+ All Categories
Home > Documents > Managing Projects with - About | openSE

Managing Projects with - About | openSE

Date post: 22-Oct-2021
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
23
DOCUMENT NO. 16004 VERSION 1.5 Managing Projects with Part 3 Table of Content Project Planning & Scheduling ........................................................................................... 1 Product Breakdown Structure ....................................................................................... 6 Work Breakdown Structure .......................................................................................... 8 RACI Matrix ........................................................................................................ 14 Scheduling ......................................................................................................... 15 Project Costing ......................................................................................................... 16 Cost Estimating .................................................................................................... 17 Budgeting .......................................................................................................... 22 Project Planning & Scheduling Typology 2 types of project schedules Master Schedule ~ Summary Schedule Masterplan Calendrier directeur Coordination Schedule ~ “PERT”, Gantt chart Activity network Calendrier de coordination S t r a t e g i c level T h e w h o l e p r o j e c t I n t u i t i v e approach T a c t i c a l level O n e o r a f e w p h a s e s A n a l y t i c a l approach One page/slide Can be in the P r o j e c t R o a d m a p Several pages Can be in the P M P This work is licensed under a Creative Commons Attribution – Share Alike 3.0 Switzerland License. Pierre Bonnal
Transcript
Page 1: Managing Projects with - About | openSE

DOCUMENT NO.

16004VERSION

1.5

Managing Projects withPart 3

Table of Content

Project Planning & Scheduling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1

Product Breakdown Structure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6

Work Breakdown Structure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8

RACI Matrix . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14

Scheduling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

Project Costing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16

Cost Estimating . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17

Budgeting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22

Project Planning & Scheduling

Typology

2 types of project schedules

Master Schedule~ Summary Schedule

MasterplanCalendrier directeur

Coordination Schedule~ “PERT”, Gantt chart

Activity networkCalendrier de coordination

Strategic levelThe whole projectIntuitive approach

Tactical levelOne or a few phasesAnalytical approach

One page/slideCan be in the Project Roadmap

Several pagesCan be in the PMP

This work is licensed under a Creative Commons Attribution – Share Alike 3.0 Switzerland License. Pierre Bonnal

Page 2: Managing Projects with - About | openSE

DOCUMENT NO.

16004VERSION

1.5PAGE

2

FINALIZECOMMISSIONBUILDDESIGNSTUDYINITIALIZE

Initiators

Master ScheduleWhen and which effort?

Master Schedule preparation

Master Schedule (re)validation

Project Board

Master Schedule updateStudy Team

Master Schedule updatesProject Team

FINALIZECOMMISSIONBUILDDESIGNSTUDYINITIALIZE

Coordination ScheduleWhen and which effort?

Study Coordination Schedule* preparation (if needed)Study Team

Project Coordination Schedule* updatesProject Team

Study Team

Project Coordination Schedule* preparation

* incl. PBS, WBS, LoA (list of activities), RBS, RACI matrix

Managing Projects with --- Part 3 Pierre Bonnal

Page 3: Managing Projects with - About | openSE

DOCUMENT NO.

16004VERSION

1.5PAGE

3

MayAprilMarchFeb.Jan.Dec.Nov.Oct.Sep.

BRZ•KITE project launched

CDR released Perform Basic Design

Perform Engi neering Design TDR released

Make & Test PrototypeSet Supply Chain

Perform Detailed Design of Manufacturing Facility Procure Equipment & Tooling

Perform Civil Engineering WorksInstal & Commission Equipment & Tooling

Ramp-up Production1st batch ofkites shipped

Coordination Planning & SchedulingA three-step process

q Identifying the project activities

w Identifying the resources available, estimating the resources required

a Gantt chartMicrosoft Project Gantt chart® ®

ProjectWizard Merlin Gantt chart® ®

The Work Breakdown Structure (WBS)

The RACI Matrix

e Scheduling the activities

The Coordination Schedule

Managing Projects with --- Part 3 Pierre Bonnal

Page 4: Managing Projects with - About | openSE

DOCUMENT NO.

16004VERSION

1.5PAGE

4

Coordination Planning & Scheduling

3 possible approaches

Intuitiveapproaches

Analogicalapproaches

Analyticalapproaches

creativitytechniques Practice Standard

for Work BreakdownStructures

q Identifying the project activities

PMBOK Quintilianheptameter

-inspired

Coordination Planning & Schedulingq Identifying the project activities Ú analogical approaches

> Approach sold as systematic,but not that much!

> Global lessons learned collectedby the Project Management Institute

NASA's Work Breakdown Structure Handbook (NASA/SP-2010-3404)Project Management Institute's Practice Standard to Work Breakdown Structures

Managing Projects with --- Part 3 Pierre Bonnal

Page 5: Managing Projects with - About | openSE

DOCUMENT NO.

16004VERSION

1.5PAGE

5

Coordination Planning & Schedulingq Identifying the project activities Ú analogical approaches

Project Management Institute's Practice Standard to Work Breakdown Structures

Coordination Planning & Schedulingq Identifying the project activities Ú analytical approach

> Inspired from the Quintilian heptameter

Marcus Fabius Quintilianus(c. 35 – c. 100 CE) was a Roman

rhetorician from Hispania, widely referred to in medieval schools of

rhetoric and in Renaissance writing

quiswho

quidwhat

ubiwhere

quibus auxiliiswhich means

curwhy

quomodohow

quandowhen

1=! Describing the final deliverable(s)

The Product Breakdown Structure (PBS)

1=@ Deriving the Work Breakdown Structure (WBS) from the PBS

The WBS top nodes, then the WBS-matrix

1=# Generating the list of activities from the WBS-matrix

The activity portfolio

Managing Projects with --- Part 3 Pierre Bonnal

Page 6: Managing Projects with - About | openSE

DOCUMENT NO.

16004VERSION

1.5PAGE

6

Coordination Planning & Schedulingq Identifying the project activities Ú analytical approach

1=! Describing the final deliverable(s)

Computing / Software

Construction

Industrial Plants

New ProductsNew Services

Events

Training / HR

Organizational

Complex Systems

the buildingthe facilitythe system

the prototype

the product (item)+ the supply chain

(i.e. the manufacturing facility)

the software

It can become a rather complex mix of “objects”

Qty11122222121122122262221111

Component specication1800 mm × 700 mm ; 0.5 m2 ; Polyamide 5.5 nylonReinforced polyamide nylonReinforced polyamide nylonReinforced polyamide nylonReinforced polyamide nylonReinforced polyamide nylonØ6 mm × 1100 mm ; carbon rodØ6 mm × 600 mm ; carbon rodØ6 mm × 550 mm ; carbon rodØ6 mm × 120 mm ; carbon rodCycolac ABSCycolac ABSCycolac ABSCycolac ABSØ10 mm × 0.4 mm2 ; stainless steelØ10 mm × 0.4 mm2 ; stainless steelØ10 mm × 0.4 mm2 ; stainless steelØ10 mm × 0.4 mm2 ; stainless steel0.1 mm2 × ca. 800 mm ; nylon rope 0.15 mm2 × ca. 800 mm ; nylon ropeØ20 mm × 1 mm2 ; stainless steel20 mm width nylon strapCycolac ABSTransparent nylonPrinted material ; A6 formatPrinted material ; A6 format

Fabrics

Carbon rods

Moulded ABS parts

Rings (COTS)

Rope & strap

Printed materialBag

ID0102030405060708091011121314151617181920212223242526

Component descriptionWing surface (canopy)Nose reinforcement pieceTail reinforcement pieceWisker reinforcement pieceWing end reinforcement pieceWing side reinforcement pieceWing side yardRear yardLongitudinal yardWiskerNose yard junction teeCentral crossWisker junction teeWing side junction teeCentral tying ringWing end tying ringWing side tying ringLine attachment ringTieLineHandle ringHandleLine winderStorage bagUser's manualSafety instructions

BoM

ProductBreakdownStructure

PBS

Managing Projects with --- Part 3 Pierre Bonnal

Page 7: Managing Projects with - About | openSE

DOCUMENT NO.

16004VERSION

1.5PAGE

7

BRZ·KITE

Fabrics

Carbon rods

Moulded ABS parts

Rings (COTS)

Rope & strap

Storage bag

Printed material

Coordination Planning & Schedulingq Identifying the project activities Ú analytical approach

1=! Describing the final deliverable(s)

Product Breakdown Structure

moniteur de positionaimant correcteur dipolaireaimant sextupolaireaimants quadripolairesaimant dipolaire

moniteur d'intensité

moniteurs de profil

zone

expé

rim

enta

le

Onduleur

RFInjection

faisceau d'électrons

Projet

Coordination Planning & Schedulingq Identifying the project activities Ú analytical approach

1=! Describing the final deliverable(s)

Managing Projects with --- Part 3 Pierre Bonnal

Page 8: Managing Projects with - About | openSE

DOCUMENT NO.

16004VERSION

1.5PAGE

8

Servicesélectriques

Bâtiments

Aéraulique

Hydraulique

Matériel Logiciel

Supervisioncentrale

Automatesprogrammables

moniteursde position moniteur

d'intensité

moniteursde prof l

Cavités Klystron

Guides d'ondes

KickersSeptum

CorrecteursOnduleur

DipôlesQuadripôles

Sextupôles

Pompes

Jauges

Chambres

Infrastructures

Systèmes de supervision

Équipements ancillairesInstrumentation du faisceau

Système d'accélération

Convertisseurs de puissance

Éléments magnétiquesSystème vide

Coordination Planning & Schedulingq Identifying the project activities Ú analytical approach

1=! Describing the final deliverable(s)

Coordination Planning & Schedulingq Identifying the project activities Ú analytical approach

What is an activity??a.k.a. work unit

] ≠ deliverable!

] consumes time

action verb (infinitive tense) + noun]

To avoid confusion, clever professional practices (e.g. MIL-HDBK-245B + appendix A) and severaltextbooks suggest to label activities as follow:

] consumes resources

] has start and end dates

] creates (a) deliverable(s)

] is measurable

] is assignable to one project participant

Some examples:Manage the projectPrepare PM documentsPerform detail design of wing surfaceSupply rope & strapsCFT for moulded ABS parts

An activity:

and only one!

Managing Projects with --- Part 3 Pierre Bonnal

Page 9: Managing Projects with - About | openSE

DOCUMENT NO.

16004VERSION

1.5PAGE

9

Coordination Planning & Schedulingq Identifying the project activities Ú analytical approach

What is an activity??An activity:

] consumes time Yes, but within certain limits!

] No definitive answer!

] No more than 5% to 10% of the project duration

] No more than 13 weeks (long lead projects)

] One or up to 1% of level-of-effort activities

What is the maximum duration?

] No definitive answer!

] But not more than 400 activities, otherwise difficult to manage

And how many activities on a coordination schedule?

activities vs. planned activities #748

Coordination Planning & Schedulingq Identifying the project activities Ú analytical approach

What is a deliverable??a.k.a. result

] ≠ activity!

noun + verb at past participle tense]

Some examples:bzh-kite designedbzh-kite specifiedbzh-kite prototype testedbzh-kite manuf. facility commissioned

] ≠ product!e.g. the brz-kite

Deliverable is a term used [...] to describe a tangible or intangible object produced as a result of the project that is intended to be delivered to a customer (either internal or external).A deliverable could be a report, a document [...] or any other building block of an overall project. en.Wikipedia.org

] ≠ milestone!

Managing Projects with --- Part 3 Pierre Bonnal

Page 10: Managing Projects with - About | openSE

DOCUMENT NO.

16004VERSION

1.5PAGE

10

Coordination Planning & Schedulingq Identifying the project activities Ú analytical approach

Deriving the Work Breakdown Structure (WBS) from the PBS1=@

PBSBoM

WBS top nodes

Project management andsystem-level design activities

Development activities associated with sub-systemsand product components

A slightly refurbished PBS

System-level integration, validation, refinement and ramp-up activities

Genericactivities

WB

S t

op n

odes

Coordination Planning & Schedulingq Identifying the project activities Ú analytical approach

Generating the list of activities from the WBS-matrix1=#

For each cell of this matrix,count how many activitiesare required to managethe project efficiently

1 One activityshall be planned

nA few activitiesshall be planned (cf. activity def.)

Sum < 400 act.

Managing Projects with --- Part 3 Pierre Bonnal

Page 11: Managing Projects with - About | openSE

DOCUMENT NO.

16004VERSION

1.5PAGE

11

Man

age

the

proj

ect

Prep

are

PM d

ocum

ents

Perf

orm

bas

ic d

esig

nCF

T an

d aw

ard

cont

ract

Prep

are

spec

ifica

tion

Perf

orm

det

ail d

esig

nSu

pply

equ

ipm

ent

Neg

otia

te a

gree

men

t

Prep

are

cons

truc

tion

Do

eart

hwor

ksPo

ur c

oncr

ete

Do

2nda

ry w

orks

Do

last

fini

shin

gs

Cont

rol,

surv

eyTr

ansf

er to

ow

ner

Coordination Planning & Schedulingq Identifying the project activities Ú analytical approach

Generating the list of activities from the WBS-matrix1=#Generic activities suited to a construction projectì

Man

age

the

proj

ect

Prep

are

PM d

ocum

ents

Perf

orm

mar

ketin

g/sa

les

activ

ities

Perf

orm

det

ail d

esig

n

Perf

orm

sys

tem

-leve

l des

ign

Perf

orm

IP /

pate

nt re

late

d ac

tiviti

esPr

epar

e pr

ocur

emen

t spe

cs /

orde

r

CFT

and

awar

d co

ntra

cts

/ pla

ce o

rder

Des

ign

and

set t

he s

uppl

y ch

ain

Prep

are

mak

ing

Mak

e, a

ssem

ble…

Verif

y, v

alid

ate…

Cons

truc

t, in

stal

l…

Refu

rbis

h…Co

mm

issi

on, r

amp-

up…

Coordination Planning & Schedulingq Identifying the project activities Ú analytical approach

Generating the list of activities from the WBS-matrix1=#Generic activities suited to a NPD projectì

Managing Projects with --- Part 3 Pierre Bonnal

Page 12: Managing Projects with - About | openSE

DOCUMENT NO.

16004VERSION

1.5PAGE

12

Genericactivities

WB

S t

op n

odes

LoA

Coordination Planning & Schedulingq Identifying the project activities Ú analytical approach

Generating the list of activities from the WBS-matrix1=#

1 2 11

11 1

1 3 11 1

1 1 111 1

2 1 11 4 11

1 21 1 3

2 1 1

The list ofActivities

(~Work Units)level n

> Work packages = level 1 of the Work Breakdown Structure

> Activities = the leaves ( ) of the WBS (from level 2 to level 6 max.)

> There is no requirement to have all activities at a same level!

Coordination Planning & Schedulingq Identifying the project activities Ú analytical approach

the Project

the WorkPackages

Sub-WP'sor CWP's

(Contractor WP)

level 0

level 1

WBS

Managing Projects with --- Part 3 Pierre Bonnal

Page 13: Managing Projects with - About | openSE

DOCUMENT NO.

16004VERSION

1.5PAGE

13

Coordination Planning & Schedulingq Identifying the project activities Ú analytical approach

WorkBreakdownStructure

ProductBreakdownStructure

PBS RBSWBSGenericActivities

ResourceBreakdownStructure

BoM

Bill ofMaterials

List ofActivities

Project Breakdown Structure

OrganisationalBreakdownStructure

OBS

to be movedto facility, itemand/or assetmanagementsystems afterthe project iscompleted

CBS

CostBreakdownStructure

w Identifying the resources available, estimating the resources requiredCoordination Planning & Scheduling

2=! Identifying the resources that are available

The Resource Breakdown Structure (RBS)

2=@ Estimating the resources that are required

See section dedicated to Project Costing

2=# Assigning resources to activities

The RACI Matrix

2 types of resources

Renewableresources

Non-renewableresources

Managing Projects with --- Part 3 Pierre Bonnal

Page 14: Managing Projects with - About | openSE

DOCUMENT NO.

16004VERSION

1.5PAGE

14

w Identifying the resources available, estimating the resources requiredCoordination Planning & Scheduling

2=# Assigning resources to activities Ú RACI Matrix

RBS

List

of

acti

viti

es

RIs required

XExecutes

FFollows up

IIs informed

HProvide help

for each cell of the matrix, resourceimplication is elicited

w Identifying the resources available, estimating the resources requiredCoordination Planning & Scheduling

2=# Assigning resources to activities Ú RACI Matrix

RIs required

XExecutes

FFollows up

IIs informed

HProvide help

XIs responsible

F

X

F

X

F

Participateto decisions

X

F

I

H

X

F

I

H

X_

F_

I-

H_

Only one per row

Managing Projects with --- Part 3 Pierre Bonnal

Page 15: Managing Projects with - About | openSE

DOCUMENT NO.

16004VERSION

1.5PAGE

15

w Identifying the resources available, estimating the resources requiredCoordination Planning & Scheduling

2=# Assigning resources to activities Ú RACI Matrix

XIX

F XI I

II

RFFF

XX

I I

II I RFFF

XX

XI

XF

XXXXH

HII H

RBS

List

of

acti

viti

es

The purpose of this RACImatrix is twofold:

1. identifying the required resources (‘X’,‘R’ and sometimes ‘F’ and ‘H’)

2. organizing information circulation (mailing lists)

MicrosoftExcel spreadsheet

®

®

3=! Estimating the duration of the activities

Defining technical constraints between activities3=@

If required, defining resource constraints3=^

If required, defining temporal constraints3=$

Coordination Planning & Schedulinge Scheduling the activities

If required, getting rid of loops3=#DSM (Design Structure Matrix)

Calculating earliest/latest start/finish dates, floats + critical path(s)3=%PDM (Precedence Diagramming Method) + Gantt Chart

RCPS (Resource-Constrained Project Scheduling) + Gantt Chart

Calculating (earliest) start/finish dates and floats3=&

Managing Projects with --- Part 3 Pierre Bonnal

Page 16: Managing Projects with - About | openSE

DOCUMENT NO.

16004VERSION

1.5PAGE

16

Project Costing

Project CostingA three-step process

q Estimating the resources required to perform the project

w Budgeting the resources allocated to the project

The (project) Cost Estimate

The (project) Budget Document

FINALIZECOMMISSIONBUILDDESIGNSTUDYINITIALIZE

Initiators

Project CostingWhen and which effort?

Preliminary Cost Estimate (study + project) preparation

Budget Document (re)validation

Project Board

Cost Estimate (project) refinement/update

Study Team

Cost Estimate + Budget Document updatesProject Team

Initial Budget Document (study + project) preparation

Budget Document (project) refinement/update

Managing Projects with --- Part 3 Pierre Bonnal

Page 17: Managing Projects with - About | openSE

DOCUMENT NO.

16004VERSION

1.5PAGE

17

Project Costing

4 families of cost estimating approaches

Globalapproaches

Modularapproaches

Detailedapproaches

q Estimating the resources required to perform the project

the project is analysed as a whole estimates donefor each activity

top-downanalogical

parametric(Cost Estimation

Relationship)

bottom-upanalytical

Intuitiveapproaches

rules-of-thumb

Project Costingq Estimating the resources required to perform the project

DECOMMISSIONOPERATE & MAINTAIN

FINALIZE

COMMISSIONBUILDDESIGNSTUDYINITIALIZE

t

incomes

expenses

Which costs (and incomes) to take into account??

projectfront-end

costs

operations andmaintenance

costs

dism.costs

development costs

Managing Projects with --- Part 3 Pierre Bonnal

Page 18: Managing Projects with - About | openSE

DOCUMENT NO.

16004VERSION

1.5PAGE

18

Project Costingq Estimating the resources required to perform the project

Which costs to take into account??

Services

Renewable resources

RESOURCES

Tooling

Vehicles

Space

Equipment*

EquipmentParticipantsInternal

External*

External*

Goods In-kindboth

Equipment

Financial

Non-renewable resources

Goods

Services

both

UtilitiesWater

Sewage

Energycontractsagreements

workload currency(person∙week, person∙month, etc.)

monetary currency(CHF, EUR, GBP, USD, JPY, etc.)

Project Costingq Estimating the resources required to perform the project

Which costs (and incomes) to take into account??

Only chargeable costs shall be considered !]

Cash flows that are distorded (i.e. suppressed or modified)]

Cash flows that are generated by the project]

Past or irrecoverable costs: no!]

Renunciation costs: yes!]

Unquantifiable costs: no!]

Cash flowsof the project =

Cash flowsof the organisation

with the project−

Cash flowsof the organisationwithout the project

These costs will existwhatever the decision

E.g. the consequence of stoppinga project that is already on-going

Benefits sometimesreplace incomes

Managing Projects with --- Part 3 Pierre Bonnal

Page 19: Managing Projects with - About | openSE

DOCUMENT NO.

16004VERSION

1.5PAGE

19

Project Costing

Global approaches

q Estimating the resources required to perform the project

1=! Estimating with global approaches

Linearregressions

Chiltonlaw

Freimanprinciple

Distanceweighing

and from tables

Project Costingq Estimating the resources required to perform the project

Dealing with price escalation?

weighing coefficients so that:

where

appropriate economical indices

Managing Projects with --- Part 3 Pierre Bonnal

Page 20: Managing Projects with - About | openSE

DOCUMENT NO.

16004VERSION

1.5PAGE

20

Project Costingq Estimating the resources required to perform the project

1=@ Estimating with modular approaches

Project cost as a function of several sizing parameters:

Software:

TruePlanning® [PRICE System] (www.pricesystems.com)>

where are the sizing parameters

Cost+ [3f] (www.3f-fr.com)>COCOMO for IT projects (csse.usc.edu)>

Handbook:

ISPA (International Society of Parametric Analysts)Parametric Estimating Handbook (www.ispa-cost.org)

Project Costingq Estimating the resources required to perform the project

DECOMMISSIONOPERATE & MAINTAIN

FINALIZE

COMMISSIONBUILDDESIGNSTUDYINITIALIZE

t

incomes

expenses

1=# Estimating with detailed approaches

projectfront-end

costs

operations andmaintenance

costs

dism.costs

development costs

PBS WBS

does not exist that muchin scientific facilities!

does not exist that muchin scientific facilities!

past andirrecoverable

costs

past andirrecoverable

costs

Managing Projects with --- Part 3 Pierre Bonnal

Page 21: Managing Projects with - About | openSE

DOCUMENT NO.

16004VERSION

1.5PAGE

21

Project Costingq Estimating the resources required to perform the project

DECOMMISSIONOPERATE & MAINTAIN

FINALIZE

COMMISSIONBUILDDESIGNSTUDYINITIALIZE

Which accuracy can be obtained??

FeasibilityStudy

OpportunityStudy

BasicDesign

DetailedDesign

Global Modular Detailed

±30% ±20% ±10% ±5%

ConceptualStudy

OpportunityStudy

SystemDesign

DetailedDesign

Global Detailed

±30% ±20% ±10% ±5%

Detailed

Process industry projects

New product development projects

imprecision ≠ uncertainty!

deterministicnature

probabilisticnature

Project Costingq Estimating the resources required to perform the project

DECOMMISSIONOPERATE & MAINTAIN

FINALIZE

COMMISSIONBUILDDESIGNSTUDYINITIALIZE

How to deal with interest rates and future price escalation??

cost of money ≠ price escalation!

interest rates(financial concept)

inflation(economical concept)

All CF’s shall be set as if they were paid now!]

t2019now

In Cost Estimate and Budget, all figures in CHFnow

E.g. a payment to occur in 2019

Managing Projects with --- Part 3 Pierre Bonnal

Page 22: Managing Projects with - About | openSE

DOCUMENT NO.

16004VERSION

1.5PAGE

22

± kCHF

± p·yr

Cost EstimateEditorial Process

Verification:> Some other Key Study (or Project) Participants+ some experts in the fields

> Authoring: Study (or Project) Manager+ a few Key Study (or Project) Participants

Validation:> Study (or Project) Manager

Typical Content

The figuresand theiraccuracy

The approach used (global, modular, detailed)The assumptions (incl. sourcing of economicalrates and indices)

A comprehensive

cost breakdown

is appreciated!

Project Costingw Budgeting the resources allocated to the project

BudgetDocument

CostEstimate

± kCHF

± p·yr

whichbecomes

kCHF

p·yr

#748

TAB orTotalAllocatedBudget

– +Logically:

MicrosoftExcel spreadsheet

®

®

Managing Projects with --- Part 3 Pierre Bonnal

Page 23: Managing Projects with - About | openSE

DOCUMENT NO.

16004VERSION

1.5PAGE

23

Project Costingw Budgeting the resources allocated to the project

BudgetDocument

kCHFp·yr

#748

TAB orTotalAllocatedBudget

BAC orBudget atCompletion

PMR orProjectManagementReserve

WBSCBS Cost

BreakdownStructure

or

Budget DocumentEditorial Process

> Verification:

at CostCenterlevel

at WorkPackagelevel

Project Board

Project Manager

> Validation:

Some other Key Study (or Project) participants+ some experts in the field

> Authoring: Study (or Project) Manager+ a few Key Study (or Project) Participants

Study Manager

Managing Projects with --- Part 3 Pierre Bonnal


Recommended