M A R C H 2 8 , 2 0 1 4
Chuck Liebold
Manager Interregional Planning
IPSAC WebEx
NCSP Next Steps
Next Steps
• Maintain ongoing coordination efforts
– Continue advancing joint production database
– Coordinate cross border impact upgrades, interconnections, and transmission service
• Next JIPC planning cycle activities– IPSAC meeting to begin planning cycle – 3/28/2014
– Exchange and review of annual planning cycles
– Discussion of timing for updated power flow exchange
– Exchange regional plans and studies with potential interregional impacts and drivers – make material available to IPSAC consistent with CEII requirements
2
Next Steps
• Process to consider and evaluate for potential Interregional Transmission Projects
– JIPC reviews regional plans
– Presentation of JIPC review of regional plans and discuss next steps with IPSAC
– Receive IPSAC input and comment
– JIPC identifies potential for interregional projects
3