Manufactured Housing Duct Sealing Pilot - Independent Evaluation Results
Tom Eckhart, Howard Reichmuth, Jill SteinerRegional Technical ForumFebruary 3, 2009
Program Description Operated by UCONS, LLC from September 2005 to June 2006 Focused on sealing and repairing duct leaks in manufactured
homes with electric furnaces Provided other low-cost measures
Efficient showerheads and aerators Temperature reset on water heater Pipe insulation Compact fluorescent lights Furnace filter
Served 1,686 Snohomish customers – about 13% of manufactured homes with electric furnaces
Program Process
Pre-Treatment Duct
Pressurization Test and Visual
Inspection
Installation of Low-Cost
Measures
Post-Treatment Duct
Pressurization Test
B
C
A
Leve
l of D
uct T
reat
men
t as
Det
erm
ined
App
ropr
iate
Duct Sealing Protocols “A” sites – Ducts tested and sealed from the interior (boots, registers, end
caps). Cross-over duct are inspected and if determined to still be in good condition but air leaks were identified at the crossover duct connections to the collars, the collar connections to the main duct runs, or there were air leaks in the crossover duct that were repairable. The identified air leaks were sealed with mastic, and/or repairs were made to crossover duct as required. These were referred to as “exterior treatment of crossover ducts”.
“B” sites – Ducts tested and sealed from the interior (boots, registers, end caps). Cross-over duct inspected and if found to be damaged, would be replaced. Collars sealed with mastic, new R-8 crossover duct installed and crossover duct connections sealed with mastic.
“C” sites - Ducts tested and sealed from the interior (boots, registers, end caps). Cross-over duct would be inspected and if no air leaks were found, no further work would be conducted.
Expected SavingsMeasure Number
InstalledEst per unit savings kWh/yr
Percent of Homes Installed
Total kWh/yr savings
Low Flow showerhead
958 158 57.1% 151,364
Aerator 1876 60 111.7% 112,560
Temp reset, pipe wrap
915 360 54.5% 329,400
CFL 7978 33 475.2% 263,274
Floor insulation 270 2.4 16.1% 848
Furnace Filter 1167 70 69.5% 81,690
Duct inspect only “C”
581 830 482,462
Duct test/seal “A”
262 1044 273,580
Duct test/seal & Repair “B”
836 1151 962,236
Totals 1,679 2,657,215
Data Challenges
Bi-monthly billing data Sought 18-months pre- and post-data
Ideally, 2 years would be available for analysis For robust sample, included some sights with less than 18-
months post-data Of the 1,686 participants, analyzable data for 572
(~34%)
Methodology
Compared pre- and post-treatment consumption data Defined energy consumption as a function of average
outside temperatures for pre- and post-periods Calculated Normalized Annual Consumption (NAC) for
pre- and post-periods to determine normalized average savings
Energy Consumption Function
Model Fit
0
20
40
60
80
100
120
140
160
35 40 45 50 55 60 65 70 75
Mean Temperature, deg F
Ener
gy/d
ay, k
Wh
PreRejectModelPostRejectModel
Participant Pre- and Post-ConsumptionNormal Monthly Use
0
500
1000
1500
2000
2500
3000
jan feb mar apr may jun jul aug sep oct nov dec
Month
Elec
tric
Use,
kW
h/m
o
pre
post
Statistical Results
Sample Mean Savings kWh/yr
Std Dev N 95% Lower Bound
95% Upper Bound
Full Sample 1,463 2,631 572 1,247 1,679
A sites 1,369 2,469 168 993 1,745
B sites 1,717 2,709 321 1,419 2,014
C sites 671 2,500 83 126 1,218
>20,000 pre 2,673 3,372 169 2,161 3,186
Program Savings
Treatment Group Average Savings kWh/yr
Number of Sites in Program
Total Savings kWh/yr
A sites 1,369 262 358,678
B sites 1,717 836 1,435,412
C sites 671 581 389,851
Total Program 1,679 2,183,941
Summary Results
Total Number of Program Participants 1,679
Mean Savings per Participant 1,301 kWh/yr
Total Participant Savings, kWh/yr 2,183,941 kWh/yr
Savings as % of Average Participant Usage
8% based on analysis sample
Realization Rate of Projected Savings 82%
Savings by Treatment Group
0
200400
600
800
1,0001,200
1,400
1,6001,800
2,000
A sites B sites C sites
Annu
al kW
h Sa
vings
Realization Rates by Treatment Group
0%
20%
40%
60%
80%
100%
120%
A sites B sites C sites
Reali
zatio
n Ra
tes
Pre- and Post- Consumption
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
18,000
20,000
A B C
Treatment Category
Annu
al E
nerg
y U
se, k
Wh/
yr
pre
post
7.3%9.5% 3.8%
8% average savings overall 9.8% savings (> 2,600 kWh) for homes with pre-treatment consumption over 20,000 kWh
Savings DistributionNormalized Savings Distribution - blue is full sample,
red is participants with pre usage > 20,000 kWh/yr
0%
5%
10%
15%
20%
25%
-6500 -5500 -4500 -3500 -2500 -1500 -500 500 1500 2500 3500 4500 5500
Center of Savings Bin, kWh/yr
Frac
tion
of S
ampl
e
Program Cost-Effectiveness
Program Cost $800,000
PV Utility Benefits $2,000,291
PV Societal Benefits $2,217,253
UCT B/C 2.50
TRC B/C 2.77
Levelized Cost 3.7¢/kWh
Findings
Longer pre- and post-periods were needed to evaluate data because of bi-monthly billing cycles
More savings would have been realized with high-quality 2.0 GPM or less showerheads
Homes with greater than 20,000 kWh pre-treatment consumption yielded higher savings, but savings across all homes electric resistance central heat was significant and cost-effective
Questions? Comments?