Date post: | 17-Jan-2018 |
Category: |
Documents |
Upload: | della-phelps |
View: | 225 times |
Download: | 0 times |
Management
Approaches
Construction Management
Customer appoints
Design teamand
Management team
Construction ManagementCUSTOMER
TRADECONTRACTORS
CONSTRUCTIONMANAGER
ARCHITECT
Construction Management Customers
Tend to be commercial developers wanting:• Large, city centre buildings• High quality architecture• Secure profitsThe most successful of these customers: • Provide leadership for projects• Are actively involved in key decisions• Concentrate attention on agreed objectives
Construction Management Design Teams
• Led by experienced architect who produces overall concept
• Include engineers and specialists who produce much of the detail design
• Guided by design meetings held at key stages • Establish quality control systems• Ensure design is complete and does not cause
delays
Construction Management Management Teams
• Led by experienced construction manager• Check completion date and budge• Establish project organization and plan• Ensures designs meet agreed objectives• Ensures competent teams are selected• Establish control systems• Ensures problems are solved quickly• Identifies good ideas emerging during project
Construction ManagementWorks Contractors
• Have direct contracts with customer• Specialists form part of design team• Ensure designs match cost and time targets• Agree how and when work will be done• Work in accordance with design and plan• Involved in project meetings• Complete work and leave site clean and tidy
Construction Management Key Relationships
CUSTOMER
TRADECONTRACTORS
CONSTRUCTIONMANAGER
ARCHITECT
SPECIALISTDESIGNERS
SPECIALISTCONSULTANTS
Construction Management Performance
• Considerably faster than traditional construction • Commercial projects completed
about 40% quicker• Helps commercial customer achieve
their financial objectives
Efficient Construction Managementacts on the following propositions
• Reduce the number of teams involved• Improve the quality of relationships• Reduce performance variability• Reduce external interference
plus
Efficient Construction Managementacts on the following propositions
• Select teams competent in the technologies required by the project
• Ensure teams accept the agreed objectives• Ensure teams are motivated to achieve agreed
objectives• Foster accurate communications between teams• Ensure teams regard the transactions as
advantageous to themselves
Management Contracting
Similar to construction management except the management team
is provided by a management contractor and works contractors are
subcontractors to the management contractor
Construction Management at Risk
Similar to construction management except the construction management
company guarantee the maximum price and employ works contractors
as subcontractors
Design and Manage
Similar to management contractingexcept the management contractoremploys the design team as well
as the works contractors
Project using Construction Management
The project is to construct a new hotel on a virgin site. The hotel has 300 guest rooms
and the other spaces expected in a 5* hotel
The building is 10 stories high with a steel structural frame, concrete beam floors and
roofs, and high quality, pre-fabricated external cladding.
Teams Team-daysBrief 1 80Design 31 780Plan 5 150Procurement 13 680Manufacturing 10 250Production 40 2340Commissioning 4 140TOTALS 104 4400
For a project with 104 teams (N=104)
Possible relationships = 104 x 103/2 = 5356
3230 of these do not occur
Actual relationships 5356 - 3230 = 2126
Largest number of teams in one time interval is 34 in 21st time interval
They are constructing theservice cores, risers and main plant, the main entrance
and vertical circulationManufacturing teams are producing building
componentsThe work is supervised by design and construction
management teams
34 x 33/2 = 561 possible relationships
During the 21st time interval the following teams work simultaneously
3 out of 4 construction manager’s plan and control teams1 out of 2 contracts and payment systems teams
4 out of 10 manufacturing teams3 out of 4 service core teams
3 out of 4 risers and main plant teams5 out of 8 entrance and vertical circulation teams
1 out of 2 designer and construction manager’s supervision teams
This gives a total of 20 teams with 190 relationships
Established Relationships
A total of 90 teams have established relationships with some of the other teams and
there are a total of 1687 established relationships
Established Relationships Indicator ER=1687/2126=0.79
The relationship fluctuation indicator FE = 0.81
This reflects a strong influence of established relationships throughout the project because
both ER and FE are comparatively high
Construction management strategy relies on established relationships between
construction management company and trade contractors
Relationship Quality Indicator for established relationships ranges from 0.40 to 0.98
Total Relationship Quality Indicator 1195/2126=0.56
Although there are a number of high values for individual Relationship Quality Indicators, the total Relationship Quality Indicator is no more than reasonably good because there are 439 boundary relationships in this project out of
possible 2126
The project organisation is not overly complex There are 31 time intervals out of a potential
maximum of 207
The intervals are relatively short in comparison to total project duration (prevent escalation
of problems when teams interact for a prolonged period)
Relationships configuration complexity indicator = 0.875
The past performance of the 104 teams over their previous 10 projects provides team Performance Variability Indicators which
range from 0.45 to 1.0
Performance Variability Indicator Rp=0.85
Historical records for projects using Construction Management gives
External Interference Indicator = 0.52
Established Relationships ER=0.79
Relationship Fluctuation FE=0.81
Relationship Quality QR=0.56
Relationship Configuration CR=0.875
Performance Variability Rp=0.85
External Interference I=0.52
Project using Construction Management