+ All Categories
Home > Documents > Manufacturing Technology (ME461) Lecture25

Manufacturing Technology (ME461) Lecture25

Date post: 03-Jun-2018
Category:
Upload: jayant-raj-saurav
View: 220 times
Download: 0 times
Share this document with a friend

of 15

Transcript
  • 8/12/2019 Manufacturing Technology (ME461) Lecture25

    1/15

    Manufacturing Technology

    (ME461)

    Instructors: Shantanu Bhattacharya

  • 8/12/2019 Manufacturing Technology (ME461) Lecture25

    2/15

    Review of previous lectures

    Acceptance sampling Occurrence ratio and fraction defective.

    Binomial distribution.

    How acceptance sampling leads to

    formulation of a binomial distribution?

    Mean and standard deviation of thebinomial distribution.

  • 8/12/2019 Manufacturing Technology (ME461) Lecture25

    3/15

    Mean and standard Deviation of a

    Binomial distribution

    Where many sets of trial are made of an event with constant probability of occurrence p,

    the expected average number of occurences in the long run is np.

    So np is the expected value, or mathematical expectation, of x where x=0 if an item is

    acceptable or x=1 if it is rejectable.

    Mathematical expectation is an operator expressed as follows:

  • 8/12/2019 Manufacturing Technology (ME461) Lecture25

    4/15

  • 8/12/2019 Manufacturing Technology (ME461) Lecture25

    5/15

  • 8/12/2019 Manufacturing Technology (ME461) Lecture25

    6/15

  • 8/12/2019 Manufacturing Technology (ME461) Lecture25

    7/15

  • 8/12/2019 Manufacturing Technology (ME461) Lecture25

    8/15

    An experimental example of the meaning of average and

    standard deviation of Binomial distribution

    No. of non

    conforming

    items

    Frequency

    4 3

    3 7

    2 9

    1 160 5

    Total 40

    The table on the left may be used to clarify certain

    aspects of the mean and standard deviation of the

    Binomial distribution.Column on the extreme left gives the number of

    non conforming items in each sample of 10.

    The result of 40 samples may be arranged into a

    frequency distribution .

    The average calculated by normal method results

    in 1.675 and the standard deviation by a similarmethod result in 1.127.

    If we use the formulae for the mean and deviation

    of a binomial distribution the expected average

  • 8/12/2019 Manufacturing Technology (ME461) Lecture25

    9/15

    The expected

    standard

    deviation

    So, the

    observed values

    seem fairly close

    to the expectedvalue.

  • 8/12/2019 Manufacturing Technology (ME461) Lecture25

    10/15

    Control charts for attributes

    There are several different types of control charts that may be used. These are the

    following:

    1. The p chart, the chart for fraction rejected as non conforming to specifications.2. The np chart, the control chart for number of non conforming items.

    3. The c chart, the control chart for non conformities.

    4. The u chart, the control chart corresponding to the non conformities per unit.

    Control charts for fraction rejected

    The most versatile and widely used attributes control chart is the p chart. This is the

    chart for the fraction rejected as non conforming to specifications. The principle

    advantage that these charts provide is that only 1 chart is sufficient to describe 10s,

    100s or 1000s of quality characteristics by classifying the item as accepted or rejected.

    Control limits for the p-chart

  • 8/12/2019 Manufacturing Technology (ME461) Lecture25

    11/15

    Problems introduced by variable

    subgroup sizeOne practical difference between the X chart and p chart is the variability in subgroupsize in the p chart.

    P charts typically use data taken for other purposes than the control chart; where

    subgroups consist of daily or weekly production and tend to vary a lot.

    Whenever subgroup size is expected to vary, a decision must be made as to the way in

    which control limits are to be shown on the p chart. There are three solutions to all these

    problems.

    1. Compute new control limits for every subgroup, and show these fluctuating limits on

    the control chart. This is illustrated in the first 2 months of the 4 months.

    2. Estimate the average subgroup size for the immediate future. Compute one set of

    limits for this average, and draw them on the control chart. Whenever the actual

    subgroup size is substantially different from this estimated average, separate limits

    may be computed for individual subgroups.

    3. Draw several sets of control limits on the chart corresponding to different subgroup

    sizes. A good plan is to use three sets of limits, one for expected average, one close

    to the expected minimum and one close to the expected maximum.

  • 8/12/2019 Manufacturing Technology (ME461) Lecture25

    12/15

    This example shows a 4 month

    record of daily 100% inspection

    of a single critical quality

    characteristics of a part of an

    electrical device.

    When after a change in design,the production of this part was

    started early in June, the daily

    fraction rejected was computed

    and plotted on a chart.

    At the end of the month the

    average fraction rejected P wascomputed.

    Trial control limits were

    computed for each point. A

    standard value of fraction

    rejected p0 was then established

    to apply to future production.During July new control limits

    were computed and plotted daily

    on the basis of the no. of parts

    n inspected during the day.

    Table 1

  • 8/12/2019 Manufacturing Technology (ME461) Lecture25

    13/15

    A single set of control limits

    was established for August,

    based on the estimated average

    daily production.

    At the end of August, a revised

    p0 was computed to apply to

    September, and the control

    chart was continued during

    September with this revised

    value.

    Calculation of the trial control

    limits:

    Table 1 shows the number

    inspected and no. rejected on

    each day. The fraction rejected

    on each day is the no. of partsrejected each day divided by the

    number inspected that day.

    For example: on June 6th, Pi =

    31/3350 = 0.0093.

    At the end of the month the

    average P is computed

    The standard deviation is calculated on the basis of thisobserved value P

    Table 2

  • 8/12/2019 Manufacturing Technology (ME461) Lecture25

    14/15

    Determination of P0: If all

    the points fall within the

    trial control limits, the

    standard value P0 may be

    assumed to be equal to P.

    Here point fell outside thecontrol limit. Thus a

    revised value of P is

    calculated.

    With the days June 7, 12,

    13 and 22 eliminated, the

    remainder no. of rejects is290 and no. inspected is

    46399. The revised P0 =

    0.0063.

    After considering this and

    the previous record on

    similar parts of slightlydifferent design, it was

    decided to assume p0 =

    0.0065.

    Table 2 is calculated on

    the basis of p0.

    Table 3

    bl h f l l

  • 8/12/2019 Manufacturing Technology (ME461) Lecture25

    15/15

    Establishment of control limit

    based on expected average

    subgroup size:

    Although the correct position of

    3-sigma control limits on a p chartdepends on subgroup size, the

    calculation of new limits for each

    new subgroup consumes some

    time and effort.

    Where the variation in subgroup

    size is not too great , thecalculation of each new subgroup

    consumes time and effort.

    Where the variation of subgroup

    size is not more than 25%, it may

    be good enough for practical

    purposes to establish a single setof control limits based on the

    expected average subgroup size.

    For the month of august (Table

    3) the estimated average daily

    production was 2600.


Recommended