Project Order
Map Showing 2014 Enrollment Projections for 2022 as a Percentage of Schools’ Capacities
Building Facts
Map Legend
>140%
130%-139%
120%-129%
110%-119%
100%-109%
90%-99%
< 89%
Priority Funding Area
Mary H. Matula118.4%
Walter J. Mitchell117.3%
Dr. Gustavus Brown130.7%
T. C. Martin131.5%
29
Worn Exterior Cladding
Maintenance Needed
Traffic Congestion
Matula Elementary School was originally constructed in 1992. Interior finishes are
in good condition, but minor maintenance is needed in many areas. The building
is efficiently laid out, but wayfinding is difficult. The media center is not effectively
separated from corridors and is utilized as a circulation zone between classroom wings.
The entrance sequence is secure and administration offices are conveniently located.
Exterior cladding shows cracking and efflorescence. Mechanical and plumbing systems
are in fair condition, the domestic water system is in need of a back-flow preventer, and
the cooling tower is in need of replacement. Electrical systems are in fair condition. The
site is adjacent to other CCPS properties. Bus and car parking are separated, but the
site is only accessible by one road.
Mary H. MatulaElementary School
Worn Finishes Efficient Circulation
95
Current Building Score
MaintenancePriority
Prescribed Work Cost Analysis
Recommendations
18
4.01
Minor Renovation.
It is recommended that Matula Elementary undergo
a minor architectural renovation, as well as a roof
replacement and minor mechanical and plumbing
upgrades.
ARCH
MEP
SITE
SURVEY 3.25
5.00
4.02
3.88
<2 Replace
2-3 Replace / Reno.3-4 Reno. / Maint.>4 Maintenance
SurveyCategories 4.01
This School Project Determination
BuildingScore
Description Qty. Unit County Share State Share Cost/Unit TOTAL
ARCH
Interior Doors/Hardware 124 ea $64,232 $109,368 $1,400 $173,600
Roof Replacement 62,823 sf $162,712 $277,049 $7 $439,761
Exterior Walls 62,823 sf $125,646 $- $2 $125,646
Minor Maintenance 62,823 sf $125,646 $- $2 $125,646
MEP
Cooling Upgrades 62,823 sf $569,490 $969,673 $25 $1,539,164
Fire Alarm System Upgrade 62,823 sf $69,734 $118,735 $3 $188,469
SITE
Stormwater Management/Water Quality 1 ls $46,250 $78,750 $125,000 $125,000
Subtotals $1,163,710 $1,553,576 $2,717,286
Total Including Soft Costs $2,327,523 $1,553,576 $3,881,099
Current
554
554
OptimumSRC 768
Proposed