+ All Categories
Home > Documents > manufacture of cumene

manufacture of cumene

Date post: 03-Apr-2018
Category:
Upload: g-vamsee-krishna
View: 235 times
Download: 0 times
Share this document with a friend

of 46

Transcript
  • 7/28/2019 manufacture of cumene

    1/46

    MATERIAL BALANCE

    Overall Material Balance:

    Basis: Per hour of operation

    Amount of cumene to be obtained =500,000 ton of cumene per annum.

    =500000/330 tons per day of cumene.(Assuming that

    the plant is operational for only 330 days per year)=500000/(330 x 24) tons of cumene per hr.

    = 63.13 x 1000kg of cumene per hr.

    =(63.13 x 1000)/120.19 kmoles of cumene per hr.

    = 525.25 Kgmole/hrAssuming 98% conversion and 2% loss.

    Cumene required = 525.25 / .98 =535.969 Kgmoles/hr= 64316.28 Kg/hr

    Hence 64316.28 kg of cumene is required to be produced per hr.

    Stoichiometry equation:Primary reaction:

    C3H6 + C6H6 C6H5-C3H7

    Propylene benzene cumene

    Side reaction:

    C3H6 + C6H5-C3H7 C3H7-C6H4-C3H7

    Propylene cumene Diisopropyl benzene (DIPB)

    For primary reaction1 Kmole of benzene = 1kmole of propylene = 1kmole of cumene

    For side reaction

    1 Kmole of benzene =2kmole of propylene = 1kmole of cumene

    Propylene required =535.969 /.97 = 552.545Kgmole/hr

    = 552.545 x 42 Kg/hr of propylene

    = 23206.89 Kg/hr of propylene

    Assuming benzene required is 25% extra

    = 552.545 x 1.25 Kmoles of benzene= 690.68125Kgmole/hr

    = 53873.1375 Kg/hr

    Propane acts as an inert in the whole process. It is used for quenching purpose in the reactor.

    It does not take part in the chemical reaction. Also it is inevitably associated with thepropylene as an impurity as their molecular weight is very close.

    We assume propylene to propane ratio as 3:1.

    Being an inert we are neglecting propane balance in the material balance to avoidcomplexity.

  • 7/28/2019 manufacture of cumene

    2/46

    1.) Material balance around reactor:

    Reactants:

    Propylene = 23206.89 Kg/hr

    Benzene = 53873.1375 Kg/hrProducts:

    Cumene = 64316.28 Kg/hrPropylene = 552.545-535.969 =16.575 Kmoles/hr is reacted to give DIPB

    Benzene required to give DIPB = 16.575/2 kmoles/hr= 8.2875kmoles/hr

    DIPB produced = 8.2875 x 162 = 1342.575 Kg/hrBenzene in product = 690.68125535.969 -8.2875 = 146.42475 kmoles/hr

    = 11421.1305 kg/hr

    Input = 23206.89 + 53873.1375 = 77080.0275 Kg/hr

    Output = 64316.28 + 1342.575 + 11421.1305 = 77080.0275 Kg/hr

    Input = output

    2.)Separator: ( Depropanasing column )

    Assuming almost all the propane is removed in depropanising column and sent to reactor forquenching. Hence material balance for depropanasing column is not considered.

    3)Distilation column 1: (Benzene column)Feed

    F = Benzene + cumene + DIPB = 77080.0275 Kg/hr

    XF = 11421.1305 /77080.0275 = 0.148

    F = D + W77080.0275 = D +W

    F XF

    = DXD

    +WXw

    Taking XD = 0.9999XW = 0.05

    77080.0275 x 0.148 = D x 0.9999 +W x 0.05

    11421.1305 = .9999 D + (77181.8655D) x 0.05

    D = 7952.25044 Kg/hr= Benzene

    W = 77080.02757952.25044 = 69127.77706 Kg/hr= cumene + DIPB

    Input = 77080.0275 kg/hr

    Output =7952.25044 + 69127.77706 = 77080.0275 kg/hr

    Input = OutputAssuming all the Benzene present in benzene column is recycled to the feed. Hence

    considering negligible amount of benzene to be part of residue.This will avoid the

    complexity of multicomponent distillation in Cumene column.Therefore amount of benzene recycled = 7952.25044 Kg/hr.

    Therefore feed actually given to the system = 77080.0275 + 7952.25044

    = 85032.27794Kg/hr

    4.)Distilation column 2: (Cumene column)

    F = Cumene + DIPB = 69127.77706 Kg/hr

    XF = 64418.16 /69127.77706 = 0.932F = D +W

  • 7/28/2019 manufacture of cumene

    3/46

    69127.77706 = D +WFXF = DXD + WXW

    Taking XD = 0.995

    XW = 0.01

    69127.77706 x 0.932= D x 0 .995 + W x 0.01

    64427.08822 = 0.995D + (69127.77706D) 0.01D = 64706.40655 kg/hr

    W = 69127.7770664706.40655 =4421.37051 Kg/hrInput = 69127.77706 Kg/hr

    Output = 64706.40655 + 4421.37051 = 69127.77706 Kg/hr.

    Input = output

    ENERGY BALANCE

    Basis: Per hour of operation

    The gases viz. Propylene, propane, benzene enter at 25C and benzene recycle enters at80C.To calculate the temperature of the mixture of gases after compression to 25 atm:

    Cp values (J/mole K) at avg temperature of 53CPropylene 64.18

    Propane 3.89

    Benzene 82.22

    Propylene in feed = 552.545 kmoles/hr.

    Benzene in feed = Benzene fed + recycled Benzene = 690.68125 + 101.952

    = 792.63325 kmoles/hr.Assuming that propylene is accompanied with propane as impurity in the ratio of 3:1.

    Therefore propane in feed = 184.18 kmoles/hr.

    Hence, XA =0.3612 , XB = 0.5184 , XC = 0.1204

    Cpavg =XACpA+ XBCpB+ XcCpcCpavg = 0.3612x 64.18 + 0.5184 x 82.22 + 0.1204 x 73.89 = 71.38 J/mole K

    Temperature of the stream after mixing:

    Cp value J/kmole k at 30oC

    Propylene 64.52

    Propane 70.17

    Benzene 98.20(552.545 x 64.52 + 690.68125 x 98.20 + 184.18 x 70.17) x 10

    3x (T-25) = 101.952x 86.22 x

    103x (80-T)

    or, 80T = 13.18 ( T-25 )or, 14.18 T = 409.5

    or, T = 29oC

    P1 =1 atm, T1= 29oC

    P2 = 25 atm, To find T2

  • 7/28/2019 manufacture of cumene

    4/46

    Considering isentropic process, we have

    T2 = T1 (P2 /P1 )( R / Cpavg )

    = 29( 25 /1 )( 8.314 / 71.38)

    = 42.19 C

    As Cpavg at 42.19 C Cpavg at 53 C =71.38 J/ mole K

    Assuming that the exit stream from pre-heater leaves at 100 C

    For the products from the reactor,

    m = cumene+DIPB+Benzene+propane

    =535.969 +8.2875+146.42475+184.18= 874.86125 kmoles/hr

    To find Cpavg at ( 250+100) /2 =175C ,Cp J /mole K

    Propane 107.76Cumene 205.24

    Di-isopropyl Benzene 302.97Propylene 97.60

    Benzene 121.19

    Cpavg = 0.6126 x 205.24 + 0.0095 x 302.97 + 0.1673 x121.19+ 0.2105x107.76

    = 168.22 J/mole K

    For the reactants leaving the pre-heater :M = propylene+benzene+propane

    = 552.545 +792.63325 +184.18= 1529.35825 k moles/hrHeat balance around the pre-heater:874.86125 x 168.22 (250-100)x10

    3= 1529.35825 x 71.38 x (T42.19)x10

    3

    T 200 C

    The reactants have to be further heated to the reaction temperature of 250 C before beingfed to the reactor.

    To find saturated steam required:

    Cpavg of reactants has to be determined at (200 + 250 )/2=225 C

    Cp value at average temperature of 2250C , J/kmole K

    Propane 117.76

    Propylene 97.60

    Benzene 141.19

    Cpavg = 0.3612 x 97.60 + 0.5184 x 141.19 + 0.1204 x 117.7= 122.62 J/mole K

    mCpavg(250-100) =msteam1529.35825 x 122.62x10

    3x 150 = msteamx 2676

    msteam = 10.511 x 106kg /hr

  • 7/28/2019 manufacture of cumene

    5/46

    Energy balance around the reactor:

    Enthalpy of reactants + heat evolved = Q + Enthalpy of products

    mCpdT reactants + heat evolved = Q + m CpdT productsHeat evolved = 23.7683 K cal / g mole =99.3964 KJ/g mole

    Moles of cumene produced = 535.969 k moles /hrHeat evolved =99.3964 x 535.969x 10

    3

    =53.273x106KJ/hr

    mCpdT reactants = 552.545 x 87.37x103(25025) +792.63325 x 93.97x103(250-25) +184.18x 97.34 x 10

    3x (250-25)

    = 3.1655 x 1010

    KJ/hr

    mCpdT products = 184.18 x103x (250 25) + 146.42475 x 93.97 x103(25025) +535.969 x 10

    3x 177.07(25025) +8.2875 x 10

    3x 267.19 x (25025)

    = 2.898 x 1010

    KJ/hr

    3.1655 x 1010+ 53.273 x 106= Q+ 2.898 x 1010Q =27.2827 x 10

    8KJ/hr

    To find propane requirement for quench :Latent heat of vaporisation of propane liquid at 25 atm

    (B .P =68.4C)=0.25104 KJ/gm =251.04 KJ/kg

    Heat removal by propane heat quench :Assuming that propane is removed completely in the depropanasing column and is sent

    for quenching .

    Propane i.e. recycled = 184.18 kmoles/hr= 184.18 x 44 kg/hr

    = 8103.92 kg/hr

    Cp of propane at T avg = (250 + 68.4) /2 = 159.2 C is 2.56 KJ/kgC

    Q = m + m Cp (25068.4)

    = 8103.92 x (251.04 + 2.56 x 181.6)= 5.802 x 10

    6KJ/hr

    Additional heat to be removed = 27.2827 x 1085.802 x 10

    6

    = 27.224 x 108KJ/hr

    = Ql

    Water is used for additional heat removal.

    To find flow rate of water :B.P. of water at 25 atm = 223.85C

    Latent heat of vaporisation = 2437 KJ/kg

    Assuming that water at 25 C is used for quenching

    Cp of water at T avg = (25+223.8)/2=124.43C is 3.7656 KJ/kg C

    Ql

    = m Cp (223.8525) + m27.224 x 10

    8=m (3.7656 x 198.85 +2437)

    m = 8.566 x 105kg/hr

  • 7/28/2019 manufacture of cumene

    6/46

    Separator:

    To find the temperature at which the product stream is fed to Separator

    At P1 = 25 atm, T1 = 200 CAt P2 =1 atm T2 = ?

    Cpavg at 100 C = 0.6126 x 163.42 +0.0095 x 243.76 + 0.1673 x 107.01 +0.2105 x 79.47=137.05 J/gm moleT2 = T1 (P2 /P1)

    R/Cpavg

    =100(1/25)8.314 / 137.05

    =82.26oC

    This is further cooled to 25 C and fed to the distillation column.

    F =874.86125 kmoles/hr

    D =184.18 kmoles/hr

    W =1059.04125 kmoles/hrEnthalpy of vapor that goes as overhead :

    Hv = Latent heat of vaporisation + sensible heat

    As propane is the major constituent that goes with the overhead, taking and Cp valuesof Propane,

    Hv =V [+ Cp (TbTo )]Assuming a reflux ratio of 0.5, we have R=L/D =0.5

    L =0.5 D =0.5 x 184.18 x 44 =4051.96 kg/hr

    V =L+D =4051.96 +8103.92 =12155.88 kg/hrTaking reference temperature as the temperature at which feed enters,

    To =25 C ; Tb= 42.1 C , Cp =2.41 KJ/kg C

    = 0.4251 KJ/gm =425.1 KJ/kgThereforeHv =12155.88 [425.1 + 2.41 ( 42.125 )]

    =5.66285 x 106

    KJ/hrHD =DCp(TbTo)

    =8103.92 x 2.41 ( 42.125 )

    =3.3365 x 105KJ/hr

    HL =L Cp (TbTo)

    =4051.96 x 2.41 (42.125)=1.668 x 10

    5KJ/hr

    Taking enthalpy balance around the condenser,

    Hv = Qc+HD+HL

    5.66285 x 106= Qc+3.3365 x 10

    5+1.668 x 10

    5

    Qc = 5.162 x 106KJ/hr

    Cooling water requirement :Let us assume inlet and exit water temperature as 25C and 45 CCp = 4.18 KJ/kg C

    Therefore Qc = msteamCpdT

    5.162 x 106

    = msteamx 4.18x 20M = 61.752 x 10

    3kg/hr

    Total enthalpy balance :

    HF + QB = HD + QC + HW

  • 7/28/2019 manufacture of cumene

    7/46

    To find HW :HW = WCpavg (TbTo )

    By using pi = XiPiand checking Pt= 760 mm Hg we found Tb = 137oC

    Cpavg = 0.776 x 176.32 + 0.01199 x 257.11 + 0.2120 x 110.73= 174 J/mole K= 174 kJ/kmole K

    Mavg = 111.72 kg/kmoleTherefore Cpavg = 174 / 111.72

    =1.5575 KJ/kg K

    Hw = 690.68125 x 1.5575(137-25) x 111.72= 13.463 x 10

    6KJ/hr

    HF = 0 [ because TF = T0 ]

    QB = HD + QC + HW - HF

    = 3.3365 x 105+ 5.162 x 10

    6+13.463 x 10

    6-0

    =18.958 x 10

    6

    KJ/hrSaturated steam required :

    QB = msteam18.958 x 10

    6= msteamx 2256.9

    Msteam = 8400.3 kg/hr

    Distillation Column1: (Benzene column)F = 77080.0275 kg/hr enters at 137 C

    D = 7952.25044 kg/hrW = 69127.77706 kg/hr

    Benzene vapor from the top is recycled. Assuming very small propane content to be a

    part of Benzene stream .Again assuming R = 0.5 = L/DHence,

    L = 0.5 x 7952.25044 =3976.125 kg/hr.

    V = L+D = 11928.375 kg/hr

    Enthalpy of vaporHv=V[+Cp(Tb-To)]Taking referenced temperature To = TF = 137 C

    B.P. of Benzene at 1 atm = 80.1 C = Tb

    of Benzene=94.14 cal/gm = 393.8818 KJ/gm =393.88 x 103 KJ/kgCp of Benzene vapor at 80.1 C = 22.83 cal/gm mole

    = 95.52 J/gm mole K

    = 1.2246 KJ/kg KHv = 11928.375 [ 393.8818 + 1.2246 ( 80.1137 )]

    = 3.867 x 106KJ/hr

    HD = 7952.25044 x 1.2246 (80.1137 )

    = -5.54110 x 105KJ/hr.

    HL = L Cp (TbT0 )

    = 3976.125 x 1.2246 (80.1137 )

    = -2.771 x 105KJ/hr

    Hv = QC + HL +HD

    3.867 x 106= QC2.771 x 10

    55.54110 x 10

    5

    QC = 4.698 x 10

    6

    KJ/hr

  • 7/28/2019 manufacture of cumene

    8/46

    Cooling water requirement :Let us assume inlet and exit water temperature as 25C and 45 C

    Cp =4.18 KJ/kg C

    Therefore Qc = msteamCpdT

    4.698 x 106

    = msteamx 4.18 x 20

    Msteam = 56.198 x 10

    4

    kg/hr

    Total enthalpy balance :HF + QB = HV + QC +Hw

    To find HW :W = 69127.77706 Kg/hr

    Tb = TF for distillation column3= 153.4 C

    Cpavg = Cp of Cumene= 1.91 KJ/kg C

    Hw = 69127.77706 x 1.91(153.4137) = 2.165 x 106KJ/hr

    HF = 0 [ because TF = T0 ]

    QB

    = 3.867 x 10

    6

    + 4.698 x 10

    6

    +2.165 x 10

    6

    -0

    = 10.73 x 106KJ/hr

    Saturated steam required :

    QB = msteam10.73 x 10

    6 = msteamx 2256.9

    msteam = 4.754 x 103kg/hr

    Distillation column2: (Cumene Column)F = 69127.77706 kg/hrD = 64706.40655 kg/hr

    W = 4421.37051 kg/hr

    Enthalpy of vapor that goes at the top:As Cumene is the major constituent that goes with the overhead, taking and Cp values ofCumene,

    Hv =V[+ Cp(Tb-To)]Taking reference temperature T0 =TF = 153.4 C

    B.P. of Cumene at 1 atm = 152.4 C

    ofCumene =74.6 cal/gm = 312.1264 KJ/kgCp of Cumenevapor at 152.4 C = 0.4047 cal/gm K

    = 1.6931 KJ/kg KV = D + L = 64706.40655 + 32353.203

    =97059.61 kg/hr

    Hv = 97059.61 [ 312.1264 + 1.6931 ( 152.4153.4)]= 30.130534 x 10

    6KJ/hr

    HD = D Cp (TbTo)= 64706.40655x 1.6931(152.4153.4)= -0.109554 x 10

    6KJ/hr

    HL = L Cp(TbT0 )

    = 32353.203x 1.6931(152.4153.4)= -0.054777 x 10

    6KJ/hr

  • 7/28/2019 manufacture of cumene

    9/46

    Hv = QC + HD +HL

    30.130534 x 106= QC -0.109554 x 10

    6-0.054777 x 10

    6

    QC = 30.29 x 106KJ/hr

    Cooling water requirement :

    Let us assume inlet and exit water temperature as 25C and 45 CCp =4.18 KJ/kg C

    Therefore Qc = msteamCpdT30.29 x 10

    6 = msteamx 4.18 x 20

    msteam = 362.32 x 103kg/hr

    Total enthalpy balance :

    HF + QB = HV + QC +Hw

    To find HW :W = 4421.37051 kg/hr

    Hw

    = W Cpavg (Tb

    T0

    )Tb at Xw= 0.2934 =184.5 CCpavg at 184.5 C = 0.013x 214.1952 + (10.013) x 288.93

    = 287.9584 J/mole K

    = 2.88795 KJ/kg K

    Hw = 4421.37051 x 2.8795(184.5153.4)= 39.59 x 10

    4KJ/hr

    HF = 0 [ because TF = T0 ]

    QB = HV + QC + HW - HF

    = 30.130534 x 106+ 30.29 x 10

    6+ 39.59 x 10

    4=60.8 x 10

    6KJ/hr

    Saturated steam required :

    QB = msteam60.8 x 10

    6 = msteamx 2256.9

    msteam = 26946.65249 kg/hr

  • 7/28/2019 manufacture of cumene

    10/46

    DESIGN OF EQUIPMENTS(A) MAJOR EQUIPMENTBasis: 1hour of operation

    Vapor-pressure data of cumene-Diispropylbenzene:

    1/T 10 2.35 2.3 2.25 2.2 2.15 2.10C

    PA 760 943 1211.9 1480.2 1998.1 2440.6

    PB 190.56 257.2 314.1 403.4 518.0 760

    LnPA 6.633 6.85 7.1 7.3 7.6 7.8

    LnPB 5.25 5.55 5.75 6.0 6.25 6.63

    T-xy data for cumeneDiispropylbenzene system :

    T C 152.4 160 170 180 190 202

    XA 1 0.733 0.496 0.331 0.163 0

    YA 1 0.909 0.791 0.644 0.429 0

    Vapour-pressure data from Perrys Chemical Engineers handbook 6th edition pg2-52

    Feed: F = 69127.77706 Kg/hr ; weight fraction ; mole fractions

    XF = 0.932 XF = 0.948

    D = 64706.40655 Kg/hr XD = 0.995 XD = 0.996

    = 539.2 Kmoles/hr

    W= 4421.37051Kg/hr XW = 0.01 XW= 0.013

    = 4569.5 Kg/hr= 28.2 Kmoles/hr

    Fmolar = (0.932 x 69127.77706 )/120 + (0.068 x 69127.77706)/162

    = 565.908 Kmols/hr

    MFeed = 69127.77706/565.908 = 122.15 Kg/kmol

    Taking feed as saturated liquid , q=1

    Slope of q-line = q/(q-1)= Therefore q-line is vertical.

    From the X-Y diagram , XD/(Rm+1) = 0.72

    Hence Rm =0.38

    Assuming a reflux ratio of 1.4 times the Rm value we get

    R = 1.4 x 0.38 = 0.532

    Now total number of stages including reboiler =10Therefore actual number of stages in the tower =9

    Number of stages in the enriching section =3

    Number of stages in the stripping section =6L = RD = 0.532 x 539.2 = 286.85 Kmoles/hr

    G = (R+1)D = 1.532 x 539.2 = 826.054 Kmoles/hr

    L = L+qF = 286.85 + 1x546.79 = 832.39 Kmoles/hrG = G+(q-1)F = 822.47+0 = 822.47 Kmoles/hr

  • 7/28/2019 manufacture of cumene

    11/46

    Plate Hydraulics:

    Enriching Section Stripping Section

    Top Bottom Top Bottom

    Liquid 285.6 285.6 832.39 832.39

    Kgmoles/hr

    Vapor 822.47 822.47 822.47 822.47Kgmoles/hr

    X 0.996 0.948 0.948 0.013

    Y 0.996 0.97 0.97 0.013

    Mavg(Liq) 120.34 122.36 122.36 161.45

    Mavg(Gas) 120.34 121.44 121.44 161.45

    Liq, Kg/hr 34369.1 34946 101851.2 134389.36

    Vap,Kg/hr 98976 99880.75 99880.75 132787.78

    Tliquid ,oC 152 153 153 202

    Tvapour ,oC 154 155 155 202

    L , (kg/m3) 746.3 745 745 600

    G ,(kg/m3) 3.436 3.826 3.826 4.072(L/G)* 0.0235 0.0250 0.0730 0.0830

    (G/L)0.5

    Enriching Section:Plate Calculations:

    1. Plate spacing ts = 500mm

    2. Hole diameter dh =5mm3. Hole pitch Lp = 3dh = 15mm

    4. Tray thickness tT = 0.6dh = 3mm

    5. Total hole area/Perforated area = ( Ah / Ap)= 0.1 for triangular pitch

    6. Plate diameter

    From above table , L /G (g/ L)0.5

    = 0.025From Perrys handbook 6th edition for ts = 18 inches

    Csb flood = 0.28

    We have,Unf = Csb(flooding) ( /20)

    0.2((L - G)/ G)

    0.5

    = 0.28(37.3/20)0.2

    ((745-3.826) / 3.826)0.

    5

    = 4.41ft/sec

    Let us take Un = 0.8 Unf( % flooding = 80%)

    = 0.8 * 4.41ft/sec= 1.158 m/sec

    Volume rate of vapour = 99880.75/(3600*3.826)= 7.2516 m

    3/sec

    Net area for gas flow, An = volumetric flow rate of vapor/Un

    = 7.2516/1.1586

    = 6.2589 m2

    Let Lw/Dc = 0.75

    Lw = Weir Length

    Dc = Column Diameter

  • 7/28/2019 manufacture of cumene

    12/46

    Area of column (Ac) = (/4) Dc2

    = 0.785 Dc2

    Sin(C/2) = (LW/2)/(DC/2) = 0.75

    c = 97.2o

    Area of down comer (Ad) = [ (/4) Dc2(C/360)

    (Lw/2)(Dc/2)(cos (C/2))]

    = (0.2120.1239) Dc2

    = 0.0879 Dc

    2

    Area for gas flow , An = Ac-Ad

    = 0.785 Dc20.0879 Dc

    2

    = 0.6971Dc2

    6.2589 = 0.6911Dc2

    Dc =2.996m

    Ac = /4 Dc2

    = 0.785 x 2.9962

    = 7.046m2

    Ad = 0.7889m2

    Active area, Aa =Ac2Ad= 7.0462(0.7889) = 5.468 m

    2

    7. Perforated area Ap:

    Lw/Dc = 0.75where Lw is the wier length

    Lw = 0.75*2.996 = 2.247m

    c = 97.2

    =180 - c = 180 97.2 = 82.8

    Periphery waste = 50mm = 50*10-3

    Area of the calming zone Acz = 2[ Lw *50*10-3

    ]

    = 2[ 2.247*50*10-3

    ]= 0.2247m

    2

    Area of the periphery waste ,

    Awz = 2[/4*2.992(82.8/360)- /4[2.99-0.05]2*(82.82/360)]

    = 2[1.61491.5606]= 0.1085m

    2

    Ap =Ac2AdAcz- Awz

    = 7.0462* 0.78890.22470.1085

    = 5.135 m

    2

    8. Hole area Ah:

    We have , Ah/Ap = 0.1

    Ah = 0.1* Ap= 0.1*5.135

    = 0.5135m2

    9. Number of holes :

    Nh = 0.5135 / /4(5*10-3

    )2

    = 26,165

  • 7/28/2019 manufacture of cumene

    13/46

    10. Weir height Hw:let us take hw = 50mm

    11. Check for weeping:

    From Perrys handbook 6th edition pg-18-9 equation 18-6

    Pressure across the disperser,Hd = K1 +K2g/l Uh2

    mm liquid

    For sieve plate K1 = 0K2 = 50.8 / Cv

    2

    Hole area/ Active area = Ah/Aa = 0.5135/5.4682 =0.0939

    Tray thickness/Hole dia = tT/dh = 3mm/5mm =0.6From figure 18-14 Cv(Discharge coefficient) = 0.73

    K2 = 50.8/ (0.73)2

    = 95.32

    Uh = linear velocity of gas through the holes

    = volumetric flow rate of vapour / Ah= 7.2516 / 0.5135

    = 14.12 m/sec

    Hd = 0 + 95.32(3.826/745) x14.122= 97.38 mm liquid

    Height of liquid creast over weir

    how = (664) Fw(q / Lw)2/3

    q = vol. flow rate of liquid ,m3/sec [weeping check is done at the point where gas

    velocity is low]

    = 34369/(746.3x3600)

    =0.0127 m3/sec

    q = volumetric flow rate of liquid in GPM

    =0.0127 /(6.309x10-5

    )

    =202.76 GPMLw = 2.247m = 2.247/0.3048 =7.372 ft

    q/(Lw)2.5

    =202.76/(7.372)2.5=1.37

    Lw/Dc =2.247/2.996=0.75Corresponding to this two values Fw=1.02

    How = 1.02x664x(0.0127/2.247)2/3

    = 21.48 mm liquidHead loss due to bubble formation,

    H = 409(/LdL)

    = 409(37.3/ 746.3x 5)

    = 4.08mm liqhd+h = 97.38+4.08= 101.47 mm liq

    hw + how = 50 +21.48 = 71.48 mm

    Ah/Aa = 0.0939, hw+how = 71.48 mmFrom fig 18-11, hd+h =17mm

    Since the value hd+h is well above the value obtained from graph no weeping will occur.

    12. Check for downcommer flooding:

    The downcommer backup is given by,

    hdl =ht+hw+how+had+hhg

  • 7/28/2019 manufacture of cumene

    14/46

    a.Hydraulic gradient across plate , hhgFor stable operation hd > 2.5hhg

    For sieve plates hhg is generally small or neiglible

    Let us take hhg =0 mmliq

    b. Total pressure drop across the plate ht:ht = hd + hl

    hl =pressure drop through the aereated liquid = hds

    where =aeration factor to be found from Perrys fig 18-15

    Fga =Ua(g)1/2

    Ua = 99880/(3600x3.826x5.468)= 1.326m/sec

    g = 3.826kg/m

    3

    Fga = Ua(g)1/2

    = 1.326 x (3.826)1/2

    (m/sec) (kg/m3)1/2

    = 2.5939/1.2199 (ft/sec)(lb/ft

    3)1/2

    = 2.1263 (ft/sec)(lb/ft3)1/2

    From figure, =0.6

    Hds =hw+how+hhg/2

    = 50+21.48 + 0= 71.48mm liq

    hl = 0.6 * 71.48 = 42.88mm liq

    ht = 97.38 +42.88= 140.27mm liq

    c loss under downcommer area head:

    had = 165.2(q/Ada)2

    let us choose c = 1 inch =25.4mmhap = hdsc

    = 71.4825.4

    = 46.08 mmliq

    Ada = Lw xhap=2.247 x46.08x10

    -3

    =0.1035m2

    Had =165.2(0.0127/0.1035)2

    =2.4873mm

    Hdc = 140.27 + 50+21.48 +2.4873+0

    = 214.23mmtaking dc = .5

    hdc = hdc/dc=214.23/0.5= 428.46 mm

  • 7/28/2019 manufacture of cumene

    15/46

    we have ts = 500 mmhence ,hdc < ts

    therefore no downcommer flooding will occur.

    Stripping Section:

    Plate Calculations:5. Plate spacing ts = 500mm

    6. Hole diameter dh =5mm

    7. Hole pitch Lp = 3dh = 15mm8. Tray thickness tT = 0.6dh = 3mm

    5. Total hole area/ Perforated area = ( Ah / Ap)

    = 0.1 for triangular pitch

    6. Plate diameter

    From above table , L /G (g/ L)0.5

    = 0.083 (maximum at bottom)

    From Perrys handbook 6th edition for ts = 18 inches

    Csb flood = 0.28We have,Unf = Csb(flooding) ( /20)

    0.2((L - G)/ G)

    0.5

    = 0.28(33.41/20)0.2

    ((600-4.072) / 4.072)0.5

    = 3.75ft/secLet us take Un = 0.8 Unf ( % flooding = 80%)

    = 0.8 * 3.75ft/sec

    = 0.9144 m/secVolume rate of vapour = 132787.78/(3600*4.072)

    = 9.058 m3/sec

    Net area for gas flow, An = volumetric flow rate of vapor/Un

    = 9.058/0.9144= 9.906 m2

    Let Lw/Dc = 0.75

    Lw = Weir Length

    Dc = Column Diameter

    Area of column (Ac ) =(/4) Dc2=0.785Dc

    2

    Sin(C/2) = (LW/2)/(DC/2) = 0.75c = 97.2

    o

    Area of down comer (Ad) =[ (/4) Dc2(C/360)

    (Lw/2)(Dc/2)(cos (C/2))]

    = (0.2120.1239) Dc2

    = 0.0879 Dc2

    Area for gas flow , An = Ac-Ad

    = 0.785 Dc20.0879 Dc

    2

    = 0.6971Dc2

    9.906 = 0.6971Dc2

    Dc =3.769m

    Ac = /4 DC2

    = 0.785 x 3.7692

    = 11.15m2

    Ad = 0.7889m2

    Active area, Aa =Ac2Ad= 11.152(1.248) = 8.654m

    2

  • 7/28/2019 manufacture of cumene

    16/46

    7. Perforated area Ap:Lw/Dc = 0.75

    where Lw is the wier length

    Lw = 0.75*3.769 = 2.827m

    c = 97.2

    =180 - c = 18097.2 = 82.8Periphery waste = 50mm = 50*10-3

    Area of the calming zone Acz = 2[ Lw *50*10-3

    ]= 2[ 2.827*50*10

    -3]= 0.2287m

    2

    Area of the periphery waste ,

    Awz = 2[/4*(3.769)2(82.8/360)- /4[3.769-0.05]

    2*(82.82/360)]

    = 0.1352m2

    Ap =Ac2AdAcz- Awz

    = 11.152* 1.2480.22870.1352

    = 8.2901 m2

    8. Hole area Ah:

    We have , Ah/Ap = 0.1Ah = 0.1* Ap= 0.1*8.2901= 0.829m

    2

    9. Number of holes :

    Nh = 0.829 / /4(5*10-3

    )2

    = 42,242

    10. Weir height Hw:

    let us take hw = 50mm

    11. Check for weeping:

    From Perrys handbook 6th edition pg-18-9 equation 18-6

    Pressure across the disperser,Hd = K1 +K2g/l Uh

    2mm liquid

    For sieve plate K1 = 0

    K2 = 50.8 / Cv2

    Hole area/Active area= Ah/Aa= 0.829/8.654=0.0958

    Tray thickness/ Hole dia= tT/dh= 3mm/5 mm=0.6

    From figure 18-14 Cv(Discharge coefficient) = 0.74

    K2 = 50.8/ (0.74)2

    = 92.74

    Uh = linear velocity of gas through the holes

    = volumetric flow rate of vapour / Ah= 9.058 / 0.829

    = 10.92 m/sec

    Hd = 0 + 92.74(4.072/600) x10.922

    = 75.14 mm liquid

    Height of liquid creast over weir ,How = (664) Fw(q / Lw)

    2/3

  • 7/28/2019 manufacture of cumene

    17/46

    Q = vol. flow rate of liquid ,m3/sec [weeping check is done at the point where gas

    velocity is low]

    = 101851.2/(745x3600)

    =0.0379 m3/sec

    q = volumetric flow rate of liquid in GPM

    =0.0379/(6.309x10

    -5

    )= 601.93 GPM

    Lw = 2.827m = 2.827/0.3048 =9.2749 ftq/(Lw)

    2.5=601.93/(9.2749)

    2.5=2.297

    Lw/Dc =2.827/3.769=0.75

    Corresponding to this two values Fw=1.02how = 1.02x664x(0.0379/2.827)

    2/3

    = 38.22 mm liquid

    Head loss due to bubble formation,

    H = 409(/ldh)= 409(33.4/ 745x 5)

    = 3.66mm liqhd+h = 75.14+3.66= 78.81 mm liqhw+how = 50 +38.22 = 88.22 mmAh/Aa = 0.1, hw+how = 88.22 mm

    From fig 18-11, hd+h=18mm

    Since the value hd+h is well above the value obtained from graph no weeping will occur.

    12 Check for downcommer flooding:

    The downcommer backup is given by,

    hdl =ht+hw+how+had+hhgc. Hydraulic gradient across plate , hhg

    For stable operation hd > 2.5hhg

    For sieve plates hhg is generally small or negligibleLet us take hhg =0 mm liq

    d. Total pressure drop across the plate ht:

    ht = hd + hlhl=pressure drop through the aereated liquid = hds

    where =aeration factor to be found from Perrys fig 18-15

    Fga =Ua(g)1/2

    Ua = 132787.78/(3600x4.072x8.654)

    = 1.046 m/sec

    g = 4.072 kg/m3Fga =Ua(g)

    1/2

    = 1.046 x (4.072)1/2

    (m/sec) (kg/m3)1/2

    = 1.73 (ft/sec)(lb/ft3)1/2

    From figure ,=0.6

    Hds =hw+how+hhg/2

    = 50+38.22 + 0= 88.22mm liq

    hl = 0.6 *88.22 = 52.93mm liq

    ht = 75.14 +52.93

    = 128.07mm liq

  • 7/28/2019 manufacture of cumene

    18/46

    c loss under downcomer area head:hda = 165.2(q/Ada)2

    let us choose c = 1 inch =25.4mm

    hap = hdsc

    = 88.2225.4

    = 62.82 mm liquidAda = Lw xhap

    =2.827 x62.82x10-3

    =0.1775m

    2

    hda =165.2(0.0379/0.1775)2

    =7.53mmhdc = 128.07 + 50+38.22 +7.53+0

    = 223.82mm

    taking dc= .5

    hdc = hdc/dc=223.82/0.5

    = 447.64 mmwe have ts= 500 mmhence ,hdc < tstherefore no downcommer flooding will occur.

    13. Column efficiency:The efficiency calculations are based on the average conditions prevailing in each

    section.

    Enriching Section:Average molar liquid rate = 285.6 Kgmoles/hr

    Average mass liquid rate = (34369.1+34969)/2= 34657.55 Kg/hr

    Average molar vapour rate = 822.47 Kgmoles/hr

    Average mass vapour rate = (98976+99880.75)/2= 99428.37 kg/hr

    Average density of liquid = (746.3 +745 )/2

    = 745.65Kgs/m3

    Average density of vapour = (3.436+3.826)/2= 3.631kgs/hm

    3

    Average temperature of liquid = (152+153)/2 = 152.5C

    Average temperature of vapour = (154+155)/2 = 154.5C

    Viscosity of cumene at 152.5C = 0.16cpViscosity of DIPB at 152.5C = 0.15cp

    X1 =(0.996+0.948)/2 = 0.972

    X2 = 1- 0.98 = 0.028

    av = [x111/3+

    x221/3

    ]3

    = [0.535+0.0106]3

    =0.1626cp

    av = [x111/3

    +x221/3

    ]3

    =[0.535+0.0106]3

    =0.1626cp

  • 7/28/2019 manufacture of cumene

    19/46

    av = [x111/3

    +x221/3

    ]3

    =[0.535+0.0106]3

    =0.1626cp

    Viscosity of cumene vapour at 154.5 C = 0.01cp Viscosity of

    DIPB vapour at 154.5 C = 0.011cp

    Average vapour composition , y1 = (0.996+0.97)/2 = 0.983 y2 = [1-0.983] = 0.017

    m =yiiMi1/2

    /yiMi1/2

    ( 0.983x0.01x1201/2

    +0.017x0.011x1621/2

    )= = 0.01 cp

    (0.983x1201 2

    +0.017x1621 2

    )

    Liquid phase diffusivities:

    Wilke-chang equation

    7.4x10-8

    (MB)0.5

    TDL =

    BVA0.6

    where,

    MB = Molecular weight of solvent B = 162 =1 for cumeneVA& VB are molar volume of solvent A & B

    VA = 16.5x 9 + 1.98x12 = 172.26

    VB =16.5x18 + 1.98x22 = 340.56

    7.4x10-8

    (1x162)0.5

    x425.5

    DL =

    1.14x 10-4

    cm2/sec 0.16x(172.26)

    0.6

    Vapour phase diffusivity:

    Fuller Etal equation,

    10-3xT1.75(1/MA+1/MB)0.5Dg =

    P[VA)1/3

    (VB)1/3

    ]2

    10-3

    (273+154.5)1.75

    (1/120 + 1/162)0.5

    Dg =

    1x[(172.26)1/3

    + (340.56)1/3

    ]2

    = 0.0319cm2/sec

  • 7/28/2019 manufacture of cumene

    20/46

    N

    scg=

    g/

    g Dg

    =0.01 x10-3

    / (3.631 x0.0319 x10-4

    )

    =0.863Stripping Section:

    Average molar liquid rate = 275.34 Kgmoles/hr

    Average mass liquid rate = (101851.2+134389.36)/2

    = 118120.28 Kg/hrAverage molar vapour rate = 822.47 Kgmoles/hrAverage mass vapour rate = (99880.75+132787.78)/2

    = 116334.26 Kgmoles/hr

    Average temperature of liquid = (153+202)/2= 117 C

    Average temperature of vapour = (155+202)/2

    = 178.5 C

    Viscosity of liquid at 177.5 C = 0.11cpViscosity of liquid at 177.5 C = 0.1cp

    l =[x111/3

    + x2 21/3

    ]3

    x1 =(0.948+0.013)/2 = 0.4805

    x2 = 1- 0.4805 = 0.5195

    l =[0.4805x0.111/3

    +0.5195x0.11/3

    ]3

    =0.1071 cp

    Viscocity of vapour cumene at 178.5 C= 0.01cp Viscosity of vapour DIPB at 178.5C = 0.0115cp Y1=(0.97+0.013)/2 = 0.4915

    Y2 = 1-0.4915 = 0.5085

    yiiMi1/2

    v =

    yiMi1/2

    =(0.0553+0.072)/(5.531+6.261)=0.0108 cp

    Liquid phase diffusivity:

    Using wilky-chang equation

    DL = 1.672x10-4

    cm2/sec

    Vapour phase diffusivity:

    Dg = 0.0351 cm2/sec

    Nscg = g /gxDg

    = 0.779

  • 7/28/2019 manufacture of cumene

    21/46

    Table of average conditions:

    Condition Enriching Section Stripping Section

    Liq flow rate Kgmoles/hr 285.6 832.39Liq flow rate 34657.55 118120.28Kg/hr

    !L Kg/m3 745.65 672.5

    TL & 152.5 177.5L cp 0.1626 0.1071

    DL cm /sec 1.14x10-

    1.672x10-

    Vap flow rate Kgmoles/hr 822.47 822.47

    Vap flow rate Kg/hr 99428.37 116334.26

    !V Kg/m 3.631 3.95Tv & 154.5 178.5

    Dg cm /sec 0.0319 x10-

    0.0351Nscg 0.863 0.779

    Enriching section Efficiency:

    0.776+0.0045hw - 0.238Uag0.5

    +0.0712WNg =

    Nscg0.5

    Ua =gas velocity theory

    =99428.37/(3600x3.631x5.4682)=1.391 m/sec

    Q =34657.55/(3600x745.65) = 0.0129m3/sec

    Df =( Dc+LW )/ 2

    =(2.996+2.247)/2=2.6215m

    W = q/Df= 0.0129/2.6215

    = 4.92x10-3 m2/sec

    hw =50mm

    g = 3.631Kg/m3

    Nscg = 0.863

  • 7/28/2019 manufacture of cumene

    22/46

    0.776+.0045x50-0.238x1.391(3.631)0.5

    +0.0712x4.92x10-3

    Ng =

    (0.863)0.5

    Ng = 0.3988

    Nl = KLa L

    Klxa = (3.875x108DL)

    0.5(0.4Uag

    0.5+ 0.17)

    =(3.875x108x1.14x10

    -8)0.5

    [0.40x1.391x(3.631)0.5

    +0.17]=2.585/sec

    l = hl Aa / 1000q[hl=hl]= 42.88x5.4682)/(1000x0.0129)

    =18.17

    Nl

    = 2.585 x 18.17

    = 46.986

    Nog = 1/(1/Ng+/Nr)Where, =mGm/Lm

    Gm/Lm = 822.47/285.6= 2.88

    M =slope of the equilibriumcurve mtop = 0.2857mbottom = 0.2857

    m value is same at the top and bottom as slope of equilibrium line is same at both

    the points

    =0.2857x 2.88

    =0.8228

    Nog = 1/ (1/0.3988+0.8228/46.98)

    = 0.3960

    Eog = 1-e-Nog

    =0.3270

    Murphy plate efficiency:

    Npl = zl2/DE l

    Zl = 2[(De/2)cos(C/2)]= 2[(2.996/2) cos (97.18/2)]=1.981

  • 7/28/2019 manufacture of cumene

    23/46

    DE = 6.675x10-3Ua1.44

    + 0.922x10-4

    hl-0.00562

    =6.675x10-3

    x(1.3981)1.44

    + 0.922x10-4

    x42.880.00562

    = 9.069x10-3

    m2/sec

    Npl = (1.981)2/(9.069x10

    -3x18.17)

    = 22.470Eog =0.8238 x 0.3270

    = 0.269

    from fig 18.29(a) , Emv/Eog = 1.12

    Overall efficiency

    Eoc =Nt/NA= log[1+Ea(-1) / log]

    Ea/Emv= 1/ 1+Emv( / (1-)]

    Taking

    L/G(g/L)0.5

    =0.02425 (avg.value)

    We get, =0.13

    Ea/Emv = 1/(1+0.3597(0.13/1-0.13) )

    = 0.94289

    Ea = 0.9489x0.3597= 0.3413

    Eoc = log[1+0.3413(0.8228-1)]/log(0.8228) =0.3208

    NA = Nt/Eoc

    =3/0.3207

    =9.35 9 trays

    Height of enriching section is = 9x0.5

    = 4.5 m

    Stripping Section Efficiency:

    0.776+0.0045hw

    -0.238Ua

    g

    0.5+0.0712W

    Ng =

    Nscg0.5

    Ua = 116334.26/(3600x3.95x8.654)

    = 0.9453 m/sec

  • 7/28/2019 manufacture of cumene

    24/46

    q = 118120.28/(3600x672.5) = 0.0488

    Df = (Dc + Lw)/2

    = 3.298 m

    w = q/Df = 0.0488/3.298

    hw = 50mm

    g = 3.95kg/m3

    Nscg = 0.779

    Ng = [(0.776+0.0045 x 50 - 0.238 x 0.9453 x (3.95)0.5

    +0.0712 x 0.0148] / (0.779)0.5

    = 0.6287

    Nl = KLDL

    Klxa = (3.875x108DL)

    0.5(0.4Uag

    0.5+ 0.17)

    = (3.875x108x1.672x10

    -4)0.5

    (0.4x0.9453x(93.95)0.5

    +0.17)

    =2.345 sec-1

    l = hl Aa / 1000q[hl=hl] = (52.93x8.654) / (1000x0.0488) =9.386

    Nl = 2.345 x 9.386= 22.01

    Nog = 1/(1/Ng+/Nt)Where, = mGm/Lm

    Gm/Lm = 822.47/832.39

    =0.9880m=slope of the equilibrium curve

    mtop = 0.2857

    mbottom = 4.37

    top = 0.2857x0.9880

    = 0.2822bottom = 4.37x0.9880 = 4.3175

  • 7/28/2019 manufacture of cumene

    25/46

    = (top+bottom) / 2=2.29

    Nog = 1/ (1/0.6287+2.29/22.01)

    = 0.5901

    Eog = 1-e-Nog

    =0.4457

    Murphy plate efficiency:

    Npl = zl2

    / DE l

    Zl = 2[(Dc/2)cos(C/2)]= 2[(3.769/2)

    cos (97.2/2)] =2.493

    DE = 6.675x10-3Ua1.44 + 0.922x10-4hl-0.00562

    =6.675x10-3

    x(0.9453)1.44

    + 0.922x10-4

    x52.930.00562

    = 5.41x10-3

    m2/sec

    Npl = (2.493)2/(5.41x10

    -3x9.386)

    = 122.39

    Eog = 2.29x 0.4457

    = 1.02

    from fig 18.29(a) , Emv/Eog = 1.7

    Overall efficiency

    Eoc = Nt/NA = log [1+Ea(-1)] / log

    Ea/Emv = 1/ 1+Emv( /1- )

    TakingL/G(g/L)

    0.5=0.02425 (avg.value)

    We get, = 0.037

    Ea/Emv = 1/(1+0.7577(0.037/1-0.037) )= 0.6920

    Ea = 0.692 x 0.7577

    = 0.5243

  • 7/28/2019 manufacture of cumene

    26/46

    Eoc = log[1+0.5243(2.29-1)] / log(2.29) =0.6225

    NA = Nt / Eoc= 6 / 0.6225

    = 9.64 10 traysHeight of stripping section is = 5x0.5

    = 4.5 m

    Total height of tower = 4.5+5=9.5

    (B). MECHANICAL DESIGN

    Specifications:-

    Inside Diameter:- 3.769m = 3769mm

    Ht of top disengaging section = 40cm.

    Working pressure = 1atm = 1.032 kg/cm2

    Design pressure = 1.032 x 1.1 = 1.135 kg/cm2

    Shell material = Carbon steel( Sp. gr. = 7.7)

    Permissible tensile stress = 950 kg/cm2

    Insulation material = asbestos

    Density of insulation = 2700 kg/m3

    Tray spacing = 500 mm

    Insulation thickness = 50 mm

    Down comer & plate material = S.S

    Sp.gr of SS = 7.8

    SKIRT = 2m

    Shell thickness:-

    ts = P.Di +C2fj -p

    ts = shell thicknessP = design pressureDi = ID of shellf = allowable stressJ = joint efficiency (0.85)

  • 7/28/2019 manufacture of cumene

    27/46

    C = corrosion allowance (2 mm)

    ts = 1.135 x 3769 +2

    2 x 0.85 x 9501.135

    = 5 mm.

    Taking min shell thickness of 6mm Shell outside Do = 3769+2x6= 3781mm

    The column is provided with torispherical head on both ends.

    For torrispherical head, crown radius

    => Ro = Do = 3781 mm

    ro = 6% Ro= 0.06 x 3781= 226 mm

    Calculation of head thickness

    t = 0.885 Prc /(fE0.1p) + C [eqn.13.12 Brownell & Young]

    rc = crown radiusE =jointeff

    n

    f = allowable stressC = corrosion allowance

    t = 0.855x 1.135 x 3781 + 2

    950 x 0.850.1 x 1.135

    =7.00

    Take head thickness to be 8mm

    Approximate blank diameter can be found out as;

    Diameter= OD + OD + 2 Sf + 2 icr24 3

    Sf = 800 m

    Diameter = 3781 + 2412 + 2 x 800 + 2 x 22624 3

    = 5683mm

    wt of head = d2t4

    = x (5.683)2 x 0.006 x 77004

    = 1172kg.

  • 7/28/2019 manufacture of cumene

    28/46

    Tensile strength R20 = 37 kgf/cm2

    Yield stress = 0.55 R20= 20.35 kgf/cm

    2

    fap = pdi4(ts-c)

    = 1.135 x 3769 4 x (62)= 267 kg/cm

    2

    fap = tensile stress due to internal pr ( kg/cm2) stresses due to dead

    load (compressive) -:

    w = (weight of the shell + attachment)+ (weight of plate)+ (weight of liquid hold up) + (weight

    w1 = weight of shell = di ts. xw2 = weight of insulation = ( do

    2ins- do

    2!ins . X

    4

    wh = wt of head = 1172 kg.Wp = wt of each plate = (An - Ah ) x tp p + [hw +( tshap)] x tpx Pp + Wa

    WL = wt of liquid = ( Aa * HL+ Ad * hdl)L

    w = w1 + w2 + wh + (wp + wL) * X

    w1 = weight of shell = (3.769) x 6 x 10-3

    x 700(X) = 547 X

    w2 = weight of insulation = (3.88123.781

    2) x2700 4

    = 1662.24 X kg.

    wh = weight of head = 1172 kg.

    wp = weight of each plate.

    = (9.902- 0.829) x 0.003 x 7800+0.05 + (0.5000.0628)x 0.003 x 7800 wa wa 50

    wp = 250 kg.

    WL = weight of liq

    8.654 x 52.93 x 10-3 + 0.1775 x 0.2238 x 673=335 kg

    w = 547 X + 1662.24 X+1172+(250 + 335) X

    = 3489 X + 1172

    Stress due to dead load (compressive) at distance X:

    fdw = w . di (ts6)

    =3489 X+ 1172

    x376.9x( 62)10-1

    =7.366 X+ 2.474 kg/cm2

  • 7/28/2019 manufacture of cumene

    29/46

    Stress due to wind load at a dist X:-

    fwx = 1.4 Pw x2

    do (tsc)

    The design is being due for a wind press of 150 kg/m2

    Pw = 150 kg/m2

    fwx

    = 1.4 x 150X

    2

    .

    x 378.1 x ( 6 2) x 10-

    = 0.4427 X2

    kg/cm2

    Resultant longitudinal stress in the upwind side:

    ftmax=

    fax+

    fap

    fdw

    950 x 0.5 = 0.4427 X2

    +267- (7.366 X +

    2.474) => 0.4427X27.366 X210.4 = 0

    X = 7.366 (7.3662

    + 4 (0.4427)(210.4))

    0.5

    2 x 0.4427= 31.65 m

    Resultant longitudinal stresses:- at downwind sides:-

    - fcmax = -fwx + fapfdw

    fcmax = 1 (yield stress)

    1 x

    20.353

    = 6.783 kg/cm2

    -6.783 = - 0.4427X2

    + 267(7.366X + 2.474)

    => 0.4427X2

    + 7.366X271.3 = 0

    X = - 7.366 (7.3662+4x(0.4427)(271.3))0.5

    2 x 0.4427= 17.8 m

    Which suggests that the design is safe. Since the design is being made on the basis ofhigher diameter, so the design is assumed to be safe for the entire length of the tower.

  • 7/28/2019 manufacture of cumene

    30/46

    Design of skirt support:-

    Specifications:-

    Top disengaging space = 1mBottom separator space = 2m

    Skirt Height = 2m.

    Total Height of column including skirtheight-

    H = 9.5 + 2.00 +1.00 + 2.00

    H = 14.5m

    Wt. of shell w1 = dit sH = 7931.5kg

    Wt of insulation w2 = 1662.24x14.5 = 24102.5kg

    Wh = Wt. of Head = 1172 kg.

    Wp = Wt. Of plate = 250kg.

    WL = wt. of liquid = 335 kg

    W = W1 + W2 + (WP + WL) H + Whts = 7931.5 + 24102.5 + (250 + 335) x 14.5 + 1172

    0.5

    Wind Load = 51767 kg

    fwb = (K P1 H DO). (H/2)

    DO2

    . t4

    =2K P1 H2

    DO DO2 t.

    K = 0.7, P1 = 128.5 kg/m2

    fbw = 2 x (0.7) (128.5 x 14.52

    x 3.781)

    kg/cm2 x (3.781)2 x t x 104

    fbw = 0.1592 kg/cm2

    t

    fds = w ,

    Dmt.

    Dm = Di + t = 2400 + 6 = 3.775 m

    fds = 51767 = 43.65

    x 3.775x t x102 t

  • 7/28/2019 manufacture of cumene

    31/46

    Seismic load :

    fsb = 8 CWH

    3 Do2t

    C = 0.08

    fsb = 8 x 0.08 x 51767 x 14.5

    3 x(3.781)2 x t x104

    = 0.3565/t kg/cm2

    Max possible tensile stress:-

    Jf = fdbfsb

    807.5 43.65 - 0.3565t t

    807.5 43.29t

    t 0.0536cm.

    We can have t = 6mm

    max permissible compressive stress:-

    Jf fdb + fsb

    807.5 43.65 + 0.3565t t

    807.5 44.00t

    t 44.00807.5

    t 0.0545 cm

    Choose skirt thickness = 6mm

    Skirt bearing plate

    Fc = W + MsA Z

    = 51767 x 4 + Msb

    (4032 - 3772) 2

    Msb = 2 CWH.

    3Z = (Dop

    4Dos

    4) x

    Dop x 32

    = 4034 - 3774 x 32 x 403

  • 7/28/2019 manufacture of cumene

    32/46

    fc = 51767 x 4 + 2 0.08 x 51767 x 14.5

    (4032- 3772) 3 (4034- 3774)32 x 403

    = 3.2496 + 0.0266= 3.2762kg/cm2

    This is much less than permissible compressive stress

    of concrete.

    Mmax = fc . b.l2/2

    f = 6 M max = 3 fcl2 = 3 x 3.2762 x 152 kg/cm2

    b tB2 tB tB

    f = 9.6 MN/m2

    = 9.5 x 102

    N/cm2

    = 96 kgf/cm2

    tB = (3x3.2762x152

    )96

    tB = 4.799 cm= 48mm

    Bolting has to be used.

    Assume W min = 45,000 kg.

    fc = 45,000 x 4 - 2x 0.08 x 51767 x 14.5 (4032 - 3772) 3 x (40343774)

    32 377= 20.83.09= 17.7 kg/cm

    = Mwt =W minR

    Mwt = W min x R

    = 45,000 x 270= 12.15 x 10

    6

    j = 12.15x 106

    4.043 x 106

    = 3.05

    j 1.5 anchor bots are not required

  • 7/28/2019 manufacture of cumene

    33/46

    (C). MINOR EQUIPMENT

    CONDENSER (PROCESS DESIGN)

    Preliminary Calculations:

    (a) Heat Balance:

    Vapor flow rate (G) = (R+1)D

    =1.532 x 64706.40655 kg/hr= 98976 kg/hr

    = 27.49 kg/s

    `Vapor Feed Inlet Temperature =152.4

    0c.

    Let Condensation occur under Isothermal conditions i.e FT =1

    Condensate outlet temperature = 152.40C

    Average Temperature = 152.4 0C

    Latent heat of vaporisation () :

    1 = C1 x (1-Tr) (C2+C3 x Tr +C4 x Tr2 )[Perry, 7

    thedition ; 2

    nd

    chapter]

    for cumene, Tc = 631.1K ; Pc = 3.25 x 106

    Now Tr = T/ Tc = (152.4+273)/ 631 = 0.6735C1= 5.795 x 10 ; C2 = 0.3956C3 = 0 ;C4 = 0

    = 5.795 x 107

    + (1 - 0.6735)0.3956

    =5.795 x 107 J/Kmole=482.153 KJ/ kg

    qh = mass flow rate of hot fluid x latent heat of fluid

    qh = heat transfer by the hot fluid .

    qh

    = 27.49 x 482.153 = 13254.3 KW

    qC = mass flow rate of cold x specific x tfluid heat

    qc = heat transfer by the cold fluid.

    Assume : qh = qc.

    Inlet temperature of water = 250C.

    Let the water be untreated water.

  • 7/28/2019 manufacture of cumene

    34/46

    Outlet temperature of water (maximum) = 40 0C

    t = 40-25= 15 0C

    Cp = 4.187 KJ/kgK.

    mc = 13254.3 = 211 kg/s.

    4.187x103x15

    (b) LMTD

    Calculations: assume :

    Counter current

    T1 T2

    t2t1

    LMTD = ( T1- t2)( T2 - t1)

    ln (T1- t2 )

    (T2 - t1)

    T1 = 152.4 0C; T2 = 152.40C ; t1 =25

    0C ; t2 =400

    C

    LMTD = 119.74 0C

    (C)Routing of fluids : Vapors - Shellside Liquid - Tube side

    (D)Heat Transfer Area:

    (i) qh = qC =UA ( LMTD,corrected)U = Overall heat transfer coefficient (W/m

    2K)

    Assume : U = 536 W/m2K

    A assumed = 13254 x103

    = 206.5 m2

    536 x 119.74

    55

  • 7/28/2019 manufacture of cumene

    35/46

    (ii) Select pipe size: ( Ref 1: p: 11-10 ; t: 11-2)

    Outer diameter of pipe (OD) = 3/4 = 0.01905 m

    Inner diameter of pipe (ID) =0.620 = 0.01574 m

    Let length of tube =16 = 4.88m

    Let allowance for tubesheet thickness = 0.05m

    Heat transfer area of each tube (aheattransfer) = x OD x (LengthAllowance)

    = x 0.01905 x (4.880.05

    = 0.2889 m2

    Number of tubes (Ntubes) = Aassumed 206.5

    =a heat-

    transfer 0.2889

    =715

    (iii)Choose Shell diameter: (Ref-1, p: 11-15, t : 11-3 (F) )

    Choose TEMA : P or S. OD tubes in 1 larpitch

    12 Horizontal Condenser

    Nearest tube count = 716

    Ntubes (Corrected ) = 1740

    Shell Diameter (Dc)=0.787 m.

    Acorrected =206.8 m2

    Ucorrected = 536 W/m2K =Uasssumed

    (iv) Fluid velocity check :

    (a)Vapor sideneed not check(b) Tube side

    Flow area (atube) = apipe x NtubesPer pass

    Ntube passes

  • 7/28/2019 manufacture of cumene

    36/46

    a pipe = C.S of pipe = (ID2)

    4

    atube= (/4)(0.01574)2

    x (716/2) = 69.71 m2/pass

    Velocity of fluid (Vpipe) vp = mpipe/pipe x atube

    mpipe = massflow rate of fluid in pipe.

    pipe = Density of fluid in pipe (water)

    Vp = 211/(995.6 x 69.71) =3.04 m/s

    Fluid velocity check is satisfied.

    (II) Film Transfer Coefficient:

    Properties are evaluated attfilm:

    a)Shell side:

    Reynolds number (Re ) =882

    For Horizontal condenser :

    Nu = 1.51 (0D)3 ()2 g (Re)-1/3/ 2

    =1.51 {0.019053

    (862.3)2

    x 9.81 }1/3

    (882)-1/3

    = 321.6

    (0.3176 x 10 3)2

    Nu = ho (OD)K

    ho = outside heat transfer coefficient (W/m2K)

    k = Thermal conductivity of liquid.

    ho = Nu x K/(OD) = 839 W/m2

    K

    b) Tube side:

    vpipe = 3.04 m/s

    Re = v(ID) = 3.04 x 0.01574 x 995.6 = 59,625

    0.8 x 10 3

    Pr = Cp = 0.8 X 103 x 4.1796 x 10 3 = 5.39

    K 0.617

  • 7/28/2019 manufacture of cumene

    37/46

    hi (ID)= 0.023 (Re )

    0.8(Pr)

    0.3K

    hi = insideheat transfer coefficient

    hi = 0.023 (59625)0.8

    (5.39)0.3

    x 0.6170.01574

    hi = 11,751 W/m2K

    Fouling factor(Dirtcoefficient) = 0.003 [Ref:1 , p :10-44, t:10-10]1/Uo =1/ho+[(OD/ID)(1/hi)]+fouling factorUo = Overall heat transfer coefficientUo = 539 W/m

    2K

    Uo > Uassumed

    (III) Pressure Drop Calculations :

    Tube Side :

    Re =59625

    F = 0.079 (Re)-

    = 0.079 (59625 )-

    = 0.0021

    f = friction factor

  • 7/28/2019 manufacture of cumene

    38/46

    Pressure Drop along

    the pipe length ( P)L = ( H)L x x g

    =4fLVp2 x xg 2g(ID)

    = 4 x 0.0021 x 4.88 x 3.04 2 x 995.6 x 9.81

    2 x 9.81 x 0.01574

    =11.981KPa

    Pressure Drop in the

    end zones ( P)e = 2.5 Vp2 = 2.5 x 995.6 x 3.04 2 =11.5 KPa

    2 2

    Total pressure dropin pipe ( total = [11.981 +11.5 ]2 = 46.96 KPa

  • 7/28/2019 manufacture of cumene

    39/46

    Shell side pressure drop (P)s =1/049 Kpa

  • 7/28/2019 manufacture of cumene

    40/46

    ts =PDi[ IS 2825, pg:13, eq :3-1]

    2fJ-P

    ts =Shell thickness

    P = design pressure = 0.11 N/ mm2Di = Inner diameter of shell = 787mmf = Allowable stress value = 95 N/mm

    2

    J= Joint factor = 0.85

    ts = 0.11 x 787

    2 x 95 (0.85).1= 0.536 mm

    Minimum thickness of shell must be 6 mm & corrosion allowance =3 mm shell thickness, ts = 10 mmHead : (Torrispherical head)

    th = PRCW[ Brownell & Young ; pg:238]

    2fJ

    th = thickness of head

    W = 3+ Rc / Rk}

    Rc = Crown radius = outer diameter of shell =787mmRk = knuckle radius = 0.06 RC

    Minimum shell thickness should be = 10 mm [IS : 4503-1967]

    th = 10mm

    Since for the shell, there are no baffles, tie-nods & spacers are not required.

    Flanges :

    Loose type except lap-joint flange.

    Design pressure (p) =0.11 N/mm2

    Flange material : IS:20041962 class 2

    Bolting steel : :5% Cr Mo steel.Gasket material = Asbestos composition

    Shell side diameter =787mmShell side thickness =10mm

    Outside diameter of shell =787 + 10x 2 = 807mm

    Determination of gasket width :

  • 7/28/2019 manufacture of cumene

    41/46

    Y = Yield stress,M = gasket factor

    Gasket material chosen is asbestos with a suitable binder for the operatingconditions. Thickness = 10mm

    M = 2.75y=2.60 x 9.81 = 25.5 N/mm

    2

    do = 25.5 - 0.11 (2.75 ) = 1.004di 25.50.1(2.75+1)

    di = inside diameter of gasket= outside diameter of shell= 807 + 5mm

    =812 mmdo = outside diameter of the gasket

    =1.004 (812)=816 mm

    Minimum gasket width = 0.8160.812 = 0.002m =

    2 mm

    2

    But minimum gasket width = 6mm G = 0.812 + 2 (0.006)

    = 1.256 m

    G = diameter at the location of gasket load reaction

    Calculation of minimum bolting area :

    Minimum bolting area (Am) = Ag= WgSg

    Sg = Tensile strength of bolt material (MN/m2)

    Consider , 5% Cr-Mo steel, as design material for bolt

    At 152.40

    C.

    Sg = 138 x 106 N/m

    2 [ B.C.Bhattacharya , pg :108

    Am = 0.3960 x 106 = 2.87 x 10

    -3m

    2

    138 x 10

    Calculation for optimum bolt size :

    g1= go = 1.415go

  • 7/28/2019 manufacture of cumene

    42/46

    gl = thickness of the hub at the back of the flange

    Selecting bolt size M18x2

    R = Radial distance from bolt circle to the connection of hub & back of flange R= 0.027C = Bolt circle diameter = ID +2 (1.415 go + R) [B.C.B, pg :122 ]

    C = 0.787 +2 (1.415 (0.0125)+0.027)=0.876 m

    Estimation of bolt loads :

    Load due to design pressure (H) = G2 P4

    H = (0.824)

    2

    (0.11x10

    6

    ) = 0.0586 x 10

    6

    N

    Load to keep the joint tight under operating conditions.

    Hp = g (2b) m p

    B = Gasket width = 6mm = 0.006m

    Hp = (0.824 ) ( 2 x 0.006) 2.75 x 0.11 x 106 =

    0.00939 x 106

    N

    Total operating load (Wo) = H+Hp=( 0.0586+0.00939 )

    = 0.06799 x 106

    N

    Load to seat gasket under boltup condition =Wg.

    Wg. = g b y

    = x 0.824 x 0.006 x 25.5 x 106

    Wg = 0.3960 x 106

    N

    Wg > W0

    Wg is the controlling load Controlling load = 0.3960 x 106 N

    Actual flange outside diameter (A) = C+ bolt diameter + 0.02

    = 0.876 +0.018+ 0.02= 0.914m

    Check for gasket width :

    Ab = minimum bolt area = 44 x 1.54 x 10-4

    m2

    A Sg (44 x 1.54 x 10-4

    )138= 30.10 N/mm2

  • 7/28/2019 manufacture of cumene

    43/46

    i.e., bolting condition is satisfied.

    Flange Moment calculations :

    (a)For operating conditions :

    WQ = W1 +W2 +W3

    W1 = B2

    P = Hydrostatic end force on area inside offlange.4

    W2 = H-W1

    W3 = gasket load = WQ - H = Hp

    B = outside shell diameter = 0.807m

    W1 = (0.807)2

    x 0.11 x 106

    = 0.05626 x 106

    N

    4

    W2 = H- W1=(0.05860.0562)x106

    =0.0026x106N

    W3 = 0.00939 x 106

    N

    Wo =( 0.05626 + 0.0026 + 0.00939 ) x 106

    = 0.068 x 106

    N

    Mo = Total flange moment =

    W1 a1 + W2 a2 + W3 a3 a1

    = (CB)/2 ; a2 = (a1 + a3)/2 ; a3 =( CG)/2

    [IS : 2825-1969 ; pg:53]

    [IS 2825-1969, pg

    :55]

    Mo =[ 0.05626 ( 0.0345) + 0.0026 ( 0.0303) +0.00939 (0.026) ] x 106

    =2.264 x 103

    J

    (b) For bolting up condition :

    Mg = Total bolting Moment =W a3 [IS 2825-1969, pg :56,Eqn:4.56]

  • 7/28/2019 manufacture of cumene

    44/46

    W = (Am +Ab)Sg . 2

    Am = 2.87 x 10-3

    Ab = 44 x 1.5 4x 10

    -4= 67.76 x 10

    -4Sg = 138 x 10

    6

    W= (2.87 x 10-3

    + 67.76 x 10-4

    ) x 138 x 106

    = 0.665 x 1062

    Mg = 0.665 x 106 x 0.026 = 0.0173 x 106 J

    Mg > Mo

    Mg is the moment under operating conditions M= Mg = 0.0173 x

    106

    J

    Calculation of the flange thickness:

    t2

    = MCFY [B.C.B: , eq:7.6.12]

    BSFO

    CF= Bolt pitch correction factor = Bs/ (2d + t)[IS 2825-1969: 4,pg:43]

    Bs = Bolt spacing = C = (0.876) = 0.0625mn 44

    N = number of bolts.

    Let CF = 1

    SFO = Nominal design stresses for the flange material at designtemperature.

    SFO = 100 x 106 N

    M = 0.0173 x 106

    J

    B = 1.239

    K = A = Flange diameter = 0.914 = 1.132

    B Inner Shell diameter 0.807

    Y = 15(B.C.Bhattacharya, pg : 1

    fig:7.

    d = 18 mm

    CF = (0.675)2

    t = 0.0567 x 0.821= 0.049

  • 7/28/2019 manufacture of cumene

    45/46

    Let t = 50mm = 0.05m

    Tube sheet thickness : (Cylindrical Shell) .

    T1s = Gc KP / f (M.V.Joshi, pg : 249, e.g. : 9.9)

    Gc = mean gasket diameter for cover.P = design pressure.K = factor = 0.25 (when cover is bolted with full faced gasket)

    F = permissible stress at design temperature.

    t1s = 0.824 (0.25 x 0.11 x 106) / ( 95 x 10

    6) = 0.014 m

    Channel and channel Cover

    th = Gc (KP/f) ( K = 0.3 for ring type gasket)

    = 0.824 (0.3 x 0.11/ 95)

    = 0.015 m =15 mm

    Consider corrosion allowance = 4 mm. th=0.004 + 0.015 = 0.019 m.

    Saddle support

    Material: Low carbon steel

    Total length of shell: 4.88 m

    Diameter of shell: 807 mm

    Knuckle radius = 0.06 x 0.807 = 0.048 m = ro

    Total depth of head (H) = (Doro/2)= (0.80= 0.139

    Weight of the shell and its contents = 12681.25 kg = W

    R=D/2 =807/2 mm

    Distance of saddle center line from shell end = A =0.5R=0.202 m.

    Weight of the vessel and condensate :

    Density of steel = 7600 kg/m3

    Weight of steel vessel = (di2

    / 4) x waterx L x Nt+ ds x t xsteel x L+ dit xLxsteel x Nt

    =(0.0157)2/4 x 994 x 4.88 +x 0.787 x 0.01 x 4.88 x7600+x 0.0157 x 0.0016 x 7600 x 716 x 4.8

    W = 3685 kg

  • 7/28/2019 manufacture of cumene

    46/46

    Longitudinal Bending Moment

    M1 = QA[1-(1-A/L+(R2-H

    2)/(2AL))/(1+4H/(3L))]

    Q = W/2(L+4H/3)

    = 3685 (4.88 + 4 x 0.139/3)/2

    =9333 kg m

    M1 =9333x0.202[1-(1.202/4.88+(0.40352-0.139

    2)/(2x4.88x0.31))/(1+4x0.139/(3x4.88))]

    = 11.97 kg-m

    Bending moment at center of the span

    M2 = QL/4[(1+2(R2-H

    2)/L)/(1+4H/(3L))-4A/L]

    M2 = 9804 kg-m

    Stresses in shell at the saddle

    (a) At the topmost fibre of the cross section

    f1 =M1/(k1 R2

    t) k1=k2=1

    =11.97/(3.14 x 0.40352

    x 0.01)

    = 0.2340 kg/cm2

    Stress in the shell at midpoint

    f2 =M2/(k2 R2 t)= 191.685 kg/cm

    2

    f1 and f2 are well within permissible limits

    Axial stress in the shell due to internal pressure

    fp = PD/4t

    = 0.11 x 106

    x 0.807 /4 x 0.01

    = 221.9 kg/cm2

    f2 + fp = (191.685 + 221.9) kg/cm2

    = 413.585 kg/cm2

    The sum f2 and fp is well within the permissible values.


Recommended