Date post: | 19-Jun-2015 |
Category: |
Investor Relations |
Upload: | no-to-mining-in-palawan |
View: | 2,573 times |
Download: | 3 times |
LEPANTO CONSOLIDATED MINING COMPANY LEPANTO MINE DIVISION
D. R. JAVIER Department Manager , Civil Engineering Services
MANAGING A GOLD MINE TAILINGS DAM
PHILIPPINES
Lepanto Mines
Mankayan, Benguet
Manila
Sea
China
Bontoc
La Union Poro Point
Baguio City
Dagupan City
Tailings Dam 5A
Outline of presentation
Design Construction Operation
VICINITY MAP
Lepanto Airstrip
TD 5A
Designer : • Energosystems and Geosciences
Incorporated Consultants :
• Knight Piesold Consulting Engineers • Woodward-Clyde (URS of Australia)
SECTION OF THE DAM
Random Fill
Sand & Gravel Filter
Boulder Toe
Zoned Earthfill Embankment
Design Height – 132 meters
Length/Width of Crest – 345 meters/10 meters
Spillway – Designed to handle probable
maximum flood
TUNNEL AND DECANT TOWER
Diversion Tunnel
Tunnel #1 3.0m wide x 3.0m high and 183m long
Tunnel #2 4.0 m wide x 5.0 m high and 550 m long
Decant Tower 1 & 2
3 inlets each at 2.0m wide x 4.0m high
PERMEABILITIES OF EMBANKMENT MATERIAL
Silty Clay 1 x 10-6 to 1 x 10-7 cm/s
Random Fill 1 x 10-5 cm/s
Sand Filter 1 x 10-3 to 1 x 10-4 cm/s
Gravel Filter 1 x 10-1 to 1 x 10-2 cm/s
Rock Toe 1 x 10 to 1 x 10-1 cm/s
SEISMIC CONSIDERATIONS
Operating Basis Earthquake (OBE) = 0.15g
Maximum Credible Earthquake (MCE) = 0.25g
FACTOR OF SAFETY
Factor of Safety vs Failure
(under static loading) = 1.2
Factor of Safety vs Maximum Probable Earthquake Loading Conditions
= 0.98-1.5
FREEBOARD REQUIREMENT
Minimum freeboard requirement is 500 year flood event compared to DMO requirement of 100 .
EMBANKMENT SLOPE
Upstream = 2 horizontal is to 1 vertical
Downstream = 2.5 horizontal is to 1
vertical
•Impounding Capacity – 50 million cubic meters • Catchment Area – 18.50 square kilometers • Reservoir Area - 103 hectares
DATE STARTED – January 1992
COMMISSIONING DATE – September 1993
The Twin Decant Tower has reached elevation 694.0m
• Driving of DiversionTunnel to divert Mankayan river before the start of embankment construction.
• Steel rib supports are used in very heavy ground where rockbolting and shotcrete is not applicable. Steel Rib Support
Decant Tower # 1
Decant Tower # 2
DIVERSION TUNNEL & DECANT TOWER
EMBANKMENT CONSTRUCTION
Stripping of the river bed is done for the dam foundation. All the boulders from the stripping activity are hauled and moved to the rock toe drain area.
A core trench 6m deep X 6m wide with 1:1 slope is excavated out of the dam foundation near the central section of the core axis to provide additional stability against sliding.
Hauling and aligning of sand/gravel filter. The sand filter was screened to produce a clean well graded fine to coarse sand while the gravel filter was crushed and screened to a uniform minus 19 mm size.
3m sand filter
3m gravel filter
piezometers
QUALITY CONTROL
A material testing laboratory on site was provided to test the following: concrete (21 Mpa), aggregates and soil materials (abrasion , permeabilities, etc).
Field density test is done to ensure that compaction is not less than 90% of the proctor density. Minimum moisture content is 13%.
Water jetting
Slush grouting
Clearing
The left and right abutments are cleaned and slush grouting is maintained over the core and filter zones. Abutment slopes are being maintained at no greater than 1:1. Water jetting, dental concreting and slush grouting are implemented for the abutment treatment.
ABUTMENTS PREPARATION
A fan pattern of grout holes are drilled at the embankment surface to intercept possible cracks and filled with a cement grout.
GROUTING
Lime Slaking Plant
Detoxification Plant
The influent is treated with lime and sodium metabisulfite to ensure the effluent is compliant to government regulatory standards.
Upstream Backfilling
Downstream Backfilling
The upstream section of the embankment has been raised to elev. 691.30m
The downstream embankment for the current backfilling operation has reached elev. 669.0m.
A once a month drain cleaning is done to control the rise of phreatic surface within the dam.
Weekly drain flow monitoring : - Dry season = 20 liters/sec - Wet season = 45 liters/sec
DIS
CH
AR
GE
, g
pm
RA
INF
AL
L,
mm
MONTH
UNDERDRAIN FLOW MONITORING
Rainfall
Discharge
Vibrating wire piezometers (VWPs) are installed along the centerline of TD5A to check on the performance of the dam especially its stability and its seepage defensive design features.
VWPs are being monitored weekly
SAND & G
RAVEL FILTER
VWP 6 VWP-15
VWP-14
VWP-10ARANDOM FILL
720 EL.
700 EL.
680 EL.
660 EL.
640 EL.
620 EL.
600 EL.
LONGITUDINAL SECTION OF T.D. # 5-A
PHREATIC SURFACE
Copyright LCMCo/agc
River
Dra
in
Rock Toe
Drain
RANDOM FILL
0 40 100
VWP = Vibrating Wire Piezometer
ROCK TOE WEIR: Q = 517 gpm
Bottom Elev. Ref. Elev. Water Depth Water Elev. Pressure (psi)
603.0606.0602.0613.5601.0600.0
691.30689.50667.00682.50677.00667.00
CREST LEVEL
WATER LEVEL
VWP 9C
PIEZOMETER LOCATIONS
Bottom Elev. Ref. Elev. Water Depth Water Elev. Pressure (psi)
VWP-6 603.00 691.30 72.50 618.80 22.50
VWP-9c 606.00 689.50 73.70 615.80 14.00
VWP-10a 602.00 667.00 62.20 604.80 3.90
VWP-14 613.50 682.50 51.40 631.10 25.00
VWP-15 601.00 677.00 62.60 614.40 19.00
VWP-16a 600.00 667.00 58.90 608.10 11.50
VWP- Vibrating Wire Piezometer
MONTHLY PIEZOMETER READING OF TD5A
0.0
100.0
200.0
300.0
400.0
500.0
600.0
700.0
800.0
900.0Jan,
2000
May
Sept
Jan,
2001
May
Sept
Jan,
2002
May
Sept
Jan,
2003
May
Sept
Jan,
2004
May
Sept
Jan,
2005
May
Sept
Jan,
2006
May
Sept
Jan.
2007
May
Sept
Jan,
2008
May
Sept
Jan.
2009
May
Sept
Jan,
2010
May
MONTH
RA
INF
AL
L,m
m
560.00
580.00
600.00
620.00
640.00
660.00
680.00
700.00
EL
EV
AT
ION
,m
Rainfall mm
Pond WaterLevel m
PZ1
PZ2
VWP6
VWP6A
PZ7
VWP8
PZ9
PZ9A
VWP9C
VWP9B
VWP10A
PZ10
PZ11
VWP14
VWP15
VWP16
VWP16A
Diversion Tunnel Regular monitoring: Ocular - for any signs of cracks, scouring of the invert, vandalism, etc . Extensometer – for tunnel movement
Regular inspection of the Decant Tower for any cracks and scouring of invert .
SUMMARY
The Lepanto TD5A has been in operation for the past 17 years. In October last year when we had the highest rainfall in the dam’s life, there were no significant movements of the structures in the dam.
To assure us of the continuous integrity of the dam, Lepanto Mine Division has engaged the services of a reputable international consulting firm to conduct annual review and evaluation of the on-going construction and performance of the dam.
Panoramic view of upstream and downstream of TD5A
Then Now
Then Now
Migratory birds have made our tailings pond their permanent habitat.
EMERGENCY MEASURES MAJOR TYPHOON
INSTALL TEMPORARY STOPLOGS - 3m TEMPORARY RAISE OF EMBANKMENT
- 3m Freeboard, 12m Berm LAST RESORT TO OVERTOPPING OF DAM
- Cut 1m deep x 12m wide Fuse Type Plug Spillway
CONDITIONS o Elevated Pore Pressures o Seepage at Random Fill Shell o Sustained Turbidity of River Drain
ACTIONS
o Inform Dam Experts (EGI, KPP, URS)/Management o If investigation confirms any of the three conditions, install
second line of defensive features
CONTINGENCY MEASURES EMBANKMENT PROBLEMS
LEPANTO MINE DIVISION
CENTRAL SAFETY RESPONSE ORGANIZATION
CHAIRMAN CONSULTANTS
CENTRAL COORDINATORS
GROUP MANAGERS PRO
FIELD COORDINATORS
SUPERINTENDENTS
COMMUNITY PNP PERSONNEL BRGY OFFICIALS
CAMP/AREA/ORGANIZATION MUNICIPAL OFFICERS
OTHER OUTSIDE CONCERN
COMMUNICATION
DISCOVERY
MONITORING TEAM (3 SHIFTS)
ON SHIFT SECURITY SUPERVISOR ON SHIFT SAFETY SUPERVISOR ON SHIFT DAM SUPERVISOR
NO
TIFI
CA
TIO
N
TAILINGS DAM FIRE TYPHOON FLOOD EARTHQUAKE, ETC.
TRIGGER
POINTS
FIRE SERVICES RESCUE &
RECOVERY
MEDICAL TEAM TRANSPORT
SERVICES
EVACUATION
TEAM
RELIEF TEAM UTILITY CONTOL
TEAM
SECURITY TEAM
CENTRAL CONTROL BASE
GENERAL OFFICE
SIGNALS/COUNTERSIGNALS
CONTINUOUS SHORT BLAST OF
SIREN
TAILINGS DAM 5A MAJOR DISASTER
DISCOVERY
NOTIFICATION OF IMMEDIATE MEN IN THE VICINITY THEN CALL THE CENTRAL
TELEPHONE OPERATOR
DISASTER CONTROLLABLE
TELEPHONE OPERATOR MUST DO -REPORT TO ALL CONCERNED -NOTIFY POWER PLANT TO SIGNAL ALARM (5 SHORT SIREN BLAST)
CONTROL DISASTER
NOTIFY OFFICIALS
RM/CES MGR (RESPONSIBLE STAFF) CENTRAL CONTROL OPERATION
CENTRAL
-DEFINE & PINPOINT LOCATION -ASSEMBLE & ORGANIZE RESCUERS - PREP. & ASSEMBLY OF RESCUE APPARATUS
CENTRAL
TD MEN RETREAT TO GATHERING POINTS
THEN COMMUNICATE WITH TD4 FIELD OFFICE
RETREAT TO TD4 FIELD OFFICE
RETREAT TO TD4 FIELD OFFICE
STAY AND AWAIT INSTRUCTION
RM/CES MGR (RESPONSIBLE STAFF) CENTRAL CONTROL OPERATION
CENTRAL
-DEFINE & PINPOINT LOCATION -ASSEMBLE & ORGANIZE RESCUERS - PREP. & ASSEMBLY OF RESCUE APPARATUS
CENTRAL
RECON TEAM TO DISASTER SCENE
ASSESS SOURCE & EXTENT OF DISASTER;
INFORM CONSULTANTS
NOTIFY SURFACE BASE
RESCUER & EQUIPMENT TO DISASTER SCENE
PERFORM RESCUE & CONTROL OPERATION
PERFORM RESCUE & CONTROL OPERATION
GAS ANALYSIS/SAMPLING
SEALING
RESCUE TEAM & EQUIPMENT
APPLY SURFACECONTROL OPERATION
RESCUE & RECOVERY CONTROL DISASTER
Date: June 2010
DATE pH Pb TOTAL DISSOLVED TOTAL SUSPENDED pH
(ppm) SOLIDS(ppm) SOLIDS(ppm)
Outlet Outlet Outlet Outlet Outlet A Outlet B Decant Decant
June
1 7.47 0.075 1031 28 0.0057 0.0066 0.529 8.30
2 7.11 0.100 1167 38 0.0188 0.0203 0.764 8.51
3 7.40 0.050 1236 29 0.0224 0.0237 1.110 8.43
4 7.32 0.100 1136 21 0.0132 0.0128 0.695 8.36
5 7.68 0.040 1154 23 0.0065 0.0055 0.989 8.95
8 - 0.050 1086 27 0.0017 0.0122 1.070 -
9 7.20 0.056 1217 23 0.0130 0.0017 1.060 8.15
10 7.44 0.050 1249 21 0.0096 0.0108 0.933 8.03
11 6.99 0.070 712 12 0.0032 0.0034 0.328 7.96
12 6.96 0.093 1043 38 0.0170 0.0168 0.673 8.62
15 6.98 0.038 983 30 0.0176 0.0109 0.316 8.58
16 7.15 0.046 798 31 0.0066 0.0071 0.232 7.85
17 7.09 0.020 763 24 0.0068 0.0081 0.653 7.80
18 6.71 0.028 922 18 0.0083 0.0090 0.861 8.05
19 6.72 0.070 986 34 0.0093 0.0063 0.687 8.17
20 6.84 0.059 1042 13 0.0353 0.0234 0.810 8.16
22 6.88 0.076 910 18 0.0223 0.0197 0.854 8.45
23 7.14 0.040 861 18 0.0106 0.0086 0.895 8.98
24 7.19 0.025 899 16 0.0122 0.0104 0.874 8.01
25 7.21 0.027 785 20 0.0120 0.0121 1.040 8.69
26 7.29 0.030 886 24 0.0087 0.0067 0.321 8.36
28 7.06 0.030 843 21 0.0163 0.0174 0.466 8.21
29 6.87 0.020 775 26 0.0248 0.0266 0.3580 8.00
Next Review Date:
Revision No.: 00
CN (ISE)
(ppm)
( Environment )
Page 1 of 1
LEPANTO CONSOLIDATED MINING COMPANY
Lepanto Mine Division
REC-ASY-022
Date Effective:
INTEGRATED MANAGEMENT SYSTEM
TITLE: ASSAY RESULTS OF TD5A EFFLUENT
Migratory birds have made our pond their permanent habitat.
Panoramic view of upstream and downstream of TD5A
Then Now
Then Now
Concrete sealing of newly installed stoplogs
Installation of stoplogs
Outlet view
Lime Slaking Plant
Detoxification Plant
Borrow area
Abutment Clearing