Manhattan Bond Project Monthly Project Report November 2017 | Karen Hedglin
Transcript
Page 1: Manhattan Bond Project Monthly Project Report...Kalwall at end of gym. Schedule & Budget Insert Caption Here Construction is on schedule at the new building. The new water main installation

Manhattan Bond Project Monthly Project ReportNovember 2017 | Karen Hedglin

Page 2: Manhattan Bond Project Monthly Project Report...Kalwall at end of gym. Schedule & Budget Insert Caption Here Construction is on schedule at the new building. The new water main installation

Report Overview

Community

Students & Parents

Teachers & Staff

Communication

Drawings & Photos Schedule

Budget

BUILDING

Page 3: Manhattan Bond Project Monthly Project Report...Kalwall at end of gym. Schedule & Budget Insert Caption Here Construction is on schedule at the new building. The new water main installation

Construction Progress Photos

New entrance steel

Page 4: Manhattan Bond Project Monthly Project Report...Kalwall at end of gym. Schedule & Budget Insert Caption Here Construction is on schedule at the new building. The new water main installation

Walking track above stage

Page 5: Manhattan Bond Project Monthly Project Report...Kalwall at end of gym. Schedule & Budget Insert Caption Here Construction is on schedule at the new building. The new water main installation

Bleacher mezzanine w/mechanical equipment slab in foreground

Page 6: Manhattan Bond Project Monthly Project Report...Kalwall at end of gym. Schedule & Budget Insert Caption Here Construction is on schedule at the new building. The new water main installation

Kalwall at end of gym

Page 7: Manhattan Bond Project Monthly Project Report...Kalwall at end of gym. Schedule & Budget Insert Caption Here Construction is on schedule at the new building. The new water main installation

Schedule & Budget

Insert Caption Here

Construction is on schedule at the new building. The new water main installation will be complete this week. Detailed planning for next summer’s work is continuing. Furniture meetings are complete.

Owner’s Contingency Balance Last Month $227,016 Remote push button at HS library $ 1,138Elementary room signage $ 6,14522 ga. Ultra Batten panel $ 591Kitchen add electrical unit heat $ 11,908Door hardware changes $ 2,683Warming kitchen ceiling modifications $ 903Elementary painting at corridors $ 9,899Stage speaker modifications $ 7,719Middle school mechanical modifications $ 9,497Hydroseed at elementary $ 1,818Balance $174,715

Page 8: Manhattan Bond Project Monthly Project Report...Kalwall at end of gym. Schedule & Budget Insert Caption Here Construction is on schedule at the new building. The new water main installation

Communication

We are considering offering another tour at the holidays, if the community desires.

Teacher tour on Tues 3:00pm and 3:30pm.