Mark Wenclawiak of All4 Inc. presented the challenges of greenhouse gas (GHG) Prevention of Significant Deterioration (PSD) permitting at the NCASI West Coast Regional Meeting on September 24, 2014. In the presentation, Mark discussed drivers for such projects and five (5) challenges encountered during the application development and agency review.
Popular Tags:
12
www.all4inc.com Kimberton, PA | 610.933.5246 Kennesaw, GA | 678.460.0324 GHG PSD Permitting Challenges Mark Wenclawiak | [email protected] | 678.460.0324 x202 September 24, 2014 Presented at NCASI West Coast Regional Meeting by All4 Inc.
Transcript
Page 1: Mark Wenclawiak All4 GHG PSD Permitting Challenges

www.all4inc.com Kimberton, PA | 610.933.5246 Kennesaw, GA | 678.460.0324

GHG PSD Permitting Challenges

Mark Wenclawiak | [email protected] | 678.460.0324 x202

September 24, 2014

Presented at NCASI West Coast Regional Meeting by All4 Inc.

Page 2: Mark Wenclawiak All4 GHG PSD Permitting Challenges

2 Your environmental compliance is clearly our business.

Outline

Project driver

5 challenges encountered

• During application development

• During agency review

Page 3: Mark Wenclawiak All4 GHG PSD Permitting Challenges

GHG PSD Permitting Challenges

Project Driver

Page 4: Mark Wenclawiak All4 GHG PSD Permitting Challenges

4 Your environmental compliance is clearly our business.

Boiler MACT compliance project

• Boilers decommissioned

• Boiler modified

• New boilers installed

Major modification in attainment area

Compressed project schedule

• Pre-application meeting

• Expedited permitting process

Background on Project

Page 5: Mark Wenclawiak All4 GHG PSD Permitting Challenges

5 Your environmental compliance is clearly our business.

Emissions inventory

• PSD applicability evaluation

New and modified units

No affected units

• Actual to projected actual emissions

• Step 1 significant increase for multiple pollutants

Netting

• Step 2 significant increase for GHGs only

Background on Project

Page 6: Mark Wenclawiak All4 GHG PSD Permitting Challenges

GHG PSD Permitting Challenges

Challenges During Application Development

Page 7: Mark Wenclawiak All4 GHG PSD Permitting Challenges

7 Your environmental compliance is clearly our business.

Challenge #1

• Biogenic emissions

Challenge #2

• BACT for modified boiler changes scope of Mill’s project

Retrofit with economizer

First Set of Challenges

Page 8: Mark Wenclawiak All4 GHG PSD Permitting Challenges

GHG PSD Permitting Challenges

Challenges During Agency Review

Page 9: Mark Wenclawiak All4 GHG PSD Permitting Challenges

9 Your environmental compliance is clearly our business.

Initial submittal in early Spring 2014

• Expedited process to issue permit by mid-summer

• 2 iterations of requests for more information

Challenge #3

• Netting calculation procedure

Challenge #4

• Regional Haze

Existing Regulatory Matters

Page 10: Mark Wenclawiak All4 GHG PSD Permitting Challenges

10 Your environmental compliance is clearly our business.

June 23, 2014 SCOTUS ruling during agency review

Challenge #5

• PSD for GHG-only – now what?

• State issues implementation policy

Rules of Game Change

Page 11: Mark Wenclawiak All4 GHG PSD Permitting Challenges

11 Your environmental compliance is clearly our business.

Hold on application

• Revise application to remove PSD references

• Boiler MACT extension request to help with budgeting

Current Path Forward

Page 12: Mark Wenclawiak All4 GHG PSD Permitting Challenges

www.all4inc.com Kimberton, PA | 610.933.5246 Kennesaw, GA | 678.460.0324

Questions & Open Discussions

Mark Wenclawiak | [email protected] | 678.460.0324 x202