REMINDER Check in on the COLLABORATE mobile app Managing Cash Flow in Primavera P6 Prepared by: Luka Novosel, PMP Primavera Implementation Consultant Primakon Ltd. How to Track Project Revenues and Expenditures in One P6 Project Session ID#: 15465
Transcript
Page 1: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

REMINDER

Check in on the COLLABORATE mobile app

Managing Cash Flow in Primavera P6

Prepared by:

Luka Novosel, PMP

Primavera Implementation Consultant

Primakon Ltd.

How to Track Project Revenues and Expenditures in One P6 Project

Session ID#: 15465

Page 2: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

About me…

■ Masters degree in Electrical Engineering

■ Primavera functional & technical consultant since 2006

■ PMI PMP certified since 2010

■ Oracle Primavera P6 & P6 R8 Implementation Specialist

■ Oracle Primavera EPPM trainer

■ PMP preparation trainer

■ Primavera EPPM API application designer & developer

■ Primavera EPPM SDK application designer & developer

Page 3: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

About us…

■ Primakon is privately owned consulting company

■ 15+ years of experience in Primavera implementations

■ Offers customer tailored education in the area of PM methodologies and Primavera products

■ References in wide area of industries (from finance sector to construction)

■ Present on markets in EU & SE Europe

Page 4: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

Presentation overview

■ The business need (NUMIP case)

■ Solution analysis

■ Model description

▪ Model overview

▪ Data entry

▪ Background jobs

▪ Primavera reports

■ BI publisher data model

■ BI reports

■ Conclusion and what’s next

Page 5: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

The business need (NUMIP case)

This is a subtitle or bulleted list

Page 6: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

The business needs …

■ About company

▪ NUMIP, privately owned engineering company,

▪ Working in different process industries such as:

— Nuclear Industry

— Pharmaceutical Industry

— Paper Industry

▪ Present in USA & Europe

▪ Project oriented company

■ Business needs:

▪ Long-running recession

▪ Huge pressure on profit margin

▪ Optimization of internal processes

Page 7: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

Requirements …

■ Primavera P6 as management tool

■ Detailed project plans in Primavera

▪ All activities with roles in planning phase for cost projections

▪ Resource and material assignments with planned and actual values for cost tracking

■ All project expenditures in one place

■ Cash flow projections in Primavera P6

■ Executive reports on future cash flow projections

■ Email alerts for invoices

Page 8: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

Key problems …

■ Primary role of P6 is to help project managers in managing projects

■ Additional requirements mustn’t interfere with primary role

■ Invoice due dates depend on contract definitions

■ The moment when the job is done (and money earned) is different from the moment when the invoice is paid

■ Management request is to have both informations in P6 and in correlation to project schedule

Page 9: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

Solution analysis: Why cost User Defined Fields (UDF)?

Page 10: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

Cost UDF Model and what’s behind it

■ WBS node called Cash Flow

■ Milestones with predecessor links to project plan

▪ Lag on relationship defines invoice due date period (i.e 30 days)

▪ Activity Cost UDF’s :

— Revenue

— Expenditure

▪ Milestone calendar: 7-day workweek

■ Milestone date gives UDF time dimension

■ Project Cost UDF’s summarizes activity level UDF’s (background job) one field for every month / type

Page 11: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

Automatic Project Cost UDF creation

■ Background job creates project UDF’s

■ Two prefixes (data type and value type)

■ Data Type

▪ PLI – planned value

▪ BLI – baseline value

■ Value type

▪ EXP – expenditure

▪ INC – revenue

▪ CF – cash flow

Page 12: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

Key benefits of this ModelWhy Cost UDF’s?

■ Financial fields do not interfere with managing project costs

■ No specific filtering is needed

■ Data is dynamically related to project schedule

■ Background job is updating project fields on predefined intervals

■ Simple project reports in P6 Web

■ Simple Project Portfolio analysis

■ Default Primavera Project Cost analysis (i.e total costs) is not affected

■ Designed as an add-on to regular project plans

■ Easy copy / paste export to Excel

Page 13: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

Model description

Page 14: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

Data input process

■ In project planning phase : Project Manager and Commercialdepartment official define planned project cash flow.

■ Revenue and expenditure milestones are linked to project management schedule

■ In P6, financial department officers have special Project and Global Security setup

▪ Read / Write access to WBS nodes with cash flow and invoice milestones

▪ Read + add relationships on project level

■ This way they have authority to define new milestones if necessary during projects execution

Page 15: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

Data input process cont.

■ In P6 web special user interface view + layout are defined for financial department

Page 16: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

Data input process cont. 2

■ Assigning relationships and monetary value to milestones

Page 17: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

Project Cost UDF creationBackground job description

■ Every UDF expenditure / revenue activity is paired with the assigned milestone date

■ With that, every expenditure / revenue is getting time distribution variable

■ Background job based on Java and P6 API summarizes all UDF’s from activity level to project level

■ In that process time variable is used to make time distribution of cost UDF’s on project level

Page 18: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

Project Cost UDF creationAccessing Baseline UDF values

■ Using P6 API, it is possible to read „baseline” activity UDF values. That data are not visible in P6 application.

■ With this, background job creates baseline time distributed values as project code UDF-s

Activity

rescheduled

Baseline Project value

Page 19: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

Project Cost UDF Naming Conventions

■ Automatically created UDF’s follow predefined naming conventions

▪ VALUE TYPE + space + DATA TYPE + space + month.year

■ In this implementation VALUE TYPES are:

▪ EXP -> for expenditures

▪ INC -> for revenues

▪ CF -> for cash flow (revenue – expenditure)

■ DATA TYPES are:

▪ BLI -> baseline values

▪ PLI -> planned values

▪ ACI -> actual values (to be implemented)

■ These properties can be altered to suite specific implementation needs

Page 20: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

Primavera out-of-the-box reports

Page 21: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

Primavera Web reports

■ Porftolio with active projects

■ Portfolio views based od project cost UDF’s

■ P6 Web summarizes project UDF’s

■ Different scorecards can be created

■ Quite limited report options directly from the web

■ Limit of 28 fields per scorecard

■ Export to Excel option

Page 22: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

Primavera Client reports

■ Generally P6 Client is not used for reporting

■ Export to Excel option is used from the P6 Client

■ No limitation in number of fields per layout

■ Easy copy / paste of fields to MS Excel for further analysis

■ Special layout is designed for that purpose

Page 23: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

BI Publisher Cash Flow Report

Page 24: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

BI Publisher reportsNew reporting in P6

■ BI Publisher is selected as main reporting source for reports in this model

■ Data model is developed to support requested reports

■ P6 desired look and feel is implemented

■ Reports are accessible via P6 web

Page 25: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

BI Publisher Data Model

■ List of Values(LOV) is created for Projects

■ Parameter p_project_id is defined to use this LOV

■ Data sets are defined

Page 26: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

BI Publisher - Data Model - Data Set

■ Data set is defined to support reporting needs

■ In this example SQL query will create number of fields from our Project Cost UDF names

■ Main fields are:

▪ DATA_TYPE

— sql: trim(SUBSTR(P6UDFTYPE.TITLE,4,4))

▪ VALUE_TYPE

— sql: trim(SUBSTR(P6UDFTYPE.TITLE,1,3))

▪ VALUE_DATE

— sql: trim(SUBSTR(P6UDFTYPE.TITLE,-7))

▪ SORT_DATE

— sql: trim(SUBSTR(P6UDFTYPE.TITLE,-4)) ||'.'||

trim(SUBSTR(P6UDFTYPE.TITLE,-7,2))

Page 27: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

BI Publisher - Data Model - Data Set cont.

■ The query result will hold one record for every sort_date-data_type-value_type pair with appropriate value and sum value to date

Value

Date

Sort

Date

Value Value Type Data

Type

Cum

Value

12.014 2014.01 90000 CF Baseline 90000

42.014 2014.04 -21312 CF Baseline 68688

72.014 2014.07 0 CF Baseline 68688

12.015 2015.01 0 CF Baseline 68688

12.014 2014.01 -31200 EXP Baseline -31200

42.014 2014.04 -21312 EXP Baseline -52512

72.014 2014.07 0 EXP Baseline -52512

12.015 2015.01 0 EXP Baseline -52512

12.014 2014.01 121200 INC Baseline 121200

42.014 2014.04 0 INC Baseline 121200

Page 28: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

BI Publisher - Data Model - Data SetRunning totals

Data sort for running

totals

Data sort for running

totals

Grouped by value typeRunning total per group

Page 29: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

BI Publisher - Data Model - Data SetSQL query String month.year and

year.month fields for

grouping

Case when for

data_type – this is done

to make chart legend

more readable

Page 30: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

BI Publisher - Data Model - Data SetSQL query cont.

Running totals are created

to enable cashflow S-curve.

Partition is done by:

1. data_type

2. value_type

All sorted by sort_date

Three tables are used in

SQL join:

• P6UDFTYPE

• P6PROJECT

• P6PROJECT_UDFVALUE

Page 31: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

BI Publisher - Data Model - Data SetSQL query cont. 2

In WHERE statement,

project UDF fields are

filtered by value_type

values (EXP, INC, CF)

UDF field with TOTAL

instead of sort_date is

excluded from this data set

Parameter value is used in

WHERE part of the

statement

That can be one or list of

project ID’s

Page 32: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

BI Publisher - Data Model - Data SetSQL query cont. 3

Grouping in SQL statement Grouping in SQL statement

is done according to SQL

standard requirements

Page 33: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

BI Publisher - Data Model - Data SetSample XML data and Report editor

■ After data set definition, XML sample data set is created

■ Report is designed in Web Report editor

■ Word .rtf templates are not used in this case

■ The goal was to create report in Web Editor only and to test it’s limitations

■ 4 layouts are defined

▪ Cumulative Graphical

▪ CashFlow Report

▪ Revenue Report

▪ Expenditure report

Page 34: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

P6 Web Report AccessTemplate selection

■ 4 report layouts defined in BI Publisher are available as templates in P6

■ Same names as Layouts in BI

Page 35: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

P6 Web Report AccessProject selection

■ In this data model project data is summarized

■ Possible uses of reports:

▪ One project

▪ Cumulative reports on portfolios

Page 36: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

Report examplesCumulative graphical report

Page 37: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

Report exampleCashFlow report

■ Table and chart filter

▪ Value_type=„CF”

■ Project List

Page 38: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

Report exampleRevenue report

■ Table and chart filter

▪ Value_type=„INC”

■ Project List

Page 39: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

Report exampleExpenditure report

■ Table and chart filter

▪ Value_type=„EXP”

■ Project List

Page 40: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

Future model development

Page 41: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

Plans for future …

■ Data integration with financial system on several key points

▪ i.e. invoice number assigned to milestones

■ New Actual fields

▪ When milestone has actual date, value in UDF (expenditure / revenue) is declared as actual value

■ New reports for key stakeholders

■ Additional forecast analysis

▪ i.e. Preset and Net Present Values

Page 42: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

Questions ?

Contact Information:

Luka Novosel, M.Eng , PMP

Primakon ltd

[email protected]

www.primakon.com

Page 43: Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14

Please complete the session evaluationWe appreciate your feedback and insight

You may complete the session evaluation either

on paper or online via the mobile app


Recommended