 12.629 5.310 3.000 201.187 Soft rock
1.0 12.629 5.310 0.000 0.000 Hard rock
0.5 Height bet. 3 to 6 m
0.30 1.0 12.629 5.310 3.000 201.187 Soil
0.6 0.6 Height above 6 m
2.81 2.30 1.0 12.629 5.310 8.000 536.499 Soil
Abutment (R)
Height Upto 3 m
1.0 12.629 4.910 3.000 186.032 Soil
1.0 12.629 4.910 0.000 0.000 Soft rock
0.5 1.0 12.629 4.910 0.000 0.000 Hard rock
0.3 Height bet. 3 to 6 m
0.6 0.6 1.0 12.629 4.910 3.000 186.032 Soil
2.41 2.30 Height above 6 m
1.0 12.629 4.910 9.000 558.095 Soil
m2
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
CRASH BARRIER RCC M30
ABUTMENT FOUNDATION LEVEL
PIER FOUNDATION LEVEL
TOP LEVEL OF ABUTMENT CAP
Item Description No. Length Breadth Depth Unit Quantity Remarks
No. (m) (m) (m)
b) Return
Left - Height Upto 3 m
2.0 3.900 3.069 3.000 71.823 Soil
2.0 3.900 3.069 0.000 0.000 Soft rock
2.0 3.900 3.069 0.000 0.000 Hard rock
Height bet. 3 to 6 m
2.0 3.900 3.069 0.418 9.995 Soil
Right - Height Upto 3 m
2.0 3.900 3.578 3.000 83.716 Soil
2.0 3.900 3.578 0.000 0.000 Soft rock
2.0 3.900 3.578 0.000 0.000 Hard rock
Height bet. 3 to 6 m
2.0 3.900 3.578 0.418 m3 11.650 Soil
Total Height Upto 3 m Excavation in Soil 542.758
Excavation in Soft Rock 201.187
Excavation in Hard Rock 0.000
Height bet. 3 to 6 m Excavation in Soil 408.864
Height above 6 m Excavation in Soil 1094.594
2 Dewatering
Quantity as per item no. 1=
Total Height Upto 3 m Excavation in Soil 542.758
Excavation in Soft Rock 201.187
Excavation in Hard Rock 0.000
Height bet. 3 to 6 m Excavation in Soil 408.864
Height above 6 m Excavation in Soil 1094.594
3 Foundation TMT Re-bar
a) Abutment (L)
1.0 12.422 5.110 0.600 38.087
1.0 12.422 1.300 0.500 6.211
44.298
b) Abutment (R)
@ 120 kg/m3
1.0 12.422 4.710 0.600 35.106
1.0 12.422 1.300 0.500 m3 6.211
41.317
Foundation Block @ Pier
@ 87.5 Kg/m3 3.0 4.000 4.141 0.400 19.876
3.0 3.150 3.261 0.900 27.734
47.610
Total 85.615
47.610
Total Quantity of Reinforcement @ 120 Kg/m3 MT 10.274
Total Quantity of Reinforcement @ 87.5 Kg/m3 MT 4.166
b) Return
@ 5 Kg/m2
Left
2.0 3.069 0.300 1.842
2.0 3.900 0.300 2.340
2.0 3.069 3.900 23.941
28.123
Right
2.0 3.578 0.300 2.147
2.0 3.900 0.300 2.340
2.0 3.578 3.900 27.905
32.392
Total 60.514
Total Quantity of Surface Reinforcement @ 5 Kg/m2 MT 0.303
Total MT 14.742
4 Foundation PCC M15
Levelling Course
a) Abutment 1.0 12.629 5.310 0.100 6.706
1.0 12.629 4.910 0.100 6.201
b) Pier 3.0 4.200 4.348 0.100 5.478
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
@ 120 kg/m3
m3
m3
m3
m3
m3
m3
m3
m2
m2
m2
m2
m2
m2
m3
m3
m3
m3
Item Description No. Length Breadth Depth Unit Quantity Remarks
No. (m) (m) (m)
Item Description No. Length Breadth Depth Unit Quantity Remarks
No. (m) (m) (m)
c) Return Left 2.0 3.900 3.048 0.300 7.133
Right 2.0 3.900 3.256 0.300 7.620
Total 33.139
5 Foundation RCC M30
a) Abutment (L) 1.0 12.422 5.110 0.600 38.087
1.0 12.422 1.300 0.500 6.211
Abutment (R) 1.0 12.422 4.710 0.600 35.106
1.0 12.422 1.300 0.500 6.211
b) Pier
Foundation Block 3.0 4.000 4.141 0.400 19.876
3.0 3.150 3.261 0.900 27.734
Total 133.225
B) SUBSTRUCTURE
6 Substructure TMT Re-bar
a) Abutment (L)
@ 120 kg/m3
Stem 1.0 12.422 0.300 15.720 58.584
Counterfort 3.0 0.500 C/S Area= 24.146 36.219
3.0 0.500 0.640 16.045 15.403
End Wall 2.0 0.500 3.310 19.500 64.545
Abutment (R)
@ 120 kg/m3
Stem 1.0 12.422 0.300 13.265 49.435
Counterfort 3.0 0.500 C/S Area= 17.742 26.612
3.0 0.500 0.640 13.590 13.046
End Wall 2.0 0.500 2.910 17.045 49.601
313.446
Total Quantity of Reinforcement of Abutment @ 120Kg/m3 37.613
b) Pier
@ 87.5 Kg/m3
3.0 Area= 3.140 15.250 143.655
143.655
Total Quantity of Reinforcement of Pier @ 87.50Kg/m3 12.570
c) Returns
@ 5 Kg/m2
Left
Outer Side 2.0 4.283 3.600 30.834
Inner Side 2.0 3.870 3.600 27.864
C/s Area 4.0 c/s Area 4.718 18.873
Right
Outer Side 2.0 5.056 3.600 36.400
Inner Side 2.0 4.575 3.600 32.942
C/s Area 4.0 c/s Area 6.208 24.831
171.743
Total Quantity of Surface Reinforcement of Return @ 5Kg/m2 MT 0.859
Abutment cap
@ 185 kg/cum Quantity for Abutment Cap in m3 12.112 MT 2.241
Pier Cap
@ 230kg/cum Quantity for Pier Cap in m3 = 106.122 MT 24.408
Pedestal
@ 90kg/cum Quantity for Pedestal in m3 = 4.194 MT 0.377
Total MT 78.068
7 Weep holes
Abutment 2.0 12.422 -0.230 0.000
3.0 3.310 -0.230 0.000
Return(L) 2.0 3.600 0.930 6.696
Return(R) 2.0 3.600 0.930 6.696
Total 13.392
1000mm C/C in Staggered Manner Nos. 4.285
Total Nos. 4.000
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
Item Description No. Length Breadth Depth Unit Quantity Remarks
No. (m) (m) (m)
8A Abutment RCC M30 Abt.cap bott. Level Upto 5m Ht. Level At 10m Ht.
0.3 Left 276.525 265.805 270.805
Height upto 5m1.0 12.422 0.300 5.000 18.634
3.0 0.500 C/S Area= 24.146 36.219
0.3 3.0 0.500 0.640 5.000 4.800
0.15 2.0 0.500 3.310 5.000 16.550
76.202
Height bet 5m to 10m0.300 1.0 12.422 0.300 5.000 18.634
16.370 3.0 0.500 0.640 5.000 4.800
16.220 2.0 0.500 3.310 5.000 16.550
39.984
Height above 10m1.0 12.422 0.300 5.720 21.317
260.305 3.0 0.500 0.640 6.045 5.803
2.0 0.500 3.310 9.500 31.445
58.565
259.71
Right Height upto 5m1.0 12.422 0.300 5.000 18.634
3.0 0.500 C/S Area= 17.742 26.612
3.0 0.500 0.640 5.000 4.800
2.0 0.500 2.910 5.000 14.550
64.596
Height bet 5m to 10m1.0 12.422 0.300 5.000 18.634
3.0 0.500 0.640 5.000 4.800
2.0 0.500 2.910 5.000 14.550
37.984
Height above 10m1.0 12.422 0.300 3.265 12.168
3.0 0.500 0.640 3.590 3.446
2.0 0.500 2.910 7.045 20.501
36.115
Height Upto 5m Total m3 140.798
Height Bet. 5 to 10m Total 77.967
Height Abv. 10m Total 94.680
B Pier RCC M30 Width at 5m Width at 10m
0.53 2.000 2.000
1.48
2.000
15.250 16.550
4.000 2.000
259.68
2.300 0.15
0.9 0.85
0.4 2.300
4.000 0.10
4.200
A)Height upto 5m
3.0 Area = 3.140 5.000 47.100
B)Height bet 5m to 10m
3.0 Area = 3.140 5.000 47.100
C)Height above 10m
3.0 Area = 3.140 5.250 49.455
Height Upto 5m Total m3 47.100
Height Bet. 5 to 10m Total 47.100
Height Abv. 10m Total 49.455
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
Foundation = Level
`
Foundation Level
B
Item Description No. Length Breadth Depth Unit Quantity Remarks
No. (m) (m) (m)
C Return Walls PCC M20 Level At 5m Level At 10m
Left 280.608 285.608
3.850
Height upto 5m
0.6211 Section 1
1.35 2.0 3.600 c/s area = 0.157 1.132
3.16 Section 2
2.0 3.600 c/s area = 2.391 17.217
Section 3
5.000 0.797 2.0 3.600 c/s area = 1.217 8.761
1.370 Section 4
0 2.0 3.600 c/s area = 0.635 4.575
Section 5
0.233 0.797 2.0 3.600 c/s area = 0.318 2.287
0.797 33.972
2.448
Right
4.545
Height upto 5m
0.621 Section 1
2.05 2.0 3.600 c/s area = 0.361 2.598
3.72 Section 2
5.000 2.0 3.600 c/s area = 2.823 20.326
Section 3
0.941 2.0 3.600 c/s area = 1.696 12.209
2.075 Section 4
0 2.0 3.600 c/s area = 0.885 6.375
Section 5
2.0 3.600 c/s area = 0.443 3.188
0.353 0.941 44.695
0.941
2.956
Height Upto 5m Total 78.667
Height Bet. 5 to 10m Total 0.000
Height above 10m Total 0.000
9 RCC M30 in Caps
1.24 0.30
0.15
0.300
i) Abutment Cap 2.0 12.422 1.240 0.300 9.242
2.0 12.422 (1.24+0.3)/2 0.150 2.870
ii) Pier Cap
2.3 3.0 2.300 10.000 0.800 55.200
0.80 3.0 2.300 (2.3+10)/2 1.200 50.922
1.20
10
0.80
1.20
2.3
Total 118.234
10 Pedestal RCC M40 8.0 0.700 0.700 0.400 1.568
8.0 0.700 0.700 0.310 1.215
8.0 0.700 0.700 0.225 0.882
8.0 0.700 0.700 0.135 0.529
Total 4.194
11 Elastomeric bearing
32.0 40.000 40.000 10 Cu.Cm. 512000.00
Total Nos 512000.00
C) SUPERSTRUCTURE
12 Superstructure TMT Re-bar
Dirt Wall @ 185 kg/cum Quantity Of Dirt Wall = 23.702 (23.702*185)/1000 MT 4.385
RCC girder & Slab @ 175 kg/cum Quantity Of RCC Girder & Slab = 522.213 (522.213*175)/1000 MT 91.387
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
3
14
5
2
3
1 4 5
2
Item Description No. Length Breadth Depth Unit Quantity Remarks
No. (m) (m) (m)
TMT MT 95.772
Item Description No. Length Breadth Depth Unit Quantity Remarks
No. (m) (m) (m)
13 RCC M30 in Dirt Walls
0.3
0.1 2.0 12.422 2.830 0.300 21.093
0.25 0.150 2.0 12.422 0.100 0.100 m3 2.484
2.830 2.0 12.422 c/s Area 0.005 m3 0.124
Total 23.702
14 Filling in Counterfort
Left 1.0 3.310 11.422 19.050 720.25
Right 1.0 2.910 11.422 16.595 551.60
Deduction of Counterfort -91.28
Filling in Return 2.0 3.600 11.180 3.850 309.91
2.0 3.600 11.180 4.545 365.86
Total 1856.342
15 Drainage spout
C/S Area = 11.00*21.5*4 860.00 Nos. 42.000
Total Nos 42.000
16 Abutments 2.0 12.422 RMT 24.845
Pier 3.0 12.422 RMT 37.267
Total RMT 62.112
17 Superstructure (Girder & Slab) -
0.700 0.900 0.900 0.700
18.860
0.925
0.15
1.28
0.325 Span(L) = 21.500
0.15 RCC M30 Girder - PLAN OF GIRDER
0.25 For 20m Span
0.625 Straight Portion- 4.0 4.0 18.860 0.625 0.250 m3 47.150
Section -1-1 4.0 4.0 18.860 0.475 0.150 m3 21.500
4.0 4.0 18.860 0.325 1.280 m3 125.532
4.0 4.0 18.860 0.625 0.150 m3 28.290
Tapering Portion 4.0 8.0 0.900 0.625 0.250 m3 4.500
4.0 8.0 0.900 0.475 0.150 m3 2.052
4.0 8.0 0.900 0.325 1.280 m3 11.981
4.0 8.0 0.900 0.625 0.150 m3 2.700
pth of
Girder End Portion - 4.0 8.0 0.700 0.625 1.830 m3 25.620
Cross Girder - 4.0 9.0 0.300 1.675 1.430 m3 25.869
Section -1-1 Deck Slab - 4.0 21.500 12.422 0.213 m3 227.019
Total 522.213
18 PCC M15 for levelling course
2.0 3.550 11.422 0.150 12.165
Total 12.165
19 M25 conc. For Approach slab
2.0 3.500 11.422 0.300 23.987
Total 23.987
20 Superstructure RCC M30
Crash Barrier 2.0 98.830 RMT 197.660
Total RMT 197.660
21 40mm thk. Bituminous Concrete
2.0 98.140 11.000 0.04 86.363
Total 86.363
22 25mm Thk. Mastic Asphalt
1.0 98.140 11.000 1079.540
Total Mastic asphalt 1079.540
m3
m3
m3
m3
m3
m3
m3
m3
(For 20 m2 area 1 Drainage Spout is Provided)
Elastomeric Slab seal Exp. Joint
m3
m3
m3
m3
m3
m3
m3
m2
m2
11
11