Mr. Glick worked with LA Metro from 1995 - 2003 on the Metro Gold Line LRT Project. Initial work consisted of trouble-shooting the project\'s five-year stalemated status. Mr. Glick led the agency through a process that included preparing for and holding four corridor-wide workshops over a six-week period, assessing the Marmion Way corridor design relative to community / agency goals, and generating a corridor design resolution that included complete urban design, civil design and systems design changes. The resulting transitway design essentially became a "complete street" within a designated historic district. Corridor design features combined to form a context sensitive composition. Mr. Glick led the project team through completion of the 30% urban design documents for the corridor and the Highland Park station vicinity. These included a two-block-long transit plaza, street trees, benches, landscaping, pergola, pedestrian lighting, paving design commemorating the historical roots of the neighborhood and arts and crafts era architectural compatibility. Mr. Glick oversaw quality assurance and quality control during the design-build construction process for the Metro Gold Line Construction Authority. The Highland Park Station Transit Plaza and Marmion Way Corridor were dedicated on Saturday, May 10, 2003, led by Los Angeles City Councilmember Ed Reyes.
45
Design of the Marmion Way Corridor Fred Glick, PLA • Urban Design • Master Planning • Landscape Architecture Metro Gold Line Light Rail Transit Project National Transportation Leadership Conference FHWA – FTA – APA Washington, DC 2004
Transcript
Page 1: Marmion Way Corridor, Metro Gold LIne Light Rail

Design of the Marmion Way Corridor

Fred Glick, PLA • Urban Design • Master Planning • Landscape Architecture

Metro Gold Line Light Rail Transit Project National Transportation Leadership Conference FHWA – FTA – APA Washington, DC 2004

Page 2: Marmion Way Corridor, Metro Gold LIne Light Rail

Purpose of Presentation

  Demonstrate extensive public involvement effort resulting in dramatic physical improvements to community

  Consensus building through urban design

  Use of historically compatible and green materials helps achieve sustainability

Page 3: Marmion Way Corridor, Metro Gold LIne Light Rail

Principal Challenge

From a physical standpoint, the challenge was

to fit light rail into an existing, historic

community fabric in a way that improved the

quality of the urban environment.

Page 4: Marmion Way Corridor, Metro Gold LIne Light Rail

Agenda

  Marmion Way: Overview

  Community Workshops

  Urban Design Process: 1996-2001

  Construction: 2001-2003

  Operations: 2003

Page 5: Marmion Way Corridor, Metro Gold LIne Light Rail

Overview: Marmion Way Southbound

Before construction: 100 year old freight corridor, single track, undersized RR worker homes built at turn of 20th century.

Page 6: Marmion Way Corridor, Metro Gold LIne Light Rail

Overview: Marmion Way Northbound

Before construction: Utility poles both directions, minimal setbacks from street, poorly delineated intersection.

Page 7: Marmion Way Corridor, Metro Gold LIne Light Rail

Overview: Unique History

100 years as freight rail line - single track

LAMTA original lead agency

13.7 mile LRT corridor •  Chinatown - Highland Park •  South Pasadena - Pasadena Marmion Way segment •  Avenue 50 to Figueroa •  Nearly 1 mile long

Page 8: Marmion Way Corridor, Metro Gold LIne Light Rail

Overview: Socio-Cultural Composition

Diverse ethnic composition Latino, Asian-American, other minorities Generally low to lower-middle income Mistake to consider Highland Park a “rollover” area •  Language differences •  Little education among some minority residents •  Economic hardship

Well-spoken, well-educated professionals as well Neighborhood is well-organized Relentless in seeking improved quality-of-life

Page 9: Marmion Way Corridor, Metro Gold LIne Light Rail

Overview: Project Background

Imminent addition of light rail transitway Pavement - concrete walls - LRV speeds Changing configuration - community concern Urban design process initiated in 1996 Engineering needs vs. community adaptation Urban design analysis implemented •  Support of elected officials •  Two EIS’s had previously overlooked real issues From exclusive transitway to street running

Page 10: Marmion Way Corridor, Metro Gold LIne Light Rail

Overview: Major Challenges

Neighborhood: •  Neighborhood character – use of sustainable materials •  Local Historic District (City of Los Angeles) •  Livability •  Pedestrian and bicycle safety •  Functional use of private properties - access & egress

Project:

•  Emergency vehicle access •  Street closings and gated RR crossings •  Noise from LRV’s •  Speed of trains

Page 11: Marmion Way Corridor, Metro Gold LIne Light Rail

Overview: Proximity of homes

Narrow setbacks: Majority of homes have minimal setback from public right-of-way; in some cases, as little as three feet.

Page 12: Marmion Way Corridor, Metro Gold LIne Light Rail

Overview: Tight tolerances

Circulation movements: Some homes have unsafe driveway locations relative to intersections. Note how utility poles crowd the intersection.

Page 13: Marmion Way Corridor, Metro Gold LIne Light Rail

Overview: Zero setback multi-family

Setback dilemma: Narrow gate openings create turning movement difficulty for motor vehicles.

Page 14: Marmion Way Corridor, Metro Gold LIne Light Rail

Overview: Garages @ ROW Line

Setback dilemma: Proximity of garage doors to public right-of-way creates turning movement difficulty for motor vehicles.

Page 15: Marmion Way Corridor, Metro Gold LIne Light Rail

Overview: Kids play here

Open space? Kids used the existing right-of-way for parks and recreation space.

Page 16: Marmion Way Corridor, Metro Gold LIne Light Rail

Overview: Narrow driveways

Turning movements: Narrow driveway gate openings create access-egress difficulty for motor vehicles.

Page 17: Marmion Way Corridor, Metro Gold LIne Light Rail

Overview: R.O.W. used for parking

Parking. Residents and visitors previously used the BNSF RR-ROW for parking.

Page 18: Marmion Way Corridor, Metro Gold LIne Light Rail

Overview: Alleyways @ mid-block

Turning radius issues: Narrow alleyways create access-egress issues onto Marmion Way.

Page 19: Marmion Way Corridor, Metro Gold LIne Light Rail

Overview: Avenue 57 Station Site

Proposed Highland Park Station Site: Right-of-way widens at the station location shown center above; Marmion Way street corridor runs south of and parallel to station site (in left of photo).

Page 20: Marmion Way Corridor, Metro Gold LIne Light Rail

Community Workshops: 1996

Initiate new round of dialogue & build consensus Cost containment measures – Redesign Stations

mandated by MTA Board Clarify MTA’s position - Design Marmion Way - Gain

community support Facilitation by urban design consultant

Page 21: Marmion Way Corridor, Metro Gold LIne Light Rail

Community Workshops: 1996

Initiate new round of dialogue & build consensus Cost containment measures – Redesign Stations

mandated by MTA Board Clarify MTA’s position - Design Marmion Way - Gain

community support Facilitation by urban design consultant

Page 22: Marmion Way Corridor, Metro Gold LIne Light Rail

Workshop #1

Place: South Pasadena Library - April 6, 1996 Purpose: •  Revisit project impacts & design with community

•  8’ high concrete sound walls enclosing transitway •  RR crossing gates, bells, horns, etc.

•  Achieve consensus for Marmion Way design

•  Introduce community to urban design consultants Results: •  Exchanged information

•  Developed communication tools

Page 23: Marmion Way Corridor, Metro Gold LIne Light Rail

Workshop #2

Place: Highland Park Senior Center - April 20, 1996

Purpose: Present MTA’s revised scheme for M.W. •  32 foot trackway, fenced both sides •  6’ high chain link fences •  13’ southbound travel lane; 15’ northbound •  Only 4 cross-streets closed to motor vehicles •  High LRV speeds of 45 mph; avg speed of 31 mph Results: •  Community response still negative •  Diverse attendance reflects of Highland Park

Page 24: Marmion Way Corridor, Metro Gold LIne Light Rail

Workshop #3

Place: Elementary School in Chinatown - May 4, 1996

Purpose: Present another iteration of Marmion Way •  32’ trackway; 4’ metal picket fence (both sides) •  13’ and 15’ travelways (peds & motor vehicles) •  Pedestrian crosswalks at all intersections (striped paint) •  4 cross-streets closed to motor vehicles •  Highest LRV speed 20 mph; avg speed 15 mph Results: •  Semi-exclusive scheme still non-responsive •  Private property impacts first raised at this meeting

Page 25: Marmion Way Corridor, Metro Gold LIne Light Rail

Right-of-Way Analysis

Block-by-block evaluation of public right-of-way and individual properties conducted to determine impacts to private properties.

Page 26: Marmion Way Corridor, Metro Gold LIne Light Rail

Workshop #4

Place: Pasadena Doubletree Hotel - May 16, 1996

Purpose: Finalize consensus on preferred scheme •  Analysis done by MTA engineer & urban design consultant •  MTA position - functional impacts to private properties

required scheme minimizing or eliminating such impacts

Results: •  Street running system - preferred approach •  Proposal well-received by community •  Modest center fence prevents errant transitway use by motor

vehicles, while directing pedestrians to intersections

Page 27: Marmion Way Corridor, Metro Gold LIne Light Rail

Vision Statement

The Marmion Way Corridor . . . is unique to the overall Pasadena Blue Line Project in that it is the core of the historical neighborhood of Highland Park. The narrow right-of-way requires a sensitive approach to the provision of urban design principles in promoting safety for the accommodation of pedestrians, bicycles, motor vehicles and light rail transit. Neighborhood character and livability are vital aspects the community seeks to maintain. They can be achieved through the efficient and creative composition of various materials, textures and colors that form the separate use areas and provide for a neighborhood compatible corridor that promotes safety, maintains or adds value and preserves the character of the community.

Page 28: Marmion Way Corridor, Metro Gold LIne Light Rail

Marmion Way Corridor Metro Gold Line LRT, Los Angeles

Marmion Way Corridor before construction.

Original engineering proposal for design of public right-of-way.

Page 29: Marmion Way Corridor, Metro Gold LIne Light Rail

Urban Design Vision: 1997

Right-of-way design concept prepared by urban design team, meeting both neighborhood compatibility and engineering requirements.

Page 30: Marmion Way Corridor, Metro Gold LIne Light Rail

Project Shutdown

Project terminated in early 1998 by LAMTA due to forecasted budget shortfalls. All work ceased. All consultants released from contracts.

Page 31: Marmion Way Corridor, Metro Gold LIne Light Rail

Project Resumption

Construction Authority formed in January, 1999 •  Sole purpose: to build the project •  Hired Chief Executive Officer •  Retained Program Management Consultant •  Retained same urban design consultant •  Design-Build method chosen

Marmion Way - •  Refined Avenue 50 - 57 segment •  Urban design approach - Avenue 57 – Figueroa

including Highland Park Station Plaza

Page 32: Marmion Way Corridor, Metro Gold LIne Light Rail

Marmion Way Right-of-Way

Rooftop photo of Marmion Way after construction.

Page 33: Marmion Way Corridor, Metro Gold LIne Light Rail

Marmion Way Right-of-Way

A corridor residents can live with.

Functional & aesthetic transitway materials.

Page 34: Marmion Way Corridor, Metro Gold LIne Light Rail

Marmion Way Trackbed

Rough-texture of transitway materials thwarts errant use by pedestrians, bicyclists and even motor vehicles.

Page 35: Marmion Way Corridor, Metro Gold LIne Light Rail

Marmion Way Typical Crosswalk

Use of historically compatible materials consistent with Craftsman era – Greene & Greene inspired architecture.

Page 36: Marmion Way Corridor, Metro Gold LIne Light Rail

Marmion Way - Ave 56 Intersection

Typical intersection design

Corridor is “emergency vehicle friendly”

Page 37: Marmion Way Corridor, Metro Gold LIne Light Rail

Design Character

Street lights on catenary pole

Typical arroyo-stone pilaster

Arroyo stone tactile strip located between mountable curb and trackway

Page 38: Marmion Way Corridor, Metro Gold LIne Light Rail

Highland Park Station Plaza

Gateway pilasters at Highland Park LRT Station transit plaza

Page 39: Marmion Way Corridor, Metro Gold LIne Light Rail

Highland Park Station Plaza

Heavy timber pergola

Copper light fixture Craftsman-era combinations of timber and arroyo stone

Page 40: Marmion Way Corridor, Metro Gold LIne Light Rail

Highland Park Station & Plaza

Note use of Arroyo-Stone washed aggregate in Highland Park Station trackway

Page 41: Marmion Way Corridor, Metro Gold LIne Light Rail

Highland Park Station & Plaza

Consistent use of Marmion Way Corridor construction materials at Highland Park Station – stone, steel picket fence & concrete

Page 42: Marmion Way Corridor, Metro Gold LIne Light Rail

Project Summary

•  Public involvement process resulted in dramatically upgraded neighborhood – use of green materials, sustainable solution

•  System, civil, urban design all changed •  Pedestrians can now walk safely •  Driveway access/egress maintained •  Residents taking new pride in neighborhood •  Public right-of-way -- neighborhood asset rather

than a liability

Page 43: Marmion Way Corridor, Metro Gold LIne Light Rail

Project Summary (cont’d.)

•  Vehicles operate at streetcar speeds - 15 mph avg •  System design functions as streetcar

Traffic lights & signal pre-emption, rather than crossing gates, bells & horns

•  Relates well to neighborhood •  Relates well to private properties •  Community takes ownership of corridor •  System has become well-integrated

Page 44: Marmion Way Corridor, Metro Gold LIne Light Rail

Summary: Project Operational

Through four years of revenue service, Marmion Way’s responsive design has functioned well, with no pedestrian accidents to date.

Page 45: Marmion Way Corridor, Metro Gold LIne Light Rail

45

2004 Transportation Planning Excellence Award

Project Name: Metro Gold Line Light Rail - Marmion Way Corridor

Category: “Safety Conscious Planning”

Co-Sponsors:

• Federal Highway Administration • Federal Transit Administration • American Planning Association

Awards Jury: - Institute of Transportation Engineers - American Association of State Highway Transportation Officials - American Association of Metropolitan Planning Organizations - American Automobile Association


Recommended