+ All Categories
Home > Documents > Martin Fischer Professor, Civil & Env. Eng. ...sb10brazil/images/SB10BRAZIL_Martin_Fischer... ·...

Martin Fischer Professor, Civil & Env. Eng. ...sb10brazil/images/SB10BRAZIL_Martin_Fischer... ·...

Date post: 19-Sep-2018
Category:
Upload: haxuyen
View: 215 times
Download: 0 times
Share this document with a friend
33
Sustainable Building: You can’t always get what you want, but if you try virtually you might get what you need Martin Fischer Professor, Civil and Environmental Engineering Director, Center for Integrated Facility Engineering (CIFE) http://www.stanford.edu/~fischer [email protected]
Transcript

Sustainable Building:You can’t always get what you want, but if you try virtually you might get what you need

Martin FischerProfessor, Civil and Environmental Engineering

Director, Center for Integrated Facility Engineering (CIFE)

http://www.stanford.edu/~fischer

[email protected]

CIFE Development and Background

• 100% funded by industry

– Building owners

– Design and construction companies

– Software and hardware vendors

• 1988-2000

– Building Information Modeling (BIM)

• 2000-2010

– Virtual Design and Construction (VDC)

• 2010+

– Integrated Facility Engineering

– Breakthrough performance

Hospital Objectives

NSH Project Objectives

ICEBIM+ ProcessCurrent State Process, T5 Rebar Detailing for Construction

De

sig

nM

an

ufa

ctu

reE

ng

ine

erin

g

Release CAD

dwg, rebar

schedule (*.CSF)

in Documentum

Document

control delay

(1 week)

Preliminary

designGA drawings

Refine RC details

and concept for

buildability/

detailing

Use model to

develop and

communicate

methods

Prepare RC detail

drawings

(drafting)

Check and

coordinate detail

drawings

CAD check

(1d/dwg)

Check against

engineering calcs

(.5d /dwg)

Independent final

check & sign off

(2 weeks)

Building control

check & sign off

(BAA, time?)

Release paper P4

dwgs & bar

bending

schedules

Rebar factory

starts bending

Pre-assembly

Ship to site

Draft spec

Comment on

spec

Update spec Release spec

Model rebar

component (Use

digital

Prototyping tool)

Issue and resolve

TQ’s (Technical

Queries)

AutoCAD CAD RC IDEAS Arma +

Design input/

changes

Technology:

Detailed

engineering

design

information

Site assembly

Preliminary drafting

2 weeks

Back drafting

1 week

Checking

2 weeks

Document control

1 weekTimeline:

NOTE: Drawings are batched into sections-

then subdivided into building components.

Each component is an assembly package,

e.g. rail box floor, wall, etc.

The number of drawing sheets per building

component vary depending on the work. On

ART for example, each component may

consist of 8-15 GA drawings and 8-15 RC

detail drawings.

All of the GA drawings are complete -

pend ing changes f rom other des ign

disciplines

NOTE: Design changes

during detailing (from:

architecture, baggage,

s y s t e m s , e t c . ) a r e

upsetting RC drawing

development.

Other / None/

Unknown

Preliminary RC

detailing

Iterative

process

Consists of:

engineering

calculations,

sketches, etc.

Most of the checking

process is done

concurrently with RC

detail development.

BAA building control

accepts the opinion

of the independent

design check - and

does not perform a

check of its own

Asse

mb

ly

Existing Process - 6 weeks

Client/Business Objectives

Project Objectives

Virtual Design and Construction (VDC)

Past Present Future

• Yesterday’s practice:

YCASWYG

You can’t always see what you get

• Today’s practice:

WYSIWYG

What you see is what you get

• Next practice:

WYMIWYG

What you model is what you get}

performance Scofield 2002

Suggested steps for creating sustainable facilities • Define project goals

– Connect them to design solutions

– Revisit them throughout the project

• Implement a solid information infrastructure

• Develop many design alternatives

– Evaluate them consistently

• Engage the right professionals for decisions in a timely manner

– Keep them engaged and accountable

• Carefully design the project schedule

• Virtually build and operate

• Document the as-built facility

• Commission

• Document the accuracy of the performance predictions

• Document operations cost and value

• Establish a culture of learning

• Enable the project team to move money between organizations

Key strategies for breakthrough

sustainability performance

• Create appropriate synergies between building

systems through integrated facility engineering

• Develop as many design options as possible

• Reduce response and decision latency

• Increase information transparency

• Set goals predict measure compare

Design and construction planning methods have

changed significantly in the last 40 years

Picture courtesy Fluor

Picture courtesy DPR

As have coordination and communication methods

Picture courtesy Fluor

Picture courtesy Accu-Crete

Is this the best we can do?

• 6 designers look for

information, 4 design(practice at a very successful

international design firm)

• 1,000s of construction

activities don’t get done as

scheduled(practice on well-managed projects)

58%

6%

36%

Management

Specification

Execution

2.85 weeks7 weeks

Subsequent

(avg.)Initial

Average Number

of Iterations Per

Project

Duration of Design

Iterations

Number and duration of design iterations

Relative time spent on design tasks by category

Specification

(6%)

Execution

(36%)

Management

(58%)

Manage

Information

58%

Plan

Design

Processes

6%

Execute

Design

Processes

36%

Flager & Haymaker, 2007

Reasons Analysis

Directive/Plan: 2524

(23%)

Labor: 2118 (19%)

Prerequisite: 1434 (13%)

Material: 1395 (13%)

Weather: 1144 (10%)

Equipment/Plant: 1058

(10%)

Information: 676 (6%)

Site Access: 563 (5%)

Unforeseen Site

Conditions: 73 (1%)

Safety/Incident: 0 (0%)

SPS 2001-2005

Is this the best we can do?

• Predicted energy

consumption

does not match

actual

consumption(findings from buildings

where owners really

cared about energy

performance)

(Turner and Frankel, 2008)

11

Why does latency (waiting) and not direct

work govern our projects?

Traditional

• 100 requests for information

• ~2 days to answer

• Project duration ~200 days

Latency -- not direct work --paces schedule

Integrated Concurrent Engineering (ICE)

• 100 requests for information

• ~1 minute to answer

Direct work (modeling + analysis + documentation) --not coordination latency --paces schedule

Copyright © 2001-2010 Strategic Project Solutions, Inc. (SPS). All Rights Reserved.

68 days to perform 9 days of work

Data

SendDrawgs to

Plann.DeptLayouts Drwg

ValueEngineer

Drwg

AddManufact.

Details

File

IssueOfficial

Document(drwg)Drwg

AproveDrawing

Drwg

80 hrs(10 days-2 weeks)

Value Stream for Rectangular Ducts

Produce"L"

Shapes

Fit"L"

ShapesWIP

FitCorners

WIP

Deliver toCCs

WIP

Deliver toT5 Main

Site

CrossTHE GATE

InstallSite

Stock

PlaceOrder

Deliverto

HotchkissSteel

Manufacture

(UK)Order

160 hrs(32 days - 4 weeks)

Data

PlaceOrder

Deliverto

HotchkissSealant

Fabricate(USA)

Order

40 hrs(5 days- 1 week)

Data

HotchkissManufacturing

Facility

80hrs(10 days-2 weeks)

DuctInstalled

THE GATE

Drwg Drwg

NumberItems

ExtractLayoutfromSME

ReviewInstall.Details

T5 SITE

Design Flow

Raw Material Flow: Steel

Raw Material Flow: Sealant

8 hrs(1 day)

120 hrs(15 days-3 weeks)

Data

UseCompuDuct

1 hr 0.5 hr 0.034 hr

(2 min.)

0.17 hr

(10 min.)

0.084 hr

(5 min.)

0.017 hr

(1 min.)

0.017 hr

(1 min)

16 hrs

(2 days)

0.034 hr

(2 min)

Steel

8 hrs

(1 day)

8 hrs

(1 day)

8 hrs

(1 day)

8 hrs

(1 day)

8 hrs

(1 day)

8 hrs

(1 day)

Sealant

0.067 hr

(4 min.)

0.084 hr

(5 min.)

0.05 hr

(3 min.)

1.5-month

Stock

9-month

Stock

MoveProductsto Hold

Area WIP

0.17 hr

(10 min.)

CheckQuality

ducts

0.084 hr

(5 min.)

LoadLorry stor.

1 night

0.17 hr

(10 min.)2 hrs

Production Capacity=100 tn of ducts/month

ducts

Consolidate

ducts

CCs

Estimated # of workers for Installation = 200no

8 hrs(1 day)

0.5 hr 0.5 hr8 hrs

(1 day)

1 hr 0.5 hr0.25 hr 3 hrs

DescriptionValueAdded

Time (hrs)

TotalDurations

(hrs)% VAT

Design 17.86 200 9%

RM-steel

Manufacturing

CCs

Installation

24 160 15%

RM-sealant 24 80 30%

2.63 80 3.3%

1 8 12.5%

3.75 17 22%

EstimatedTotals

545 13.45%73.24

Effort

(hrs)Calendar Duration

Why do we leave so many facility performance aspects to chance?

t

$, t, energy, CO2, human costs, etc.

Facility Maintenance Cost

Business Operations Cost

Design-Construction Costs

Value from Facility

Building Operations Cost

Why are we only measuring safety, cost, and schedule performance during construction and then expect a high-value, energy-efficient building?

t

$, t, energy, CO2, human costs, etc.

Facility Maintenance Cost

Business Operations Cost

Design-Construction Costs

Value from Facility

Building Operations Cost

The secret to making a good movie …

… is to make sure that

everyone is working on

the same movie.Francis Ford Coppola

Reid Senescu and John Haymaker© John Haymaker, PhD, AIA, LEED ap 2009

Establish transparent project goals

AB

C

MACDADI: Multi-Attribute Collaborative Design Analysis and Decision Integration

Figure Courtesy, WDI

On a m2 basis the “blue” building

performs poorly, i.e., it uses about 50%

more energy than the green building.

Metrics are key to facility life-cycle processes

Figure Courtesy, WDI

On a transaction per m2 basis the

“green” building performs poorly, i.e., it

uses about 80% more energy than the

green building.

How do you define and track (energy) efficiency?

FOREST FLAGER, PH.D. CANDIDATEPROFESSOR MARTIN FISCHER, ADVISOR

Design Cycle (t) 4 hrs 3 sec

Design Cycles (total) 39 8,042

Steel Cost (best design) $25 M $20 M

CASE STUDY RESULTS:

KBZ STADIUM ROOF STRUCTURE

x y

z

DESIGN LAYER

Scale: 1:727.8

Create and evaluate many options

MULTIDISCIPLINARY DESIGN

OPTIMIZATION

Engage all critical stakeholders in decision making

Image Courtesy Walt Disney Imagineering

Build virtually first

Image Courtesy DPR

Study life cycle performance

Example courtesy Optima

Define plant zones on terraces

Minimize water use by selecting the right plants

Example courtesy Optima

When selecting the heating/cooling strategy during

conceptual design, consider

operations performance

operations cost

installation costs

displacement cooling mixed cooling

Snapshots courtesy of Granlund, Helsinki, Finland

From Digital to Physical Prototypes to Rapid

Construction

Example courtesy SPS

Cut latency by colocating project team in a VDC-enabled work environment• UCSF Mission Bay Hospital

– 60,000 m2 Hospital; 23,000 m2

Outpatient Building; 9,000 m2

Energy Center

– Budget ~$1.6B

– Complete Dec. 2014

• 4-day VDC and integration

planning workshop at CIFE with

32 key project team members

• Big Room with 100 professionals

working on the project (owner,

architect, engineers, general

contractor, subcontractors)

Image Courtesy DPR Inc.

Image Courtesy DPR Inc.

Predict and see life cycle performance

Video clip available at: http://www.vimeo.com/4282317

Check all circulation paths in a building

On a 6-story courthouse,

approximately 27,000 routes were

tested using 302 circulation rules

in approximately 10 seconds.

Slide courtesy GSA, work carried at GA Tech with sponsorship by the GSA

29

relate

Connect predicted and actual performance

aggregate

Component levelSystem levelSpace level

compare

Data from

Global

Ecology

Building

P

R

E

D

I

C

T

E

D

O

B

S

E

R

V

E

D

Value Cost Intervention

Sooner or later you/we will pay for integration

t

$, t, energy, CO2, human costs, etc.

Facility Maintenance Cost

Business Operations Cost

Design-Construction Costs

Value from Facility

Building Operations Cost

Bill McDonough:

Design cradle to

cradle for use of

technical and

biological

nutrients.

Cameron Diaz:

Yes, why can’t

designers and

builders do that?

I will! Will you?

But to make it

happen on every

project we must

collaborate better

with better tools.

Launch of the Green Products Innovation

InstituteMay 20, 2010

Google HQ

Rosario Dawson, Actress

Wendy Schmidt, President, Schmidt Family Foundation

Martin Fischer, Professor, Stanford University

Vance Bell, CEO, Shaw Industries

Arnold Schwarzenegger, Governor, California

Chad Hurley, Co-Founder, YouTube

Bill McDonough, Architect

Mike Volkema, Chairman, Hermann Miller

No more excuses. Just do it!


Recommended